LIBRA @35 Main challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, Petrobras Joint Venture Operator

LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Embed Size (px)

Citation preview

Page 1: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

LIBRA @35

Main challenges and solutions

Slide 1

Orlando Ribeiro, Libra Project, Petrobras

Joint Venture Operator

Page 2: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective

Pilot: Improve reservoir recovery performance by optimizing

WAG injection scheme and evaluating impact of operating

pressure on recovery. Evaluate use of higher topsides

production pressures and advanced gas management for Libra 2

Risks and challenges overcame

Operational and reservoir management scope only – Same Pilot

development concept

Potential/Captured Benefits

Initiative Leader:

José Morell (EXPCT)

WAG OPTIMIZATION

Subsurface

Optimal duration and volume of WAG cycles, WAG operating

pressure

................................................

Page 3: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective

Optimize information acquired during Exploration & Appraisal

phase, in order to minimize the number of appraisal wells and

DSTs drilled, while still maintaining an appropriate level of

information for project approval and implementation

Risks and challenges overcame

Reassessment of information acquisition x risk level balance

Contract duration of rigs and lack of termination clauses

Constraints of material availability (completion material, subsea,

trees and casing) to anticipate wells

Potential/Captured Benefits

Initiative Leader:

Ronaldo Freire

∆BE ($/bbl)

∆NW NPV (M$)

-1.31

360

Reduction of

~460 days of

EXP/Appraisal

campaign

(considering delta

between L@35

baseline and

current case)

-1.31

360

Planned Actual

................................................

APPRAISAL STRATEGY OPTIMIZATION

Subsurface

CONCLUDED

Page 4: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective

Increase Libra recovery through the application

of real time Closed Loop Reservoir Management

Risks and challenges to be overcame

Potential/Captured Benefits

Initiative Leader:

José Morell (EXPCT)

Value delivery through faster decision making & ability to

respond to reservoir behavior

Acquisition, integration and analysis of real time data

Real time Production Optimization

Development and delivery of key enabling technologies (eg,

well downhole meters)

Delivery, cost and timeline of 3rd party companies (eg,

Halliburton, Resman)

CLOSED LOOP RESERVOIR MANAGEMENT

Subsurface

..........................................

......

Optimization & Forecasting

Field Management

Field Measurement &

Monitoring

In Well Tracers Autonomous Inflow Control

Page 5: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective

Two-zone well completion with 8 ½" open hole:

Lower zone: pre-perforated liner and on-off valve

Upper zone: multi-position control valve (ICV)

Risks and challenges

Potential/Captured Benefits

Initiative Leader:

Luiz Milagre

∆BE ($/bbl)

∆NPV (M$)

-0.40

52.0

Reduction of ~7

days for 5 wells

(5-sections) and

18 days for 3 wells

(4-sections)

-0.45

58.9

Planned Actual

Less well management

latitude

Only 1 provider qualified for

annular mechanical barrier

(BMA)

Sliding sleeve – first time

used in this large bore

Completação Seletiva a poço aberto – CI 8 ½”

IC 8½ (OPEN HOLE, 2 ZONES, ON-OFF VALVE)

Wells

..........................................

......

CONCLUDED

Page 6: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

No Tie back Well No tie back Well

Tie back

Initiative Leader:

Rosane Bonelli

Description & Objective

This initiative enables construction of wells without tie back

by using different casings adequate for production by design

modifications to be evaluated in the course of this initiative

Without the use of tie back, there is a reduction in the number of

rig days and the materials to construct producer wells.

Risks and challenges overcame

Potential/Captured Benefits

Reduction of 6,4 rig days and related materials per well and

potential possibility of increase the productivity in future

large diameter initiative

Allow completion string bigger than the current of 6 5/8”

It is expected to bring savings of 54 M USD for productions

wells of Pilot by taking out tie back and material

NO TIE BACK (FOR LARGE DIAMETER COMPLETION STRING)

Wells

..........................................

......

Page 7: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Initiative Leader:

Fabio Passarelli

Description & Objective

Promoting technology competition for the GDU (Gas

Dehydration Unit) via relaxation of the water content spec in

the reinjected gas, allowing the use of either molecular sieve

or TEG (tri-ethylen glycol) technologies. Potential topside

plant weight reduction by 1500t and footprint by 210m2

Risks and challenges to be overcome

Improve TEG reliability and availability

Potential/Captured Benefits

FPSO daily rate (%) ~5.2% reduction in the

daily rate

0.4-month reduction in

the lead timeFPSO lead time (months)

TEG Unit Mol Sieves Unit

RELAXATION OF WATER CONTENT IN REINJECTED GAS

FPU

..........................................

......

Planned

Page 8: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective

Increase the separation pressure of the 1st stage to 55-65 bar

eliminating Main A compressor and reducing topside plant

power consumption by 17 MW

Risks and challenges to be overcome

Negative impacts in the oil production curves during ramp

up

Eliminate Main A. Increase VRU (Vapor Recover Unit).

Reduction in compression power (~17 MW)

Significant reduction in area

Weight reduction in 1,500 t

Main A and VRU reduced to only one module

Potential elimination of 1 (one) TG

FPSO daily rate (%) ~5.8% reduction in the daily rate

0.4-month reduction in the lead

time

Planned

FPSO lead time

(months)

Potential/Captured Benefits

INCREASE SEPARATION PRESSURE

FPU

Initiative Leader:

Fabio Passarelli

..........................................

......

Page 9: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Source: TotalOil capacity (bopd)

30.000*

25.353

24.251

22.995

22.000

19.841

19.000

19.200

16.000

16.000

14.172

18.500

14.000

13.779

13.140

12.000

11.00010.000

10.000

10.000

9.332

9.100

9.000

9.000

8.700

8.000

8.000

7.620

7.000

7.000

7.000

6.900

6.564

6.500

6.500

6.000

6.000

5.000

5.000

4.720

3.822

3.628

3.628

-

2

4

6

8

10

12

14

- 50.000 100.000 150.000 200.000

Gas

Pro

cess

. (M

Mcm

/d)

Design Oil Rate (bopd)

Bidders' conversion units (since 2003):Design Oil Rate vs. Gas Process. vs Topside Weight (dry)

*weight estimate

Libra L1 FPSO

Libra EWT

BW OffshoreTeekay

MODECSBMBumi ArmadaBlue Water

Sources: Petrobras, IHS Petrodata

Cidade de Itaguai MV26 Cidade de

Mangaratiba MV24

BW Pioneer

Tweneboa FPSO

Cidade de Angra dos Reis

MV22

East Hub

Tartaruga

Cidade de Sao Paulo MV23

Kraken

Cidade de Sao Mateus

Armada TGT1

Madura BD

FPSO Mystras

Azurite FDPSO

Espirito Santo

N'Goma (ex-Xikomba)

Aseng FPSO

Saxi-Batuque FPSO

Berge Helene

Kikeh FPSO

Cid. de Sao Vicente

Armada Sterling (ex D1)

Armada Sterling II

Stones

Cidade de Niteroi

Aoka Mizu

Baobab Ivoirien MV10

Cidade de Santos MV20

Venture 11

Capixaba

Cid. Rio das OstrasPolvo FPSO

ABO FPSO

Cidade de Paraty

Cidade de Rio de Janeiro

Mondo Yumm K'ak'naab

Cidade de Maricá & Cidade de Saquarema

Cidade de Ilhabela

Marlim Sul

Converted FPSO (since 2003)

FPSO PILOT IS AMONG THE LARGEST PRODUCTION SYSTEMS IN THE

INDUSTRY: (CONSIDERING CONVERTED UNITS)

NATURAL GAS

PROCESSING

(MMM3/D)

Page 10: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

FPU OPTIMIZATION APPROACH TO ADD VALUE

Actions within Libra 35 ProgrammeQualitative FPU complexity without opitimizations

Page 11: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

GAS PROCESSING TECHNOLOGIES

Dense Phase CO2 Separation - Hi-SepTM : gravitacional bulk CO2 separation.

Take advantages that CO2 is liquid under certain pressure and temperature.

Pilot Plant Subsea application

Conceptual studies for subsea application with:

Page 12: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

GAS PROCESSING TECHNOLOGIES

Carbon Molecular Sieve (CMC) Membranes:

more efficient membranes for CO2 separation

from natural gas

All Membrane Technology: compact gas

treatment system capable to remove H2S,

CO2 and water; Reduction in topsides

weight and FPSO cost or possible enabler to

increase plant capacity.

Partnership with:

Partnership with: Air Liquide

..........

...

Page 13: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective

Potential/Captured Benefits

Single line WAG injection

(2 XT’s connected subsea by service hub)

Reduced cost for injector wells (total of ~$300M Pilot

CAPEX reduction)

Eliminated 1 injection line for each well

Eliminated 1 umbilical for each 2 wells

No expected impact on flow assurance

Optimized subsea configuration, eliminating need of 1

injection line and enabling WAG injection (gas and water)

through a single line

Each pair of injection wells are connected to each other

through a jumper to allow pigging

Initiative Leader:

Buk (SOE/SUB/PROJ)

SINGLE-LINE WAG

Subsea

..........................................

......

CONCLUDED

Page 14: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective Risks and challenges to be overcome

FHC configuration (using conventional flexibles) may be

challenging to validate within Libra Pilot timeline, if

supplemental qualification is required for production or WAG

flexibles in FHC design.

Potential/Captured Benefits

Initiative Leader:

Andrew

∆Subsea CAPEX (M$/Pilot) -160 to -220

Reduce overall CAPEX (materials and services) by 20%-30% for

installed ´in-situ´ 4” service/RBGL, 6” WAG and 8” production

risers

Composite flexible lines (to replace conventional flexibles

currently used in pre-salt) could be ready for L3 and subsequent

Libra production units

CAPEX gains are a preliminary estimate

Estimate

Enable use of Free Hanging Catenary (FHC) flexible riser

configuration for 4” service / RBGL, 6” WAG and 8” production

risers at Libra Field

Eliminate buoyancy modules required for lazy-wave

configuration and reduce offshore installation time (up to

50%)

Less HSE exposure, simplified installation

Typical buoyancy module

presently used in pre-salt

FREE HANGING CATENARY (FHC) FLEXIBLE RISERS

Subsea

..........................................

Page 15: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective

Anticipate subsea companies engagement since the conceptual

phase of the project and capture the benefits of the new alliances

aiming 30% of CAPEX reduction

Subsea companies, by creating new alliances / merges, could

achieve CAPEX reduction based on optimization of resources and

by engaging in the project since conceptual phase

Risks and challenges to be overcome

New bidding law ("Lei 13.303") may restrict potential

Materialization of gains after proposals

Complexity in defining proper bid criteria

Lack of reservoir maturity

Complex interfaces with other disciplines

Potential/Captured Benefits

Initiative Leader:

Fábio Hoelz

∆Subsea Capex (M$) -480

Value based on Subsea companies alliances press and congress

disclosed information

Planned

EARLY ENGAGEMENT

Subsea

Page 16: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

EARLY ENGAGEMENT APPROACH WILL ONLY BE APPLIED IN LIBRA 4 -

BUSINESS MODEL TO EVOLVE GRADUALLY

Pilot Libra2 Libra3 Libra4

Flexible risers + Flexible

flowlines

Flexible risers + Flexible

flowlines

Flexible risers + Flexible

flowlines

Supplier developed concept (early

engagement)

Bid option 2

Contract awarding

Conceptual design

Bid option 1

Comments

Rigid risers +

Rigid / Flexible flowlines

Rigid risers +

Rigid flowlines

1-stage: Best bid on

Petrobras' concept

Petrobras

1-stage: Best bid on any of

the two Petrobras' concepts

Petrobras

FPSO with hybrid riser

balcony, supporting rigid and

flexible risers

1-stage: Best bid on any of

the two Petrobras' concepts

Petrobras

2-stages: Concept

development + best bid on

own concept

Supplier

In stage 2, each supplier

makes a bid on its own

concept developed on stage 1

Gains vs. Pilot

Riser sharing

Subsea

Page 17: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Description & Objective

Implement a scheme for optimizing rig schedules considering all

Libra projects.

Main objective is to reach the project demand with CAPEX

reduction by optimizing rig resource

Efficient planning can bring cost reduction

to rig procurement and avoid idleness.

Risks and challenges to be overcome

Limitation of simultaneous operation

Project approval

Adequate procurement plan

Potential/Captured Benefits

Initiative Leader:

Gustavo Viana

Avoid "Rig mobilization" fees

Improved learning curve

Improved HSE performance

Shared rigs (optimized)

Dedicated rigs (original)Optimization consists of using a pool

of rigs for multiple projects vs. 2

dedicated rigs per project

OPTIMIZE USE/SCHEDULING OF RESOURCES

Cross Function

........................

Page 18: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

TECHNOLOGY FEEDING LIBRA@35

LIBRA Technology Conveyor Belt

LIBRA Technology MappingLIBRA@35

We need to determine the

baseline Cost for

technology evaluation

Page 19: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

FINAL REMARKS Petrobras and its partners are committed with the Libra

project optimization, working together to make it

competitive in the current price scenario.

The management of the projects in a multidisciplinary and dedicated fashion has brought agility in the analyses and decisions.

Those initiatives have the potential to reduce the breakeven price by up

to US$ 12,9/bbl on NW Area incorporating the knowledge, experience and best practices from Petrobras and its partners.

Over 200 initiatives have already been raised, analyzed, ranked and 70 of

them was prioritized and are under implementation.

Beyond technical optimization, commercial and regulatory issues must also be addressed to keep projects competitive.

Ongoing engagement with technology providers / suppliers community will be intensified.

Page 20: LIBRA @35 Main challenges and solutions - · PDF fileMain challenges and solutions Slide 1 Orlando Ribeiro, Libra Project, ... Saxi-Batuque FPSO Berge Helene Kikeh FPSO Cid. de Sao

Slide 20

Thank You

FPSO Sail Away (03.28.2017)Joint Venture Operator