LEVI PLAZA FOUNTAIN 6”
PIPELINING PROJECT
Nu Flow America
November 2016
Dale Houts
ACCESS POINTSAfterBefore
PREPARING THE FELT LINER
Verifying Air Pressure Combine Epoxy Mixing the epoxy
SATURATING THE EPOXY INTO THE FELT
Pour epoxy into felt Score felt Saturation complete
PROCESS CONTINUED
Install air bladder into felt Tape felt to make it narrower Cont.
INSTALL THE FELT LINER
Drop liner into pipe Expand air bladder with
air pressure Seal lip with excess epoxy
EXTRACT THE AIR BLADDER
Spout access point Pump room access point
FINISHED PRODUCT
From SpoutFrom Pump Room