LHCb – Stato dell’esperimento

LHCb – Stato dell’esperimento · • Zurich swamped by sensors: IT 440/531 pcs; TT 200/1000 pcs • sensors so far of excellent quality (HPK) Beetle FEE wafer chips under test

Embed Size (px)

Citation preview

LHCb – Stato dell’esperimento

LHCb si sta materializzando al pit 8

Status of Status of ••ECAL ECAL ••HCALHCAL••GantryGantry••MagnetMagnet••Preparation workPreparation work••ScheduleSchedule

Il calorimetro elettromagnetico ha completato l’installazione

All HCAL modules have been installed in July.Beam plugs are in position.Calibration system with radioactive source has been tested.

Gantry

PS/SPD/M1 support

ECALUpper platformLower platform

HCAL platform

RICH 2 is ready for transportation, but …the special lift (from UK) will be available at CERN only mid of October

UX85 – Detector Area (Sept. 05)

FIG. 1

RIGHT SIDEIP8

LHC RingCenter

ECAL

BUNKER

MAGNET LHC CRYO

POINT 7

POINT 1

Mu-FILTERS

HCAL

RA

DIA

TIO

N S

HIE

LD

PX SHAFT

LHC BEAM AXIS

QRL8-1 junction

CA

SHIELDING PLUG

RB86

RB84

SCAFFOLDINGMF4

GANTRY

Metallic structure – Mu-System - Right

Euclid mockup performed by J.F. HERRANZ TS/LEA

Adaptation of metallic structurebehind Mu-chamber 5 (right side)

... quando ci dicono che LHC partira’ “on schedule”...

La linea criogenica in UX85 sarebbe dovuta essere completata a fine giugno (schedula di inizio 2005)

...il 12 settembre e’ partita una campagna di test che, se positiva, si concludera’ in ottobre (con circa 3 mesi di ritardo)

Pensavamo di poter iniziare il montaggio dei muri di sostegno delle camere a fine settembre. A causa di questo ritardo, tale lavoro non potra’ iniziare prima di gennaio del 2006

Ancor piu’ grave e’ che tutte le operazioni saranno compresse nel 2006 (e sono operazioni seriali) :

muri > cablaggi & gas > camere lato criogenia > camere lato c.room

con ovvio sforamento nel 2007

Un’importante scadenza e’ quella di fine luglio 2006, quando la beam pipe sara’ installata, rendendo l’accesso dal lato criogenia molto problematico. Sembra ormai molto difficile riuscire a montare tutto quel lato prima di quella data

Per la parte di nostra responsabilita’ avremo la prima parete consegnata al CERN a fine settembre e il resto del materiale pronto per la fine di ottobre

Stiamo studiando una strategia di installazione delle pareti che ci permetta di fare del lavoro preparatorio fuori dal pozzo, prima della loro installazione,Per poter poi andare spediti dopo

Velo Status

• Sensors under production (delivered sensors are ok)• Module PRR expected in beginning of Nov.• Module production start expected beginning of November• Production schedule starts with 1/wk, cranks up to 2/wk in Jan.• 46 modules to be built• Installation in the pit foreseen for

October 2006

VELO will undergo an important test beam in 2006 aiming to:

• verify alignment constants, in vacuum and in final power and cooling configuration• If necessary, correct detector positions for LHCb trigger operation• Entire half is powered, and 10 modules are read out• safety issue: that the software is sufficiently reliable to be able to move detector into LHC beams

This is THE full “rehearsal” with beam particles and the LHCbenvironment !

Sensors• Zurich swamped by sensors: IT 440/531 pcs; TT 200/1000 pcs• sensors so far of excellent quality (HPK)

Beetle FEE wafer chips under testIT/TT hybrid pre-series: some initial problems (solved)

IT Ladder production• bonding problem on pre-series pitch adapters• slightly slower startup

TT ladder production• preseries completed in July (smooth)• production started in August

IT+TT installation foreseen in July 2006

Silicon Tracker Status

Outer Tracker Status

La produzione nei vari siti sta procedendo benee si pensa di concludere la produzione deimoduli per la fine del 2005 (on schedule)

Test beam at DESY with final modules - the OT detector showed good performance:• High efficiency (>98%)• Coordinate resolution ~ 200 µm• Acceptable noise • Cross talk level (< 5%)

OT Infrastructure history

TDR : Global Movement Present : 12 independent C-Frames

Major Re-Design in the OT Infrastructure, with 12 C-Frames, rolling ducts, facilities to support IT, etc.

Consequences for time schedule and finances, working hard to minimize both…

Focus on infrastructure and installation

• C-Frames production on schedule

• Support Structure remains a concern, but we are trying hard

• First version of detailed installation plan, including personnel, available

Calorimeters Status

ECAL e HCAL installatiIl cablaggio e’ in corso Per la fine dell’anno pronti per essere calibrati con le sorgenti

I moduli di PS/SPD sono in corso di assemblaggio. La meccanica (piombo+sospensione) arrivera’ nei primi mesi del 2006

Integrazione con M1 (Annecy): sospensione, scorrimento e sviluppo del sistema di cablaggio

Elettronica in fase di completamento

Warning from refined Geant 4 simulation of background :

• New Geant 4 numbers indicate higher current in PMTs of HCAL and ECAL

• Especially true for HCAL cells close to beam => could be cured by lowering PMTs gain

• Smaller effect for ECAL but more critical => gain already very low and lowering the gain increases the electronic noise contribution…. Real measurement in 2007 !!!

Un simile risultato si ottiene nella zona piu’ interna di M2 (muoni), doveuna parte del fattore di sicurezza (x 2 @ L=5 x 10**32) e’ perso

Notizie varie

• Nella ultima LHCb week e’ stata approvata la proposta di avere un flusso di dati L0-L1-HLT sincrono (“1 MHz proposal”, vd talk Marconi) che semplifica molto il daq e lo rende potenzialmente flessibile (questo ha un moderato extracosto sul Trigger)

• Si sta organizzando il lavoro preparatorio per un Physics book ensure that we develop a plan and strategy for the first couple of

years of LHCb physicsfocus the collaboration on the preparation for physics with real data,

including work on HLTreach a better overall view of our physics potential and priorities, and

how we are going to achieve our physics goalsthe physics book should ideally be finished at the end of 2006, so that

effort can be concentrated in 2007 on the "commissioning of the calibration and analyses", and on the analyses themselves.

Items that should have priority

Production and decay models WG:sigma_bb with b J/psi X (needs luminosity)production asymmetry, e.g. B0 J/psi K*

Flavour tagging WG:sin2beta from B0 J/psi Kshort, using B0 J/psi K*0 as control

sampleProper time and mixing WG:

dms from Bs Ds pilifetimes from b J/psi X

CP measurements WG:B0 pi+pi-, CP asymmetryother b-hadron h+h- modes, including rare B0 K+K- and Bs pi+pi-

Rare decays WG:B0 K*0 mu+mu-, forward-backward asymmetryBs mu+mu-, discovery or limit

• E’ stato costituito un Commissioning Group che ha il compito di portare LHCb al pilot run.Chairman O.Callot (Orsay) + 1 persona per sottorivelatore

• In estate e’ stato fatto un esercizio per vedere l’effetto di una crescita di luminosita’ in LHCb (5x10**32 o piu’)

>> risultati molto preliminari :• i canali in mu ne beneficiano quasi linearmente (ma non si e’ ancora valutato l’aumento del background nelle zone vicino alla BP)• nei canali adronici non c’e’ miglioramento• il tagging non peggiora (ma neanche migliora)

Mancano ancora molti ingredienti (ottimizzazione dei tagli a 5x10**32, comprensione del min. b., effetti sui rivelatori) per poter dare un giudizio definitivo e comunque la questione e’ rimandata al day1quando il vero fondo sara’ misurato

Stato finanziario dell’esperimento (ksf)

Infrastrutture, Magnete, Velo, Silicon Tracker, Trigger, Calorimetri in budget

MUONI –deficit 2970 : default Brasile, extracosti 1240 CF, 185 CERN, *1545 INFN

RICH –deficit 2117 : riottimizzazione, extracosti687 CF, 614 CERN, 600 (daq)+*44 UK, 172 (daq) INFN>> nota : gli extracosti INFN sono circa 130

OT –deficit 1641 : extracosti costruzione e infrastrutture(491 CF, *229 NL, *381 D) 540 mancanti, si spera ancora di poterli riassorbire nel progetto

* sj ad approvazione f.a.

La priorita’ e’ avere tutti i rivelatori finanziati perche’ siano pronti nel 2007.

La filosofia e’ di spostare tutto il deficit sulla farm, ad oggi valutato in 1634 (su 3420, includendo anche il contributo di Syracuse di 400):- la luminosita’ integrata nel 2007 non sara’ alta (if any);- c’e’ interesse da parte di UK a reintegrare il daq;- ulteriori fondi potrebbero venire da NSF (Syracuse ha presentato una richiesta di 700 ksf per la farm online, finanziamento 2006-8)

Un ulteriore contributo potrebbe essere chiesto nel 2007, specie ai paesi che hanno contribuito proporzionalmente di meno

Questa nuova proposta di Money Matrix verra’ presentata al prossimoRRB. Vorremmo che questa commissione si esprimesse in merito

Nota: gli extracosti INFN sono “stabili” da marzo 2004

MOFB

E’ venuto il tempo dell’installazione e sembrerebbe ragionevole attivarli nel 2006.Parte dei fondi per la preparazione e il funzionamento dei lab al CERN potrebbe venire da li.

Ad oggi l’interesse e’ solo dei muoni.Va presa una decisione anche per iniziare la trattativa con CERN e PNPI.

Item che possono andare sui MOFB:• spares (rivelatori e elettronica, parte gia’ messa in CORE)• spese di installazione (consumi, manpower)• attrezzature per infrastrutture al CERN (sia per il test che per la manutenzione a lungo termine di camere ed elettronica)• aob