19
Challenges in the Nordic Power system NordREG meeting, Arlanda, June 25, 2014 Lennart Söder Professor in Electric Power Systems, KTH Electric Power Systems Power System Dynamics and Control Smart Transmission Systems Power System Operation and Planning Electricity Market analysis Electric Power Systems Power System Dynamics and Control Mehrdad Robert (pd) Mohamadreza Amin Mohammad Na. Marina Afshin Harold Omar Smart Transmission Systems Luigi Raphael (pd) Rujiroj (pd) Almas Tetiana Yuwa Wei Vedran Doan Tu Jan Power System Operation and Planning Lennart Lars (pd) Pia Camille Yalin Angela German Ilan Desta Electricity Market analysis Mohammad Hector (pd) Ekatrina Mahir Richard Yaser Kristina Yelena Ezgi Mikael Ebrahim Ilias Richard Some Nordic Power System Challenges A. Pricing challenges B. High share of variable renewables C. Smart-grids: Consu- mer interaction D. Covering Peak load Discussion: 1. DSO role and responsibility 2. Information exchange TSO role and responsibility, access between hubs/information-exchange systems 3. Market rules for demand response 4. Market rules energy services 5. Market rules micro-production 6. Market rules for charging electrical vehicles 7. Unbundling etc

Lennart Soder Presentation Nordic Regulators 140625

  • Upload
    fpttmm

  • View
    221

  • Download
    5

Embed Size (px)

DESCRIPTION

na

Citation preview

  • Challenges in the Nordic Power system

    NordREG meeting, Arlanda, June 25, 2014

    Lennart SderProfessor in Electric Power Systems, KTH

    Electric Power Systems

    Power System Dynamics and Control

    Smart Transmission Systems

    Power System Operation and Planning

    Electricity Market analysis

    Electric Power Systems

    Power System Dynamics and Control

    MehrdadRobert (pd)MohamadrezaAminMohammad Na.MarinaAfshinHaroldOmar

    Smart Transmission Systems

    LuigiRaphael (pd)Rujiroj (pd)AlmasTetianaYuwaWeiVedranDoan TuJan

    Power System Operation and Planning

    LennartLars (pd)PiaCamilleYalinAngelaGermanIlanDesta

    ElectricityMarket analysis

    MohammadHector (pd)EkatrinaMahirRichardYaserKristinaYelenaEzgi

    MikaelEbrahimIliasRichard

    Some Nordic Power System Challenges

    A. Pricing challengesB. High share of

    variable renewablesC. Smart-grids: Consu-

    mer interactionD. Covering Peak load

    Discussion:1. DSO role and responsibility2. Information exchange TSO role and

    responsibility, access betweenhubs/information-exchange systems

    3. Market rules for demand response4. Market rules energy services5. Market rules micro-production6. Market rules for charging electrical

    vehicles7. Unbundling etc

  • Pricing challenges in the future Nordic Power Market with large

    amounts of renewable low marginal cost units.

    Nordic Power SupplyTWh 2012

    Country Nuclear Hydro Fossil Wind Bio Total

    Norway 0 142,9 2,4 1,6 0 147,8Finland 22,1 16,6 17,9 0,5 9,9 67,7Sweden 61,2 77,7 4,6 7,1 10,8 161,6Denmark 0 0,02 16,3 10,2 2,3 29,4

    In 2012 the Nordic hydro power production was 237 TWh.

    This corresponds to an inflow of around 4,5 TWh/week

    A heavy rain every second week implies 9 TWh

    Nordic hydro power New Nordic interconnections. ENTSO-E: Ten-Year Network Development Plan 2012

    2012-2016 2017-2022

  • Energy is produced where the resource isThe energy has to be transported to consumption centerThe energy inflow varies, which requires storage and/or flexible system solutions

    This is valid for hydro power, wind power, and solar power

    Renewable energy systems Example

    Nordic hydro power (inflow) can vary 86 TWh between different years (2001 to 1996)Transport from NV to SE + continent Energy balancing with thermal power in i Dk+F+Ge+Pl+NL+Ee

    Wind power gives the same variations/uncertainties (and solutions) as hydro power.But: time perspective is much shorter!

    Transmission capacity plansfor Sweden

    Sweden-neighbours: ca 10100 MW(continuously 88 TWh/year)Nordel-neighbours: ca 5500 MW (DC!)

    Plans:Jrpstrmmen-Nea, S-N, ~1000 MW(South-West link, S-N, 2x600 MW -cancelled)Nordbalt, S-L, ~600 MWNew line to GotlandStrengthening North to FinlandNew cut 2 line, ev. DC Sweden-neighbors: +~1600 MW

    Pricing in power systems

    Thermal power systems: Price is set by marginal costHydro power: Price is set by the water value = the expected marginal cost in the future to which the water could be stored.Wind power: Price is set by marginal cost = negative subsidy, since subsidy is only obtained at production (e.g. -2 Euro-cent if certificate price is 2 Euro-cent.)

  • Pricing in power systems:Norway

    Nearly only hydro power (97%)Price is set by the water value = the expected marginal cost in the future to which the water could be stored. Price is not set in Norway!

    Pricing in power systems:Sweden

    Hydro + Nuclear + wind (90%)Large part of the rest is CHP (industrial and distr. heat) Price is set by the water value = the expected marginal cost in the future to which the water could be stored. Price is not set in Sweden!

    Pricing in power systems:Denmark

    2020: High wind power (50%)A part of the rest is CHP (industrial and distr. heat) When it is windy, then the prices will be low

    High prices are often not set in Denmark!

    Pricing in power systems:Finland

    Nuclear + hydro + wind (58%-now)CHP + more nuclear in the futureAt wind and low demand, then the prices will be low

    Prices are then often not set in Finland!

  • Pricing in future Nordic power systems:

    Much more often: Prices are not set by Nordic power plants.At wind and low demand, then the prices can be really low There is then a challenge to get prices that are high enough to finance all power plant.Enough transmission to high MC areas essential

    Identified wind power projects in Sweden:

    Identified wind power projects: 45000 MW ( 100 TWh/year)

    Today capacities: Hydro Power: 16000 MW ( 65

    TWh) Nuclear power: 9000 MW ( 65

    TWh) total of 25000 MW

    Results from new Swedish studies on larger amounts of wind power

    Lennart Sder, KTH

    IEA Wind, Task 25, MeetingGolden/Denver/NREL, April 9, 2014

    Swedish production: Total: 145,6 TWh(same as 2011)

  • Current (2011) Swedish Power System

    Source TWh -2011

    Energy % -2011

    MW-capacity -2011

    Hydro 66,0 44,9 16197Nuclear 58,0 39,5 9363Wind 6,1 4,2 2899Solar 0 0 0CHP-Ind 6,4 4,4 1240CHP-distr. 9,4 6,4 3551Condens 1,01 0,7 3197Total 146,9 100 36447

    Studied Swedish Power System

    Source TWh Energy % MW-max

    Hydro 64,9 44,5 12951Nuclear 0 0 0Wind 46,7 32,1 15633Solar 12,6 8,6 9849CHP-Ind 6,4 4,4 1240CHP-distr. 13,9 9,5 4126Other 1,3 0,9 5081Total 139,9 100 48180

    Hydro power: Duration curve

    Min level: 1875 MW: Needed during 860 hoursMax level: 12951 MW: Needed during 765 hours

    Deficit situation

    High wind decrease in CHP

    50 100 150 200 250 300 350 4000

    0.5

    1

    1.5

    2

    2.5

    x 104

    M

    W

    h

    /

    h

    Consumption from 14 January to 30 January

    ConsumptionHydro powerWind powerSolar powerCHP

  • Deficit situation (yearly basis)Assumed need of OCGT

    Cost for this: 2 re/kWh = 0,2 Eurocent/kWh

    0 500 1000 15000

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    4500

    5000

    Number of hours with need of more production

    E

    n

    e

    r

    g

    y

    l

    e

    v

    e

    l

    [

    M

    W

    h

    /

    h

    ]

    Max level: 5081 MW

    Number of hours with need: 765 h

    Energy: 1.259 TWh

    Surplus situation (August)

    Not OK: 83% limit, min-hydro, min-CHP

    20 40 60 80 100 120 140 160 180 200 2200

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    M

    W

    h

    /

    h

    Consumption from 1 August to 10 August

    ConsumptionHydro powerWind powerSolar powerCHP

    Now OK: 83% limit, min-hydro, min-CHP

    Surplus situation (August)

    20 40 60 80 100 120 140 160 180 200 2200

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    M

    W

    h

    /

    h

    Consumption from 1 August to 10 August

    ConsumptionHydro powerWind powerSolar powerCHP

    Surplus during a year

    0 200 400 600 800 1000 12000

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    9000

    Number of hours with surplus/possible export

    E

    n

    e

    r

    g

    y

    l

    e

    v

    e

    l

    [

    M

    W

    h

    /

    h

    ]

    Energy volume: 1.63 TWh

    Max level: 9510 MWNumber of surplus hours: 860 h

  • General transmission challenge

    A. Voltage stability limits betweenareas

    B. Q-control importantC. More transmission required, but

    low utilization timeD. Challenge to identify future

    transmission capacity with less nuclear

    E. Detailed hydro simulation takes10 minutes per week.

    Surplus situation (August 1-10)

    Wind Power production

    Surplus situation (August 1-10) Surplus situation (August 1-10)

  • Transmission situation (Jan 21 Feb 1)

    Wind Power production

    Transmission situation (Jan 21 Feb 1)

    Transmission: Yearly duration : today 7000 MW On transmission needs

    A. Increase production in receivingend (= thermal, currently OCGT)

    B. Capacity is available, small energy increase for first GW.

    C. Since limit is voltage stability, SVC may be enough

    D. Discussion on exchange of AC toDC

    E. Optimization approach may be interesting

  • Pricing in power systems

    With an assumption of perfect competition:Prices are based on production marginal costsLow costs units are used firstHigher load higher prices:

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    1 10 19 28 37 46 55 64 73 82 91 100 109 118 127 136 145 154 163

    Weekly demand

    0

    20

    40

    60

    80

    100

    120

    1 13 25 37 49 61 73 85 97 109 121 133 145 157 169

    E

    u

    r

    o

    /

    M

    W

    h

    Pricing

    Pricing in presence of variable sources (e.g. wind)

    Wind power has a marginal cost zeroThe production level is depending on wind speedIt is not easy to make good long term (hours) forecastsOther units have to cover the net load = demand - wind

    0500

    1000150020002500300035004000

    1 13 25 37 49 61 73 85 97 109 121 133 145 157 169

    M

    W

    h

    /

    h

    Weeklydemand+ wind

    -5000

    500100015002000250030003500

    1 13 25 37 49 61 73 85 97 109 121 133 145 157 169

    M

    W

    h

    /

    h Weeklynetdemand

    W Denmark 10/1-17/1 2005

    Pricing in presence of variable sources

    -5000

    500100015002000250030003500

    1 13 25 37 49 61 73 85 97 109 121 133 145 157 169

    M

    W

    h

    /

    h Weeklynetdemand

    Thermalpricing

    0

    20

    40

    60

    80

    100

    1 13 25 37 49 61 73 85 97 109 121 133 145 157 169

    E

    u

    r

    o

    /

    M

    W

    h

    Other units have to cover the net load = demand windThe other units production is controlled by price! more volatile prices

    Note: This is independent of fixed price etc

    0

    20

    40

    60

    80

    100

    1 13 25 37 49 61 73 85 97 109 121 133 145 157 169

    E

    u

    r

    o

    /

    M

    W

    h

    Solutions and competition

    Assume a system with large pricevariation: Three types of business opportunities

    More trading with neighbors Flexible plantsDemand side management

    There is a competition between these methods. Much transmission reduces price changes less interest in DSM

  • Peak capacity responsibilities

    Norway: TSO-Statnet is responsible for enough capacityFinland: TSO-Fingrid is NOT

    responsible for enough capacitySweden: TSO-Svenska Kraftnt is

    NOT responsible for enough capacity. But: up to 2000 MWDenmark: TSO-Energinet.dk is

    responsible for enough capacity

    Peak capacity responsibilitiesexample 1

    1. Assume that there is a capacity problem in South Sweden and Denmark exports 1000 MW to Sweden.

    2. Assume that there is an outage in Denmark so they have to decrease consumption.

    3. According to EU legislation non-discrimination Denmark cannot prioritize Danish consumers before Swedish ones.

    4. Does this has as a consequence that Denmark is also responsible for Sweden?

    Peak capacity responsibilitiesexample - 2

    1. There are discussions of capacity payments to a rather large volume in UK

    2. Probably this then leads to comparatively low energy prices compared to a case with no cap. payments

    3. Both Norway and Denmark plan new cables to UK.

    4. Does this mean that Denmark and Norway can import and only pay the energy price?

    Peak loads in Sweden 1992-2011

    Year 1992 - 2011

    M

    W

    h

    /

    h

  • High load reserves in SwedenSelective capacity market

    TSO responsible to purchase up to 2000 MW of reserves for peak load situations.There is a bidding process where the cheapest offers are accepted.Pricing:The bids are placed on Nordpool spot. They are only used if all other bids are accepted.The Net Regulation Price should not be allowed to exceed 5,000 Euro/MWh.TSO can immediately impose a Disconnection Price in The event of Critical Power Shortage of 20 000 SEK/MWh 2300 Euro/MWhAustralia: Max price 12000 AUD 9000 Euro/MWh

    Reserves in Sweden 2012-13Consumers accepted to reduce consumption

    Company Area MWStora Enso AB 3-4 210Hgans Sweden AB 4 25Rottneros Bruk AB 3 27Befesa Scandust AB 4 18Vattenfall AB 3-4 92Gteborg Energi AB 3 25AV Reserveffekt 3-4 + 67TOTAL 464

    Risk for prices so low so power plants cannotbe financedLarge amounts of renewables often verylow pricesBut still other units are needed need of either (very) high prices or somekind of capacity payment mechanism.Large amount of transmission is one part solution, but perhaps also large amounts ofsolar/wind power on the other end?

    Summary of (some) Nordic market challenges

    There should be a (renewable) unit (biogas?) with MC as

    Idea to market solution to last unit

    Call it a market maker unit reduced need of cap. payment. If DSM is cheaper then it will be used instead As low LOLP as requested can be obtained (= size of unit)

    High operation cost (or bidprice) essential

  • How high costs should we allow tomake market work:Costs for market-making plantsCosts for new lines are needed toincrease the number of participants and to decrease risk of use of market powerCosts for IT solutions for consumerflexibility since this is essential to make the market work.

    Comments toNordic market challenges

    How high costs should we allow tomake market work:Costs for market-making plantsCosts for new lines are needed toincrease the number of participants and to decrease risk of use of market powerCosts for IT solutions for consumerflexibility since this is essential to make the market work.(But what is the alternative?)

    Comments toNordic market challenges

    Some Nordic Power System Challenges

    A. Pricing challengesB. High share of

    variable renewablesC. Smart-grids: Consu-

    mer interactionD. Covering Peak load

    Discussion:1. DSO role and responsibility2. Information exchange TSO role and

    responsibility, access betweenhubs/information-exchange systems

    3. Market rules for demand response4. Market rules energy services5. Market rules micro-production6. Market rules for charging electrical

    vehicles7. Unbundling

    1. DSO role and responsibility- More distributed power production,- PV voltage control (rules or market?)- Supply voltage to feeding grid- Coordination with retailer concerning DSM- Grid planning? (if DG pays connection, then why plan?)2. Information exchange TSO role and responsibility, access between hubs/information-exchange systems- DSO:s possibility to help TSO- Peak capacity: Market? Tender? Rely on neighbours?

    Comments to someNordic market challenges - 1

  • 3. Market rules for demand response- Contract with DSO and/or retailer?- React on prices and/or externally controlled?- Time frame: minutes/hours- How long time in advance are one informed?4. Market rules energy services- DSO:s possibility/responsibility to help TSO (Q-support)- DG ancillary services requires ICT technology

    Comments to someNordic market challenges - 2

    5. Market rules micro-production- How to handle voltage control at large scale?- React on prices and/or externally controlled?- Time frame: minutes/hours- 100% access to grid or less? (cheaper)6. Market rules for charging electrical vehicles- Possibility to have same price everywhere?- Different price/taxes special meter ?- Externally controllable? If so: How?

    Comments to someNordic market challenges - 3

    7. Unbundling etc- Not so rational if TSO should plan for all possible

    expansion of wind power- Off-shore grids- How much should Swedish grid-users pay for power

    transferred through Sweden?- More detailed DSO-regulation?- How to allow TSO:s to take risks for long-term

    investments?- How to make neighbor TSO:s to think about total social

    surplus

    Comments to someNordic market challenges - 4 Reserve slides

    Lennart Sder, KTH

    Arlanda, June 25, 2014

  • What is a good market? - 1

    Static allocation efficiency (=are available resources used as efficient as possible? E.g. in deficit situations)Management efficiency (= is the administrative organization efficient?)Plant operation efficiency (= is each plant operated in an efficient and reliable manner?)Production optimization (= correct merit order = is cheapest possible operation, including externalities, applied?)

    What is a good market? - 2

    Transaction cost efficiency (= the amount of transactions costs, as measurements, spread of information and contracts)Dynamic investment efficiency (= are the correct investments done at the right time?)Risk management efficiency (= are risks and uncertainties handled in an efficient way?)System reliability (= is it on a correct level?)

    C2: Surplus at 55 TWh wind+solarDifferent assumptions on wind/solar 70-90% of consumption

    0 500 1000 15000

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    9000

    10000

    Antal timmar som verskottsproduktion i Exempel 2a-2c verskrids

    E

    f

    f

    e

    k

    t

    n

    i

    v

    [

    M

    W

    ]

    Exempel 2a ej fjrrvrmeExempel 2a med fjrrvrmeExempel 2b ej fjrrvrmeExempel 2b med fjrrvrmeExempel 2c ej fjrrvrmeExempel 2c med fjrrvrme

    Solution:- Export- District heating- Other head- El. vehicles- Etc- Inertia?

    Max ca 90 percent ofconsumption- No distr. heat.- surplus:- 0,61 TWh/year

    (no nuclear)Model of CHP and district heating

    a. In Part 2 there is the assumption that one canuse surplus electricity (MC=0) in the districtheating instead of spillage.

    b. In Part 3 there is the assumption that one can use surplus electricity (MC=0) to replace CHP instead of spillage.

    c. Reality is probably both with some limitations.

  • Model of district heating - 1

    a. Total district heating in Stockholm during 2012 per hour (City-Sder, including Sderenergi and Nordvstra including E.ON Jrflla)

    0 1000 2000 3000 4000 5000 6000 7000 8000 90000

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    Stockholm fjrrvremeleverens under 2012

    [

    M

    W

    ]

    Model of district heating - 2

    a. Amount of excess of wind+solar > 75% ofdeman.

    0 1000 2000 3000 4000 5000 6000 7000 8000 90000

    2000

    4000

    6000

    8000

    10000

    12000

    Timme p ret med niv ver 75 procent av frbrukning

    E

    f

    f

    e

    k

    t

    n

    i

    v

    [

    M

    W

    ]

    januari februari mars april maj juni juli augusti september oktober november december

    Model of district heating - 3

    Assumptions:a. Swedish yearly disstrict heating same profile as

    in Stockholmb. Same level of fuel waste as today (18%) which

    is not replace (negative MC)c. Heat spillage or rkgaskondensering not

    replaced with electricity.

    Model of district heating - 4

    a. Result for the potential of heat replacement

    0 1000 2000 3000 4000 5000 6000 7000 8000 90000

    2000

    4000

    6000

    8000

    10000

    12000

    14000

    16000

    18000

    Vrmebehov under 2012

    [

    M

    W

    ]

    AvfallsfrbrnningSpillvrme

  • Model of district heating - 5

    a. Result for the replacement: 1.2 TWh used (out of3,0 TWh available surplus)

    0 1000 2000 3000 4000 5000 6000 7000 8000 90000

    2000

    4000

    6000

    8000

    10000

    12000

    Mjlig elfrbrukning (trappstegskurva) och tillgnglig elproduktion

    [

    M

    W

    ]

    Model of CHP- 1

    a. Yearly CHP production in 20110,00

    500,00

    1000,00

    1500,00

    2000,00

    2500,00

    3000,00

    3500,00

    4000,00

    4500,00

    DataKraftvrme:1Januari 31December

    Model of CHP - 2

    Model:a. 50% more CHP than today (from Profu report)b. It is possible to decrease CHP down to 25% of

    its original value during each hourc. But the total amount of hydro + CHP muast be

    17% of production (synchronous machinerequirement)

    d. Excel sheet available to change these data.

    Model of CHP- 3

    a. Example of resulting CHP decrease:

    50 100 150 200 250 300 350 4000

    0.5

    1

    1.5

    2

    2.5

    x 104

    Frbrukning frn 14 januari till 30 januari

    M

    W

    h

    /

    h

    ElfrbrukningVattenkraftVindkraftSolkraftVrmekraft

  • Model of CHP- 4

    a. Resulting CHP decrease: 0,79 TWh = 5,4%0,00

    500,00

    1000,00

    1500,00

    2000,00

    2500,00

    Resultatkraftvrmeminskning:1Januari 31December

    Model of CHP- 5

    a. Resulting CHP decrease: 0,79 TWh = 5,4%

    0

    500

    1000

    1500

    2000

    2500

    0 1000 2000 3000 4000 5000 6000 7000 8000

    Resultatkraftvrmeminskning:Varaktighetskurva;Max=2267MW;Energi=0,79TWh

    Questions on CHP + District heating

    a. Amount of waste etc (MC

  • Simulation method (Sweden isolated)2: Detailed simulation

    a. Objective function:

    b. where Hspill(k)= hydro spillage during hour k, Vspill(k) = Wind spillage during hour k, EXP(k) = extra export during hour k, IMP(k) = extra import during hour k, K = number of hours in the studied period (=168).

    Preliminary simulation for a January week

    20 40 60 80 100 120 140 1600

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    1.4

    1.6

    1.8

    2

    x 104

    Frbrukning frn 1 november till 7 november

    M

    W

    h

    /

    h

    ElfrbrukningVattenkraftVindkraftSolkraftVrmekraft

    Result after detailed simulation (normal inflow)

    0 20 40 60 80 100 120 140 1600

    0.5

    1

    1.5

    2

    x 104

    Timme under studerad vecka

    M

    W

    h

    /

    h

    FrbrukningVattenkraftVind + solvrig produktion

    Result after detailed simulation (160% ofnormal inflow)

    0 20 40 60 80 100 120 140 1600

    0.5

    1

    1.5

    2

    x 104

    Timme under studerad vecka

    M

    W

    h

    /

    h

    FrbrukningVattenkraftVind + solvrig produktion