  • ID Task

    Mode

    Task Name Duration Start Finish

    0 Commercial Construction

    344 days Wed 17/06/15

    Mon 10/10/16

    1 General Conditions 17 days Wed 17/06/15Thu 09/07/15

    2 Receive notice to proceed and sign contract

    3 days Wed 17/06/15

    Fri 19/06/15

    3 Submit bond and insurance documents

    2 days Mon 22/06/15

    Tue 23/06/15

    4 Prepare and submit project schedule

    2 days Wed 24/06/15

    Thu 25/06/15

    5 Prepare and submit schedule of values

    2 days Fri 26/06/15 Mon 29/06/15

    6 Obtain building permits

    4 days Mon 22/06/15

    Thu 25/06/15

    7 Submit preliminary shopdrawings

    2 wks Fri 26/06/15 Thu 09/07/15

    8 Submit monthly requests for payment

    1 day Mon 22/06/15

    Mon 22/06/15

    9 Long Lead Procurement

    70 days Tue 23/06/15

    Mon 28/09/15

    G.C. General Management

    G.C. Project Management,G.C. General Management[25%]

    G.C. Project Management[25%],G.C. Scheduler

    G.C. General Management[10%],G.C. Project Management

    G.C. Project Management[50%],G.C. Procurement[50%]

    G.C. Project Management[50%],G.C. Procurement[50%]

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 1

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    10 Submit shop drawings and order long lead items - steel

    2 wks Tue 23/06/15

    Mon 06/07/15

    11 Submit shop drawings and order long lead items - roofing

    2 wks Fri 10/07/15 Thu 23/07/15

    12 Submit shop drawings and order long lead items - elevator

    2 wks Fri 10/07/15 Thu 23/07/15

    13 Submit shop drawings and order long lead items - plumbing

    2 wks Fri 10/07/15 Thu 23/07/15

    14 Submit shop drawings and order long lead items - electric

    2 wks Fri 10/07/15 Thu 23/07/15

    15 Submit shop drawings and order long lead items - HVAC

    2 wks Fri 10/07/15 Thu 23/07/15

    Steel Erection Contractor Management

    Roofing Contractor Management

    Elevator Contractor Management

    Plumbing Contractor Management

    Electric Contractor Management

    HVAC Contractor Management

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 2

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    16 Detail, fabricate and deliver steel

    12 wks Tue 07/07/15

    Mon 28/09/15

    17 Mobilize on Site 10 days Mon 22/06/15Fri 03/07/15

    18 Install temporary power

    2 days Mon 22/06/15

    Tue 23/06/15

    19 Install temporary water service

    2 days Mon 22/06/15

    Tue 23/06/15

    20 Set up site office 3 days Wed 24/06/15Fri 26/06/15

    21 Set line and grade benchmarks

    3 days Mon 29/06/15

    Wed 01/07/15

    22 Prepare site - laydown yard and temporary fencing

    2 days Thu 02/07/15

    Fri 03/07/15

    23 Site Grading and Utilities

    35 days Mon 06/07/15

    Fri 21/08/15

    24 Clear and grub site

    3 days Mon 06/07/15

    Wed 08/07/15

    25 Stone site accessand temporary parking area

    2 days Thu 09/07/15

    Fri 10/07/15

    Steel Erection Contractor Management[50%],Steel Erection Contractor[50%]

    Electric Contractor

    Plumbing Contractor

    G.C. Superintendent,G.C. Labor Crew[10%]

    G.C. Survey Crew

    Site Grading Contractor,G.C. Labor Crew[10%]

    Site Grading Contractor

    Site Grading Contractor

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 3

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    26 Rough grade site(cut and fill)

    1 wk Mon 13/07/15

    Fri 17/07/15

    27 Install storm drainage

    2 wks Mon 20/07/15

    Fri 31/07/15

    28 Install exterior fire line and building fire riser

    2 wks Mon 20/07/15

    Fri 31/07/15

    29 Perform final site grading

    2 wks Mon 03/08/15

    Fri 14/08/15

    30 Erect building batter boards and layout building

    1 wk Mon 17/08/15

    Fri 21/08/15

    31 Foundations 33 days Mon 24/08/15Wed 07/10/15

    32 Excavate foundations

    2 wks Mon 24/08/15

    Fri 04/09/15

    33 Excavate elevator pit

    2 days Mon 24/08/15

    Tue 25/08/15

    34 Form column piers and spreadfoundations

    4 days Mon 07/09/15

    Thu 10/09/15

    Site Grading Contractor

    Site Grading Contractor

    Plumbing Contractor

    Site Grading Contractor

    G.C. Survey Crew

    Site Grading Contractor[50%]

    Site Grading Contractor

    G.C. Rough Carpenter Crew

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 4

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    35 Rough-in electricand plumbing in elevator

    4 days Wed 26/08/15

    Mon 31/08/15

    36 Form elevator pit walls

    4 days Tue 01/09/15

    Fri 04/09/15

    37 Set reinforcing and anchor bolts

    4 days Fri 11/09/15 Wed 16/09/15

    38 Pour column piers and foundations

    5 days Thu 17/09/15

    Wed 23/09/15

    39 Pour concrete elevator walls

    1 day Mon 07/09/15

    Mon 07/09/15

    40 Cure elevator wall concrete

    7 days Tue 08/09/15

    Wed 16/09/15

    41 Cure piers and foundations

    7 days Thu 24/09/15

    Fri 02/10/15

    42 Strip wall forms 1 day Thu 17/09/15Thu 17/09/15

    43 Strip column piers and foundation forms

    3 days Mon 05/10/15

    Wed 07/10/15

    44 Install pneumatic tube in elevator pit

    3 days Fri 18/09/15 Tue 22/09/15

    Plumbing Contractor,Electric Contractor

    G.C. Rough Carpenter Crew

    G.C. Rough Carpenter Crew

    G.C. Concrete Crew

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew[10%]

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    Elevator Contractor

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 5

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    45 Prepare and pour concrete floor in elevator pit

    1 day Wed 23/09/15

    Wed 23/09/15

    46 Steel Erection 45 days Thu 08/10/15Wed 09/12/15

    47 Erect steel columns, beams and joist - 1st and 2nd floors

    2 wks Thu 08/10/15

    Wed 21/10/15

    48 Erect steel columns, beams and joist - 3rd floor and roof

    2 wks Thu 22/10/15

    Wed 04/11/15

    49 Install miscellaneous iron and bracing - 1st and 2nd floors

    2 wks Thu 22/10/15

    Wed 04/11/15

    50 Install miscellaneous iron and bracing - 3rd floor and roof

    2 wks Thu 05/11/15

    Wed 18/11/15

    G.C. Concrete Crew

    Steel Erection Contractor

    Steel Erection Contractor

    Steel Erection Contractor[75%]

    Steel Erection Contractor[75%]

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 6

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    51 Install stairs and miscellaneous iron railing

    2 wks Thu 19/11/15

    Wed 02/12/15

    52 Touch-up paint on steel

    1 wk Thu 03/12/15

    Wed 09/12/15

    53 Form and Pour Concrete - Floors and Roof

    85 days Thu 22/10/15

    Wed 17/02/16

    54 Form 2nd floor including all floor openings

    5 days Thu 10/12/15

    Wed 16/12/15

    55 Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

    5 days Thu 22/10/15

    Wed 28/10/15

    56 Pour 2nd floor slab

    4 days Thu 17/12/15

    Tue 22/12/15

    57 Cure 2nd floor slab

    7 days Wed 23/12/15

    Thu 31/12/15

    58 Strip forms from2nd floor slab

    2 days Fri 01/01/16 Mon 04/01/16

    59 Form 3rd floor including all floor openings

    5 days Fri 01/01/16 Thu 07/01/16

    Steel Erection Contractor[50%]

    Steel Erection Contractor[20%]

    G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    G.C. Rough Carpenter Crew[50%],G.C. Labor Crew[20%]

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 7

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    60 Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

    5 days Fri 01/01/16 Thu 07/01/16

    61 Pour 3rd floor slab

    4 days Fri 08/01/16 Wed 13/01/16

    62 Cure 3rd floor slab

    7 days Thu 14/01/16

    Fri 22/01/16

    63 Strip forms from3rd floor slab

    2 days Mon 25/01/16

    Tue 26/01/16

    64 Form roof slab including all floor openings

    5 days Mon 25/01/16

    Fri 29/01/16

    65 Install rebar and in-floor utilities (including mechanical, electrical, plumbing)

    5 days Mon 25/01/16

    Fri 29/01/16

    66 Pour roof slab 4 days Mon 01/02/16Thu 04/02/16

    67 Cure roof slab 7 days Fri 05/02/16 Mon 15/02/16

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 8

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    68 Strip forms fromroof slab

    2 days Tue 16/02/16

    Wed 17/02/16

    69 Form 1st floor 4 days Tue 05/01/16Fri 08/01/16

    70 Install electrical underground

    1 wk Tue 05/01/16

    Mon 11/01/16

    71 Install plumbing underground

    1 wk Tue 05/01/16

    Mon 11/01/16

    72 Install rebar and in-floor utilities

    4 days Tue 05/01/16

    Fri 08/01/16

    73 Pour 1st floor slab

    4 days Tue 12/01/16

    Fri 15/01/16

    74 Cure 1st floor slab

    7 days Mon 18/01/16

    Tue 26/01/16

    75 Strip forms from1st floor slab

    2 days Wed 27/01/16

    Thu 28/01/16

    76 Carpentry Work 15 days Thu 18/02/16Wed 09/03/16

    77 Install exterior sheathing and metal studs

    3 wks Thu 18/02/16

    Wed 09/03/16

    78 Masonry Work 110 days Thu 19/11/15Wed 20/04/16

    G.C. Labor Crew

    G.C. Rough Carpenter Crew

    Electric Contractor

    Plumbing Contractor

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    Drywall Contractor

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 9

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    79 Rough-in plumbing at toilets and masonry walls

    4 wks Fri 29/01/16 Thu 25/02/16

    80 Lay masonry at core, mechanical, and toilets

    4 wks Thu 19/11/15

    Wed 16/12/15

    81 Install exterior masonry work

    5 wks Thu 10/03/16

    Wed 13/04/16

    82 Install roof drains

    2 days Thu 14/04/16

    Fri 15/04/16

    83 Install tile in toilet rooms

    2 wks Fri 26/02/16 Thu 10/03/16

    84 Clean masonry 1 wk Thu 14/04/16Wed 20/04/16

    85 Clean toilet room tile

    1 wk Fri 11/03/16 Thu 17/03/16

    86 Roofing 31 days Thu 14/04/16Thu 26/05/16

    87 Install flashing atparapet walls

    4 days Thu 14/04/16

    Tue 19/04/16

    88 Pour lightweightconcrete roof fill

    2 days Wed 20/04/16

    Thu 21/04/16

    89 Install seamless roofing material

    5 days Fri 29/04/16 Thu 05/05/16

    Plumbing Contractor

    Masonry Contractor

    Masonry Contractor

    Roofing Contractor

    Tile Contractor

    Masonry Contractor[50%]

    Tile Contractor[50%]

    Roofing Contractor

    Roofing Contractor

    Roofing Contractor

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 10

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    90 Spread stone ballast on seamless roof

    5 days Fri 06/05/16 Thu 12/05/16

    91 Set rooftop equipment

    2 wks Fri 13/05/16 Thu 26/05/16

    92 Window wall and store front closures

    60 days Thu 14/04/16

    Wed 06/07/16

    93 Install window wall aluminum and glass

    5 wks Thu 14/04/16

    Wed 18/05/16

    94 Install interior stud walls and drywall

    5 wks Thu 19/05/16

    Wed 22/06/16

    95 Install interior doors and hardware

    2 wks Thu 23/06/16

    Wed 06/07/16

    96 Install store front doors and hardware

    3 wks Thu 14/04/16

    Wed 04/05/16

    97 Building Finishes 80 days Thu 19/05/16Wed 07/09/16

    98 Install millwork and wood trim

    3 wks Thu 23/06/16

    Wed 13/07/16

    99 Paint walls and woodwork

    4 wks Thu 14/07/16

    Wed 10/08/16

    Roofing Contractor

    HVAC Contractor

    Window Contractor

    Drywall Contractor

    G.C. Finish Carpenter Crew

    Window Contractor

    G.C. Finish Carpenter Crew

    Painting Contractor

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 11

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    100 Install conduit atceiling plenum space

    3 wks Thu 19/05/16

    Wed 08/06/16

    101 Install duct in ceiling plenum space

    3 wks Thu 23/06/16

    Wed 13/07/16

    102 Install ceiling grid

    2 wks Thu 14/07/16

    Wed 27/07/16

    103 Install ceiling tile 2 wks Thu 28/07/16

    Wed 10/08/16

    104 Hang wallpaper 2 wks Thu 28/07/16Wed 10/08/16

    105 Install building carpet

    4 wks Thu 11/08/16

    Wed 07/09/16

    106 Install hardware and accessories

    3 wks Thu 11/08/16

    Wed 31/08/16

    107 Complete interior and exterior sod andplantings

    2 wks Thu 11/08/16

    Wed 24/08/16

    108 Pave, curb, and stripe parking lot

    2 wks Thu 25/08/16

    Wed 07/09/16

    109 Elevators 40 days Thu 17/12/15Wed 10/02/16

    Electric Contractor

    HVAC Contractor

    Drywall Contractor

    Drywall Contractor

    Painting Contractor

    Carpet Contractor

    G.C. Finish Carpenter Crew

    Landscape Contractor

    Paving Contractor

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 12

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    110 Set elevator equipment in shafts

    4 wks Thu 17/12/15

    Wed 13/01/16

    111 Set equipment in mechanical room

    2 wks Thu 14/01/16

    Wed 27/01/16

    112 Test and align doors and equipment

    2 wks Thu 28/01/16

    Wed 10/02/16

    113 Plumbing 90 days Thu 21/04/16Wed 24/08/16

    114 Rough-in plumbing in drywall walls

    4 wks Thu 19/05/16

    Wed 15/06/16

    115 Tie-in fire line riser and set valves

    2 wks Thu 21/04/16

    Wed 04/05/16

    116 Set plumbing fixtures and trim

    3 wks Thu 16/06/16

    Wed 06/07/16

    117 Flush, test, and clean piping and fixtures

    2 wks Thu 11/08/16

    Wed 24/08/16

    118 Electrical 139 days Fri 29/01/16 Wed 10/08/16

    Elevator Contractor

    Elevator Contractor

    Elevator Contractor

    Plumbing Contractor

    Plumbing Contractor

    Plumbing Contractor

    Plumbing Contractor

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 13

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    119 Rough-in electrical in masonry walls

    4 wks Fri 29/01/16 Thu 25/02/16

    120 Rough-in electrical in drywall walls

    4 wks Thu 19/05/16

    Wed 15/06/16

    121 Pull wire in conduit and set area transformers

    3 wks Thu 09/06/16

    Wed 29/06/16

    122 Install and terminate electrical devices

    3 wks Thu 30/06/16

    Wed 20/07/16

    123 Make electrical terminations for HVAC equipment

    2 days Thu 30/06/16

    Fri 01/07/16

    124 Install light fixtures - test and clean

    2 wks Thu 28/07/16

    Wed 10/08/16

    125 Heating and Ventilating - AC

    180 days Thu 17/12/15

    Wed 24/08/16

    126 Set equipment in mechanical room

    2 wks Thu 17/12/15

    Wed 30/12/15

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    HVAC Contractor

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 14

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    127 Rough-in mechanical in masonry walls

    4 wks Fri 29/01/16 Thu 25/02/16

    128 Rough-in mechanical in drywall walls

    2 wks Thu 19/05/16

    Wed 01/06/16

    129 Install duct in building chase

    3 wks Thu 19/05/16

    Wed 08/06/16

    130 Set HVAC trim and test and balance system

    4 wks Thu 28/07/16

    Wed 24/08/16

    131 Final Clean-up and Occupancy

    60 days Thu 23/06/16

    Wed 14/09/16

    132 Install hard tile flooring in common areas

    1 wk Thu 23/06/16

    Wed 29/06/16

    133 Clean hard tile floors

    4 days Thu 30/06/16

    Tue 05/07/16

    134 Remove debris from building and do final clean-up

    4 days Thu 08/09/16

    Tue 13/09/16

    135 Substantial completion date

    1 day Wed 14/09/16

    Wed 14/09/16

    136 Complete Final Inspections

    6 days Wed 14/09/16

    Wed 21/09/16

    HVAC Contractor

    HVAC Contractor

    HVAC Contractor

    HVAC Contractor

    Tile Contractor

    Tile Contractor[50%]

    G.C. Labor Crew

    G.C. Superintendent

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 15

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • ID Task

    Mode

    Task Name Duration Start Finish

    137 Complete elevator inspection and certification

    3 days Wed 14/09/16

    Fri 16/09/16

    138 Perform architect's inspection

    1 day Mon 19/09/16

    Mon 19/09/16

    139 Perform local building agency inspection

    1 day Tue 20/09/16

    Tue 20/09/16

    140 Perform Fire Marshal's inspection

    1 day Wed 21/09/16

    Wed 21/09/16

    141 Complete punch list items from all inspections

    2 wks Thu 22/09/16

    Wed 05/10/16

    142 Obtain certificate of occupancy

    2 days Thu 06/10/16

    Fri 07/10/16

    143 Issue final completion documents including warranties

    1 day Thu 06/10/16

    Thu 06/10/16

    144 Issue final request for payment

    1 day Mon 10/10/16

    Mon 10/10/16

    Elevator Contractor

    G.C. Superintendent[50%],G.C. Project Management[50%]

    G.C. Project Management[50%],G.C. Superintendent[50%]

    G.C. Superintendent[50%],G.C. Project Management[50%]

    G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contractor[11%],Electric Contractor[11%],HVAC Contractor[11%],Drywall Contractor[11%],Carpet Contractor[11%],Paving Contractor[11%],Painting Contractor[11%]

    G.C. Project Management

    G.C. Project Management

    G.C. Project Management[33%],G.C. Accounting[33%],G.C. General Management[33%]

    M F T S W S T M F T S W

    12 Apr '15 07 Jun '15 02 Aug '15 27 Sep '15 22 Nov '15 17 Jan '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 16

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • G.C. General Management

    G.C. Project Management,G.C. General Management[25%]

    G.C. Project Management[25%],G.C. Scheduler

    G.C. General Management[10%],G.C. Project Management

    G.C. Project Management[50%],G.C. Procurement[50%]

    G.C. Project Management[50%],G.C. Procurement[50%]

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 17

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Steel Erection Contractor Management

    Roofing Contractor Management

    Elevator Contractor Management

    Plumbing Contractor Management

    Electric Contractor Management

    HVAC Contractor Management

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 18

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Steel Erection Contractor Management[50%],Steel Erection Contractor[50%]

    Electric Contractor

    Plumbing Contractor

    G.C. Superintendent,G.C. Labor Crew[10%]

    G.C. Survey Crew

    Site Grading Contractor,G.C. Labor Crew[10%]

    Site Grading Contractor

    Site Grading Contractor

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 19

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Site Grading Contractor

    Site Grading Contractor

    Plumbing Contractor

    Site Grading Contractor

    G.C. Survey Crew

    Site Grading Contractor[50%]

    Site Grading Contractor

    G.C. Rough Carpenter Crew

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 20

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Plumbing Contractor,Electric Contractor

    G.C. Rough Carpenter Crew

    G.C. Rough Carpenter Crew

    G.C. Concrete Crew

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew[10%]

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    Elevator Contractor

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 21

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • G.C. Concrete Crew

    Steel Erection Contractor

    Steel Erection Contractor

    Steel Erection Contractor[75%]

    Steel Erection Contractor[75%]

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 22

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Steel Erection Contractor[50%]

    Steel Erection Contractor[20%]

    G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    G.C. Rough Carpenter Crew[50%],G.C. Labor Crew[20%]

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 23

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 24

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • G.C. Labor Crew

    G.C. Rough Carpenter Crew

    Electric Contractor

    Plumbing Contractor

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    Drywall Contractor

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 25

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Plumbing Contractor

    Masonry Contractor

    Masonry Contractor

    Roofing Contractor

    Tile Contractor

    Masonry Contractor[50%]

    Tile Contractor[50%]

    Roofing Contractor

    Roofing Contractor

    Roofing Contractor

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 26

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Roofing Contractor

    HVAC Contractor

    Window Contractor

    Drywall Contractor

    G.C. Finish Carpenter Crew

    Window Contractor

    G.C. Finish Carpenter Crew

    Painting Contractor

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 27

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Electric Contractor

    HVAC Contractor

    Drywall Contractor

    Drywall Contractor

    Painting Contractor

    Carpet Contractor

    G.C. Finish Carpenter Crew

    Landscape Contractor

    Paving Contractor

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 28

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Elevator Contractor

    Elevator Contractor

    Elevator Contractor

    Plumbing Contractor

    Plumbing Contractor

    Plumbing Contractor

    Plumbing Contractor

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 29

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    HVAC Contractor

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 30

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • HVAC Contractor

    HVAC Contractor

    HVAC Contractor

    HVAC Contractor

    Tile Contractor

    Tile Contractor[50%]

    G.C. Labor Crew

    G.C. Superintendent

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 31

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Elevator Contractor

    G.C. Superintendent[50%],G.C. Project Management[50%]

    G.C. Project Management[50%],G.C. Superintendent[50%]

    G.C. Superintendent[50%],G.C. Project Management[50%]

    G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contractor[11%],Electric Contractor[11%],HVAC Contractor[11%],Drywall Contractor[11%],Carpet Contractor[11%],Paving Contractor[11%],Painting Contractor[11%]

    G.C. Project Management

    G.C. Project Management

    G.C. Project Management[33%],G.C. Accounting[33%],G.C. General Management[33%]

    W S T M F T S W S T M F T S W S T M F T S W S T M F

    22 Nov '15 17 Jan '16 13 Mar '16 08 May '16 03 Jul '16 28 Aug '16 23 Oct '16 18 Dec '16 12 Feb '17 09 Apr '17 04 Jun '17 30 Jul '17 24 Sep '17

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 32

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 33

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 34

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 35

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 36

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 37

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 38

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 39

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

    G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 40

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • G.C. Labor Crew

    G.C. Concrete Crew

    G.C. Labor Crew[10%]

    G.C. Labor Crew

    Drywall Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 41

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Plumbing Contractor

    Masonry Contractor

    Roofing Contractor

    Tile Contractor

    Masonry Contractor[50%]

    Tile Contractor[50%]

    Roofing Contractor

    Roofing Contractor

    Roofing Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 42

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Roofing Contractor

    HVAC Contractor

    Window Contractor

    Drywall Contractor

    G.C. Finish Carpenter Crew

    Window Contractor

    G.C. Finish Carpenter Crew

    Painting Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 43

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Electric Contractor

    HVAC Contractor

    Drywall Contractor

    Drywall Contractor

    Painting Contractor

    Carpet Contractor

    G.C. Finish Carpenter Crew

    Landscape Contractor

    Paving Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 44

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Elevator Contractor

    Elevator Contractor

    Elevator Contractor

    Plumbing Contractor

    Plumbing Contractor

    Plumbing Contractor

    Plumbing Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 45

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    Electric Contractor

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 46

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • HVAC Contractor

    HVAC Contractor

    HVAC Contractor

    HVAC Contractor

    Tile Contractor

    Tile Contractor[50%]

    G.C. Labor Crew

    G.C. Superintendent

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 47

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • Elevator Contractor

    G.C. Superintendent[50%],G.C. Project Management[50%]

    G.C. Project Management[50%],G.C. Superintendent[50%]

    G.C. Superintendent[50%],G.C. Project Management[50%]

    G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contractor[11%],Electric Contractor[11%],HVAC Contractor[11%],Drywall Contractor[11%],Carpet Contractor[11%],Paving Contractor[11%],Painting Contractor[11%]

    G.C. Project Management

    G.C. Project Management

    G.C. Project Management[33%],G.C. Accounting[33%],G.C. General Management[33%]

    F T S W S T M F T S W S T M F T S W S T M F T S W S

    24 Sep '17 19 Nov '17 14 Jan '18 11 Mar '18 06 May '18 01 Jul '18 26 Aug '18 21 Oct '18 16 Dec '18 10 Feb '19 07 Apr '19 02 Jun '19

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 48

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 49

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 50

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 51

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 52

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 53

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 54

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 55

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 56

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 57

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 58

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 59

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 60

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 61

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 62

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 63

    Project: Commercial Constructio

    Date: Wed 17/06/15

  • S T M F T S W S T M F T S W S T M F T S W S T M F T

    02 Jun '19 28 Jul '19 22 Sep '19 17 Nov '19 12 Jan '20 08 Mar '20 03 May '20 28 Jun '20 23 Aug '20 18 Oct '20 13 Dec '20 07 Feb '21

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 64

    Project: Commercial Constructio

    Date: Wed 17/06/15