16
1 Allens is an independent partnership operating in alliance with Linklaters LLP. Legal and Enabling Framework for PPPs in Australia Leighton O’Brien Partner Transport & Infrastructure Sector Leader 14 August 2015

Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

1 Allens is an independent partnership operating in alliance with Linklaters LLP.

Legal and Enabling Framework

for PPPs in Australia

Leighton O’Brien

Partner

Transport & Infrastructure Sector Leader

14 August 2015

Page 2: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

2

1. Background to PPPs in Australia

2. Procurement process

3. The Project Deed

4. International best practice

Agenda

Page 3: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

3

The Philippines

• The Build-Operate-Transfer (BOT) Law of 1990 as amended by Republic Act No. 7718 (the Amended BOT Law) and its Revised Implementing Rules and Regulations 2012 (the Revised IRR) authorises the financing, construction, operation and maintenance of infrastructure projects by the private sector, and for other purposes.

Australia

• Less regulated; no overall set of rules.

• Various Commonwealth/State government entities.

• Various laws and policies govern procurement process.

• Contractual provisions in relation to financing, construction, operation and maintenance are usually based on precedent deals (deals of similar type and scope).

Comparison: PPPs in the Philippines and Australia

Page 4: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

4

http://www.peo.gov.au/learning/fact-sheets/three-levels-of-law-making.html

Page 5: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

5

Background to PPPs in Australia

General PPP framework

• No legislative framework or overall set of rules governing PPPs.

• Decision on project and procurement method is decentralised to

“line agencies”.

• Control over funds is centralised within each Treasury.

State, Territory and Commonwealth government may have a centralised

PPP unit associated with Treasury.

Treasuries take a similar, but not uniform, approach.

• Tension between “line agencies” and Treasuries.

Page 6: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

6

Background to PPPs in Australia

Key bodies (States)

• Centralised PPP authorities associated with treasury department (e.g. Major Projects Victoria) – function varies between jurisdictions.

• In most jurisdictions, individual projects are procured by specific government departments or “line agencies” (e.g. Transport for NSW, RMS, Commonwealth Department of Defence).

• Infrastructure NSW assists the NSW Government in identifying and prioritising the delivery of critical public infrastructure for NSW.

Page 7: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

7

Background to PPPs in Australia

Key bodies (Commonwealth)

• Infrastructure Australia is a national statutory body that develops strategy for delivering infrastructure and modernising assets and provides advice to the Commonwealth, state, territory and local governments on infrastructure matters.

• The National PPP Policy and Guidelines, administered by Infrastructure Australia present a unified national policy framework for the procurement of PPPs.

Attempt to capture “best practice” but not a legal requirement.

Useful for benchmarking purposes.

• Public Works Committee (constituted by the Public Works Committee Act 1969 (Cth) (the Act))

All public works for the Commonwealth estimated to cost more than $15 million must be referred to the Committee.

Reports on the need for the work, cost effectiveness of the proposal, (if relevant) the amount of revenue it will produce and the current and prospective value of the work.

Page 8: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

8

Procurement Process

Procurement process for PPPs

• Typically procured through a competitive tender process, carried out with strict probity rules.

Different procurement rules / processes apply in different States and Territories.

• Bid costs usually not reimbursed.

• Few legal restrictions on foreign entities.

Foreign Investment Review Board approval may be required.

Legal considerations can be highly complex.

Foreign investors and participants will require local legal counsel.

Page 9: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

9

Procurement Process

Internal Government rules (NSW)

• Approval process governed by NSW Public Private Partnerships Guidelines (2012) +

National Guidelines.

• Procuring agency has responsibility for delivery, along with NSW Treasury.

• Sub-committee of Cabinet (Expenditure Review Committee) generally approves most

procurement milestones, including business case, EOI and negotiation parameters.

• Treasurer's approval required under the PAFA Act to enter into a Joint Financing

Arrangement.

• Project management/governance structures established at agency / whole of

government level.

• In addition to the Expenditure Review Committee, disclosure under Government

Information (Public Access) Act 2009, Contract Summary to the Auditor General.

Page 10: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

10

The Project Deed

Key issues

• Absence of PPP law gives greater flexibility both in terms of:

Form of documents; and

Process to be followed.

• However, there are many similarities in major PPPs and market precedents

are very important.

• The market has called for uniform documentation and the government is now

responding.

Page 11: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

11

• Neither federal nor state law mandates any particular form of Project Deed, although:

NSW is developing its own standard form; and

the National PPP Guidelines set out preferred terms and some procuring governments and agencies have their own standard forms.

• Common law contracting (Australian general contract law rules apply)

• Specific clauses to address and allocate market risks

Time

Cost

Quality

The Project Deed

Key issues

Page 12: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

12

• Public Authorities (Financial Arrangements) Act 1987 (NSW) (PAFA)

Key legislation for PPP arrangements.

Allows an authority to enter into a joint financing arrangement.

Reduces the complexity of contracting with government by helping parties identify the legislative authority for entering into long-term contractual arrangements.

Crown may be called upon to provide a guarantee of the contracting agency’s performance

• Common Law rules in relation to power of State to contract and who can sign.

• Internal government rules, policies provide central agency control over expenditure/contracts.

The Project Deed

Other laws

Page 13: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

13

• Australian governments have used private sector contractors to

provide a wide range of public services for many years.

• Key issues:

PPP pipeline – including, when should the PPP model be used?

Average procurement time

Bid costs

• Australian PPP success stories:

Social infrastructure – hospitals, schools

Economic infrastructure – convention centres, toll roads

International best practice

Page 14: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

14

Q&A

Page 15: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

15

Contacts

Leighton O’Brien

Partner T +61 2 9230 4205

Leighton.O’[email protected]

Page 16: Legal and Enabling Framework for PPPs in Australiappp.gov.ph/wp-content/uploads/2015/08/PH-AUS-PPP-Policy...5 Background to PPPs in Australia General PPP framework •No legislative

16 Allens is an independent partnership operating in alliance with Linklaters LLP.