25
1 Lessons for the wind industry from Australia NZWEA Conference, Wellington, New Zealand Ashley Grohn 1 May 2019

Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

1

Lessons for the wind industry – from Australia

NZWEA Conference, Wellington, New Zealand

Ashley Grohn

1 May 2019

Page 2: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

2

Outline

Current State

Future State

➢Trends

➢Uncertainties

Lessons learned

Page 3: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

3

Current State

Page 4: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

4

-

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

Queensland New SouthWales

Victoria SouthAustralia

Tasmania

Insta

lled c

apacity (

MW

)

Source: Australian Energy Regulator (AER), Sept 2018

Installed generation capacity

Current state: the National Electricity Market is

still dominated by coal fired power generation...

...however the age of the fleet means the next 10-20 years will see ~ 75%

of this capacity retire, and the Lowest LCOE is VRE (wind and solar)

Black coal

Brown coal

Gas

Hydro

Wind

Liquids

Solar

Other

Installed generation capacity share of market

Page 5: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

5

Coal retirement forecast

-

5,000

10,000

15,000

20,000

25,000

30,000

201

2

201

4

201

6

201

8

202

0

202

2

202

4

202

6

202

8

203

0

203

2

203

4

203

6

203

8

204

0

204

2

204

4

204

6

204

8

205

0

Fore

cast re

gis

tere

d c

apacity,

bla

ck c

oal (M

W)

Wallerawang C (1,000MW)

Hazelwood (1,760MW)

Liddell (2,000 MW)

Gladstone (1,680 MW)

Vales Point B (1,320 MW)

Bayswater (2,640 MW)

Eraring (2,820 MW)

Yallourn W (1,480 MW)

Tarong (1,400 MW)

Loy Yang A (2,210 MW)

Callide B (700 MW)

Callide C (900 MW)

Mt Piper (1,400 MW)

Millmerran (852 MW)

Tarong North (450 MW)

Stanwell (1,460 MW)

Loy Yang B (1,026

MW)

Kogan Creek

(744 MW)

Legend

QLD

NSW

Vic

The impending Liddell exit has sparked debate

about the impact of renewables

Reductions in dispatchable capacity have driven policy developments to

maintain security and reliability, as variable renewables share increases

• Queensland coal generators

are the youngest in the NEM

and despite being more

modern, have more limited

flexibility to deal with variability

of wind and solar

• Victorian brown coal

generators are the biggest

emitters of carbon dioxide on a

per unit output basis

• The impact of coal retirements

on wholesale pricing in South

Australian and Victoria mean

that policy makers are

increasingly focussed on

ensuring long notice periods for

closures

Page 6: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

6 Source: All target data from Clean Energy Regulator, www.cleanenergyregulator.gov.au/RET, State targets various State Govt publications

Note Vic and QLD target detailed pricing and mechanisms under development, NSW net zero emissions aspiration by 2050

Renewable energy capacity has grown 100 fold

since 2001, forecast to quadruple to 2030

State targets are likely to be the driver of additional

renewables deployment (Vic +5GW and QLD +5GW)

4204 MW

5000 MW

680 MW

73 MW

33.6 MW

11100 MW

17050 MW

9105 MW

37 GW10 GW0.1 GW

2030 FC20182001

100 X 4 X

Deployment driven by Federal

Government renewable target and state

based rooftop solar subsidies

Page 7: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

7

Declining renewable PPA prices and political

uncertainty is driving corporates to buy direct

40

60

80

100

120

140

160

180

200

220

240

2011 2012 2013 2014 2015 2016 2017 2018

AU

D$/M

Wh

Australian Renewable PPA Prices

Wind Farm

Wind Farm

Wind Farm

Wind Farm

0

200

400

600

800

1000

1200

1400

1600

2016 2017 2018

Annual M

W c

orp

ora

te P

PA

capacity

NSW

QLD

SA

VIC

Corporate PPA activity by capacity and region

Source: Company announcements, public information

This creates opportunities for large energy users to mitigate price risk

In the absence of power purchase agreements from the large retailers, corporate agreements

enable developers to underwrite new build assets. This in turn is leading should see an increase

in retail competition as typically smaller contracts require multiple power purchaser per project

Page 8: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

8 Source: Australian Energy Regulator (AER)

Growth in rooftop solar is likely to further

increase this requirement for flexible supply

Minimum daytime operational demand, forecastMaximum daytime operational demand, forecast

1 GW in 2-3 hours

1.5 GW in 3-5 hours

Future rooftop solar creates a significant need

for a ‘ramp’ period in the afternoon where

hundreds of MWs need to come online. Local

firming capacity to meet this ramp will come

from gas, demand management, and storage.

SA will remain reliant on interconnector(s) to meet local net

demand profiles without new peaking plant or energy storage

Page 9: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

9

SA Market snapshotN

SP

sL

oa

d

Syncons – System Strength1

Eyre Peninsula – New Demand (Iron Road or Liberty?)2

SA Grid ~ 50%

renewable@

SA Grid ~ 70-75%

renewable@Additional announced utility and rooftop solar (AEMO March 2018)

1 AEMO December network update indicates 18-24 months2 Assumes ruling by AER mid CY 2018 with target delivery as per the PACR www.electranet.com.au/wp-content/uploads/2017/04/20170428-Report-EyrePeninsulaElectricitySupplyOptionsPSCR.pdf3 Assumes interconnector RITT process proceeds further to the publication of AEMO’s Integrated System Plan, to be published mid 20184 OZ Minerals Power strategy indicates new transmission line must be operational mid 2020 www.ozminerals.com/uploads/media/180309_OZ_Minerals_power_strategy_ASX_Release.pdf5 BHP has indicated a possible board decision on Brownfield Expansion Project (BFX) to be taken in 2020. Given timing of BHP procurement processes. + 2 year construction time to 2022/20236 AGL TIPS replacement no net increase in capacity. Origin (180MW) and Alinta (300MW) development approval submissions in CY2018 assume 18-24 month construction time from approval

New line and demand by mid 20204

New Interconnector – SA-NSW (requires TransGrid involvement on NSW side of border)3. Expect 5-8 year delivery

Decision on BFX to be taken in 2020 – assume 2-3 year build time for new transmission line5

Su

pp

ly ~100-400MW net new peaking capacity6

Committed

Not committed

Market activity shown relative to a typical WF development process

Priva

te S

ecto

r

Currently ~4,000MW new utility solar supply (includes SA Water Project Zero)

Today2019 20212020 2022 2023

Process

Delivery

TY

P W

ind F

arm

Prep

Page 10: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

10

Trends &

Uncertainties

Page 11: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

11

Trends have clear patterns that move incrementally in a specific direction, you can say something is increasing, decreasing or remaining stable and can make an educated estimate of how it will play out.

Uncertainties are where feedback loops between trends interact to generate multiple plausible outcomes for how they will develop in the future, they are impacted by decisions yet to be made and unforeseen events.

The distinction between uncertainties and trends

Page 12: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

12

• Identified over 40 trends through the

stakeholder interviews and review of

existing scenarios and research

• Grouped those trends into four main

categories of uncertainties

1. Decentralisation

2. Lower carbon future

3. Energy consumption

(Electrification)

40 trends acting at multiple scales grouped into 4 key

uncertainties that will shape the future of the NEM

Global

National

Industry

NEM

Transco

Page 13: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

13

Orchestration of DER is essential

-

3,000

6,000

9,000

-

20,000

40,000

60,000

80,000

Cu

mu

lative

ca

pa

city (

MW

)

Mo

nth

ly in

sta

llatio

ns

Monthly installations (left hand axis) Cumulative installed capacity (right hand axis)

Solar PV uptake in the National Electricity Market

Sources: (APVI, 2018) (IRENA, 2017)

Potential future grid options

Increasing

installation

sizes

1

Virtual Power Plant Example

• The South Australian virtual power plant

has already begun solar PV and battery

installations

• The project aims to complete installation

of 50,000 home power and battery

systems for a total 250 MW capacity.

Electricity data will be conveyed via smart

phone applications. Generated energy

will be first dispatched to the household

with excess generation dispatched to the

grid.

Page 14: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

14

Product Load

Forecasting

RE

Forecasting

Power

Optimisation

Portfolio

Optimisation

Price

Forecasting

Merchant

Trading

Metering

Data Mgmt

Digital Twin Intelligent

Asset Mgmt

Edge

Integration

DSO ✅ ✅ ✅ ✅ ✅ ✅ ❌ ✅ ✅ ✅

VPP ✅ ✅ ✅ ✅ ✅ ✅ ✅ ✅ ✅ ✅

Embedded

Grid

✅ ✅ ✅ ✅ ❌ ✅ ✅ ❌ ❌ ✅

Retailer ✅ ✅ ✅ ✅ ✅ ✅ ✅ ❌ ❌ ✅

Storage ✅ ✅ ✅ ✅ ✅ ✅ ❌ ❌ ❌ ✅

Gentailers ✅ ✅ ✅ ✅ ✅ ✅ ❌ ❌ ❌ ❌

RE

Generators

❎ ✅ ❌ ✅ ✅ ✅ ❌ ❌ ❌ ❌

Orchestration of DER

Use of AI / Machine Learning

brings other opportunities….

1

Page 15: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

15

Even in a federal policy vacuum,

decarbonisation is a matter of when….2

Page 16: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

16

Fast evolving energy storage advances give

us confidence, but there are limits ….2

Page 17: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

17

Energy Consumption -

Demand growth opportunities3

Demand growth at Tx scale can come from ICT (eg. data centres)

and development of a global hydrogen economy

Source: (CSIRO, 2018)

https://www.chiefscientist.gov.au/wp-

content/uploads/HydrogenCOAGWhitePaper_WEB.pdf

https://www.csiro.au/en/Do-business/Futures/Reports/Hydrogen-

Roadmap

Page 18: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

18

Lessons Learn(ing)

Page 19: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

19

MLF - Background

May result in grid congestion and increased energy losses which impact project revenue

Identifying causal factors of congestion & losses supports quantification of curtailment and loss factor risk

Accurate quantification of these risks increases investment certainty & supports strategy

Large generators increasingly connecting to grid locations not dimensioned for bulk power supply

Tomas Keraitis (Aurecon)

CEC – Wind Industry Forum, Melbourne 2019

Using AI to improve forecasting of grid congestion and loss factors

Presentation

Page 20: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

20

Generators:

o Buildout scenarios (when and where)

o Retirements

o Generating profiles

o Availability

Demand:

o New large load connections (e.g. mines)

o Large load retirements

o Demand profile

o EV Uptake

Market:

o Spot prices

o Bidding behaviour

o Inter-regional (interconnector) power flows

o Constraint equations

Network:

o Plant ratings

o Augmentation/replacements

o Availability

o Re-configurations

What makes MLF and curtailment forecasting challenging?

Non-linear correlated complex variables

In addition to existing complexity, our energy system is rapidly evolving

Study inputs

Page 21: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

21

Value

Drivers

“Classical” Power System

Simulation Based Approach

Machine Learning

Approach

Computational

Efficiency

Requires high computer

processing effort

Less computing power required.

Once model is trained, results

are rapid

Error

Quantification

Calculated manually on the basis

of user experience/knowledge

Calculated by the computer on

the basis of data and patterns

FlexibilityRestricted to the capability of the

software packages being used

Can overlay many dimensions of

data potentially supporting

deeper insights

Existing approach versusMachine Learning

Machine learning techniques require large amounts of input data but provide deeper insights than classical techniques

Page 22: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

22

Significant transmission investment planned

Source: AER, AEMO Interconnector Capabilities Report. AEMO Integrated System Plan (AEMO) 2018

QNI (AC)

2 x NSW-Vic (AC)

Terranora (DC)

Red Cliffs (AC)

Basslink (DC)

Heywood (AC)

MurrayLink (DC)

ISP and NEM interconnectorsISP and REZ’s

Interconnections are recognised as a key ‘enabler’ that unlocks value for

intermittent renewables by diversifying the generation and load pools

Page 23: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

23

Widely varying levels of

performance

Owner & Site Team > Contractor

Early establishment of culture

Make it personal ……..

Don’t rely on past performances

Don’t underestimate the value of

detailed EPC negotiations pre-FC

Construction / Implementation

Site Safety Performance

0

5

10

15

20

25

Incid

ents

per

100,0

00 w

ork

er

hours

Health and Safety Events for projects

Injury Rate Incident Rate (including near miss events)

Page 24: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

24

Under investment in pre-FC project

planning (MacLeamy Curve) – is there a

need to shift to integrated project

teams?

Un-finalised project agreements at FC:

➢ Generator Registration (AEMO / Rule changes)

➢ Local council approvals (roads, landowners,

infrastructure, etc)

Timely involvement of cranage

contractor(s) in design process

Repeat of lessons learned from ~10

years ago …… don’t assume

knowledge is retained

Inter-related learnings from utility scale

solar

Construction / Implementation

Site factors (delays and over-runs)

MacLeamy CurveRef: https://www.danieldavis.com/macleamy/

Page 25: Lessons for the wind industry from Australia...4-2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 Queensland New South Wales Victoria South Australia Tasmania) Source: Australian

Follow us on

www.twitter.com/Aurecon

Join us on

www.facebook.com/Aurecon

Watch us on

www.youtube.com/user/AureconGroup

Follow us on

www.instagram.com/Aurecon

Follow us on

www.linkedin.com/company/Aurecon

Follow us on

www.slideshare.net/Aurecon

Ashley Grohn

Client Director – Energy APAC

+61 491217021