Lessons Learnt and Experience Sharing

BY

JAMIL AHMED BASRA

DISTRICT OFFICER ROADS GUJRANWALA

ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF)

UNDE PCGIP

Page 3: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

• Contents• Schemes of F.Y 2013-014• Implementation of ESMF 2013014• Lesson Learnt and Experience Sharing

3

Page 4: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

PROGRESS OF YEAR FY 2013-14

Page 5: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

5

NO NAME OF SCHEME EXPENDITURE STATUS

1Repair / Rehabilitation of Gujranwala Hafizabad Road from GT Road Sheranwala Bagh to Alam Chowk Western Bye Pass (Section Niyian Chowk to AryWalaChowk and Baghbanpura Chowk to Gala Gartallian (Length = 4.36 Kms)

48.912 Million Completed

2Repair / rehabilitation of Gujranwala Haifzabad Road from Araya Wala Chowk to Alam Chowk Western Bypass (Construction of Centre median and providing and fixing street light. (Length = 3.08 Kms)

30.309 Million Completed

3Repair/Rehabilitation, Providing / fixing LED lights in place of sodium street lights from G.T. Road chan Da Qila to NigarPathak Gujranwala. 18.393 Million Completed

4Repair /Rehabilitation of Jinnah Road from GT road to Shamsi Chowk.Including Gill Road & DC road 13.856 Million Completed

5Repair/rehabilitation of road shamsi chowk to g.t.road (dps school) via railway crossing length=2050 rft or 0.63 km. 8.353 Million Completed

6Repair/rehabilitation of church road from sailkot road to commissioner office chowk length=0.41 km. 4.188 Million Completed

7Repair/rehabilitation of college road from sialkot road to (h.f.c) satellite town market length=1547 rft or 4.7 km. 9.220 Million

Completed

SCHEMES OF FY 2013-14

Page 6: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

6

NO NAME OF SCHEME TOTAL EXPENDITURE STATUS

8Repair/rehablitaion of road from munir chowk to old session court road

2.798 Million Completed

9Repair / Rehabilitation of Road from Civil Line National Bank Chowk to RPO Office chowk 7.831 Million Completed

10Repair/Rehabilitation of Road from Sialkot Road to Jinnah Stadium chowk in City Gujranwala 9.495 Million Completed

11Repair / Rehabilitation of Road from CPO Office Chowk to MunirChowk Trauma Center 7.863 Million Completed

12 Repair / Rehabilitation of road from Commissioner Office to Civil Lines Police Station in City Gujranwala 6.026 Million Completed

13Improvement / rehabilitation of G.T. Road in mile No. 41 (Construction of Slip Road at Sheikhupura More Gujranwala) 2.818 Million Completed

14 Repair/Rehabilitation of Road around Jinnah Stadium Gujranwala 9.087 Million Completed

15 Repair/rehablitaion of flyover road towards Sialkot road Gujranwala L= 1020 RFT 3.380 Millions Completed

16Repair / Rehabilitation of College Road from Kashmir road (Near Sasta Bazar) to upper chanab canal people colony Gujranwala (Length = 2300 Rft) 9.229 Million Completed

17 Restoration of street lights and traffic signal in Gujranwala city.  9.512 Million Completed

SCHEMES OF FY 2013-14

Page 7: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

IMPLEMENTATION OF ESMF (2013-014)

Page 8: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

IMPLEMENTATION OF ESMF (2013-014)

Environmental and Social Survey of PCGIP/EEPs schemes and Public Consultation

Page 9: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

APPLICATION OF ESMF

Environmental and Social Screening: Environmental and Social Screening of PCGIP and ADP schemes was

carried out.

Environment and Social Management Plans: Prepared Environmental and Social Management Plans (ESMPs) for

each scheme of E-2 category. EPA, Punjab accorded approvals.

ESMP cost was included in Procurement plan and Bidding Documents Training session held with contractors in Gujranwala on April 19, 2014

Page 10: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

APPLICATION OF ESMF (CONTI….)

Environmental and Social Monitoring: Monitoring Team (Do, Environment, DO, Social Welfare,

Env & Social Safeguard Specialist & Monitoring and Evaluation Specialist), focal persons conducted environmental and social monitoring of E-2 schemes to ensure effective implementation of the mitigation measures included in the ESMP

Site visits, photographic records, public consultation at each step, Lab analysis and development of monitoring report) .

Monitoring was conducted with the help of checklists.

Page 11: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE
Page 12: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE
Page 13: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

APPLICATION OF ESMF (CONTI….)

Third Party Validation: For an independent assessment of the ESMF implementation, was

held in Gujranwala on 3-5 July 2014. TPV team visited following 05 schemes of CDG-G.

1. Repair / Rehabilitation of Gujranwala Hafizabad Road from GT Road Sheranwala Bagh to Alam Chowk Western Bye Pass (Section Niyian Chowk to Ary Wala Chowk and Baghbanpura Chowk to Gala Gartallian

2. Repair/Rehabilitation of Jinnah Road From G.T.Road to Shamsi Chowk I/C Gill Road & DC Road, Gujranwala

3. Repair/Rehablitaion of Road from Munir Chowk to old Session Court Road

4. Repair / Rehabilitation of Road from Civil Line National Bank Chowk to Commissioner

Office

5. Rehabilitation of Road from Sialkot Road to Jinnah Stadium Chowk, City Gujranwala

Page 14: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

Lesson Learnt and Experience Sharing• General public and residents of the city are satisfied and happy for R & M

of Roads from PCGIP funds

• For small schemes like R& M and District ADP Schemes, general public and local community were not involved before PCGIP/ESMF

• Due to Public Consultation the moral of inhabitants is enhanced for Government Departments, especially works and Services Department

• Eventhough there is legislation for mitigation of environmental issues raised during development of ADP Schemes, but there was no implantation of Environmental laws due to non awareness.

• Due to frequent training sessions organized by the Urban Unit, we are now familiar with Punjab Environmental Protection Act 1997 (Amended 2012), Environmental Impact assessment and (EIA) Initial Environmental Examination

• CDG also implementing ESMF on its ADP Schemes, which is helping for sustainable development

Page 15: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

• Labours are providing training regarding use of Personal Protective Equipments (PPEs) and implementation of Social & Environmental Management Guidelines.

• The labour/workers are provided with following Personal Protective Equipments (PPEs) during scheme execution:

•  Safety Masks

• Safety Helmets

• Safety Shoes

• Gloves

• Safety Jackets

• Safety Glasses

• Ear Plugs/Ear Muffs

•  First aid in case of injuries

• Emergency Contact Nos. are al so displayed at site areas

Page 16: Lessons Learnt and Experience Sharing BY JAMIL AHMED BASRA DISTRICT OFFICER ROADS GUJRANWALA 2 ENVIRONMET AND SOCIAL MANAGEMENT FRAMEWORK (ESMF) UNDE

Environmental and social Screening of R&M schemes, which was not carried out before PCGIP

Environmental and social monitoring of schemes by ESMF Committee during execution, which was not done before PCGIP

Gender issues is a problem during public consultation

Due to Consolidated ADPs , so many problems are being resolved

Over all there is a positive impact on environment of the city due to implementation of ESMF