16
All experimenters meeting – July 7, 2014 LHC Crab Cavity Overview Tom Nicol – Fermilab All Experimenter’s Meeting July 7, 2014 1 It’s a group effort – Many thanks to Jean Delayen, HyeKyoung Park, Subashini De Silva, Rocio Olave at ODU Sergey Belomestnykh, Qiong Wu, Silvia Verdú-Andrés, Binping Xiao at BNL Zenghai Li at SLAC Ofelia Capatina, Luis Alberty, Rama Calaga, Giuseppe Foffano at CERN Tom Jones, Shrikant Pattalwar, Graeme Burt at STFC

LHC Crab Cavity Overview

  • Upload
    nuri

  • View
    36

  • Download
    0

Embed Size (px)

DESCRIPTION

LHC Crab Cavity Overview. Tom Nicol – Fermilab All Experimenter’s Meeting July 7, 2014. It’s a group effort – Many thanks to Jean Delayen, HyeKyoung Park , Subashini De Silva, Rocio Olave at ODU Sergey Belomestnykh , Qiong Wu, Silvia Verdú -Andrés , Binping Xiao at BNL - PowerPoint PPT Presentation

Citation preview

Page 1: LHC Crab Cavity Overview

All experimenters meeting – July 7, 20141

LHC Crab Cavity OverviewTom Nicol – Fermilab

All Experimenter’s MeetingJuly 7, 2014

It’s a group effort – Many thanks toJean Delayen, HyeKyoung Park, Subashini De Silva, Rocio Olave at ODUSergey Belomestnykh, Qiong Wu, Silvia Verdú-Andrés, Binping Xiao at BNLZenghai Li at SLACOfelia Capatina, Luis Alberty, Rama Calaga, Giuseppe Foffano at CERNTom Jones, Shrikant Pattalwar, Graeme Burt at STFC and Lancaster, UK

and many others...

Page 2: LHC Crab Cavity Overview

Crab Cavities

• Technical Challenges– Crab cavities have only barely been shown to work.

• Never in hadron machines– LHC bunch length requires low frequency (400 MHz)– 19.4 cm beam separation needs “compact”

(exotic) design

• Additional benefit– Crab cavities are an easy way to level luminosity!

• Currently aiming for:– Down-select ~next year– SPS test in 2015 2

LARPUK

Without some compensation for crossing angle,Reducing the b* will only increase luminosity by ~75% !

“Piwinski Angle”

Page 3: LHC Crab Cavity Overview

All experimenters meeting – July 7, 20143

Crab cavities in the LHC

Page 4: LHC Crab Cavity Overview

All experimenters meeting – July 7, 20144

Dress Cavity andCryomodule Highlights

• Initially three cavity designs.– RF Dipole (Old Dominion University and SLAC)– Double Quarter Wave (Brookhaven)– 4-Rod (UK)

• A single vendor for all US dressed cavity assemblies.• Funding source for US dressed cavities is a $1M 2013 Phase 2 SBIR award

to Niowave for the crab cavity cryomodule design and fabrication.• Niowave built the prototype for all three designs.• No dressed cavities have been built.• The cryomodule for both US cavities will be designed and built at CERN.• Goal is to have as much commonality in the cryomodule designs as

possible.

Page 5: LHC Crab Cavity Overview

All experimenters meeting – July 7, 20145

Dress Cavity andCryomodule Highlights (cont’d)

• BNL is coordinating the double quarter wave cavity design.– Bare cavity design at BNL– Dressed cavity design in collaboration with CERN

• ODU is coordinating the RF dipole cavity design.– Bare cavity design at ODU– Dressed cavity design in collaboration with Fermilab

• The tuners will be a joint effort between BNL, ODU, and CERN.• The input coupler will be provided by CERN.• In addition to being involved in the RF dipole dressed cavity

design, Fermilab will play provide oversight of fabrication at Niowave.

• Eventual need for the LHC is 32 cavities + 4 spares.

Page 6: LHC Crab Cavity Overview

All experimenters meeting – July 7, 20146

Preliminary high levelcavity and cryomodule schedule

2013-2014 2015-2016 2017 2018-2021 2022

Cavity Testing & Prototype Cryomodule

SPS Cryomodule Fabrication

SPS Beam Tests

LHC Cryomodule Construction

LHC Installation

Current focus of all groups is installation and testing in the SPS

Page 7: LHC Crab Cavity Overview

All experimenters meeting – July 7, 20147

SPS tunnel location

Cryomodule Bypass beamline

Page 8: LHC Crab Cavity Overview

All experimenters meeting – July 7, 20148

SPS tunnel location

Page 9: LHC Crab Cavity Overview

All experimenters meeting – July 7, 20149

Sample crab cavity cryomodule in the LHC

4 cm with 2 cavities each2 cm with 4 cavities each1 cm with 8 cavities

Page 10: LHC Crab Cavity Overview

All experimenters meeting – July 7, 201410

RFD dressed cavity (ODU)Waveguide HOM option

Helium vessel HOM waveguide

Input coupler

Vertical HOM

Pickup port

Dummybeam tube

Page 11: LHC Crab Cavity Overview

All experimenters meeting – July 7, 201411

RFD cryomodule (ODU)

FPC

Tuning system

Cryo jumper

Thermal and magnetic shielding not shown

Side loaded vacuum vessel

Waveguide

Beam gate valve

Cold to warm transition

Tuning frame

Page 12: LHC Crab Cavity Overview

All experimenters meeting – July 7, 201412

SPS integration

Page 13: LHC Crab Cavity Overview

All experimenters meeting – July 7, 201413

Tuner + reinforcement

beam

Space for adjacent beam pipe

HOM

FPC

HOM

Cryo jumper

Piezo + reinforcement

362.4 mm

400 mm

565 mm

DQW dressed cavity (BNL)

Page 14: LHC Crab Cavity Overview

All experimenters meeting – July 7, 201414

DQW cryomodule (BNL)

Page 15: LHC Crab Cavity Overview

All experimenters meeting – July 7, 201415

Dress Cavity andCryomodule Status

• Final designs for the RF dipole and DQW are nearly complete at ODU and BNL.

• Dressed cavity helium vessels, tuners, HOM interfaces, etc. are in process at ODU, BNL, CERN, and Fermilab.

• The initial release of data from the US labs to Niowave took place in February, final releases will take place over the next several weeks.

• Solid model and drawing data is being managed through CERN’s EDMS.

• A technical specs has been released to Niowave from CERN.• CERN will approve all drawings, material and fabrication specs,

etc. prior to manufacture.

Page 16: LHC Crab Cavity Overview

All experimenters meeting – July 7, 201416

Thanks very much