39
No. SARCO/MDA/708 3 rd January, 2005 Ch. Muhammad Shamim, Director MDA, Multan. Sub: CONSTRUCTION OF SOUTHERN BYEPASS, MULTAN ON B.O.T. BASIS Dear Sir, We, M/s Sh. Abdur Razzaq & Company (Pvt) Ltd.(SARCO) are involved in construction of Highways/ Bridges projects with various departments like NHA, (C&W) Punjab Highway, CDA & BRDP since last two decades. We are registered with PEC as constructor in category C-1 (NO LIMIT). Our firm is financially sound and is equipped with latest machinery. We are interested to participate in the bid of above said project on BOT basis. In this connection, we would like to propose that the required land should be acquired by MDA to avoid any legal problem to facilitate the construction work. We do hope that our proposal would be accepted in the best interest of the project. This would also be helpful for contractors to concentrate only on the construction activities. Assuring you of our best professional services all the times. Thanks & regards. (SHAHID HUMAYUN) Director, SH. ABDUR RAZZAQ & CO. (PVT.) LTD.

Letters

Embed Size (px)

DESCRIPTION

Letter

Citation preview

No

No. SARCO/MDA/708

3rd January, 2005

Ch. Muhammad Shamim,

Director MDA,

Multan.

Sub:CONSTRUCTION OF SOUTHERN BYEPASS, MULTAN ON B.O.T. BASISDear Sir,

We, M/s Sh. Abdur Razzaq & Company (Pvt) Ltd.(SARCO) are involved in construction of Highways/ Bridges projects with various departments like NHA, (C&W) Punjab Highway, CDA & BRDP since last two decades. We are registered with PEC as constructor in category C-1 (NO LIMIT). Our firm is financially sound and is equipped with latest machinery.

We are interested to participate in the bid of above said project on BOT basis. In this connection, we would like to propose that the required land should be acquired by MDA to avoid any legal problem to facilitate the construction work.

We do hope that our proposal would be accepted in the best interest of the project. This would also be helpful for contractors to concentrate only on the construction activities.

Assuring you of our best professional services all the times.

Thanks & regards.

(SHAHID HUMAYUN)

Director,

SH. ABDUR RAZZAQ & CO. (PVT.) LTD.

No. SARCO/MDA/

8th February, 2007

Ch. Muhammad Shamim,

Director Engineering,

Multan Development Authority,

Multan.

Sub:SUB MISSION OF PROPOSALS REGARDING TENDER FOR Dear Sir,

We, M/s Sh. Abdur Razzaq & Company (Pvt) Ltd.(SARCO) are involved in construction of Highways/ Bridges projects with various departments like NHA, (C&W) Punjab Highway, CDA & BRDP since last two decades. We are registered with PEC as constructor in category C-1 (NO LIMIT). Our firm is financially sound and is equipped with latest machinery.

We are interested to participate in the bid of above said project on BOT basis. In this connection, we would like to propose that the required land should be acquired by MDA to avoid any legal problem to facilitate the construction work.

We do hope that our proposal would be accepted in the best interest of the project. This would also be helpful for contractors to concentrate only on the construction activities.

Assuring you of our best professional services all the times.

Thanks & regards.

(SHAHID HUMAYUN)

Director,

SH. ABDUR RAZZAQ & CO. (PVT.) LTD.

No. SARCO/MDA/

24th August, 2007

DIRECTOR ENGINEERING,

Multan Development Authority,

Multan.

Sub:REQUEST FOR EXTENSION IN TENDER ISSUANCE DATE

DEVELOPMENT OF FATIMA JINNAH TOWN, MULTAN

Ref:Your Letter No. 3354/DE/MDA Dated 16-08-2007

Dear Sir,

In connection with the above, we hereby inform you that due to our commitments on 24-08-2007, we are unable to purchase the tender from your office.

It is therefore humbly requested that the tender may be issued in the next announced date so that we are also able to purchase the same and participate in the tender bidding.

Assuring you of our best professional services all the times.

Thanks & regards.

No. SARCO/MDA/966

24th February, 2009The Executive Engineer ll- Division,Multan Development Authority,

Multan.

Sub:MOBILIZATION OF FIRM

(Construction of Roads, Water Supply, Sewerage, Overhead Reservoir, And Boundary Wall Around The Scheme In Fatima Jinnah Town Phase-II)

Dear Sir,

The above captioned work amounting to Rs.837,875,050/- with a completion time of 24 Months, reckoned from 01-02-2009 was awarded to us vide your Acceptance Letter No. 379/DE/MDA dated 26-01-2009.

According to the stipulation of contract, we have mobilized with our full fledge workforce along with allied equipment at site w.e.f 01-02-2009, with the aim to start the work with full zeal and zests.

It is worth mentionable that still process of the acquisition of land proposed for scheme has yet not been taken up and the same could not be handed over to us to start the work. With the result, our workforce and equipment have to stand idle at site of work. The detail of our machinery and staff will be submitted latter on.

However, the keen interest and sincere interaction of MDA with the land owners regarding taking over possession of land is regarded with great appreciation. Nevertheless we would like to submit further that the arrangement of possession, free of any encumbrance, of the entire land required for the said scheme may be made without breaking stride at the earliest so that the work could be started at site and financial burden impact due to the idleness of the firms sources may be avoided/minimized please.

Assuring you of our best professional services all the time.

Thanks and regards,

(Shahid HUMAYUN)

Director,

SH. ABDUR RAZZAQ & CO. (PVT) LTD.Copy to:

Director General, Multan Development Authority, Multan

Director Engineering, Multan Development Authority, Multan

No. SARCO/MDA/

4th March, 2009The Executive Engineer-II Division,

Multan Development Authority,

Multan.

Sub:REQUEST FOR REMOVAL OF HINDRANCES AT SITE(Construction of Roads, Water Supply, Sewerage, Overhead Reservoir, and Boundary Wall Around The Scheme In Fatima Jinnah Town Phase-II)

Dear Sir,

With reference to our letter No. SARCO/MDA/966 dated 24-02-2009, we have since stand mobilized at site to take up to stipulated work. Even on lapse of one month, still we have not been handed over a considerable space except only 18 acres land to start the work physically at site. That very area of 18 acres is consisted of an old and thick mango garden through which it is not possible even to take up precise survey what to say of execution of work. The big tall trees of mango are the hindrance in the work. It is further pointed out that in the said construction area of scheme, there exists a high level water course full of running water being a root cause of stagnant water received from perculation or deliberately cut over the land to be surveyed, hence is also a hindrance in the working area. Due to the reasons as mentioned above, we are facing physical hindrances in the execution of work. It is therefore requested that pursuant to the contractual obligations, the necessary effective arrangements for removal of mango trees of heavy girth, demolishing and shifting of water course may kindly be made at the earliest so that we may proceed further without let or hindrance. Thanks & regards.

for SH. ABDUR RAZZAQ & CO. (PVT.) LTD.Copy to:

Director Engineering, MDA, Multan S.D.O, Fatima Jinnah Town Ph-II, MDA, Multan. File.No. SARCO/EE-II/MDA/MUL/

9th February, 2009

The Executive Engineer-II Division,

Multan Development Authority,

Multan.

Sub:WORK SCHEDULE (Tentative) FOR CONSTRUCTION OF ROADS, WATER SUPPLY, SEWERAGE, OVERHEAD RESERVOIR, AND BOUNDARY WALL AROUND THE SCHEME IN FATIMA JINNAH TOWN PHASE-IIDear Sir,

Enclosed please find the Work Schedule of the above cited work in pursuant to Additional Conditions No. 5 of the acceptance letter for further necessary action.Thanks & regards.

SHAHID HUMAYUNDirector,

SH. ABDUR RAZZAQ & CO. (PVT) LTD.Encl: Work Schedule (Tentative)No. SARCO/EE-II/MDA/MUL/

11th March, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:SUBMISSION OF PERFORMANCE BONDRef:Construction Of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around The Scheme In Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

Please find enclosed herewith Performance Bond No. MS-BPB-0001907-03-2009 dated 09-03-2009 for Rs. 41,893,753/- issued from Shaheen Insurance Company. Limited in favour of Executive Engineer-II, Multan Development Authority, Multan..

Assuring you of our best professional services all the times.

Thanks and regards.

SHAHID HUMAYUN

Director,

SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Encl:Performance BondNo. SARCO/EE-II/MDA/MUL/985

14th March, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:PHYSICAL OBSTRUCTIONS BEING FACED AT SITERef:Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around The Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

In response of your letter No. 301/EE-II/MDA dated 06-03-2009, we submit that it is well known to your goodself and your field staff that we stand mobilized since 01-02-2009 and we also acknowledge the possession of a parcel of land of 18 acres out of 360 acres which comes only to 05% of the required land. In this regard, your kind attention is invited to our Letter No. SARCO/MDA/ dated 04-03-2009 wherein we informed your good office about the physical obstructions being faced in commencement of work in the area acquired so far.We once again state that the even the survey work is impossible to be carried out at site what to speak of start of earth work etc.At present the major obstructions are:

i) Trees of heavy girth of mango garden.ii) Marshy area because of overflow / cut of water courses running in the area.

It is therefore, repeatedly requested that pursuant to the contractual obligations, the above mentioned obstruction may kindly be got removed from the work area as early as possible so that we may be able to take-up the survey work and then proceed further for the relevant component of works.

Thanks and regards.

for SH. ABDUR RAZZAQ & CO. (PVT) LTD.Copy to:

Director Engineering, MDA, Multan SDO-II/A, MDA, Multan. File.No. SARCO/EE-II/MDA/MUL/986

14th March, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:PROCUREMENT OF NOCs FROM DIFFERENT DEPARTMENTS Ref:Construction Of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around The Scheme In Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

It is submitted that in the construction area of the above named scheme, numerous R.O.W / constructions owned by the Govt. Functionaries other than MDA are coming in the various component of scheme. Prior to start of works at the said sites, we envisage it very necessary that the procurement of NOCs from the concerned department are the legal obligations. It is therefore requested that the concerned departments like Irrigation, Forest and Local Govt. etc. may be approached to obtain the NOCs so that the works of different nature, which are just going to be started in such areas may not be interrupted during the construction.

We hope that in this regard, a prompt action would be initiated well-on-time to avoid any complicacy arisen later on please.

Thanks and regards.

for SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Copy to:

Director Engineering, MDA, Multan SDO-II/A, MDA, Multan. File.No. SARCO/EE-II/MDA/MUL/987

14th March, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:REQUEST FOR AVAILABILITY OF CONSTRUCTION DRAWINGS Ref:Construction Of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around The Scheme In Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

We intend to start in near future, lying of sewer of 12 i/d and 27 i/d pipe lines and the relevant structures in the area yet made us available. In this regard, we are in need of Construction Drawings which should illustrate the followings:-

i) Bench Marks with RL Values.

ii) Hydraulic data of sewer lines.

iii) Manholes for 12, 18, 27 & 36 dia pipe lines.

iv) Complete drawing of 12, 18, 27 & 36 dia pipes.

v) Drawing of culverts for x-ing of 17-Kassi at Intersections. The same may kindly be made available to us at the earliest please. Thanks and regards.

for SH. ABDUR RAZZAQ & CO. (PVT) LTD.Copy to:

Director Engineering, MDA, Multan SDO-II/A, MDA, Multan. File.No. SARCO/EE-II/MDA/MUL/1021

4th April, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:REQUEST FOR TAKING IN ACCOUNT THE EXTRA COST TO BE INCURRED DUE TO EXCESSIVE LEAD OF 12~16 MILES INSTEAD OF 5 MILES FOR MAKING EMBANKMENTRef:Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

The above referred work amounting to Rs. 837,875,050/- with 24 months of completion time reckoned from 01-02-2009 was allotted to us vide letter No. 379/DE/MDA dated 26-01-2009 issued from office of Director Engineering MDA Multan.. Your attention is invited to a major item i.e. Earth work for making embankment. Originally cost of this item is estimated based on the lead of 5 miles. But on contrary to provision of estimate, no borrow area is available within this lead. As per our findings, the borrow areas for suitable soil are available a distance of 12~16 miles from site of construction. At the prevailing circumstances, the cost impact of this very heavy item on account of incorrect lead would arise as worked out on MRS-IV 2008 under here:-

Haulage cost for 5-miles lead:Rs. 3,335.80

Haulage cost for 14-miles lead: Rs. 4,018.60

Difference [4018.60-3335.80]: Rs. 682.80

Quantity:

29,798.683 %oCft.

Extra Cost [29798.683 x 682.80]:Rs. 20,346,541/-

It is therefore very humbly submitted that necessary timely action should be taken to avoid a predicted financial loss of more than Rs. 20 million as worked out above, which is apprehended to be incurred by us due to this considerable lead difference. We hope that our above narrated submission may very kindly be considered favourably and on expeditious action is taken. Thanks and regards.

for SH. ABDUR RAZZAQ & CO. (PVT) LTD.Copy to:

Director Engineering, MDA, Multan File.No. SARCO/EE-II/MDA/MUL/1024

4th April, 2009Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:REQUEST FOR HANDING OVER CONSTRUCTION AREA & SUPPLY OF CONSTRUCTION DRAWINGSRef:Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

Kindly refer to our following correspondence standing made so far on the above referred project:-i) No. SARCO/MDA/966 dated 24-02-2009 Mobilization of Firmii) No. SARCO/MDA/nil dated 04-03-2009Regarding request for removal of hindrances.iii) No. SARCO/MDA/985 dated 14-03-2009Regarding request for removal of obstructions.iv) No. SARCO/MDA/986 dated 14-03-2009Regarding request for procurement of NOCs.v) No. SARCO/MDA/987 dated 14-03-2009Regarding request for supply of Const. Drawings.We, very regretfully, express here that uptill now neither we have been responded for our grievances detailed in the above mentioned letters nor any of the site problems is resolved at yet. We once again submit that for expeditious acquisition of construction area, the process may be accelerated. It is also learnt from reliable sources that the compensation of property of locals has yet not been paid to the concerned persons. If the information is correct, then it is quite evident that possession of land will be abnormally delayed and the work could not be started physically at site for a long span in future. For supply of Construction Drawings which is within the purview of your good office, preferably a serious consideration is solicited.In view of facts stated above, we once again submit that all the grievances we are facing since the day-one are standing unresolved. The same may kindly be got resolved at an early date so that we may come in a position to take-up an encumbrance-free start and proceed onwards without further loss of time and money in the best interest of project please. Hoping for a favourable and expeditious action.

Thanks and regards.

for SH. ABDUR RAZZAQ & CO. (PVT) LTD.Copy to:

Director Engineering, MDA, Multan File.No. SARCO/EE-II/MDA/MUL/

17th April, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:PHYSICAL OBSTRUCTION

Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Ref: Your letter No. 490/EE-II/MDA dated 15-04-2009

Dear Sir,

In response of your above letter, we like to submit as under:- 1. Our survey team and MDA field staff could have jointly executed the following survey item since the last 2 months time:-

a. Southern boundary of scheme was demarcated with help of square stone located in area near Phase-I of the scheme. b. RL value of Bench Mark already established in Phase-I, was carried to the southern side of the scheme. Except the minor operations of survey work as mentioned above, no any significant survey work could has been carried-out at site because of physical obstructions yet prevailing at site. The same are once again briefly explained hereunder:-

i) Due to existence of mango trees sighting of objects is impossible.

ii) Due to non-permission to enter upon in the most of areas of scheme all kinds of work are held-up.

Contrary to informational contents of your letter as referred above, no possession except only 5% of area exists at site. Your information imparted in the said letter, seems based on some wrong speculations/misunderstandings, thus it is not possible to take over any kind of work at site until and unless obstruction-free construction area is acquired.

Under the circumstantial conditions prevailing at site, we like to suggest your good office that an urgent meeting may kindly be called for resolution of the impedimenta being faced in physical start of work at site so that the wastage of further time and money be avoided.

Assuring you of our best professional services all the times.

Thanks and regards.

for SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Copy to:

Director Engineering, MDA, MultanNo. SARCO/EE-II/MDA/MUL/

27th April, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:PHYSICAL OBSTRUCTION

Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Ref: i) Your letter No. 490/EE-II/MDA dated 15-04-2009

ii) Site visit by the Worthy D.G MDA on 20-04-2009

Dear Sir,

In context with the above cited references, we like to submit as under:-1- Removal of Mango Trees in the available area has recently been under taken by the auction holder, employing insufficient labour, thus the progress of site clearing is very slow. Anyhow our work-force is covering the site immediately by making embankment for road network in Block-J of the scheme. The work is expending accordingly as soon as the working areas are being made available to us. According to the verbal instruction of worthy Director Engineering MDA, on 21-04-2009, we intended to take possession of surrounding/adjacent land by entering upon by means of heavy machinery. In reaction, the land owners are adopting the tactics of letting their areas to be flooded daily as a barrier to enter-upon. The re-location of the water-course running through the construction area as earlier solicited vide our letter No. Nil dated 04-03-2009 is the best solution of such nuisance created by the locals. The latest circumstantial conditions prevailing at site are hereby brought in your kind notice for timely redress of the inconvenience being faced by the company since the day one of our mobilization. Hoping for an effective and prompt action please.

Thanks and regards.

for SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Copy to:

Director Engineering, MDA, MultanNo. SARCO/EE-II/MDA/MUL/1083

11th May, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:PHYSICAL OBSTRUCTION DUE TO NON-PAYMENT TO LAND OWNERS / EFFECTEES

Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Ref: Your letter No. 490/EE-II/MDA dated 15-04-2009

Dear Sir,In context with the above cited reference, we state that in view of the verbal instruction of worthy Director Engineering MDA, on 20-04-2009, to take possession of surrounding/ adjacent land by entering upon by means of heavy machinery. Yesterday we succeeded in entering upon in a land strip situated near the land already acquired. Some mischievous persons claiming themselves yet uncompensated, interrupted with violent attitude and misbehaved with our working staff. They threatened the worker and warned for serious consequences if the machinery is not withdrawn from their land forthwith. Our crew was enforced to turn back. Today, too, the same action and reaction was revealed as happened on yesterday. The most of the land owners were alleging for payment of compensation of their properties. The affectees were adamant not to allow any entry till their dues are not cleared. The incidents happened in presence of field staff of MDA who was also helpless to tackle the situation.

In addition, it is further stated that removal of auctioned mango trees is very slow, thus hindering the work badly.

In the light of the latest circumstantial conditions prevailing at site, we once again request for timely and effective remedial measures to be taken against the obstructions, so that the work could be taken up with full swing progress for timely completion and to avoid financial loss being born by the firm regarding idleness of staff and machinery etc.

Hoping for an effective and prompt action please.

Thanks and regards.

SH. ABDUR RAZZAQ & CO. (PVT) LTD.Copy is forwarded for information necessary action to:

Director General, MDA, Multan. Director Engineering, MDA, Multan.No. SARCO/EE-II/MDA/MUL/1150

19th June, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:IMPACT OF LOAD CONTROL ON MATERIAL PRICESRef:Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

Above referred contract was awarded to us vide letter No. 379/DE/MDA dated 26-01-2009 issued from office of Director Engineering MDA Multan. While bidding for this project, we quoted our price based on the input material prices prevailing in the market.

Now in previous week, NH&MP (National Highways & Motorway Police) has implemented axle load limits for trucks plying on roads. This restriction has forced the trucks to lower the load what they carry in daily routine. In consequence, this has led to hike in prices of transportation especially for quarry materials to the extent of Rs. 600/- per %Cft, thus causing a substantial increase of Rs. 6000/- per truck-load.

Since this situation has resulted into an unpredicted financial burden to us, we hereby request to your good office for compensation of this cost impact. Thanks and regards.

SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Copy to:

Director Engineering, MDA, Multan File.No. SARCO/EE-II/MDA/MUL/

21st July, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:SUBMISSION OF DETAILED DESIGN OF OVERHEAD RESERVOIR Ref:Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

Kindly find herewith enclosed the detailed Design of Overhead Reservoir for under reference project. It comprises of:1- Soil Investigation Report01 Bound Copy

2- Drawings 01 to 05

05 Nos.

3- Calculation sheets

28 Pages.

It is requested that the approval of same may very kindly be accorded at the earliest so that the activity may be started accordingly. Upon approval of the design from the competent authority, seven (07) copies will be furnished as per requirement outlined in acceptance letter.An early action in this connection is requested, please.

Thanks & regards.

Engr. Zafar Iqbal

Construction Manager,

SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Encl.As mentioned aboveCopy to:

Director Engineering, MDA, Multan File.No. SARCO/DADEX/MUL/

5th September, 2009

Mr. Riaz Ahmad Lodhi

Sales Manager,

Dadex Eternit Limited,

Multan.

Sub:QUOTATION FOR SUPPLY OF WATER SUPPLY PIPES Ref:Fatima Jinnah Town Phase-II, Multan

Dear Sir,

The above referred project has been allotted to us by MDA. For this scheme we intend to purchase water supply pipe along with accessories as specified under MRS Ch.23, Item 23. Kindly send us your best quotation for the following sizes and quantity:

Sr. No.SizeQuantity

1. 3 i/d88996 Rft

2. 4 i/d76245 Rft

3. 6 i/d23420 Rft

4. 8 i/d13380 Rft

5. 12 i/d7670 Rft

6. 16 i/d6950 Rft

An early action in this connection will be highly appreciated.

Thanks & regards.

Engr. Zafar Iqbal

Construction Manager,

SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Copy to:

File.No. SARCO/EE-II/MDA/MUL/

11th September, 2009

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:SUBMISSION OF 3RD / RUNNING BILLRef:Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

Kindly find enclosed herewith 3rd / Running Bill for the above referred project. This is for your checking, certification and further process for payment.

Your early action is highly appreciated.Thanks & regards.

(ABDUL BASIT)Project Manager,

SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Encl.As mentioned aboveCopy to:

File.No. SARCO/DE/MDA/MUL/

29th December, 2009

DIRECTOR ENGINEERING, Multan Development Authority,

Multan.

Sub:SUBMISSION OF DETAILED DESIGN OF OVERHEAD RESERVOIR Ref:Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

Please recall that above referenced project was allotted to us vide your office letter No. 379/DE/MDA dated 26-01-2009.Now in this respect for issuance of cheques from MDA against our due payments, we hereby submit that:

1- All payments should be made by issuing cheques in favour of M/s Sh. Abdur Razzaq & Co. (Pvt) Ltd. like Mobilization Advance payment (Bill # 1 & 2), Bill # 03 and Bill # 04 payments (copy of 4 No. cheques enclosed).OR

2- For payments against workdone for sewerage work items 100 to 117 & 121, cheques may be issued in favour of N.A. Builders as we have already agreed mutually on date 08-12-2009 (copy enclosed).

OR3- All future payments be made by issuing cheques for 75% amount in favour of M/s Sh. Abdur Razzaq & Co. (Pvt) Ltd. and for 25% amount in favour of M/s N.A. Builders as per respective share in joint venture (copy enclosed). In view of the best interest of the project and to keep good relationships with all stake holders we hereby submit our agreement to accept any of the above mentioned three options. This is for your kind information and appropriate action at your end, please

Thanks & regards.

SHAHID MEHMOODDirector,

SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Encl: As aboveCopy to:

Executive Engineer-II, MDA, Multan.

Director Accounts, MDA, Multan.

No. SARCO/EE-II/MDA/MUL/1507

03rd Aug, 2010

Executive Engineer-II,

Multan Development Authority,

Multan.

Sub:COMPLETION OF EARTH WORK OF ROADS IN THE HANDED OVER AREAS OF SCHEME Ref:Construction of Roads, Water Supply Sewerage, Overhead Reservoir and Boundary Wall Around the Scheme in Fatima Jinnah Town Phase-II (Part-I) on Vehari Road Multan

Dear Sir,

It is submitted that for above cited scheme, we since the date of commencement to date have been handed over 65 % of entire working area. In this working area, the earth work of roads net work has almost been completed by us. Our unit of labour and equipment deployed on earth work of roads is going to be idle within a weeks time or so.

Now it is requested that we may kindly be informed about handing over of the remaining 35% areas or otherwise should we demobilize our said unit from the site of work as we cant afford it sitting idle.

Your are requested for an early response in this regard so that we may proceed further accordingly please.Thanks & regards.

(Muhammad Shabbir Malik)Project Manager,

SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Copy to:

Director Engineering, MDA, Multan File.No. SARCO/DADEX/MUL/

18th August, 2010Mr. Riaz Ahmad Lodhi

Sales Manager,

Dadex Eternit Limited,

Multan.

Sub:2nd PURCHASE ORDER FOR SUPPLY OF WATER SUPPLY PIPES Ref:Fatima Jinnah Town Phase-II, Multan

Dear Sir,

We would like to place a purchase order for water supply pipes as described below:

Sr. No.SizeQuantity

1. 3 i/d 16,330 Rft

2. 4 i/d 10,310 Rft

3. 6 i/d 2,750 Rft

4. 8 i/d 3,110 Rft

5. 16 i/d3,240 Rft

(Note: 5% extra sockets required)

Please deliver the merchandise at following address:

Sh. Abdur Razzaq & Co. Site Camp at Fatima Jinnah Town Phase-II, Vehari Road, Multan.Contact Person Muhammad Tariq (0300-6364465, 0300-7816995)

Thanks & regards.

SH. ABDUR RAZZAQ & CO. (PVT) LTD.

Copy to:

File.