24
1 Lessons from Indian Flagship Programmes: The Disconnect for Evaluation Framework 1 Abstract This paper critically examines the management information system (MIS) in thirteen Indian flagship programmes that are under operation for quite sometimes now. Yet the MIS for these programmes has not reached maturity and as many as four programmes do not have any MIS. Clearly, there is a disconnect among the information gathering, monitoring and measuring impacts in the development programmes. Key Words: Management information system, Flagship programmes, Log-frame hierarchy, Result-based monitoring and evaluation, Implementation framework Introduction The MIS plays a critical role in the implementation of programme in terms of monitoring periodic progress. A well designed MIS facilitates flow of information among various levels and enables setting up of the necessary feedback mechanism for planning and management of a programme, project or policy. A comprehensive MIS is a necessary condition for taking informed and timely decisions including those related to operational, strategic and tactical ones. A well designed management information system (MIS) must be simple and easy to comprehend by the different stakeholders of the programme at national, sub-national and community levels; and it should provide reliable information. The information should be specific, accurate and verifiable; and facilitate timely management decision in terms of frequency and flow of information (i.e. a two-way feedback system in a decentralized framework), and management of database. Information generated by the system should be easy to access, process and use thereby facilitating wider dissemination and it should be amenable to computer software. However, literature on information system in the national level planning and decision making process is scarce and most of the literature is contextualized to organizations that facilitates managers to take various decisions (Gupta, 1996). With the advancement of information and communication technology (ICT), importance of MIS has been widely acknowledged in resolving many decision making problems at macro level. 1 Dr. I.C.Awasthi, Faculty, Institute of Applied Manpower Research, Delhi, India. e-mail: [email protected]

Lessons from Indian Flagship Programmes: The Disconnect for Evaluation … · 2014. 4. 16. · 1 Lessons from Indian Flagship Programmes: The Disconnect for Evaluation Framework 1

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • 1

    Lessons from Indian Flagship Programmes: The Disconnect for Evaluation

    Framework 1

    Abstract

    This paper critically examines the management information system (MIS) in thirteen Indian flagship

    programmes that are under operation for quite sometimes now. Yet the MIS for these programmes has not

    reached maturity and as many as four programmes do not have any MIS. Clearly, there is a disconnect

    among the information gathering, monitoring and measuring impacts in the development programmes.

    Key Words: Management information system, Flagship programmes, Log-frame

    hierarchy, Result-based monitoring and evaluation, Implementation framework

    Introduction

    The MIS plays a critical role in the implementation of programme in terms of

    monitoring periodic progress. A well designed MIS facilitates flow of information among

    various levels and enables setting up of the necessary feedback mechanism for planning

    and management of a programme, project or policy. A comprehensive MIS is a necessary

    condition for taking informed and timely decisions including those related to operational,

    strategic and tactical ones.

    A well designed management information system (MIS) must be simple and easy

    to comprehend by the different stakeholders of the programme at national, sub-national

    and community levels; and it should provide reliable information. The information should

    be specific, accurate and verifiable; and facilitate timely management decision in terms of

    frequency and flow of information (i.e. a two-way feedback system in a decentralized

    framework), and management of database. Information generated by the system should

    be easy to access, process and use thereby facilitating wider dissemination and it should

    be amenable to computer software.

    However, literature on information system in the national level planning and

    decision making process is scarce and most of the literature is contextualized to

    organizations that facilitates managers to take various decisions (Gupta, 1996). With the

    advancement of information and communication technology (ICT), importance of MIS

    has been widely acknowledged in resolving many decision making problems at macro

    level.

    1 Dr. I.C.Awasthi, Faculty, Institute of Applied Manpower Research, Delhi, India.

    e-mail: [email protected]

    mailto:[email protected]

  • 2

    Conventionally, governance structures have been characterised by rule-based

    approaches that primarily focused on process regulation, compliance with centrally

    prescribed standards and rules. Performance has been thus judged not by the results or

    outcomes but by compliance with processes and inputs. This has severely undermined the

    performance of the development projects or programmes. However, in a changed

    economic milieu, the performance is evaluated by results or outcomes not by the outputs;

    the fallacy of mere outputs has been seriously questioned in evaluation literature (Kusek

    and Rist, 2004; Linda and Rist, 2009).

    A large number of centrally sponsored and central sector schemes are

    implemented through different Ministries across the country. With enormous diversity in

    the implementation hierarchy across space, it has become all the more important to have

    information about the physical and financial details of a project or a programme in order

    to monitor the progress. The Eleventh Five Year Plan underscored the deficiencies in the

    existing accounting system for the Plan schemes and its inability to support informed

    planning, budgeting and effective monitoring of these schemes (Planning Commission,

    2008).

    This paper examines the efficacy of the MIS in flagship programmes and checks

    how credible MIS can become an effective tool for management. The MIS is critical for

    generating information which is indispensable for conducting result-based monitoring

    and evaluation (M&E). This paper argues that MIS is still in its infancy stage in most of

    the flagship programmes, and this has to be put in place in order to provide evidence-

    based management.

    The second section explores the rationale of MIS as an evidence-based tool for

    management. The third section reviews the MIS in India’s flagship programmes and the

    last section recapitulates some of the issues from the policy perspectives.

  • 3

    Rationale of MIS

    Some of the basic principles of MIS are indicated as under:

    MIS has to be derived from to the Log Frame

    The MIS must describe performance and impact indicators with a clear inter se

    relationship. However, indicators for outputs are mainly used for monitoring and no

    separate indicators are used for activities or inputs. Indicators must be relevant, realistic,

    specific and readily available. In the implementation framework, these involve inputs,

    activities and outputs, while outcomes and impacts are parts of the result based

    monitoring and evaluation; though all these must function as an integrated whole. The log

    frame must clearly outline the defined and realistic objectives and assumptions that

    describe how the interventions are designed to work. Log-frame hierarchy must identify

    the inputs, activities, outputs, programme objectives and outcomes with explicit clear

    links.

    It has been noted that in most of the flagship programmes no log frame matrix is

    structured for the programme design – what to speak about revising the original

    programme design. Without detailing the critical components of the objective hierarchy,

    it is most likely that programme objective indicators are not specified and hence the

    impact of programme is unclear.

    Authentication and Validation

    The data need to be collected at disaggregated levels and it must be ensured that

    the data are collected with agreed indicators. The database must reflect the log frame

    structure, and comprise all the activities with budgets, and all the outputs with their

    respective indicators. The system should be able to quickly collect and edit data,

    summarize results and be able to adjust and correct errors promptly. Traveling of data

    from source area to web portal should be quick and supported by ICT infrastructure.

    Data Reporting Mechanism

    The MIS must provide timely information about the project or the programme

    indicating how well and to what extent it has performed or not performed as envisaged in

    the implementation framework. The MIS must clearly indicate the demonstrated

    performance at the outputs and objectives levels. Activities are generally reported on a

  • 4

    recurrent basis, yet these can be reported as per programme strategy depending on the

    nature of the project or the programme. The information should be such designed as to

    expedite the reporting of the information. Efforts are needed to bring out analytical

    reports quickly in the form of fact-sheet that ought to give signals for policy purposes.

    However, there appears to be a gap in data generation and reporting system in some of

    the flagship programmes that often hinder in realization of the project or the programme

    objectives (for example, the rural road programme (PMGSY), Irrigation, Mid-Day Meal

    Scheme (MDMS) and Jawaharlal Nehru National Urban Renewal Mission (JNNURM)).

    Accessibility of Data for Public

    The data and information need to be fully accessible to and usable for all the

    stakeholders including researchers and the community at large. The data collected at local

    or community level must bear the ownership among the people and eventually benefit the

    people from the information generated. The information should not only flow to the

    national monitors but also be made available to the community. It has been noted that in

    some of the flagship programmes, either no feedback system exists or the existing

    mechanism is weak (for example, Irrigation, Rural Telephony, Rural Electrification,

    Universalization of Elementary Education (SSA), Mid-Day Meal Scheme, and Integrated

    Child Development Service (ICDS)).

    Utilization of Data

    Accessibility of data helps in using the data for analysis and further research,

    which eventually helps improve the implementation framework. The data can be utilized

    by the variety of stakeholders. The intent should be made transparent enabling the

    participation of the major stakeholders in the utilization of the data with a proper

    feedback mechanism.

    The MIS data are primarily used for monitoring purposes and there is virtually no

    linkage between the MIS information with that of evaluation studies. It has been noted

    that M&E functions in a compartmentalized manner rather than articulating relationship

    between the two. Enormous data are generated in every programme but there is very little

    utilization of these data in terms of generating analytical reports. Even evaluation reports

    do not use the data generated by these programmes.

  • 5

    Connecting Output, Outcome and Survey Data

    It is often observed that there is a weak connection or linkage between the

    implementation framework and the outcome framework within the perspective of the

    theory of change. This arises due to lack of clarity on the indicators and assumptions of

    the log frame. It is also noticed that there is a divergence between the project or the

    programme data and that of large survey data that often makes difficult to aid policy

    (ICDS and National Family Health Survey (NFHS), for example).

    User-friendly Website

    While developing a website, the users’ needs should always be in the forefront of

    the decision-making process. The design and development process must create a site that

    satisfies the visitors with customer-focused content. The website should have an in-built

    feedback device. Feedback is an essential component of the evaluation process that

    provides the link between the past and future activities. In order to ensure that the results

    of evaluations are utilized in future policy and programme, it is necessary to establish

    feedback mechanisms involving all the stakeholders (OECD, 1991). But most of the

    flagship programmes in India though have dedicated websites but in some cases these do

    not have any feedback devise and lack user-focused design.

    MIS in Flagship Programmes

    There is a growing need for effective and efficient utilization of public money

    through continuous monitoring process in order to measure the progress. Precisely, with

    this in view, every project and programme has some monitoring process in place in order

    to track the progress. For major schemes, MIS have been developed by the different

    Ministries for tracking the progress of the schemes, both in terms of physical and

    financial parameters (PEO, 2009).

    At present as many as thirteen flagship programmes are being implemented,

    primarily with a view to constructing of rural infrastructure; education for all; improving

    health and sanitation; providing opportunities for improved living conditions as well as

  • 6

    livelihoods; and augmenting the economic and social infrastructure of cities etc. with

    huge investments.2

    This section examines the MIS in the flagship programmes which is in no way

    exhaustive appraisal but indicative in some sense that might raise research questions for

    further work in this area. This section draws on preliminary analysis based on the

    information available in the website. There are no MIS (as many as in four flagship

    programmes) worth the name and also in many cases one is not permitted to visit MIS

    online without a valid authorization. The programmes which have no MIS are: Irrigation,

    Rural Telephony, Mid-Day Meal Scheme and Jawaharlal Nehru National Urban Renewal

    Mission.

    The flagship programmes are as under:

    1. Building Rural Infrastructure: Bharat Nirman (www.bharatnirman.gov.in) (i) The Rural Road Programme: Pradhan Mantri Gram Sadak Yojana (PMGSY)

    (ii) Low Cost Housing to Rural Poor: Indira Awaas Yojana (IAY) (iii) National

    Drinking Water Programme (iv) Irrigation (v) Rural Telephony (vi) Rural

    Electrification Programme: Rajiv Gandhi Gramin Vidyut Yojana (RGGVY)

    2. The Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA)

    3. Universalization of Elementary Education: Sarva Shiksha Abhiyan (SSA)

    4. Mid-Day Meal Scheme (MDMS) 5. Integrated Child Development Services (ICDS) 6. National Rural Health Mission (NRHM) 7. Jawaharlal Nehru National Urban Renewal Mission (JNNURM); and 8. Total Sanitation Campaign (TSC)

    First, we discuss national flagship programmes that have MIS and subsequently

    those programmes which do not have.

    The Rural Road Programme: Pradhan Mantri Gram Sadak Yojana (PMGSY)

    The programme was launched in December, 2000 by the Ministry of Rural

    Development, Government of India. The primary focus of the programme is to provide

    2 Total allocation under Flagship Programmes during the XIth Five Year Plan is of the order of Rs. 5,310

    billion and for 2011-12 it is as under:

    Bharat Nirman: Rs. 5,80,000 million; MGNREGA: Rs. 4,00,000 million; SSA: Rs. 2,10,000 million;

    MDMS: Rs. 1,03,800 million; NRHM: Rs. 1,81,720 million; JNNURM: Rs. 1,37,000 million; TSC: Rs.

    16,500 million; ICDS: Rs. 1,03,300 million.

    http://www.bharatnirman.gov.in/

  • 7

    rural road connectivity that involves construction of new roads and up-gradation of the

    existing roads so as to ensure connectivity through good all-weather roads. The key

    component of this programme is to improve the access to economic and social services

    and thereby generating increased agricultural incomes and productive employment

    resulting in a sustainable poverty reduction.

    A modern management and monitoring system has been set up for the PMGSY

    (www.pmgsy.nic.in). This web-based online monitoring system is developed to facilitate

    monitoring and create transparency and embedded decision support systems for on-time

    delivery, cost management and quality control. The entire database is placed in the

    citizens’ domain.

    The analysis of the MIS we undertook, brought out some of the following observations:

    The guidelines deal primarily with the inspection procedure of the works rather

    than monitoring and evaluation. It focuses on a three-tier quality control and

    quality monitoring mechanism. The procedure discusses the inputs, activities and

    outputs.

    Some of the information on the on-going and completed works is of qualitative

    nature (comments and observations) which is often hard to measure directly.

    There is therefore a need for evolving proxy to measure the progress.

    Quality monitoring indicators are not expressed in terms of quantifiable entities.

    For instance, it is very difficult to assess the progress on the basis of judgments

    such as ‘satisfactory’ or ‘unsatisfactory’.

    National, state and district reports are also prepared in terms of physical and

    financial targets and achievements, but it is not clear how this information is

    being used to track the progress.

    Low Cost Housing to Rural Poor: Indira Awaas Yojana (IAY)

    The IAY, low-cost housing for the rural poor, was launched during 1985-86. The

    objective of the IAY is primarily to help construction/up-gradation of dwelling units of

    the members of socially disadvantaged groups and other minorities in the below

    poverty line (BPL) category living in rural areas (www.bharatnirman.gov.in).

    There is an on-line data entry provision in the portal by field staff. Guidelines and

    the prescribed procedure have been neatly structured and also envisioned that officers

    dealing with IAY shall ascertain through field visits whether the programme is being

    http://www.pmgsy.nic.in/http://www.bharatnirman.gov.in/

  • 8

    implemented satisfactorily and whether construction of houses is in accordance with

    the prescribed procedure. The state governments shall conduct periodic evaluation

    studies through reputed institutions and organizations on issues thrown up by the

    concurrent evaluation. The software was designed and developed for collecting

    information from the location where the scheme is implementing. Main purpose of MIS

    is to collect data to know the progress of physical and financial aspect of the scheme

    (http://iay.nic.in).

    The portal contains a variety of information at Gram Panchayat, block, district, state

    and national level on BPL, above poverty line (APL) families requirements of houses,

    women headed houses; disabled persons’ housing requirement details etc. However,

    updating data is perennial problem owing to lack of ICT infrastructure.

    An examination of the MIS reveals some of the issues as follows:

    State-wise and district-wise monthly progress report (MPR) is presented in terms

    of physical and financial parameters, but it is not clear how the information is

    being utilized to measure the outcomes.

    The scheme was implemented from 1st January, 1996 but the information is

    available for the last three years i.e. 2009-10, 2010-11 and 2011-12 in the MIS.

    MPR in terms of physical, financial details by state/district-wise is given, but it is

    not mentioned for which month the data relate to.

    National Rural Drinking Water Programme (NRDWP)

    NRDWP is one of the six components of Building Rural Infrastructure: Bharat

    Nirman. During its Phase – I period (2005-06 to 2008-09), 55,067 uncovered and about

    0.33 million slipped back habitations were to be covered with provisions of drinking

    water facilities and 0.217 million quality-affected habitations were to be addressed for

    water quality problem. The phase II is being implemented from 2009-10 to 2011-12.

    The Department of Drinking Water Supply, Ministry of Rural Development, is

    responsible for meeting this goal in partnership with the State Governments

    (www.bharatnirman.gov.in).

    Ministry has been assisting the States and Union Territories (UTs) to accelerate

    the pace of coverage of drinking water supply. The entire programme was given a

    http://iay.nic.in/http://www.bharatnirman.gov.in/

  • 9

    mission approach in order to improve the performance, cost effectiveness and to ensure

    adequate supply of safe drinking water. The Technology Mission on drinking water and

    related water management was launched in 1986. It was also called the National Drinking

    Water Mission (NDWM), which was renamed as Rajiv Gandhi National Drinking Water

    mission (RGNDWM) in 1991(www.ddws.nic.in). From 2005 onwards it is called

    NRDWP and it is the only flagship programme to provide safe drinking to every

    habitations/villages. The scheme is 50:50 cost sharing basis between the Central and

    State governments. State government is fully implementing the scheme because water

    resource is state subject. During the last one and half year the Integrated Management

    Information System has been functioning (including for TSC) (www.indiawater.gov.in).

    It is also planned to introduce the automatic short message service from next

    financial year for getting MPR and other related information. Also, there is a plan to

    introduce social auditing by including the village communities and to utilize Block

    Resource Centre-block level to be made nodal centre of the scheme (every block will

    have a technical person in charge for the scheme). Then the data entry level would come

    down one level below from district to block.

    Some of the observations on the scheme are described as under:

    The data is cumulative from 2005-06 to 2011-12 making it difficult to carry out

    the analysis annually. It is also not clear whether data relates to monthly or

    quarterly.

    The delivery monitoring unit (DMU) report is quarterly but the information is

    given on annual basis. It would have been better had the information is collected

    and presented quarterly basis in order to monitor the effectiveness of

    implementation.

    It is not clear whether the information provided is used for the preparation of

    analytical reports in order to measure progress.

    As regards accuracy of data, Ministry depends completely upon the state

    governments. The data is placed in the portal by the district officials dealing with

    the programme. No validation mechanism exists in this process.

    http://www.ddws.nic.in/http://www.indiawater.gov.in/

  • 10

    Monitoring is done by the concerned state government department and not by the

    Ministry. However, if wrong or inconsistent data is noticed then concerned person

    in the Ministry points it out then the same is got rectified by the concerned

    officials from the state government.

    Some sort of feedback mechanism flows to the Ministry from the local elected

    representatives/audit performance report/general public about the progress and the

    problems in the programme. It is not clear how and to what extent this feedback is

    incorporated in the programme.

    There is huge data generated in the scheme but it is hardly used for analysis

    purposes and there is vast scope for statistical analysis of the data, in particular

    interlinking of health indicator with safe drinking water which is extremely

    important. It is also unclear how huge data collected would help in generating

    analysis for policy purposes since no analytical framework appears to exist.

    Rural Electrification Programme: Rajiv Gandhi Grameen Vidhyutikaran Yojana

    (RGGVY)

    The Ministry of Power has, a rural electrification programme, which is one of the

    flagship programmes launched in March 2005 with an objective to electrify over 0.1

    million un-electrified villages and to provide free electricity connections to 23.4 million

    rural BPL households. The MIS of the RGGVY is detailed in terms of projects approved

    for implementation, achievements and compliance (www.rggvy.gov.in).

    Under the programme 90 percent grant is provided by Govt. of India and 10

    percent as loan by Rural Electrification Corporation (REC) to the State Governments.

    REC is the nodal agency for the implementation of the programme. The scheme aims at:

    Electrifying all villages and habitations as per new definition, providing access to

    electricity to all rural households, and providing electricity connection to BPL families

    free of charge. The basic infrastructure under RGGVY scheme is; rural electricity

    distribution backbone with 33/11 KV (or 66/11 KV) sub-station of adequate capacity in

    blocks where these do not exist; village electrification infrastructure with provision of

    distribution transformer of appropriate capacity in villages/habitations; and decentralized

    distributed generation systems based on conventional & non- conventional energy

    sources where grid supply is not feasible or cost-effective.

    http://www.rggvy.gov.in/

  • 11

    Some preliminary observations of the above MIS are presented as under:

    The MIS is very brief (one page) that has little or no usability for analytical

    purposes for evaluating the scheme.

    While the RGGVY claims that a village or a BPL rural house hold has been

    electrified, there is no information whether any electricity ever flows through the

    lines that are running into the village or households. Whenever urban areas are

    suffering serious load-shedding, it is unlikely that rural BPL households are

    receiving power.

    The Mahatma Gandhi National Rural Employment Guarantee Act

    (MGNREGA)

    The MGNREGA, 2005 aims at enhancing the livelihood security of the people in

    rural areas by guaranteeing hundred days of wage employment in a financial year to a

    rural household whose adult members volunteer for doing unskilled manual work. This is

    one of the major programmes launched by the Ministry of Rural Development (MHRD).

    The scheme was started in February 2006, initially in 200 districts, and later extended to

    all districts from April 1, 2008 (www.nrega.nic.in).

    Massive information is collected – right from the registration to implementation stage

    from about 0.25 million Gram Panchayats, 6,465 Blocks, 619 Districts and 34 States &

    UTs through computerized information system. The MIS portal provides a single-point

    access to all stakeholders of MGNREGA. The aim is to provide data that are transparent

    and user friendly. The portal places complete transaction level data in public domain for

    job cards, demand for work and muster rolls (attendance-cum-payment sheet) for a

    worker.

    Proper checks are used to validate the data entered and to stop the wrong entries in

    MGNREGASoft. Recently, biometric database of the MGNREGA linking Unique

    Identification Authority of India has been introduced and it is expected to bring about

    more transparency, to curb irregularities and reduce corruption.

    The DMU and MIS reports provide information on employment, works and funds

    across states. Information for the majority of states and UTs is provided for current years

    and months.

    Some of the preliminary observations on the MIS are as follows:

    http://www.nrega.nic.in/

  • 12

    The DMU treats employment generation, assets and finances as ‘outcomes’

    which in fact are outputs and not outcomes. Outputs and outcomes are

    conceptually misconstrued.

    In the case of MGNREGA, there is divergence or lack of update in Prime

    Minister’s Office (PMOs) DMU section of the scheme. Data are available for

    the years 2008-09 and 2009-10 only in PMO’s DMU but in the scheme DMU

    Report section, the information is available till November, 2011.

    The time taken between data sending and uploading ranges between 1 to 7

    days.

    There appears to be a time-lag in the ICT network interconnecting all the

    village committees, blocks, districts, States and the union ministry,

    particularly, in certain small states/UTs. Lack of a dedicated broadband

    connectivity at the block level hampers the flow of information upwards.

    Despite the fact that MGNREGA has the most comprehensive MIS system, it

    has not been able to raise an alert on delays in wage payments. The principal

    reason for this is attributed to an undue delay in updating the website data, and

    hence undermining the very basis of monitoring (Ambasta, 2009).

    The assets have been reported in the form of number of assets taken up and

    completed, but there is no information regarding their durability and

    sustainability – an issue that has never been raised by the MHRD.

    The overall status of the completed works as per cent of total projects turns

    out to be less than half (49 per cent for the financial year 2009-10) with huge

    differences across states.

    It would be useful if the time taken for transfer of funds (flow chart) from

    different sources (Centre, State, district planning committee, programme

    officer at the village committee level) are also presented which would have

    been helpful in tracking the financial progress.

    Enormous data at disaggregated level are collected but no analytical reports

    are being generated, which could have been an effective instrument for

    monitoring the progress and taking corrective measures.

    Universalization of Elementary Education: Sarva Shiksha Abhiyan (SSA)

    The SSA is Government of India's flagship programme for achievement of

    Universalization of Elementary Education in a time-bound manner, as mandated by the

    86th amendment of the Constitution of India – making free and compulsory education to

    the children of 6-14 years age group a fundamental right. The scheme of SSA was

    launched by the Ministry of Human Resource Development in 2001 and is being

  • 13

    implemented in partnership with the state governments to cover the entire country

    addressing the needs of 192 million children in 1.1 million habitations (www.ssa.nic.in).

    The monitoring and MIS unit are in place. The monitoring institutions have been

    identified state–wise, but much of the work of monitoring is to bring out data on access,

    enrolment & retention and quality (including infrastructure).The MIS has been divided

    into three modules viz. district level, state level and ministry level. Each level has four

    types of users, namely, data entry, data approver, view reports, and user manager.

    Some of the observations made are recorded in what follows:

    Surprisingly, there is no access to the MIS for the public that prevents one to

    make any assessment of the information system of such a massive programme.

    The data reported under the SSA web portal is only the quarterly progress of the

    physical and financial activities of the scheme.

    There is very limited updated information in the portal of the scheme. The on-line

    data entry provisions are in place in the portal but updated information on all the

    aspects and for all the states is not placed on time. The latest data paced are for

    the first quarter (April - June) of 2011. The DMU information is also available up

    to June, 2011.

    No feedback mechanism is developed in order to improve the MIS.

    Travelling time of data from source to destination is between 15-30 days.

    The outcome of the programme is not being checked with the programme

    objective; presumably no log-frame has been used in the design.

    Integrated Child Development Services (ICDS)

    The ICDS is one of the most unique programmes for early childhood development

    launched on 2nd

    October, 1975 by the Ministry of Women and Child Development,

    Government of India. Its objectives are to improve the nutritional and health status of the

    children in the age-group 0-6 years; to reduce the incidence of mortality, morbidity,

    malnutrition and school dropout; and to enhance the capability of the mother to look after

    the normal health and nutritional needs of the child through proper nutrition and health

    education (www.wcd.nic.in).

    The MIS is in place since its inception but it is inadequate as an effective tool for

    improving programme implementation (Adhikari and Bredenkamp, 2009). As yet, there

    is no online computerized MIS developed for the ICDS and Anganwadi Centre is the

    focal point of delivery of services under the scheme. Therefore, all the data pertaining to

    http://www.ssa.nic.in/http://www.wcd.nic.in/

  • 14

    the services (six types of records and registers prescribed) and the beneficiaries are

    captured at this level.

    Some of the observations on the MIS structure are presented below:

    The information about the scheme especially on the physical targets and

    achievements; and the release of fund are given in the portal. Data formats do not

    help in checking the consistency as the data were presented quarterly and

    annually, separately. The one-point data are given in a particular year that makes

    difficult to report the progress over time.

    No uniformity is followed in the presentation of data under the scheme.

    The given information is not available by social groups.

    The information provided does not help much to track the progress of the scheme.

    No institutional mechanism is in place in order to know the links between the

    progress made and the financial allocation for the scheme.

    There is neither any feedback device in the portal nor any evaluation report placed

    in order to examine the effectiveness of the scheme or the results.

    No data are available for DMU section.

    The MIS programme mainly tracks inputs, some of the intermediary processes

    and limited outputs rather than nutrition outcomes, such as, indicators of

    appropriate infant care and feeding behaviours (Adhikari and Bredenkamp, 2009).

    The divergence in the ICDS and NFHS findings poses some kind of puzzle that

    needs to look into and a mechanism need to be evolved for data authentication

    and validation.

    National Rural Health Mission (NRHM)

    The NRHM was launched in 2005 by the Ministry of Health & Family Welfare

    with an objective to improve the availability of and access to the quality health care by

    the people, especially the poor, women and children and those who reside in rural areas.

    The mission (2005-12) seeks to provide an effective healthcare to rural population

    throughout the country with special focus on 18 states, which have weak public health

    indicators and/or weak infrastructure. The health MIS was launched in October, 2008 and

    for capturing data it has generated formats on a web-based system at the district level so

    that the primary data can easily be aggregated and the information/reports flow quickly to

    the State headquarters and the Ministry. It also compiles periodic reports from Health

    Management Information System (HMIS) portals (www.mohfw.nic.in).

    Some preliminary observations of the MIS are presented below:

    http://www.mohfw.nic.in/

  • 15

    The scheme has collaboration with the international agencies like World Health

    Organization, World Bank, The United Nations Children's Fund to build an

    accurate reporting system under the HMIS.

    More focus is needed on generating analytical reports, which should help

    measuring the real outcomes and impacts.

    The HMIS system has a strong mechanism to control inconsistency and wrong

    entries and assures reliable and consistent information and reporting.

    Community-based monitoring of health services is a key strategy of the scheme

    and there is a provision for monitoring and planning committees at primary health

    centre (PHC), Block, District and State levels.

    The MIS does not report any information on maternal deaths and estimates of

    maternal mortality ratio on a regular basis.

    For monitoring and evaluation of the programme, health MIS should be

    developed up to the community health centre level. Sub-centers, primary health

    centres and community health centers would be reporting on their performance

    regularly to the people’s bodies like village committees and District Health

    Mission (Bajpai, et al., 2009).

    HMIS reporting system should entertain feedback/suggestions from its

    stakeholders at all levels.

    Total Sanitation Campaign (TSC)

    The TSC was launched by the Department of Drinking Water and Sanitation,

    Ministry of Rural Development. TSC is a comprehensive programme to ensure sanitation

    facilities in rural areas with broader goal to eradicate the practice of open defecation.

    TSC as a part of reform principles was initiated in 1999 when Central Rural Sanitation

    Programme was restructured making it demand driven and people centered. The main

    goal of the TSC is to eradicate the practice of open defecation by 2010

    (www.ddws.nic.in). According to National Sample Survey 2009, 51 percent of

    households in India do not even have a toilet, and many of those that do have toilets do

    not use them. However, the objective seems to be distant dream to be realized.

    For TSC, on-line progress monitoring system is in place and data entry system

    (district wise) has been devised. The state has designed district, block and panchayat

    level data collection form and base-line survey for reporting monthly progress. The

    information as on date is available but the portal is not updated with its site map. TSC is,

    http://www.ddws.nic.in/

  • 16

    probably the first scheme which introduced the on line MIS among the government of

    India’s programmes in 2002 and other programmes followed the MIS pattern of TSC.

    Under the online monitoring system, the household sanitation details for

    villages/habitations are entered at district level on daily basis. The scheme is being

    implemented in 609 districts in the country of which almost 80-90 percent of the district

    send their monthly reports on time (for instance, monthly report for December 2010 is

    forwarded by 403 districts as on today). There are certain unexpected delays owing to

    technical and communication (on line connectivity) that hinders the delay in submission

    of monthly reports on time.

    District level officials who are in charge for the scheme are responsible for editing

    and accuracy of the data given in the portal. For validation and cross checking the data,

    other national and international organizations are also independently doing the field

    studies. Panchayat Raj Department is planning to give the ICT facilities to every

    panchayats; once it is being implemented the data would be available straightaway from

    panchayats which will ensure more transparency, faster and timely availability of data.

    In spite of relatively better performance of the scheme, there are certain issues that

    need attention:

    The goal of the TSC is to eradicate the practice of open defecation by 2017

    seems distant objective, as the scheme is nowhere near the goal. Evidently,

    lack of monitoring of actual use of toilets built and the poor quality of toilets

    appears to be the reason for poor progress.

    There are no reports based on the MIS data

    There are following four flagship programmes that do not have MIS.

    Irrigation

    The scheme is being implemented by the Ministry of Water Resources in

    collaboration with State Governments for creation of additional irrigation capacity. There

    is a huge gap between irrigation potential created and the potential utilized. There are

    considerable areas in the country with unutilized ground water resources. The target of

    creation of additional irrigation potential is 10 million hectare. The 4.2 million hectare is

  • 17

    planned to be created by expeditiously completing such on-going major and medium

    projects, one million hectare through implementation of extension, renovation and

    modernization of schemes along with command area development and water

    management practices, 2.8 million hectare through ground water development, one

    million hectare is planned by way of minor irrigation schemes using surface flow and one

    million hectare is also planned by way of repair, renovation and restoration of water

    bodies and extension, renovation and modernization of minor irrigation schemes

    (www.bharatnirman.gov.in).

    No online system is in place for data collection. Only the Ministry is the predominant

    user of the data which is for own review and sanctioning and release of grants.

    Headquarters knows the range for the data which is normal for a state. On that basis, a

    check is done at head quarter. Through the monitoring of the data the inconsistency is

    checked and if any visible inconsistency found then concerned states are asked to rectify

    the data. During the review meeting organized at head quarter each states information

    were used to do double check for the approval/sanctioning.

    Some of the initial observations on the above programme are as follows:

    No MIS has been developed for the irrigation component of Bharat Nirman.

    However, information on achievement is given till 2009-10. Even that

    information is not complete for all the states and in some cases either the

    information is not reported or partially reported.

    There is divergence in the data presentation and updating of the data. The web

    portal gives DMU data for the year 2010-11 (data up to 10th

    March, 2011). The

    PMOs’ DMU report gives the data for 2009-10 only.

    The DMU format suggests that a quarterly report must be submitted, but

    surprisingly, achievements by the Ministry are given for 2009-10 and 2010-11,

    that is the entire year

    The information regarding achievement is given as reported by the state

    governments but, it is not clear whether or not the information is validated at the

    level of Ministry.

    http://www.bharatnirman.gov.in/

  • 18

    No formats for data collection are provided either on-line or otherwise without

    which it becomes extremely difficult to make any observation and track the

    monitoring.

    No feedback mechanism exists from the major stake holder’s point of view.

    Rural Telephony

    Telecommunication connectivity constitutes an important part of the effort to upgrade

    the rural infrastructure and it is important to improve the tele-density in rural areas. It

    aims at achieving 40 per cent rural tele-densities by 2014 and ensures broadband to all

    panchayats by setting up India Building Service Centre. The Department of

    Telecommunication in the Ministry of Communications and Information Technology has

    the responsibility of providing telephone connectivity to the villages that remain to be

    covered (www.bharatnirman.gov.in). The Central Government provides village public

    telephones in uncovered villages through subsidy support through universal service

    obligation fund.

    The target of the scheme is that, under the Bharat Nirman Programme, rural

    teledensity of at least 40 per cent by 2014, and broadband coverage of all 2,50,000 village

    panchayats and Setting up of Bharat Nirman Common Service Centers at Panchayat

    level by 2012 will be achieved

    Some preliminary observations are reported as under:

    There is no MIS for the programme even though the programme was initiated

    in 2005, and without MIS it becomes extremely difficult to monitor the

    programme effectively.

    There is very little data available on the website that too is highly aggregated

    and not beyond state/ circles levels.

    There is no provision of on line data submission and data is provided by

    service provider. State-owned Bharat Sanchar Nigam Limited (Indian state-

    http://www.bharatnirman.gov.in/http://en.wikipedia.org/wiki/State-owned

  • 19

    owned telecommunications company) is the largest service provider for

    telephones and broad band connectivity, which can only provide date.

    Data forwarding authority (at state level) have to self certify for the validity of

    the data. Controller of Communication Accounts also cross checks the service

    on sample basis and conducts monthly or quarterly review of the progress of

    the work performance etc.

    Latest information on rural tele-density is provided till 2009. But the

    information is insufficient to make any kind of analysis. Disaggregated

    information on a number of revenue villages are provided with village public

    telephone (VPT), remotely located villages provided with VPTs through

    digital satellite phone terminals. Broadband coverage would have been useful

    to make any definitive analysis across districts and states.

    Similarly, targets and achievements should have been presented at

    disaggregated levels.

    The DMU report gives only broadband coverage (up to March, 2011) and not

    VPTs year-wise.

    A comprehensive MIS detailing activity and outputs is warranted.

    Mid-Day Meal Scheme (MDMS)

    MDMS, the world’s largest school feeding programme, was launched by the Ministry

    of Human Resource Development in 1995, which is aimed at boosting universalization of

    primary education and is expected to attract enrolment, attendance, retention and

    reduction of the drop-out rates, simultaneously improving the nutritional levels among

    children. The scheme is spread over 1.2 million schools and covering over 120 million

    children’s in the country and collecting information on time. There are reports that show

    that as a result of MDMS there has been a remarkable improvement in attendance and

    retention of the children in the schools.

    No MIS has been developed for the scheme separately. However, the mechanism for

    monitoring and supervision of the MDMS has been in place which includes local level

    http://en.wikipedia.org/wiki/State-ownedhttp://en.wikipedia.org/wiki/Telecommunications

  • 20

    monitoring, display of information under Right to Information Act and inspection by the

    state government officials, periodic returns etc. (www.education.nic.in).

    There are national, state review committees and also over three dozen social science

    research institutions that have been identified and entrusted for monitoring the scheme.

    These institutions bring out monitoring reports based on 5 per cent sample basis. But

    there is no on-line monitoring mechanism. The scheme largely relies on inspection as a

    principal monitoring instrument that primarily focuses on inputs and activities rather than

    deliverables.

    The National Programme of Nutritional Support to Primary Education was

    launched as a centrally sponsored scheme on 15th August, 1995. However, data are

    presented only for last two years (2008-9 and 2009-10). Information for first quarter

    2009-10 (April-January) is available only for 14 states. Even quarterly information for

    the last quarter (January-March) for the year 208-09 is not available for all the states.

    At present the scheme has wide coverage - 120 million children, 1.2.6 million

    schools, 2.4 million staff (cooks cum helpers) and 0.58 million kitchen cum store rooms.

    At present a system is in place to gather all the important data in a systematic manner. It

    is planned to have the Mid Day Meals Index for the states/schools on the lines of human

    development index

    Some of the pointers for assessment bring about the following observations:

    No MIS has been developed for the scheme even after existence of this scheme

    for quite long time. Without comprehensive MIS, monitoring of the scheme

    becomes somewhat difficult.

    The information is available for fewer states for the year 2011-12 and majority of

    the states have not yet submitted their last quarter reports for the year 2010-11.

    No information is available beyond the state levels and even no consolidated all

    India report is available.

    Normally, monthly statement should be submitted by the district level officials to

    the states and states in turn are required to compile it and forward it to the Central

    Ministry.

    http://www.education.nic.in/

  • 21

    The information also does not provide disaggregation by gender and social

    groups.

    Some linkages between provision of mid-day meals and enrolment and dropouts

    may also be included in the report formats in order to determine whether the

    programme is performing according to plan and budgets.

    There is no feedback devise under the scheme that is essential to improve the

    design for effective implementation of any scheme/programme.

    Enrolments data are presented for one point of time and it would be worthwhile to

    add for more years in order to make the comparison over time.

    Jawaharlal Nehru National Urban Renewal Mission (JNNURM)

    The JNNURM was launched by the Ministry of Urban Development in 2005 with the

    objectives to create economically productive, efficient, equitable and responsive cities; to

    improve and augment the economic and social infrastructure of cities and to ensure basic

    services to the urban poor including security of tenure at affordable prices, etc. The

    JNNURM has two sub-missions – one on urban infrastructure and governance and

    another on basic services to urban poor. Urban infrastructure and governance has

    elaborate programme monitoring and evaluation system that has user manual data entry

    formats for city development plan. Monitoring formats have been devised for quarterly

    reporting. City development plan and detailed project report user manuals have been

    prepared as tools for programme monitoring and evaluation system (www.jnnurm.nic.in).

    Elaborate guidelines have been structured and expected outcomes outlined but how these

    outcomes will be achieved is not defined.

    Some of the observations on the scheme are as follows;

    Amazingly, no clear time-lines with mile-stones of project are given. Similarly,

    flow of daily progress report (DPR) is presented and progress is tracked through

    on-line but it is not clear how frequently the progress is tracked and how the

    information generated is analyzed for the operational and strategic decisions.

    More quantitative and qualitative details are required for better reporting of the

    scheme, particularly in regard to projects proposed, projects completed on

    housing, road, drainage, etc. along with cost benefit analysis, impact assessment

    etc.

    http://www.jnnurm.nic.in/

  • 22

    The quarterly progress report is available up to the first quarter (April-June,

    2010). Apparently, time-lag is substantive in reporting the information.

    There is no information on which analytical reports are prepared based on the

    information generated, nor if there outcome indicators developed in the case of

    DPR of beneficiaries.

    No feedback device is given in the portal which is essential to measure the project

    implementation framework.

    The Way Ahead

    It is of paramount importance to institutionalize a credible MIS in every major

    project or programme with a detailed conceptual framework. It has been noted that in

    many of the programmes or projects there have been some sort of MIS for tracking the

    progress, but still there is a scope for further improvement so that it becomes evidence-

    based management tool.

    Massive public investments are being made on development programmes and

    projects and obviously governments and other stakeholders want to know how well and

    to what extent the delivery mechanism is achieving the desired goals or intents of

    policies. For instance, in thirteen flagship and iconic programmes Rs. 5,310 billion has

    been proposed to be invested during the XIth Five Year Plan, and without any credible

    MIS and monitoring system in place the efficacy and effectiveness of these programmes

    will remain largely unknown.

    There is disconnect between the information gathering, monitoring and measuring

    impacts in most of the projects or programmes. Even having elaborate information

    collection system and monitoring mechanism in place does not necessarily lead to impact

    evaluation of most of the social programmes. Report of the Evaluation Gap Working

    Group (2006) aptly described “most of these resources are directed toward monitoring the

    use of funds, deploying and managing personnel, and producing outputs and services. By

    contrast, relatively little is spent to rigorously assess whether programs are having the

    desired impact beyond what would have occurred without them”. There is greater

    demand for effective and efficient utilization of public money with clear impacts and

    governments are under enormous pressure to demonstrate results both on account of their

    survival and greater value to public money.

  • 23

    There is, therefore, a need for an M&E framework in place in every project or

    programme that eventually aids to improve the design and delivery of projects,

    programmes and policies and it must move beyond an emphasis on inputs and outputs to

    a greater focus on outcomes and impacts or results. There ought to be visibly clear

    linkages between evaluation findings and resource allocation in order to narrow down the

    hiatus between the intents and outcomes of the programmes. We must clearly learn the

    lesson that is driving development evaluation in many developing countries with clear

    results and also to unlearn from our own experiences. Obviously, there is a need for

    building institutional capacity, developing capabilities and competencies and strong

    demand for ownership of an evaluation system in order to spreading evaluation culture as

    part of economic reforms.

    Acknowledgements

    Author is grateful to Dr. Santosh Mehrotra for guidance and helpful comments and Mr.

    Indra Kumar for providing valuable inputs in preparation of this paper.

    Bibliography

    1. Adhikari, Saroj K. and Bredenkamp, Caryn, Moving Towards an Outcomes-Oriented Approach to Nutrition Program Monitoring: The India ICDS Program.

    Discussion Paper, Health, Nutrition and Population, The World Bank, 2009.

    2. Ambasta, Pramathesh, Programming NREGS to Succeed. The Hindu, October, 30, 2009.

    3. Bajpai, Nirupam, Jeffrey D. Sachs and Dholakia, Ravindra H., Mid-term Evaluation of the National Rural Health Mission. Working Paper No. 37, Center

    on Globalization and Sustainable Development, The Earth Institute at Columbia

    University, 2009.

    4. Center for Global Development, Report of the Evaluation Gap Working Group, When Will We Ever Learn? Improving Lives through Impact Evaluation.

    Washington, D.C., 2006.

    5. Gupta, M.P., Management Information System at National Level in India: Analysis of Problems and Issues. Vikalpa, Vol. 21, No. 3, July-September 1996.

    6. Kusek, Jody Zall and Ray C. Rist, Ten Steps to a Result-based Monitoring and Evaluation System. The World Bank, DC, 2004.

    7. Linda, G. Morra Imas and Ray C. Rist, The Road to Results: Designing and Conducting Effective Development Evaluation. The World Bank, Washington DC

    20433, 2009.

    8. Organization for Economic Co-operation and Development, DAC Principles for Evaluation of Development Assistance. Paris, 1991.

  • 24

    9. Planning Commission, Government of India, Eleventh Five Year Plan (2007-12), Vol. I, Chapter 3, 2008.

    10. Programme Evaluation Organization (PEO), Planning Commission, Monitoring Information System (MIS) of Major Schemes. September, 2009.

    11. http://www.bharatnirman.gov.in; www.pmgsy.nic.in; www.nrega.nic.in; http://www.ssa.nic.in; www.wcd.nic.in; www.mohfw.nic.in; www.ddws.nic.in;

    www.education.nic.in; www.jnnurm.nic.in

    Glossary

    Anganwadi: Courtyard shelter is government sponsored child-care and mother-care

    centres.

    Bharat Nirman: Unlocking rural India’s development potential through infrastructure.

    Block: Community development block is a rural area earmarked for development.

    Gram Panchayat: Gram panchayat or village panchayat is units of self-government. They

    are like village courts.

    Gram Sabha: All men and women in the village who are above 18 years of age form the

    Gram Sabha (village councils).

    Panchayat Raj Department: Government by the village council.

    Indira Awaas Yojana (IAY): The scheme is named after the former Prime Minister Mrs.

    Indira Gandhi.

    Jawaharlal Nehru National Urban Renewal Mission (JNNURM): The programme is

    named after the first Prime Minister of India, Jawaharlal Nehru.

    Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA): The

    programme is named after the Father of the Nation, Mahatma Gandhi

    Pradhan Mantri Gram Sadak Yojana (PMGSY): Rural road connectivity programme

    named after the Prime Minister.

    Rajiv Gandhi Grameen Vidyut Yojana (RGGVY): The programme is named after the

    former Prime Minister Mr. Rajiv Gandhi.

    Sarva Shiksha Abhiyan (SSA): is a programme for achievement of universalization of

    elementary education (UEE) in a time-bound manner making free and compulsory

    education to the children of 6-14 years age group, a fundamental right.

    http://www.bharatnirman.gov.in/http://www.pmgsy.nic.in/http://www.nrega.nic.in/http://www.ssa.nic.in/http://www.wcd.nic.in/http://www.mohfw.nic.in/http://www.ddws.nic.in/http://www.education.nic.in/