Upload
joel-craig
View
216
Download
0
Embed Size (px)
Citation preview
LIGO-G010262-00-M
Management of the LIGO Project
Gary Sanders
California Institute of Technology
Presented to the Committee on Programs and Plans of the National Science Board
August 9, 2001
2LIGO-G010262-00-M
This Presentation
Introduction to LIGO How we have managed LIGO How NSF has managed LIGO Status of LIGO today
4LIGO-G010262-00-M
Detection of Gravitational Waves by Interferometry
suspended test masses
LIGO (4 km), stretch (squash) = 10-18 m will be detected at frequencies of 10 Hz to 104 Hz. It can detect waves from a distance of 600 106 light years
5LIGO-G010262-00-M
LIGO Scope and Costs
The Laser Interferometer Gravitational Wave Observatory (LIGO) is:» a joint project of Caltech and MIT
» construct and operate two observatories with 4 km interferometers
» detect gravitational waves
» initiate ground-based gravitational wave astronomy
LIGO has been supported through the NSF Division of Physics/Gravity Program» Construction cost $292 million (Major Research Equipment + R&D)
» Commissioning, early operations and R&D cost $79 million
» This funding covers 1994 - 2001
11LIGO-G010262-00-M
LIGO Schedule
1996 Construction Underway (mostly civil)
1997 Facility Construction (vacuum system)
1998 Interferometer Construction (complete facilities)
1999 Construction Complete (interferometers in vacuum)
2000 Detector Installation (commissioning subsystems)
2001 Commission Interferometers (first coincidences)
2002 Sensitivity studies (initiate LIGO I Science Run)
2003+ LIGO I data run (one year integrated data at h ~ 10-21)
2006+ Begin ‘advanced’ LIGO installation
12LIGO-G010262-00-M
Construction Cost Schedule Performance
0
50
100
150
200
250
300
95-2
95-4
96-2
96-4
97-2
97-4
98-2
98-4
99-2
99-4
00-2
00-4
01-2
01-4
LIGO Quarter
$ M
illio
ns
Original Plan - $250M
Current Plan - $290M
Cooperative Agreement - $292M
Performance - $281M
Actuals Costs - $278M
Earned Value
98% complete
13LIGO-G010262-00-M
Features of the LIGO Construction Project
University (Caltech+MIT) managed, no national laboratory
Two green field sites Carried out as two major subprojects
» 2/3 of the project constructs buildings, clean labs, vacuum system designed for ultimate terrestrial detectors
» 1/3 of project constructs initial detectors
NSF funding provided when scheduled, leading to a technically limited project
14LIGO-G010262-00-M
Features of the LIGO Construction Project
Organized and executed like a bridge building project» Product oriented Work Breakdown Structure (WBS)» Scope and technical configuration defined and controlled» Cost and schedule integrated into a performance measurement baseline
with earned value analysis» Contingency funds managed centrally through a Change Control Board» Organization matches WBS
– Subsystem managers responsible to deliver products
» Subcontractors managed rigorously» Scientists fully integrated and aware of Voltaire’s maxim “le mieux est
l'ennemi du bien”– Scientists did not destabilize project but were also the source for project repair
and workaround
Big Science culture new to NSF and to Caltech/MIT scientists
15LIGO-G010262-00-M
LIGO Project Work Breakdown and Organization
W o rk B re akd o w n S tru c tu re
C iv il F a c ilit ie sV a cu u m E qu ip m e ntB e am Tu beB e a m T ub e E n c losu re
F a c ilit ie s
L a se rs/O p ticsIso la tio n /S usp e ns ionC o n tro lsE n v . M o n ito r
.
.
D e te c to r
4 0 M e te r T e stP h a se N o ise T e stC a m pu s R ese a rch
R & D
P ro jec t M a n ag e m e ntC o s t/S che d u leS ys tem E n g in ee ringQ A /E S & HD o cu m e n t C o n tro lC o m pu ting
P ro jec t M a n ag e m e nt
L IG O P ro je ct
L IG O P ro jec t O rg a n iza tion
C iv il F a c ilit ie sV a cu u m E qu ip m e ntB e am Tu beB e a m T ub e E n c losu re
F a c ilit ie s
L a se rs/O p ticsIso la tio n /S usp e ns ionC o n tro lsE n v . M o n ito r
.
.
D e te c to r
4 0 M e te r T e stP h a se N o ise T e stC a m pu s R ese a rch
R & D
P ro jec t M a n ag e m e ntC o s t/S che d u leS ys tem E n g in ee ringQ A /E S & HD o cu m e n t Co n tro lC o m pu ting
P ro jec t M a n ag e m e nt
L IG O P I a nd P M
17LIGO-G010262-00-M
Post Construction
Operating as a scientific program has been initiated Organized LIGO Scientific Collaboration (LSC)
» a ~30 institution, ~300 scientist international collaboration to carry out the
– observational science and– advanced R&D
» LSC includes LIGO Laboratory scientific staff
18LIGO-G010262-00-M
What NSF Has Done
Through the Gravity Program, NSF has created an oversight function for LIGO
Cooperative Agreement and Project Management Plan created the formal framework
A dedicated program officer led the oversight and structured NSF review
Semiannual project reviews during construction used a standing committee with slowly varying membership to provide review of progress
Program officer employed an internal multidisciplinary team to coordinate NSF reviews and approvals with periodic meetings
» Gravity program, grants and agreements, legal, public affairs, government affairs, property management, budget,…
20LIGO-G010262-00-M
LIGO Status
Hanford 2 kilometer interferometer commissioned in final optical configuration
Livingston 4 kilometer interferometer commissioning in recombined configuration
Hanford 4 kilometer interferometer laser and mode cleaner commissioned with arms about to be illuminated
Engineering runs and mock data challenges carried out
Coincidence studies later this year Scientific running commences in 2002