60
Light Rail Transit in Ottawa January 30, 2020 Michael Morgan Director, Rail Construction Program City of Ottawa 1

Light Rail Transit in Ottawa · 2020. 2. 20. · Design Build Finance (DBF) Procurement: • 12 km of track Blair Station Trim Road Station ... • Operating range of -40C to +40C

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • Light Rail Transit in Ottawa

    January 30, 2020

    Michael MorganDirector, Rail Construction ProgramCity of Ottawa

    1

  • Agenda

    • Background

    • Stage 1 Project

    • Stage 2 Project

  • Ottawa’s Transit Challenge

  • BRT to LRT Conversion

  • Stage 1 Project

  • Confederation Line Alignment

  • Project Overview

    Stage 1 Confederation Line

    • Conversion of the existing bus “Transitway” to a 12.5km dedicated light rail transit line running

    • 2.5km tunnel through the downtown core

    • 13 stations including 3 downtown underground stations

    • A new Maintenance and Storage Facility where the light rail vehicles will be assembled, maintained and stored

    • 30 year maintenance concession period

  • Procurement Approach

    Affordability Cap

    Project Solutions

    Defined Service Proven Vehicle

    and System

    RFP Innovations

    Geotechnical risk ladder

    Operations Matters

    Energy Matters

    Mobility Matters

    Bundled Hwy 417 Expansion

    Project

    Flexibility in construction &

    tunnel excavation

    methodology

    Provided station “innovation

    zones”

    Bundled cash allowance projects

  • Rideau Transit Group (RTG)

    • Design Build Finance Maintain

    • Owned and operated by the City of Ottawa

    • $2.1B project including $300M in private financing

    • 30-year maintenance term with performance incentives

    • Rideau Transit Group (RTG):

  • Design Challenges

    • System had to be designed to allow for long term capacity needs: 18,000 pphpd by 2031; Ultimate ridership 24,000 pphpd.

    • System had to designed to be fully accessible, include public art, address the need of stakeholders and include cycling/pedestrian connections.

    • Design consideration had to be made for the Rideau Canal and other major infrastructure throughout the alignment (sewers, existing road and transit network, etc.), and integrated station entrances in the down tunnel area.

  • Construction Challenges

    • Coordinating Confederation Line project works (stations, guideway, MSF, vehicles, etc.) with:

    • Highway 417 expansion works;

    • OC Transpo transitway shutdown and bus detours;

    • Bundled civil projects (Queen Street renewal, Booth Street bridge, etc.); and,

    • Other City infrastructure projects (Rideau Street renewal, Ottawa Art Gallery construction, etc.).

    • Minimizing impacts to transit customers, property owners, commuters, and residents.

  • Construction: Rideau Station

  • Construction: uOttawa Station

  • Construction: Hurdman Station

  • • The method of tunneling used was sequential excavation with three road header machines (named Chewrocka, Jawbreaker and Crocodile Rouge).

    • Excavation work started in Fall 2013 and was completed in Winter 2017.

    • Surface excavation was required for the tunnel ventilation shafts and station entrances at the Lyon west, Parliament west and east & Rideau west entrances.

    • Surface excavation was performed at the east and west portals on sections of the closed BRT, the Central Shaft (Queen & Kent), and station entrances at Lyon east and Rideau east.

    Tunneling

  • Tunneling (cont’d)

  • Tunneling (cont’d)

  • 18

    • Bicycle parking• Bicycle stairway runnels• Customer information points• Ticket machines• Fare gates• Fare-paid zones• Audible & visual

    announcements• Public washrooms at major

    transfer stations • Spacious & secure platforms• Transecure areas

    • Heated waiting areas• Video camera monitoring• Escalators• Network maps• Emergency telephones• Clear signage & wayfinding• Lantern boxes• Public art• Accessibility features

    including: two elevators, tactile wayfinding tiles & platform edge indicator strips

    Station Amenities

  • 19

    Public Art

    • The Confederation Line stations include both integrated and non-integrated public art.

    • Station themes were approved by Council in 2011, and included:o uOttawa – “Innovation”o Rideau – “Gallery”o Parliament – “Confederation”o Lyon – “Bytown”o Pimisi – “Algonquin”o Bayview – “Sustainability”

  • 20

    Public Art (cont’d)

    • The Confederation Line stations include both integrated and non-integrated public art.

    • Station themes were approved by Council in 2011, and included themes of innovation, sustainability, confederation, and most notably Algonquin culture and heritage.

    • The public art and artists was chosen in line with the City’s public art procurement process, which includes a call to artists through a request for qualification process, and two jury selection processes to shortlist and select the final artist(s) for each station.

  • Public Art: Tunney’s Pasture Station

  • Public Art: Pimisi Station

  • Public Art: Pimisi Station (cont’d)

  • Public Art: Lyon Station

  • Public Art: Parliament Station

  • Public Art: Rideau Station

  • Public Art: Lees Station

  • Public Art: Lees Station (cont’d)

  • Public Art: Hurdman Station

  • Public Art: St-Laurent Station

  • Stage 1 Benefits

    • Capacity to move 10,700 passengers per hour in each direction on day-one of revenue service;

    • Potential to grow to over 18,000 passengers per hour in each direction by 2031;

    • Travel time between Tunney’s Pasture Station and Blair Station will be less than 25 minutes, any time of the day;

  • Alstom Citadis Spirit

  • Stage 1 Benefits (cont’d)

    • Replacing bus and car trips with the electric Alstom Citadis Spirit trains will reduce carbon dioxide by approximately 94,000 tonnes per year by 2031; and,

    • The investment in LRT has generated thousands of direct and indirect jobs, and will provide a total economic output of approximately $3.2 billion.

  • Stage 1 Lessons Learned

    The major lessons learned and best practices from Stage 1 include:

    • Placing a concerted focus on preliminary engineering to create reference concepts project designs from the outset of procurement planning;

    • Early operator involvement in procurement and design;

    • Strengthened penalty regime;

    • Earned value payment mechanism instead of milestone payments;

  • Stage 1 Lessons Learned (cont’d)

    • Incorporating City projects into the project to benefit from full risk transfer, cost and schedule certainty of the P3 contract;

    • Expanding Mobility Matters requirements to include pedestrians and cyclists, and a lane rental system to minimize the impacts on the City;

    • Importance of stress testing bus loops at major transfer stations; and,

    • Importance and value of a full transformational project office to prepare the transit system for multi-modal operations (Multi Modal Transportation Project Office).

  • Stage 2 Project

  • Stage 2 Rail Network

  • Procurement Model

    Confederation Line East and West Extensions

    Design-Build-Finance (DBF) Rideau Transit Group Stage 2 MOU

    • Confederation Line East Extension• Confederation Line West Extension

    • 38 Vehicles• Belfast Yard MSF expansion• Civil, vehicle maintenance

    and lifecycle for Stage 1 and 2

    Trillium Line Extensions

    Design-Build-Finance-Maintain (DBFM)

    • Trillium Line Extension, including Airport Link• Upgrade existing Trillium Line• Maintain existing and expanded Trillium Line

  • Stage 2: Confederation Line

    Design Build Finance (DBF) Procurement:

    • 12 km of track Blair Station Trim Road Station

    • 15 km of track to Moodie and Baseline Stations

    • 2.5 km cut and cover tunnel through Byron Linear Park

    • Sixteen (16) passenger light rail stations

    • Light maintenance and storage facility

  • Montreal Station

  • Orleans Station

  • Trim Station

  • Lincoln Fields Station

  • Iris Station

  • Westboro Station

  • Confederation Line East Schedule

  • Confederation Line West Schedule

  • Stage 2: Trillium Line

    Design Build Finance Maintain (DBFM) Procurement:

    • 16 km of new track and eight new stations

    • Rail link from South Keys to E&Y Centre and Airport Station

    • Seven (7) Stadler FLIRT vehicles added to fleet of vehicles

    • Purpose built Walkley Storage & Maintenance Facility

    • Extensive safety and reliability enhancements

  • Walkley Yard

  • Gladstone Station

  • Bowesville Station

  • Airport Station

  • Trillium Line Schedule

  • Alstom LINT

  • Stage 2: Trillium Line

    Mainline service vehicles

    Airport Link service vehicles

    Vehicle Total

    Stadler Flirt (new) 7

    Alstom Lint (existing) 6

  • Stadler FLIRT

  • Stadler Vehicle

    The Stage 2 O-Train South vehicle contract included a number of requirements for the new Diesel Multiple Unit (DMU) vehicles, including, but not limited to:

    • Tier IV Final Emissions Standards (latest EPA standard);

    • Increased door count for efficient passenger flow as compared to the previous and existing vehicles;

    • Operating range of -40C to +40C degrees; and,

    • 35 year lifespan with conversion to electric possible.

  • Stage 2 Benefits

    Stage will result in the removal of approximately 14,000 cars off the road during rush hour

    Stage 2 will bring over 77% of residents within 5kms of rail transit

    Encourage active transportation through the creation of approximately 25 kilometres of multi-use pathways (MUPs), cycle-tracks and pedestrian bridges

    Replace more than 900,000 bus trips annually during the peak periods.

  • Stage 2 Summary

  • Questions?