20
1 Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges, President Process Improvement Institute, Inc. (PII) 1321 Waterside Lane Knoxville, TN 37922 Phone: (865) 675-3458 Fax: (865) 622-6800 e-mail: [email protected] 2014 © Copyright reserved by Process Improvement Institute, Inc. Prepared for Presentation at 10 th Global Congress on Process Safety New Orleans, LA March 31-April 2, 2014 Keywords: layer of protection analysis, LOPA, independent protection layer, IPL, initiating event, PFD, IEF Abstract LOPA has been implemented throughout major capital projects, on existing facility PHAs, and in PHA revalidations and management of change risk reviews. This paper discusses lessons learned for implementing LOPA in each phase of a process lifecycle and outlines some of the ways to optimize the use of LOPA. The paper describes how implementation of standards for IPLs and initiating event maintenance is necessary in each company. The paper also covers consolidation of SIL evaluation into the related PHA and LOPA at each life cycle phase. Special emphasis is given to optimizing the application of LOPA and SIL evaluation through the various phases of a major capital project.

Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

1

Lessons Learned from Application of LOPA throughout the

Process Lifecycle

William G. Bridges, President

Process Improvement Institute, Inc. (PII)

1321 Waterside Lane

Knoxville, TN 37922

Phone: (865) 675-3458

Fax: (865) 622-6800

e-mail: [email protected]

2014 © Copyright reserved by Process Improvement Institute, Inc.

Prepared for Presentation at

10th

Global Congress on Process Safety

New Orleans, LA

March 31-April 2, 2014

Keywords: layer of protection analysis, LOPA, independent protection

layer, IPL, initiating event, PFD, IEF

Abstract

LOPA has been implemented throughout major capital projects, on

existing facility PHAs, and in PHA revalidations and management of

change risk reviews. This paper discusses lessons learned for

implementing LOPA in each phase of a process lifecycle and outlines

some of the ways to optimize the use of LOPA. The paper describes

how implementation of standards for IPLs and initiating event

maintenance is necessary in each company. The paper also covers

consolidation of SIL evaluation into the related PHA and LOPA at each

life cycle phase. Special emphasis is given to optimizing the application

of LOPA and SIL evaluation through the various phases of a major

capital project.

Page 2: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

2

1. Brief History of LOPA

The initial development of layer of protection analysis (LOPA) was done internally

within individual companies. However, once a method had been developed and refined,

several companies published papers describing the driving forces behind their efforts to

develop the method, their experience with LOPA, and examples of its use (Bridges,

19971; Dowell, 1997

2; Ewbank and York, 1997

3). In particular, the papers and discussion

among the attendees at the October 1997 CCPS (Center for Chemical Process Safety, part

of AIChE), International Conference and Workshop on Risk Analysis in Process Safety,

brought agreement that a book describing the LOPA method should be developed.

In parallel with these efforts, discussions took place on the requirements for the design of

safety instrumented systems (SIS) to provide the required levels of availability. United

States and international standards (ISA S84.01 [1996], IEC [1998, 2000])4,5,6

described

the architecture and design features of SISs. Informative sections suggested methods to

determine the required safety integrity level (SIL), but LOPA was not mentioned until the

draft of International Electrotechnical Commission (IEC) 61511, Part 3, which appeared

in late 1999. These issues were summarized in the CCPS workshop on the application of

ISA S84, held in 2000.

The first LOPA book was developed by a CCPS committee from 1997 through 2000 and

was published in 20017 (William Bridges and Art Dowell were the two co-originators and

principal authors of the book). LOPA became widely used following the publication and

most companies around the world have used LOPA, with some companies having used

LOPA a lot. During roughly 15-years of widespread use of LOPA, and especially during

the last 10-years, use of LOPA has greatly accelerated. It is likely that several million

LOPAs have been performed. During this same period, many abuses of LOPA have

been noted and several innovations have occurred.

In 2007, CCPS commissioned a new guideline book (1) to expand the list of independent

protection layers (IPLs) and initiating events (IEs) and (2) to try to remedy some of the

major issues noted in the use of LOPA. The new book is discussed in another paper at

this conference; this book is due into publication this year (2014; William Bridges was

the primary contractor/author of this book until April 2012). Another companion book

on the related topics of conditional modifiers and enabling events and conditions was

published in 2013 (Mr. Bridges was committee member and contributed to this book as

well).

2. Intent of LOPA

LOPA is one of many methods for assessing a given scenario to determine if the risk is

acceptable. It uses rigid rules to simplify and standardize the definitions of independent

protection layers (IPLs) and initiating events (IEs). If these rules are followed, then the

simplified risk assessment math of LOPA is valid and the risk assessment should give an

order-of-magnitude approximation of the risk of a given cause-consequence pair

Page 3: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

3

(scenario). The rules also cover the minimum criteria for maintaining features and task

executions that relate to IEs and IPLs.

LOPA is only one option for judging risk. The most common and still the best method

for judging the risk of most scenarios is the process hazard analysis (PHA) team; their

judgment is qualitative, but the “fuzzy” math of the individual team members usually

coalesces into excellent judgment of risk for nearly all accident scenarios.

3. Relationship to SIL determination

LOPA started with and continues to have a unique relationship with SIS, and particularly

to SIF identification and SIL assignment (sometimes called SIL determination). Some of

the originators of LOPA needed LOPA to defend against an arbitrary assignment of

safety instrumented functions (SIFs) for systems that were already “adequately”

safeguarded by other means. This became apparent in the mid-1990s with the early

development of SIS standards within chemical companies and by (at that time) the

Instrument Society of America (ISA). Some of these early standards would have

imposed a minimum SIL for a given consequence, without much regard for the number

and value of other IPLs that already existed or were viable alternatives to the SIFs. Much

of these arbitrary requirements for SIS have disappeared, but some remain.

For the most part today, LOPA is seen as one tool (in many parts of the world, the

preferred tool) for determining if a SIF is necessary and if it is the correct choice of risk

reduction; and LOPA is the preferred method for determining what SIL is necessary, if an

SIF is chosen as the risk reduction method. With that said, PHA teams are also allowed

by IEC 61508, 61511, and related TR from ANSI/ISA to make these same

determinations. Per ISA TR 84.00.02, 2002 (and 2004), Section 3.88:

A qualitative method may be used as a first pass to determine the required SIL of

all SIFs. Those which are assigned a SIL 3 or 4 by this method should then be

considered in greater detail using a quantitative method to gain a more rigorous

understanding of their required safety integrity.

However, some organizations use LOPA to answer the question: “What SIL is needed to

lower the risk to the risk target?” without first asking, “Are we at tolerable risk already?”

or “Are there better alternatives for lowering the risk?” This leads to a huge over-

specification of SIFs (and the wasting of resources to design, implement, and maintain

these SIFs) and to many spurious shutdowns of units (which also waste money and

increase the risk of accidents that can occur during re-start of the process).

NOTE: As stated in all books and papers on the topic, LOPA does not find accident

scenarios. Typically only the qualitative hazard evaluation methods (such as

HAZOP, What-if, and FMEA) can find new accident scenarios.

Page 4: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

4

Note that the system (loop) boundary for an instrumented safety system is defined

differently by SIS standards versus LOPA (see Figure 1). As illustrated below, the

system boundary for calculating the SIL for a given SIF includes only the instrumented

components of the system. This omits the systemic failures possible from the process

itself and more importantly omits the specific human errors of leaving the system in

bypass or dependent errors of mis-calibrating multiple sensors in high SIL SIFs. LOPA

however, requires that the system boundary for any IPL include all aspects of the IPL.

This difference in system boundary definitions can make the difference between an SIF

being a SIL 1 or a SIL 3 (installed predicted performance versus instrument only

reliability).

Figure 1: Boundary for SIF (courtesy of Process Improvement Institute, Inc.)

4. When to Use LOPA (in general)

The originators thought LOPA would be used a lot less frequently than it is currently. As

shown in Figure 2, it was anticipated that LOPA would be used on 1-5% of the scenarios

uncovered in PHAs. It was also anticipated that LOPA would eventually be used “after”

a PHA team meeting, since that is how the originators were using it. Various examples

of overuse are discussed below (Bridges 200710

, discussed these issues in detail):

Using LOPA within PHAs - a bad idea as it detracts from brainstorming. Many

of us on the original LOPA book authorship considered LOPA a single analyst job,

after a PHA/HAZOP, for just a few scenarios (maybe after 100 HAZOP nodes, you

Page 5: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

5

would do 1-10 LOPA). Instead, the trend appears to be that companies (or perhaps

their consultants) make LOPA part of the PHA (in-situ). If the PHA/HAZOP team is

properly disciplined on what qualifies as a safeguard (a qualitative definition of an

IPL from LOPA), then performing LOPA in situ is usually overkill. In most

situations, a qualitative team (HAZOP team) can make just as good or better

judgment than provided by LOPA. LOPA is just another way to make a decision, has

many pitfalls, and doesn’t work for many types of scenarios. Other issues with use of

LOPA within a PHA setting is that it distracts the team from brainstorming and it

adds to team burnout because it takes time away from what is critical for the PHA

team to do: Identify scenarios for ALL modes of operation.

Use for every Medium and High Risk Scenario -- Like in the point above,

increasing the number of scenarios that must go through LOPA, reduces the resources

available to find (in a PHA/HAZOP/What-if) the undiscovered scenarios and to

manage existing layers of protection.

When to use LOPA The following is the guide we use to decide when a LOPA is

required (Category 6 is equivalent to consequences greater than $100,000,000 and/or

with potential multiple fatalities):

Page 6: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

6

FIGURE 2: When to use LOPA (courtesy of Process Improvement Institute, Inc., 2004)11

Page 7: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

7

4.1 Hazard Evaluation at Different Plant Lifetime Stages

Process hazards can be identified from the onset of a project through its end (or

assimilation into another project), and process hazards of changes are evaluated in mini-

PHAs during the operating phase of the lifecycle. Hazard evaluations are also required

for decommissioning. Industry has found that hazard evaluation must be used in all

phases of a unit life cycle to ensure safe operations.

As usual, LOPA can be used in conjunction with any of these hazard evaluations to help

estimate the risk of selected scenarios.

The following plant lifetime stages will be used in this section:

Process development (perhaps several hazard evaluations during lab and pilot

phases)

Capital Projects

o Conceptual and Preliminary design (1-2 hazard evaluation phases)

o Detailed design (1-3 hazard evaluation phases)

o Construction and start-up (completion of the initial and post-startup PHA)

Operating lifetime (revalidations and MOC risk reviews)

Extended shutdowns

Decommissioning

4.2 Process Development Phase (Technology Phase) of Lifecycle

During the process development phases, various hazard reviews are necessary to help

understand the risks and more and more is known of the chemistry and operations.

HAZOP, What-if, and checklists are very useful during process development.

4.3 Major Capital Project Phase of Lifecycle

There are various sizes and structures of projects, depending on the scope of the

endeavor, the urgency, the nature of the business, the company culture, the company

sophistication, and many other factors. The two most important project types (factors)

for purposes of this paper are (1) project size (expressed usually in expenditure expected

or size and number of pieces of equipment to be installed) and (2) type of financial

control for the project.

LOPA may be required for selected scenarios during normal, startup, switch-

overs, modifications, etc., especially for large pilot plants.

Page 8: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

8

4.3.1 Typical Project Sizes:

Table 1 below provides a basic definition of projects sizes and the typical number of risk

reviews conducted during the project:

Table 1: Project Size/Scopes, Relative Project Length, and Risk Review Effort

Project Size Example Project Scope Example Project

Length/Duration (concept commissioning)

Number of

Risk Reviews

Major

Major projects handled external to an

affiliate/plant, such as expansions and

new facilities

12-36 months 4-7

Moderate

Works engineered by an affiliate/

plant (installing a new design of

knockout pot for a feed to a unit)

6-9 months 2-3

Small Minor affiliate/plant works (installing

piping to bypass a control valve) 1-2 months 1

4.3.2 Scope of Risk Reviews and PSM Development For Each Project Phase

As mentioned earlier, major projects can have 4 to 7 or more phases and these can be

spread over 12 months to 36 months or more depending on the project size. However,

decisions for controlling risk made during the project phases echo through the next 20 to

50 years of operation, because design features, automated control features, and human

interactions must be managed continuously to control the inherent hazards of chemical

processes.

Figure 4 presents an example of a major capital project’s phases for a large new

chemical process unit or plant, with six “in-project” phases and one “post-project” phase.

Though not universal, this approach appears to be a widely accepted view of major

project phases. For smaller projects, condense this approach to 5, 4, or a minimum of

two phases. Table 2 on the following pages provides much more detail on the risk

review for each project phase.

Note the six hazard evaluations (risk reviews) that are required. The six build on the

prior risk review; at the end, the site has a complete PHA/HAZOP for use as the initial

PHA for the new process. Further note that LOPA would only be used on the middle 3-4

hazard reviews, and only for scenarios that the PHA/HAZOP team has trouble in making

tolerable risk decisions.

Page 9: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

9

Phase 1

Conceptual

Design

Phase 2

Feasibility &

Detailed

Specification

Phase 3

Preliminary

Design

Phase 4

Detailed

Design

Phase 5

Construction

Phase 6 Pre-

Commissioning

Phase 7Post-

Commissioning

Fit to business

strategic plan

Fit to existing

operations

Review of

available

technology

Inherent safety

options

Site planning

Raw material

resourcing options

Detailed feasibility

study (availability of

technical staff;

marketing plan)

Detailed technology

review and

specification

development

Preliminary plot plan

and tie-in plan

+/- 40% cost

estimate

Preliminary

schedule &

milestones

Conceptual RR

Strategic plans

Inherent safety

Plot plan review for

Facility Siting;

consequence

modeling for major

releases

Begin Human

Factor

consideration

Project ResponsibilityPlant/Unit

Responsibility

Preliminary

construction &

operation plans

Initial process flow

diagrams (PFDs)

Initial material and

energy balances

Raw material

planning

Utility planning

Candidate vendors

for major

components

Fire protection plan

Process design and

generation of Rev 0

P&IDs; continuing to

Rev 5 (nominal) in

this phase.

Revise material &

energy balance

Technical specs for

all components

Basics design of

process controller

Fabrication started

and major

components

ordered

Execute fabrication

and installation plan

Develop detail plans

for tie-ins to OSBL

Continue to develop

specs for OEM

manuals and

operating

procedures

Set up CMMS/

database for ITPM

Draft PSM

management

systems/procedures

Complete

fabrication/

installation

Complete

development and

closure of PSSR

and other punchlists

Commission/

validate equipment

(dry, wet, with HHC)

Populate CMMS

and other PSM/

reliability databases

Complete operating

and MI procedures

(by SMEs); validate

Assist

commissioning team

Ensure training by

vendors/OEMs are

completed in the

field and proficiency

of plant staff is

validated

Complete

performance

measure of initial

operation (to ensure

contract

commitments are

met)

Manage changes

Closeout project

Preliminary

Design RR

What-if analysis of

each major unit

operation

HAZOP/FMEA of

selected scenarios

LOPA of selected

scenarios & review

options for inherent

safety

Detailed Design

RR

HAZOP/FMEA of

most nodes

(focusing on

continuous mode of

operation)

LOPA of 1-5% of

scenarios

Final SIL (if needed)

determination

Final Detailed

Design RR

HAZOP/FMEA of

changes since

previous RR,

including rec.

resolutions; place

special attention to

changes in field

Begin human factor

and facility siting

(HF&FS) checklists

Commissioning

RR (“Initial PHA

for new unit”)

HAZOP/FMEA of

changes

HAZOP and/or

What-if of non-

routine operating

modes (startup,

emergency

shutdown, etc.)

Complete HF&FS

checklists

Post-Startup RR

(3 to 6 months

after startup)

Close any

recommendations

that were rated as

post-startup issues

Review each MOC

for its impact on the

“Initial Unit PHA”

Perform critique of

risk review efforts

during project.

Ris

k R

ev

iew

sP

roje

ct

Co

nc

ern

s a

nd

De

liv

era

ble

sFigure 4: Example Project Phases and Related Scope of Risk Reviews (RR), which

in this instance means the same as hazard evaluation12

Page 10: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

10

Table 2: Details of Process Safety Development Phases of a Major Capital Project (with LOPA highlighted)12

Project Phase

#

Phase Name

Goals of RISK REVIEW RISK REVIEW Methodology RISK REVIEW Team Membership

(in addition to leader & scribe)

1&2 Conceptual Choose inherently safer option, ensure overall feasibility, estimate impact on neighbors

Consequence modeling (to help on next project phase)

What-If (no guidewords)

Selected checklist for judging inherent safety

Senior operator for unit or from similar unit

Senior process engineer for unit or from similar unit

Process/design engineer from project

Process Safety specialist (if not already listed above)

3 Preliminary Design

Identify and resolve most expensive design alternatives, including layout of plant, facility siting concerns, environmental protection issues, and major tie-ins

What-If (no guidewords)

HAZOP/FMEA of selected scenarios

LOPA of selected scenarios (note

that sufficient information for LOPA

will likely be missing for 20-30% of

accident scenarios at this phase)

Senior operator for unit or from similar unit

Senior process engineer for unit or from similar unit

Process/design engineer from project

Process Safety specialist (if not already listed above)

Possibly I&E Engineer

LOPA should be performed by a single analyst

4 Detailed Design

Begin detailed identification of potential accident scenarios, primarily focused on normal (usually continuous) mode of operation. Begin risk assessment for scenarios with large residual risk

HAZOP/FMEA of equipment nodes, focusing on normal (usually continuous) mode of operation

What-If of lower consequence & lower complexity systems

LOPA of 1-5% of the scenarios; determine SIL, as necessary

Senior operator for unit or from similar unit

Senior process engineer for unit or from similar unit

Process/design engineer from project

Process Safety specialist (if not already listed above)

Possibly I&E Engineer

Possible vendor of unique equipment

LOPA should be performed by a

Page 11: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

11

Project Phase

#

Phase Name

Goals of RISK REVIEW RISK REVIEW Methodology RISK REVIEW Team Membership

(in addition to leader & scribe)

single analyst

5 Final Design

Update results of previous RR for new details, identify potential accident scenarios for nodes not previously reviewed, primarily focused on normal (usually continuous) mode of operation. Resolve most previous recommendations Complete risk assessment for scenarios with large residual risk

Complete HAZOP, FMEA, or What-If for nodes started in previous RR

Perform HAZOP, FMEA, What-If for nodes not covered in previous RR (due to previously missing information)

Begin Human Factors and Facility Siting checklist

Perform general Utility Failure checklist

LOPA of 1-5% of the scenarios; determine SIL, as necessary

Senior operator for unit or from similar unit

Senior process engineer for unit or from similar unit

Process/design engineer from project

Process Safety specialist (if not already listed above)

Possibly I&E Engineer

Possible vendor of unique equipment

LOPA should be performed by a single analyst

6 Commis-sioning

Conduct full hazard/risk review of operating procedures to control risk of errors during startup, shutdown, emergency shutdown, and other non-routine modes of operation Close out previous RISK REVIEW issues (from earlier phases of project) and complete the human factors & facility siting checklist This RISK REVIEW creates the “Initial PHA” of the process

HAZOP (2 guideword or 8 guideword) or What-If (no guideword) of operating procedures (choose method based on hazard and complexity of each task)

Complete HAZOP, FMEA, or What-If for nodes started in previous risk reviews

Perform HAZOP, FMEA, What-If for nodes not covered in previous risk reviews (due to previously missing information)

LOPA of 1-5% of the scenarios; determine SIL, as necessary

Complete Human Factors and Facility Siting checklist

Senior operator for unit or from similar unit

New/junior operator for unit

Senior process engineer for unit or from similar unit

Process/design engineer from project

Process Safety specialist (if not already listed above)

Possibly I&E Engineer

LOPA should be performed by a single analyst

7 Post-Startup

Conducted 3-6 months after startup similar to the future Revalidations, but with the goal of compensating for

Audit of MOCs (and P&IDs and SOPs) since “Initial PHA” (since commissioning RR) to ensure nothing has been missed by MOC

Senior operator for unit or from similar unit

New/junior operator for unit

Senior process engineer for unit or

Page 12: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

12

Project Phase

#

Phase Name

Goals of RISK REVIEW RISK REVIEW Methodology RISK REVIEW Team Membership

(in addition to leader & scribe)

weaknesses in MOC process at the initial startup of the new unit/process

HAZOP or What-If of missed or poorly reviewed changes

Update PHA for the entire set of changes (looking at whole picture for effect of all changes)

Close any pending recommendations (if possible)

from similar unit

Possibly project/design engineer (for QA of project)

Page 13: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

13

4.3.4 Risk Control – Initial Phases of a Major Capital Project

As described in Figure 4 and Table 2, the first two project phases are critical for

establishing the inherent safety of the process, and therefore an opportunity for company

leadership to show their true colors.

4.3.5 Risk Control – Detailed Design Phases of a Major Capital Project

The risk reviews are a major risk control feature of the design phases of a project as well.

These risk reviews can be one to three progressive efforts over one to three project

phases, depending on the size of the “major capital project,” with the Risk Review report

building toward the “initial” official hazard review report for the process unit (discussed

in the next section).

The Risk Reviews during the detailed design phases can typically include:

Using HAZOP, FMEA, and/or What-if (brainstorming methods) in progressively

more detail

Initiating and then progressively improving (from phase to phase) the risk review

record (HAZOP tables, What-If tables, checklist tables)

As mentioned in Figure 1 and Table 2, the risk reviews during detailed engineering

will evaluate the risk of any design modifications and/or newly identified hazardous

scenarios, which have been added since the previous reviews.

Maximize inherently safer design in the selected process

Addressing damage mechanisms and ensuring materials and equipment location

and engineered safeguards minimize the likelihood or effects of external impacts

Performing a final review of equipment, ventilation, containment, and environmental

safeguards, including instrumentation, interlocks, fail-safe decisions, detailed layouts,

and fire protection provisions

Begin the Human Factors risk review (checklist-based)

Continue the Facility Siting risk review initiated earlier (checklist-based and

modeling-based risk reviews)

Apply Layers of Protection Analysis (LOPA) to complex risk scenarios and use

this to define Safety Instrumented Systems’ needs. These phases of the project

are where LOPA gets used the most. With that said, only 1-5% of potential

accident scenarios will require LOPA in the risk decision making process.

Exceptions will be for novel technology:

There typically is no call for LOPA during the conceptual stage or very

preliminary design phase of a major capital project.

LOPA occur frequently during this Detailed Design project phase

Page 14: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

14

Example: We performed a PHA/HAZOP over a six (6) week period for a new

way to make an explosive. There had only been limited pilot testing of some of

the technology before scale up. The PHA/HAZOP normally would have taken

two (2) weeks, but the PHA/HAZOP was doubling as a design review. In

addition, since the controls and safeguarding for this process were all novel,

about 7% of the accident scenarios went to LOPA. This is more than the 1-5%

of the scenarios that normally go to LOPA. About 30 LOPA in all were

performed.

As before, the Risk Reviews during the detailed engineering phase require intensive

participation by operations’ senior staff, including operators, supervisors, and process

engineers.

4.3.6 Risk Control – Pre-Commissioning / Commissioning (Initial Startup) Phase of a

Major Capital Project

The pre-commissioning Risk Review builds upon the previous Risk Reviews in the

project. As the equipment design is completed the fabrication and construction begins.

During this same period, initial training of the new or transferred staff occurs, using the

procedures mentioned in the previous section. The pre-commissioning Risk Review can

begin just prior (4-6 weeks prior) to start-up of a new facility, or a little earlier if possible.

The key consideration for this project phase is to complete the risk review of non-routine

modes of operations. The project Risk Reviews to this point will not have covered these

modes of operation very well. (Note that in perfect world, the risk review of the non-

routine modes of operations, which uses the operating procedures as a basis, would be

completed before training begins. However, in most cases, the training begins as the

procedures are being completed and as the risk review is done.) The risk review of non-

routine operating modes can be performed using a full 8 guideword HAZOP, a streamline

2 Guideword approach (which is what was used before HAZOP was invented in the

1960s), or a No Guideword What-if.13

All of these approaches are described elsewhere13

and will be explained in some detail in the 3rd

Edition of the Guidelines for Hazard

Evaluation Procedures, CCPS14

. This procedural analysis is to ensure that hazards due to

human error in association with the process design have been identified and analyzed.

During this final risk review before start up, the project team must also ensure that all the

PSM requirements for initial PHAs have been met. PHAs must address the hazards of

the process; therefore hazards during all modes of operation must be analyzed. The

resulting report will be the “initial PHA” of the process unit, which is required to meet

PSM standards.

And as before, the LOPA is usually performed by a single analyst, outside of the

qualitative risk review (PHA/HAZOP).

Page 15: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

15

This pre-commissioning risk review should not be confused with the pre-startup safety

review (PSSR; also referred to as Operational Readiness Review [ORR]), which is also

necessary but the purpose of the PSSR is to validate that the process design and

specifications have been met.

This final Risk Review session before startup consists of:

Reviewing and evaluating changes made during construction, ensuring that no new

hazards have been added since the last hazard review. High priority is given to

detecting details which may have been overlooked, and to concentrating on the

adequacies of plans to cope with operating emergencies that might arise

Maximizing inherently safer design in the selected process, such as planning for

rework of initial product

Completing reviews for Facility Siting and access issues

Completing the review for Human Factors issues

Reviewing (HAZOP/What-If) of start-up, shutdown, emergency shutdown, and on-

line maintenance procedures. Some believe this risk review to be another

“validation” review of procedures, to ensure they are correct. But that is not the

purpose of this risk review of procedures. Our aim in the HAZOP/What-If of the

procedures is to ensure we have adequate safeguards (hardware, interlocks, SIL,

and/or independent administrative safeguards) to offset the errors of skipping steps

and performing steps wrong – such human errors WILL occur, it is just a matter of

when.13

Performing any LOPA, if necessary for the new scenarios that are uncovered during

the hazard review of non-routine modes of operation.

After this risk review, the project team can proceed to close recommendations, decide

which (if any) of the recommendations can be deferred until after initial startup, close the

PSSR (not part of the risk review, but part of PSM in general), and finalize the initial

PHA report for the new process unit. Typically, the plant MOC system begins to take

over control of new risks after the pre-commissioning Risk Review meeting is closed.

There are of course many deliverables from the project team, including the finished

equipment, ready to commission and then smoothly commissioned, operating and

maintenance procedures, populated databases for mechanical integrity (MI), Process

Safety Information - files of all necessary design bases for relief valves, completed

drawings, complete equipment files of all types, etc.

Although LOPA is valuable during this project phase, the lack of risk review of

non-routine mode of operations, such as by HAZOP or What-if of procedural steps,

is the most frequently observed weakness in the project risk review cycle

Page 16: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

16

4.4 Operating Phase of Lifecycle

4.4.1 Management of Change

Change is an inevitable and necessary feature for all organizations. When changes occur

in an operation that contains hazards of any sort, it is necessary that the change process

be managed to understand and control those hazards. Most organizations have some

“Management of Change” (MOC) policies and procedures in place to address the wide

range of issues related to changes. Regardless of the type of change, the risk of change

must be analyzed. All of the hazard evaluation methods are applicable to MOC risk

reviews and the criteria for selecting the appropriate technique is the same as for other

risk reviews. However, one nuance is that the choice of technique may depend also on

how the unit hazard evaluation will be revalidated (updated). For instance, if the unit

hazard evaluation (called a Process Hazard Analysis in the US) was accomplished using

primarily HAZOP, then long-term it might be best if the risk review of the “change” also

be documented in HAZOP format; this will make rolling-up the data into the next

revalidation that much easier for the company.

4.4.2 Cyclic Reviews (Revalidations)

Even as process changes never end during the life of a facility, there will always be the

necessity to continue hazard evaluations. Periodic updating or revalidation of the hazard

study is the method used to maintain adequate safeguards. The timing of these cyclic

reviews depends on factors such as regulations, the rate of process changes, and the

nature of those changes. A significant change outside the fence line can also trigger the

need for a hazard review. Examples of such changes are:

Population changes such as new residential housing nearby

Land/water/air traffic pattern changes

Necessary community emergency and security adjustments

New buildings such as schools or commercial establishments

Demolished buildings.

Some of the MOC risk reviews may affect an existing LOPA or the risk review

team (best understood as a mini-PHA team) may recommend a LOPA for a

new scenario resulting from the change. For the case of an MOC effecting and

existing LOPA, the prior LOPA should be updated, with a notation on the

LOPA documentation that makes it easy for the change to be incorporated in

the next Revalidation cycle. Again, LOPA will likely only be required for 1-5%

of the scenarios.

Page 17: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

17

4.4.3 Restarts

During the normal operating phase, units restarted following:

a normal shutdown

an emergency (abnormal) shutdown

a “turnaround” or maintenance phase.

Each has safety issues associated which could be unique to the shutdown event. Start-up

from a normal or scheduled shutdown (without maintenance action) should already have

been addressed as a procedure-based hazard evaluation (HAZOP, What-if, or 2 Guide

Word technique) of non-routine operations. Less likely to have had an established safety

review is the start-up from an emergency or abnormal shutdown, since not all possible

emergency scenarios would have been predicted. These are frequently considered to be

operated like a normal start-up once the system has reached a safe state. A careful restart

review (usually 2 Guide Word or What-if) is advised, since by the (hopefully) unique

nature of the emergency, experience with the specific type of restart is limited.

4.5 Extended Shutdowns

Mothballing a plant or a unit within a plant site goes beyond the steps taken to shut down

a process to an established safe state. Tanks, lines, and valves must all be drained and

any residual reactive materials neutralized. Most of these operations will likely be

performed only once during the lifetime of the operation, and hence will have no history

to help guide the safe implementation of the mothballing effort. A potentially riskier

activity is a restart from an extended shutdown. In that event, the condition and intended

operation of all equipment and instruments must be checked. In particular, the safety

systems must be re-verified and validated. The restart of a mothballed unit within and

perhaps attached to an active production site should include a review of the hazard

evaluation for the connected active units.

LOPA may be required for the new scenarios that are uncovered during the

hazard review of these unique, non-routine modes of operation.

Although LOPA is likely not needed for preparation for extended shutdown, a

restart back to the “normal” mode of operation may need a new PHA/HAZOP

and therefore some LOPA may be required.

Although MOCs may require a few LOPA, Revalidations almost never require

new LOPA. But, if one or more of the MOCs affect existing LOPAs or the MOC

risk review team required a new LOPA, then related changes or notation are

likely necessary for the Revalidation report.

Page 18: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

18

4.6 Decommissioning Phase of Lifecycle

An active plant or unit that is slated for decommissioning would go through the stages of

a normal shutdown, then cleanout in preparation for mothballing, followed by

disassembly. In the refining industry as well as in other process industries, a hazard

review is conducted before decommissioning. Health, safety, and environmental issues

would be related to uncontrolled pressure releases, workers potentially exposed to

noxious or toxic vapors, and spills during line separation. A plant or unit that has been

previously mothballed would have all the issues associated with the decommissioning of

an active plant or unit, with the added potential hazard associated with corrosion

products. Over a period of time, residues can change such that these new compounds may

be unknown and have unknown health and environmental effects or thermal

decomposition sensitivities.

6. Conclusions

LOPA is one risk assessment tool that has proven useful in helping organizations judge if

selected accident scenarios have sufficient safeguards. Throughout the process lifecycle,

from the technology phase through the end of ongoing operations, LOPA has and

continues to be used. If the general rules outlined in this paper are followed and if LOPA

is not arbitrarily applied, then it will continue to benefit industry as a valuable tool for

risk assessment.

7. ABBREVIATIONS and GLOSSARY

HAZOP – Hazard and Operability; as in HAZOP Analysis or HAZOP Study

IE – Initiating Event

IEC – International Electrotechnical Commission

IEF – Initiating Event Frequency

IPL – Independent Protection Layer

ISA – International Society of Automation

LOPA – Layer of Protection Analysis

MOC – Management of Change

PFD – Probability of Failure on Demand

PHA – Process Hazard Analysis

P&ID – Piping & Instrumentation Diagram

LOPA would only rarely be required for decommissioning of an entire process;

but if a part of a process is decommissioned; this may affect existing LOPA

scenarios for the portion of the process that will remain in operation.

Page 19: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

19

PSM – Process Safety Management

SIF – Safety Instrumented Function

SIL – Safety Integrity Level

SIS – Safety Instrumented System

8. References

1. Bridges, William G., and Tom R. Williams (1997), “Risk Acceptance Criteria and

Risk Judgment Tools Applied Worldwide within a Chemical Company,”

International Conference and Workshop on Risk Analysis in Process Safety, October

21–24, 1997, Atlanta, GA, pp. 13–28. New York: American Institute of Chemical

Engineers.

2. Dowell, A. M., III (1997), “Layer of Protection Analysis: A New PHA Tool, After

HAZOP, Before Fault Tree,” International Conference and Workshop on Risk

Analysis in Process Safety, October 21–24, 1997, Atlanta, GA, pp. 13–28. New York:

American Institute of Chemical Engineers.

3. Ewbank, Rodger M., and Gary S. York (1997), “Rhône-Poulenc Inc. Process Hazard

Analysis and Risk Assessment Methodology,” International Conference and

Workshop on Risk Analysis in Process Safety, October 21–24, 1997, Atlanta, GA, pp.

61–74, New York: American Institute of Chemical Engineers.

4. IEC 61508, Functional Safety of Electrical Electronic/Programmable Electronic

Safety-Related Systems, The International Electrotechnical Commission, 2010.

5. IEC 61511, Functional Safety: Safety Instrumented Systems for the Process Industry

Sector - Part 1: Framework, Definitions, System, Hardware and Software

Requirements, International Electrotechnical Commission, 2003.

6. ANSI/ISA 84.00.01-2004 (IEC61511-1 Mod), Functional Safety: Safety Instrumented

Systems for the Process Industry Sector - Part 1: Framework, Definitions, System,

Hardware and Software Requirements, 2004.

7. Layer of Protection Analysis: Simplified Process Risk Assessment, CCPS/AIChE,

2001.

8. ISA TR84.00.02, Safety Instrumented Functions (SIF) – Safety Integrity Level (SIL)

Evaluation Techniques, International Society of Automation, 2002.

9. Guidelines for Initiating Events and Independent Protection Layers, 2014 (pending),

CCPS/AIChE.

10. Bridges, W. and Clark, T., “Key Issues with Implementing LOPA (Layer of

Protection Analysis) – Perspective from One of the Originators of LOPA,”, 5th

Global Congress on Process Safety, April 2009, AIChE.

11. Layer of Protection Analysis, Training Course Notebook, Process Improvement

Institute, Inc., 2004-2014.

Page 20: Lessons Learned from Application of LOPA throughout the Process Lifecycle · 2014-04-23 · Lessons Learned from Application of LOPA throughout the Process Lifecycle William G. Bridges,

20

12. Bridges, W. and Tew, R., “Controlling Risk During Major Capital Projects,” 24th

CCPS International Conference and Workshop on Process Safety (CCPS/AICHE),

New Orleans, LA, April 2008.

13. Bridges, W. and Clark, T., “How to Efficiently Perform the Hazard Evaluation (PHA)

Required for Non-Routine Modes of Operation (Startup, Shutdown, Online

Maintenance),” 7th Global Congress on Process Safety, Chicago, AIChE, March

2011.

14. Guidelines for Hazard Evaluation Procedures, 3rd

Edition, 2008, CCPS/AIChE.