Page 1: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

LECTURE NOTES ON WATER RESOURCES ENGINEERING-II

III B. Tech II semester (JNTU(A)-R13)

P.PAVITHRA

Assistant Professor

G.PULLAIAH COLLEGE OF ENGINEERING AND TECHNOLOGY

CIVIL ENGINEERING

Page 2: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

UNIT-III

RESERVOIRS-DAMS

Water storage reservoirs may be created by constructing a dam across a river, along with suitable appurtenant

structures. However, in that lesson not much was discussed about fixing the size of reservoir based on the demand

for which it is being constructed. Further, reservoirs are also meant to absorb a part of flood water and the excess is

discharged through a spillway. It is also essential to study the relation between flood discharge, reservoirs capacity

and spillway size in order to propose an economic solution to the whole project. These and topics on reservoir

sedimentation have been discussed in this lesson which shall give an idea as to how a reservoir should be built and

optimally operated. Fundamentally, a reservoir serves to store water and the size of the reservoir is governed by the

volume of the water that must be stored, which in turn is affected by the variability of the inflow available for the

reservoir. Reservoirs are of two main categories: (a) Impounding reservoirs intowhich a river flows naturally, and

(b) Service or balancing reservoirs receiving supplies that arepumped or channeled into them artificially. In general,

service or balancing reservoirs are required to balance supply with demand. Reservoirs of the second type are

relatively small in volume because the storage required by them is to balance flows for a few hours or a few days at

the most. Impounding or storage reservoirs are intended to accumulate a part of the flood flow ofthe river for use

during the non-flood months.

Page 3: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

These specific levels and parts are generally defined as follows:

Full Reservoir Level (FRL): It is the level corresponding to the storage which includes both inactive and

active storages and also the flood storage, if provided for. In fact, this is the highest reservoir level that can be

maintained without spillway discharge or without passing water downstream through sluice ways.

Minimum Drawdown Level (MDDL): It is the level below which the reservoir will not be drawn

down so as to maintain a minimum head required in power projects.

Dead Storage Level (DSL): Below the level, there are no outlets to drain the water in the reservoir by

gravity.

Maximum Water Level (MWL): This id the water level that is ever likely to be attained during

the passage of the design flood. It depends upon the specified initial reservoir level and the spillway gate

operation rule. This level is also called sometimes as the Highest Reservoir Level or the Highest Flood Level.

Live storage: This is the storage available for the intended purpose between Full Supply Level and the

Invert Level of the lowest discharge outlet. The Full Supply Level is normally that level above which over spill to

waste would take place. The minimum operating level must be sufficiently above the lowest discharge outlet to

avoid vortex formation and air entrainment. This may also be termed as the volume of water actually available at

any time between the Dead Storage Level and the lower of the actual water level and Full Reservoir Level.

Dead storage: It is the total storage below the invert level of the lowest discharge outlet from the reservoir.

It may be available to contain sedimentation, provided the sediment does not adversely affect the lowest discharge.

Outlet Surcharge or Flood storage: This is required as a reserve between Full Reservoir Level and the

Maximum Water level to contain the peaks of floods that might occur when there is insufficient storage capacity for

them below Full Reservoir Level.

Some other terms related to reservoirs are defined as follows:

Buffer Storage: This is the space located just above the Dead Storage Level up to Minimum Drawdown

Level. As the name implies, this zone is a buffer between the active and dead storage zones and releases from this

zone are made in dry situations to cater for essential requirements only. Dead Storage and Buffer Storage

together is called Interactive Storage.

Within-the-Year Storage: This term is used to denote the storage of a reservoir meant for meeting the

demands of a specific hydrologic year used for planning the project.

Carry-Over Storage: When the entire water stored in a reservoir is not used up in a year, the unused water

is stored as carry-over storage for use in subsequent years.

Silt / Sedimentation zones: The space occupied by the sediment in the reservoir can be divided into

separate zones. A schematic diagram showing these zones is illustrated in Figure (as defined in IS: 5477).

Page 4: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

Freeboard: It is the margin kept for safety between the level at which the dam would be overtopped and the

maximum still water level. This is required to allow for settlement of the dam, for wave run up above still water

level and for unforeseen rises in water level, because of surges resulting from landslides into the reservoir from

the peripheral hills, earthquakes or unforeseen floods or operational deficiencies.

The functions of reservoirs are to provide water for one or more of the following purposes. Reservoirs that provide

water for a combination of these purpose, are termed as „Multi Purpose‟ reservoirs.

FUNCTIONS OF THE RESERVOIRS:

1. Human consumption and/or industrial use:

2. Irrigation: usually to supplement insufficient rainfall.

3. Hydropower: to generate power and energy whenever water is available or to provide

reliable supplies of power and energy at all times when needed to meet demand.

Page 5: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

4.Pumped storage hydropower schemes: in which the water flows from an upper to a lower reservoir, generating

power and energy at times of high demand through turbines, which may be reversible, and the water is pumped back

to the upper reservoir when surplus energy is available. The cycle is usually daily or twice daily to meet peak

demands. Inflow to such a reservoir is not essential, provided it is required to replace water losses through leakage

and evaporation or to generate additional electricity. In such facilities, the power stations, conduits and either or

both of the reservoirs could be constructed underground if it was found to do so.

4. Flood control: storage capacity is required to be maintained to absorb foreseeable flood inflows to the

reservoirs, so far as they would cause excess of acceptable discharge spillway opening. Storage allows future

use of the flood water retained.

5. Amenity use: this may include provision for boating, water sports, fishing, sight seeing. Formally, the Bureau

of Indian Standards code IS: 4410 (part 6)1983 “

Reservoirs" defines the following types of reservoirs:

1. Auxiliary or Compensatory Reservoir: A reservoir which supplements and absorbed the spill of a main

reservoir.

2. Balancing Reservoirs: A reservoir downstream of the main reservoir for holding water let down from the

main reservoir in excess of that required for irrigation, power generation or other purposes.

3. Conservation Reservoir: A reservoir impounding water for useful purposes, such as irrigation, power

generation, recreation, domestic, industrial and municipal supply etc.

4. Detention Reservoir: A reservoir where in water is stored for a relatively brief period of time, past of it

being retained until the stream can safely carry the ordinary flow plus the released water. Such reservoirs

usually have outlets without control gates and are used for flood regulation. These reservoirs are also called

as the Flood Control Reservoir or Retarding Reservoir.

5. Distribution Reservoir: A reservoir connected with distribution system a water supply project, used

primarily to care for fluctuations in demand which occur over short periods and as local storage in case of

emergency such as a break in a main supply line failure of a pumping plant.

6. Impounding or Storage Reservoir: A reservoir with gate-controlled outlets wherein surface water may

be retained for a considerable period of time and released for use at a time when the normal flow of the

stream is in sufficient to satisfy requirements.

7. Multipurpose Reservoir: A reservoir constructed and equipped to provide storage and release of water

for two or more purposes such as irrigation, flood control,power generation, navigation, pollution

abatement, domestic and industrial water supply,fish culture, recreation, etc.

PLANNING OF RESERVOIRS

The first step in planning the construction of a reservoir with the help of a dam is for the decision makers to be sure

of the needs and purposes for which the reservoir is going to be built together with the known constraints

(including financial), desired benefits. There may be social constraints, for examples people‟s activism may not

allow a reservoir to be built up to the desired level or even the submergence of good agricultural level may be a

constraint. Some times, the construction of a dam may be done that is labour intensive and using local materials,

which helps the community for whom the dam is being built. This sort of work is quite common in the minor

irrigation departments of various steps, especially in the drought prone areas. The Food-for-Work schemes can be

Page 6: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

utilised in creating small reservoirs that helps to serve the community. In a larger scale, similar strategy was

adopted for the construction of the Nagarjuna Sagar Dam on the River Krishna, which was built entirely of coursed

rubble masonry and using manual labour in thousands.

The second step is the assembly of all relevant existing information, which includes the

following:

1. Reports of any previous investigations and studies, if any.

2. Reports on projects similar to that proposed which have already been constructed in the region.

3. A geographical information system (GIS) for the area of interest may be created using a base survey map of

the region.

4. Topographical data in the form of maps and satellite pictures, which may be integrated within the GIS.

5. Geological data in the form of maps and borehole logs, along with the values of relevant parameters.

6. Seismic activity data of the region that includes recorded peak accelerations or ground motion record.

7. Meteorological and hydrological data - of available parameters like rainfall, atmospheric and water

temperatures, evaporation, humidity, wind speed, hours of sunshine, river flows, river levels, sediment

concentration in rivers, etc.

8. For water supply projects, data on population and future population growth based on some acceptable

forecast method, industrial water requirement and probable future industrial development.

9. For irrigation projects, data on soils in the project area and on the crops already grown, including water

requirement for the crops.

10. For hydropower projects, data on past demand and forecasts of future public and industrial demand for

power and energy; data on existing transmission systems, including transmission voltage and capacity.

11. Data on flora and fauna in the project and on the fish in the rivers and lakes, including data on their

migratory and breeding habits.

12. Data on tourism and recreational use of rivers and lakes and how this may be encouraged on completion of

the proposed reservoir.

13. As may be noted, some of the data mentioned above would be needed to design and construct the dam and

its appurtenant structures which would help to store water behind the reservoir.

14. Size of the reservoir and, consequently, height of the dam

15. Size of the spillway and elevation of the Spillway crest level

16. Sizes of the sluices

17. Two important aspects of reservoirs planning: Sedimentation Studies and Geological Explorations

RESERVOIR SEDIMENTATION:

It is important to note that storage reservoirs built across rivers and streams loose their capacity on account

of deposition of sediment. This deposition which takes place progressively in time reduces the active capacity of the

reservoir to provide the outputs of water through passage of time. Accumulation of sediment at or near the

dam may interfere with the future functioning of water intakes and hence affects decisions regarding location and

height of various outlets. It may also result in greater inflow of into canals / water conveyance systems drawing

water from the reservoir. Problems of rise in flood levels in the head reaches and unsightly deposition of sediment

from recreation point of may also crop up in course of time.In this regard, the Bureau of Indian Standard code IS:

12182 - 1987 “Guidelines for

determination of effects of sedimentation in planning and performance of reservoir” is an important document

which discusses some of the aspects of sedimentation that have to be considered while planning reservoirs.

Some of the important points from the code are as follows: While planning a reservoir, the degree of seriousness

and the effect of sedimentation at the proposed location has to be judged from studies, which normally combination

consists of:

In special cases, where the effects of sedimentation on backwater levels are likely to be significant,

Page 7: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

backwater studies would be useful to understand the size of river water levels. Similarly, special studies to bring out

delta formation region changes may be of interest. The steps to be followed for performance assessment studies

with varying rates of sedimentation are as follows:

a. Estimation of annual sediment yields into the reservoir or the average annual sediment yield and of trap

efficiency expected.

b. Distribution of sediment within reservoir to obtain a sediment elevation and capacity curve at any

appropriate time.

c. Simulation studies with varying rates of sedimentation.

d. Assessment of effect of sedimentation.

In general, the performance assessment of reservoir projects has to be done for varying hydrologic inputs to meet

varying demands. Although analytical probability based methods are available to some extent, simulation of the

reservoir system is the standard method. The method is also known as the working tables or sequential routing. In

this method, the water balance of the reservoir s and of other specific locations of water use and constraints in the

systems are considered. All inflows to and outflows from the reservoirs are worked out to decide the changed

storage during the period. In simulation studies, the inflows to be used may be either historical inflow series,

adjusted for future up stream water use changes or an adjusted synthetically generated series.

Procedure for planning a new reservoir

The standard procedure that needs to be carried out for planned storages requires an assessment of the importance of

the problem to classify the reservoir sedimentation problem as insignificant, significant, or serious. Assessment of

reservoir sedimentation problem, in a particular case may be made by comparing the expected average annual

volume of sediment deposition with the gross capacity of the reservoir planned. If the ratio is more than 0.5 percent

per year, the problem is usually said to be serious and special care is required in estimating the sediment yields from

the catchment. If it is less than 0.1 percent per year, the problem of siltation may be insignificant and changes in

reservoir performance. For cases falling between these two limits, the sedimentation problem is considered

significant and requires further studies.

The following studies are required if the problem is insignificant:

1. No simulation studies with sediment correlation are necessary.

2. The feasible service time for the project may be decided. Sediment distribution studies to ensure that

the new zero-elevation does not exceed the dead storage level may be made.

In the above, the following terms have been used, which are explained below:

Feasible Service Time: For a special purpose, the period or notional period for which a reservoir is expected to

provide a part of the planned benefit in respect of storage in the reservoirs being impaired by sedimentation.

Customarily, it is estimated as the time after which the new zero elevation of the reservoir would equal the sill of

the outlet relevant for the purpose.

New Zero Elevation: The level up to which all the available capacity of the reservoir is expected to be lost due to

progressive sedimentation of the reservoir up to the specified time. The specified time should be any length of time

such as Full Service Time, Feasible Service time, etc.

Full Service Time: For a specified purpose, the period or notional period for which the reservoir provided is

expected to provide, a part of the full planned benefit inspite of sedimentation.

The following studies are required if the problem of sedimentation in the reservoir is assessed to be significant, but

Page 8: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

not serious.

1. Both the full service time and feasible service time for the reservoir may be decided.

2. Simulation studies for conditions expected at the end of full service time may be made to ensure that firm outputs

with required depend ability are obtained. The studies used also assess non-dependable secondary outputs, if

relevant, available at the end of this period. Studies without sedimentation, with the same firm outputs should

bring out the additional potential secondary outputs which may be used, if required in economic analysis, using a

linear decrease of these additional benefits over the full service time.

3. No simulation studies beyond full service time, is required.

4. Sediment distribution studies required for feasible service time are essential.

The following studies are required if the problem of sedimentation is serious.

1. All studies described for the „Significant‟ case have to be made.

2. The secondary benefits available in the initial years should be more in such cases. If they are being utilized, for a

proper assessment of the change of these, a simulation at half of full service time should be required.

3. In these cases, the drop of benefits after the full service time may be sharper. To bring out these effects, a

simulation of the project at the end of the feasible service time is required to be done.

Life of reservoir and design criteria

A reservoir exists for a long time and the period of its operation should normally check large

technological and socio-economic changes. The planning assumptions about the exact socio-economic

outputs are, therefore, likely to be changed during operation, and similarly, the implication of socio-economic

differences in the output due to sedimentation are difficult to access. The ever increasing demands due to both

increase of population and increases in per capita needs are of a larger magnitude than the reductions in outputs, if

any, of existing reservoirs. Thus effects of sedimentation, obsolescence, structural deterioration, etc. of reservoirs

may require adjustments in future developmental plans and not simply replacement projects to bring back the lost

potential. On a regional or national scale, it is the sufficiency of the total economic outputs, and not outputs of a

particular project which is relevant. However, from local considerations, the reduction of outputs of reservoir like

irrigation and flood control may cause a much greater degree of distress to the population which has got used to

better socio-economic conditions because of the reservoir. „Life‟ strictly is a term which may be used for system

having two functional states „ON‟ and „OFF‟. Systems showing gradual degradation of performance and not

showing any sudden non-functional stage have no specific life period. Reservoirs fall in the later category. The term

„life of reservoir‟ as loosely used denotes the period during which whole or a specified fraction of its total or active

capacity is lost. In calculating this life, the progressive changes in trap efficiency towards the end of the period are

commonly not considered. In some of the earlier projects, it has been assumed that all the sedimentation would

occur only in the dead storage pocket and the number of years in which the pocket should be filled under this

assumption was also sometimes termed as the life of reservoir. This concept was in fact used to decide the minimum

size of the pocket. Under this concept, no effect of sedimentation should be felt within the live storage of the

reservoir. It has subsequently been established that the silt occupies the space in the live storage of reservoir as well

as the dead storage.

If the operation of the reservoir becomes impossible due to any structural defects, foundation defects, accidental

damages, etc., this situation should also signify the end of the feasible service time. Before the expiry of this feasible

service time, it may be possible to make large changes in the reservoir (for example, new higher level

outlets,structural strengthening, etc.) or other measures, if it is economically feasible to do so. If these studies are

done, the feasible service time may be extended.

Page 9: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

FACTORS GOVERNING THE SELECTION OF SITE FOR THE RESERVOIR

Though a dam is constructed to build a reservoir, a reservoir has a large area of spread and contained in a big chunk

of the river valley upstream of the dam. Hence, while identifying a suitable site for a proposed dam, it is of

paramount importance that the proposed reservoir site is also thoroughly investigated and explored. The basis of

planning for such explorations is to have a rapid economical and dependable pre-investment evaluation of

subsurface conditions. It is also necessary that a degree of uniformity be followed while carrying out subsurface

explorations so that the frame of reference of the investigation covers all requisite aspects. In view of above, the

Bureau of Indian Standards has brought out a code IS: 13216 - 1991 “Code of practice for geological exploration for

reservoir sites”, that discusses the relevant aspects. According to the code since reservoir projects in river valleys

are meant to hold water; therefore, the following aspects of the reservoirs have to be properly investigated

(a) Water tightness of the basins

(b) Stability of the reservoir rim

(c) Availability of construction material in the reservoir area

(d) Silting

(e) Direct and indirect submergence of economic mineral wealth

(f) Seismo-techtonics

These aspects are determined through investigations carried out by surface and sub- surface exploration of

proposed basin during the reconnaissance, preliminary investigation, detailed investigation, construction and

post-construction stages of the project. The two basic stages of investigation: reconnaissance and preliminary

investigations are explained below:

Reconnaissance In the reconnaissance stage, the objective of investigation is to bring out the overall geological features of the

reservoir and the adjacent area to enable the designers, construction engineers and geologists to pinpoint the

geotechnical and ecological problems which have to be tackled. The scale of geological mapping for this stage of

work need not be very large and the available geological maps on 1:50,000 or 1: 250,000 scales may be made use of.

It is advantageous to carry out photo geological interpretation of aerial photographs of the area, if available. If a

geological map of the area is not available, a traverse geological map should be prepared at this stage preferably

using the aerial photos as base maps on which the engineering evaluation of the various geotechnical features

exposed in the area should be depicted.

A topographical index map on 1: 50 000 scales should be used at this stage to delineate the areas which would

require detailed study, subsequently. To prevent an undesirable amount of leakage from the reservoir, the likely

zones of such leakage, such as major dislocations and pervious or cavernous formations running across the divide of

the reservoir should be identified at this stage of investigation for further detailed investigations.Major unstable

zones, particularly in the vicinity of the dam in tight gorges, should be identified at this stage for carrying out

detailed investigations for the stability of the reservoir rim. The locations for suitable construction material

available in the reservoir area should be pin pointed at this stage so that after detailed surveys such materials can

be exploited for proper utilisation during the construction stage prior to impounding of reservoir.The rate of

silting of the reservoir is vital for planning the height of the dam and working out the economic life of the project.

Since the rate of silting, in addition to other factors, is dependent on the type of terrain in the catchment area

of the reservoir, the major geological formations and the ecological set up should be recognized at this stage to

enable a more accurate estimation of the rate of silting of the reservoir. For example, it should be possible to

estimate at this stage that forty percent of the catchment of a storage dam project is covered by Quaternary sediment

and that this is a condition which is likely to a yield a high silt rate or that ninety percent of the catchment of another

Page 10: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

storage dam project is composed of igneous and metamorphic rocks and is likely to yield a relatively low sediment

rate. This information will also be useful in examining whether or not tributaries flowing for long distances through

soft or unconsolidated formations, prior to forming the proposed reservoir, can be avoided and if not, what

remedial measures can be taken to control the silt load brought by these tributaries.

The impounding of a reservoir may submerge economic/strategic mineral deposits occurring within the reservoir

area or the resultant rise in the water table around the reservoir may cause flooding, increased seepage in quarries

and mines located in the area and water logging in other areas. It is, therefore, necessary that the economic mineral

deposits, which are likely to be adversely affected by the reservoir area, are identified at this stage of the

investigation. For example, if an underground working is located close to a proposed storage reservoir area, it

should be identified for regular systematic geo-hydrological studies subsequently. These studies would establish

whether the impoundment of the water in the reservoir had adversely affected the underground working or not.

References should also be made to various agencies dealing with the economic minerals likely to be affected by the

impoundment in the reservoir for proper evaluation of the problem and suitable necessary action. A dam and its

reservoir are affected by the environment in which they are located and in turn they also change the environment.

Impoundment of a reservoir sometimes results in an increase of seismic activity at, or near the reservoir. The

seismic activity may lead to microtremors and in some cases lead to earthquakes of high magnitude. It is, therefore,

necessary to undertake the regional seismotechtonic study of the project area. The faults having active seismic

status

should be delineated at this stage.

Simultaneous action to plan and install a network of seismological observatories encompassing the reservoir

area should also be taken.

Preliminary Investigation The object of preliminary investigation of the reservoir area is to collect further details of the surface and

subsurface geological conditions, with reference to the likely problems identified during the reconnaissance stage

of investigation by means of surface mapping supplemented by photo geological interpretation of aerial

photographs, hydro geological investigations, geophysical investigations, preliminary subsurface exploration and

by conducting geo-seismological studies of the area. On the basis of studies carried out during the reconnaissance

stage it should be possible to estimate the extent of exploration that may be required during the preliminary stage of

investigation including the total number of holes required to be drilled and the total number and depth of pits,

trenches and drifts as also the extent of geophysical surveys which may be necessary. For exploration by pits,

trenches, drifts and shafts guidelines laid down in IS 4453: 1980 Name of IS code should be followed. The

potential zones of leakage from the reservoir and the lateral extent of various features, such as extent of aeolian sand

deposits, glacial till, land slides, major dislocations or pervious and cavernous formations running across the divide,

should be delineated on a scale of 1: 50000. The geo-hydrological conditions of the reservoir rim should be

established by surface and sub-surface investigation as well as inventory, as a free ground water divide rising above

the proposed level of the reservoir is a favourable condition against leakage from the reservoir. The level of water in

a bore hole should be determined as given in IS 6935: 1973. The extension of various features at depth, wherever

necessary, is investigated by geophysical exploration and by means of pits, trenches, drifts and drill holes. For

example, the resistivity survey should be able to identify water saturated zones.

Trap Efficiency Trap efficiency of reservoir, over a period, is the ratio of total deposited sediment to the total sediment

inflow. Figures 1 and 2 given in Annex A of IS 12182 cover relationship between sedimentation index of the

reservoir and percentage of incoming sediment and these curves may be used for calculation of trap efficiency.

Losses in Reservoir

Page 11: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

Water losses mainly of evaporation and seepage occur under pre-project conditions and are reflected in the

stream flow records used for estimating water yield. The construction of new reservoirs and canals is often

accompanied by additional evaporation and infiltration. Estimation of these losses may be based on measurements

at existing reservoirs and canals. The measured flows and outflows and the rate of change of storage are balanced by

computed total loss rate. The depth of water evaporated per year from the reservoir surface may vary from about

400 mm in cool and humid climate to more than 2500 mm in hot and arid regions. Therefore, evaporation is an

important consideration in many projects and deserves careful attention. Various methods like water budget

method, energy budget method, etc may be applied for estimating the evaporation from reservoir. However, to be

more accurate, evaporation from reservoir is estimated by using data from pan-evaporimeters or pans exposed to

atmosphere with or without meshing in or near the reservoir site and suitably adjusted. Seepage losses from

reservoirs and irrigation canals may be significant if these facilities are located in an area underlain by permeable

strata. Avoidance in full or in part of seepage losses may be very expensive and technical difficulties involved may

render a project unfeasible. These are generally covered under the conveyance losses in canals projected on the

demand side of simulation studies.

Measurement of sediment yields The sediment yield in a reservoir may be estimated by any one of the following two methods:

a) Sedimentation surveys of reservoirs with similar catchment characteristics, or

b) Sediment load measurements of the stream.

Reservoir Sedimentation Survey The sediment yield from the catchment is determined by measuring the accumulated sediment in a reservoir

for a known period, by means of echo sounders and other electronic devices since the normal sounding operations

give erroneous results in large depths. The volume of sediment accumulated in a reservoir is computed as the

difference between the present reservoir capacity and the original capacity after the completion of the dam. The unit

weight of deposit is determined in the laboratory front the representative undisturbed samples or by field

determination using a calibrated density probe developed for this purpose. The total sediment volume is then

converted to dry- weight of sediment on the basis of average unit weight of deposits. The total sediment yield for the

period of record covered by the survey will then be equal to the total weight of the sediment deposited in the

reservoir plus that which has passed out of the reservoir based on the trap efficiency. In this way, reliable records

may be readily and economically obtained on long-term basis.

The density of deposited sediment varies with the composition of the deposits, location of the deposit within the

reservoir, the flocculation characteristics of clay content and water, the age of deposit, etc. For coarse material

(0.0625 mm and above) variation of density with location and age may be unimportant. Normally a time and space

average density of deposited materials applicable for the period under study is required for finding the overall

volume of deposits. For this purpose the trapped sediment for the period under study would have to be classified in

different fractions. Most of the sediment escape front getting deposited into the reservoir should be front the silt and

clay fractions. In some special cases local estimates of densities at points in the reservoir may be required instead of

average density over the whole reservoir. The trap efficiency mainly depends upon the capacity-in-flow ratio but

may vary with location f outlets and reservoir operating procedure. Computation of reservoir trap

Page 12: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor
Page 13: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

Estimation of a Demand from a Given Live Storage Capacity The net inflow mass curve is plotted from the available records. The demand lines arc, drawn at peak

points of the mass curve in such a way that the maximum ordinate between the demand line and the mass curve is

equal to the specified live storage. The demand lines shall intersect the mass curve when extended forward. The

slop of the flattest line indicates the film demand that could he met by the given live storage Capacity. Before

fixing the reservoir capacity, it would be desirable to plot a curve between the net annual drafts and the required live

storage capacities for these drafts. This curve will give an indication of the required live storage capacity. However,

the economics of the capacity will have to be considered before deciding final capacity.

Fixing of flood and surcharge storage In case of reservoirs having flood control as one of the purposes, separate flood control storage is to be set

apart above the storage meant for power, irrigation and water supply. Flood control storage is meant for storing

flood waters above a particular return period temporarily and to attenuate discharges up to that flood magnitude to

minimize effects on downstream areas from flooding. Flood and surcharge storage between the full reservoir level

(FRL), and maximum water level (MWL) attainable even with full surplus by the spillway takes care of high floods

and moderates them.

Flood Control Storage Storage space is provided in the reservoir for storing flood water temporarily in order to reduce peak

discharge of a specified return period flood and to minimize flooding of downstream areas for all floods IS: 5477 (

Part 1) : 1999 equal to or lower than the return period flood considered. In the case of reservoirs envisaging flood

moderation as a purpose and having separate flood control storage, the flood storage is provided above the top of

conservation pool.

Surcharge Storage Surcharge storage is the storage between the full reservoir level (FRL) and the maximum water level

(MWL) of a reservoir which may be attained with capacity exceeding the reservoir at FRL to start with. The

spillway capacity has to be adequate to pass the inflow design flood making moderation possible with surcharge

storage. The methods that are generally used for estimate of the Design Flood for computing the Flood Storage are

broadly classified as under:

1. Application of a suitable factor of safety to maximum observed flood or maximum

historical flood.

2. Empirical flood formulae.

3. Envelope curves.

4. Frequency analysis.

5. Rating method of derivation of design flood from storm studies and application of the

Page 14: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

1. Initial reservoir stage

2. The design flood hydrograph

3. Rate of outflow including the flow over the crest, through sluices or outlets and through

power units, and

4. Incremental storage capacity of the reservoir.

Control of sediment deposition The deposition of sediment in a reservoir may be controlled to a certain extent by designing and

operating gates or other outlets in the dam in such a manner as to permit selective withdrawals of

water having a higher than average sediment content. The suspended sediment content of the water in

reservoirs is higher during and just after flood flow. Thus, more the water wasted at such times, the smaller will be

the percentage of the total sediment load to settle into permanent deposits. There are generally two methods: (a)

density currents, and (b) waste-water release, for controlling the deposition and both will necessarily result in loss

of water

Page 15: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

DAMS A dam is a barrier that stops or restricts the flow of water or underground streams. Reservoirs created by dams not

only suppress floods but also provide water for activities such as irrigation, human consumption, industrial

use, aquaculture, and navigability. Hydropower is often used in conjunction with dams to generate electricity. A

dam can also be used to collect water or for storage of water which can be evenly distributed between locations.

Dams generally serve the primary purpose of retaining water, while other structures such

as floodgates or levees (also known as dikes) are used to manage or prevent water flow into specific land regions.

The purpose of a dam is to impound (store) water for any of several reasons, e.g., flood control, water supply

for humans or livestock, irrigation, energy generation, recreation, or pollution control.

Types of Dams Dams may either be human-built or result from natural phenomena, such as landslides or glacial deposition.

The majority of dams are human structures normally constructed of earthfill or concrete. Naturally occurring lakes

may also be modified by adding a spillway to allow for safe, efficient release of excess water from the resulting

reservoir.

■ the different types of dams

■ essential components of a dam

■ how the components function, and

■ important physical conditions likely to affect a dam.

Human-built dams may be classified according to the type of construction materials used, the methods used in

construc-tion, their slope or cross-section, the way they resist the forces of the water pressure behind them, the

means of controlling seepage, and occasionally, their purpose.

Construction Materials— The materials used for construction of dams include earth, rock, tailings from mining or

milling, concrete, masonry, steel, and any combination of tho se materials.

Embankment Dams—Embankment dams, the most common type in use today, have the general shape shown in

Their side slopes typically have a grade of two to one (horizontal to vertical) or flatter.Their capacity for water

retention is due to the low permeability of the entire mass (in the case of a homoge- neous embankment) or of a zone

of low-permeability material (in the case of a zoned embankment dam).Materials used for embankment dams

include natural soil or rock obtained from borrow areas or nearby quarries, or waste materials obtained from mining

or milling. If the natural material has a high permeability, then a zone of very-low-permeability material must be

included in the dam to retain water. An embankment dam is termed an “earthfill” or “rockfill” dam depending on

whether it is com-posed mostly of compacted earth or mostly of compacted or dumped pervious rock. The ability of

an embankment dam to resist the hydrostatic pressure caused by reservoir water is primarily the result of the mass,

weight, and strength of its materials.

Concrete Dams—Concrete dams may be categorized into gravity and arch dams according to the designs used to

resist the stress due to reservoir water pressure. A concrete gravity dam (shown in Figure 2.2) is the most common

form of concrete dam. In it, the mass weight of the concrete and friction resist the reservoir water pressure. A

buttress dam is a specific type of gravity dam in which the large mass of concrete is reduced, and the forces are

diverted to the dam foundation through vertical or sloping buttresses. Gravity dams are constructed of

non-reinforced vertical blocks of concrete with flexible seals in the joints between the blocks.Concrete arch dams

Page 16: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

are typically rather thin in cross-section (Figure 2.3). The reservoir water forces acting on an arch dam are carried

laterally into the abutments. The shape of the arch may resemble a segment of a circle or an ellipse, and the arch

may be curved in the vertical plane as well. Such dams are usually built from a series of thin vertical blocks that are

keyed together, with water stops between the blocks. Variations of arch dams include multi-arch dams, in which

more than one curved section is used, and arch gravity dams, which combine some features of the two types.A

recently developed method for constructing concrete gravity dams involves the use of a relatively weak concrete

mix which is placed and compacted in a manner similar to that used for earthfill dams. Roller-compacted concrete

has the advan-tages of decreased cost and time. In addition, there are no joints where seepage could occur.

Arch dams

In the arch dam, stability is obtained by a combination of arch and gravity action. If the upstream face is vertical the

entire weight of the dam must be carried to the foundation by gravity, while the distribution of the

normal hydrostatic pressure between vertical cantilever and arch action will depend upon the stiffness of the dam in

a vertical and horizontal direction. When the upstream face is sloped the distribution is more complicated.

The normal component of the weight of the arch ring may be taken by the arch action, while the normal hydrostatic

pressure will be distributed as described above. For this type of dam, firm reliable supports at

the abutments (either buttress or canyon side wall) are more important. The most desirable place for an arch dam is

a narrow canyon with steep side walls composed of sound rock.[39]

The safety of an arch dam is dependent on the

strength of the side wall abutments, hence not only should the arch be well seated on the side walls but also the

character of the rock should be carefully inspected. Two types of single-arch dams are in use, namely the

constant-angle and the constant-radius dam. The constant-radius type employs the same face radius at all elevations

of the dam, which means that as the channel grows narrower towards the bottom of the dam the central angle

subtended by the face of the dam becomes smaller. The multiple-arch dam does not require as many buttresses as

the hollow gravity type, but requires good rock foundation because the buttress loads are heavy.

Gravity Dam :In a gravity dam, the force that holds the dam in place against the push from the water is Earth's

gravity pulling down on the mass of the dam.[40]

The water presses laterally (downstream) on the dam, tending to

overturn the dam by rotating about its toe (a point at the bottom downstream side of the dam). The dam's weight

counteracts that force, tending to rotate the dam the other way about its toe. The designer ensures that the dam is

heavy enough that the dam's weight wins that contest. In engineering terms, that is true whenever the resultant of

the forces of gravity acting on the dam and water pressure on the dam acts in a line that passes upstream of the toe of

the dam.

Furthermore, the designer tries to shape the dam so if one were to consider the part of dam above any particular

height to be a whole dam itself, that dam also would be held in place by gravity. i.e. there is no tension in the

upstream face of the dam holding the top of the dam down. The designer does this because it is usually more

practical to make a dam of material essentially just piled up than to make the material stick together against vertical

tension.

Note that the shape that prevents tension in the upstream face also eliminates a balancing compression stress in the

downstream face, providing additional economy.For this type of dam, it is essential to have an impervious

foundation with high bearing strength.When situated on a suitable site, a gravity dam can prove to be a better

alternative to other types of dams. When built on a carefully studied foundation, the gravity dam probably

represents the best developed example of dam building. Since the fear of flood is a strong motivator in many

regions, gravity dams are being built in some instances where an arch dam would have been more economical.

Gravity dams are classified as "solid" or "hollow" and are generally made of either concrete or masonry.

Page 17: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

Arch-gravity dams

A gravity dam can be combined with an arch dam into an arch-gravity dam for areas with massive amounts of water

flow but less material available for a purely gravity dam. The inward compression of the dam by the water reduces

the lateral (horizontal) force acting on the dam. Thus, the gravitation force required by the dam is lessened, i.e. the

dam does not need to be so massive. This enables thinner dams and saves resources.

Other Types—Various construction techniques could be used in a single dam. For example, a dam could include

an earthen or rockfill embank-ment as well as a portion made of concrete. In such a case, the concrete section would

normally contain the spillway or other outlet works.A recent design for low-head dams (with a minimal height of

water behind the dam) uses inflatable rubber or plastic materials anchored at the bottom by a concrete slab.Some

dams are constructed for special purposes, such as diversion of water, or permit construction of other facilities in

river valleys. These dams are called diversion dams and cofferdams, respectively.

Water-Retention Ability Because the purpose of a dam is to retain water effectively and safely, its water-retention ability is of prime

impor-tance. Water may pass from the reservoir to the downstream side of a dam by:

(1)Seeping through the dam.

(2)Seeping through the abutments.

(3)Seeping under the dam.

(4)Overtopping the dam.

(5)Passing through the outlet works.

(6)Passing through or over a service (primary) spillway.

(7)Passing over an emergency spillway.

Seepage through a Dam—All embankment dams and most concrete dams allow some seepage. The earth or

other material used to construct embankment dams has some perme-ability, and water under pressure from the

reservoir will eventually seep through. However, it is important to control the quantity of seepage by using

low-permeability materials in construction and by channeling and restricting the flow so that embankment

materials do not erode.

Seepage through a concrete dam is usually minimal and is almost always through joints between blocks, or

through cracks or deteriorated concrete which may have developed. Maintenance of these joints and cracks is

therefore essential. The seepage water should be collected and channelized, so that its quantity can be measured

and erosion minimized.

Seepage Around a Dam—Seepage under a dam, through the dam foundation material, or around the ends of a

dam through the abutment materials may become a serious problem if the flow is large or of sufficient velocity to

cause erosion. Seepage under a dam also creates high hydrostatic uplift (pore-water) pressure,which has the effect

of diminishing the weight of the dam, making it less stable.Seepage through abutments or foundations can dissolve

the constitu-ents of certain rocks such as limestone, dolomite, or gypsum so that any cracks or joints in the rock

become progres-sively larger and in turn allow more seepage. Abutment or foundation seepage may also result in

Page 18: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

“piping” internal erosion, in which the flow of water is fast enough to erode away small particles of soil. This

erosion progresses from the water exit point backward to the entrance point. When that point is reached, water may

then flow without restriction, resulting in even greater erosion and probable dam failure.

Obviously, large, unrestricted seepage is undesirable. To minimize this possibility, dams are constructed with

internal impermeable barriers and internal drainage facilities such as drainpipes or filter systems, or other drainage

systems such as toe, blanket, or chimney drains.Flow through a dam foundation may be diminished by grouting

known or suspected highly permeable material, constructing a cutoff wall or trench below a dam, or constructing an

upstream impermeable blanket.

Selection of Dam Site

The selection of Dam site for constructing a dam should be governed by the following factors.

1. Suitable foundation must be available.

2. For economy, the length of the dam should be as small as possible, and for a given height, it should store the

maximum volume of water.

3. The general bed level at dam site should preferably be higher than that of the river basin. This will reduce the

height of the dam.

4. A suitable site for the spillway should be available in the near vicinity.

5. Materials required for the construction of dam should be easily available, either locally or in the near vicinity.

6. The value of land and property submerged by the proposed dam should be as low as possible.

7. The dam site should be easily accessible, so that it can be economically connected to important towns and cities.

8. Site for establishing labor colonies and a healthy environment should be available near the site.

Factors Affecting Selection of Dam

These factors are discussed one by one.

Topography

Topography dictates the first choice of the type of dam.

1. A narrow U-shaped valley, i.e. a narrow stream flowing between high rocky walls, would suggest a concrete

overflow dam.

2. A low plain country, would suggest an earth fill dam with separate spillways.

3. A narrow V-shaped valley indicates the choice of an Arch dam

Geological and Foundation Conditions

Geological and Foundation conditions should be thoroughly surveyed because the foundations have to carry the

weight of the dam. Various kind of foundations generally encountered are

1. Solid rock foundations such as granite have strong bearing power and almost every kind of dam can be built on

such foundations.

2. Gravel foundations are suitable for earthen and rock fill dams.

3. Silt and fine sand foundations suggest construction of earth dams or very low gravity dams.

4. Clay foundations are likely to cause enormous settlement of the dam. Constructions of gravity dams or rock fill

dams are not suitable on such foundations. Earthen dams after special treatments can be built.

Page 19: LECTURE NOTES ON WATER RESOURCES ENGINEERING-II · 2017-04-25 · lecture notes on water resources engineering-ii iii b. tech ii semester (jntu(a)-r13) p.pavithra assistant professor

Availability of Materials

Availability of materials is another important factor in selecting the type of dam. In order to achieve economy in

dam construction, the materials required must be available locally or at short distances from the construction site.

Spillway Size and Location

spillway disposes the surplus river discharge. The capacity of the spillway will depend on the magnitude of the

floods to be by-passed. The spillway is therefore much more important on rivers and streams with large flood

potential.

Earthquake Zone

If dam is situated in an earthquake zone, its design must include earthquake forces. The type of structure best suited

to resist earthquake shocks without danger are earthen dams and concrete gravity dams.

Height of Dam

Earthen dams are usually not provided for heights more than 30 m or so. For greater heights, gravity dams are

generally preferred.

Hint: The availability of spillway site is very important in selection of a particular type of dam