1.040/1.401Project ManagementSpring 2007
Lecture 7Dr. SangHyun [email protected] of Civil and Environmental EngineeringMassachusetts Institute of Technology Planning Basics
Project Management PhaseFEASIBILITYCLOSEOUTDEVELOPMENTOPERATIONS Fin.&Eval.RiskEstimatingPlanningDESIGNPLANNING Organization
Outline Planning Hierarchical Project StructuresWork Breakdown StructureOrganization Breakdown StructureCost Breakdown Structure
Planning ComponentsWhat: Work Breakdown StructureHow: Plans and SpecificationsWho: Organization Breakdown StructureHow much: Cost Breakdown Structure (via estimate)When: Schedule
Outline Planning Hierarchical Project StructuresWork Breakdown StructureOrganization Breakdown StructureCost Breakdown Structure
Work Breakdown StructureA WBS is a deliverable-oriented grouping of project components that organizes and defines the total scope of the projectWork not in the WBS is outside the scope of the projectWBS is usually an operative tool used by contractorsFirst step towards constructing a scheduleCentral role in project monitoring and control
WBS: ExampleSource: Shtub et al., 1994different summary level
Work PackageLowest levelDistinguish from OthersSingle Responsible OrganizationAssigned Start and FinishAssigned BudgetLimited Duration
Types of WBSProject WBSOperative tool for monitoring and control contractor workContractual WBSDefines the level of reporting that the seller will provide the buyerMay include less detail than Project WBSAgreed between owner and contractor
Functional Approachlevel 0
level 1
level 2
level 3
level 4
level 5GAS-STEAM COMBINED POWER PLANT
MAIN FUNCTIONS OF PLANTUNITSGASINTERFACESSTEAMTURBINECOMPRESSION STATIONGENERATORCOMPRESSORSENCLOSUREGAS TREATMENTSUB-UNITS
WORK PACKAGESITEMSCOMPRESSOR 1FOUNDATIONSCOMPRESSOR 2DESIGNINSTALLATIONPROCUREMENT
Physical Space ApproachProjectMain building1st floorStructuresPlumbingsElectricalHVAC2nd floorService buildingStructuresPlumbingsElectricalHVAC
Procedure ApproachProjectFeasibilityDesignBasicDetailBid documentsShop drawingsBidConstructionFoundations subcontractMain buildingPilesConcrete foundationsService buildingPilesConcrete foundationsSteel erectionFinishingsCommissioning
WBS: CSI Master Format - Example Source: Schaufelberger et al., 2002Sample
Outline Planning Hierarchical Project StructuresWork Breakdown StructureOrganization Breakdown StructureCost Breakdown Structure
Organization Breakdown StructureDecomposition of necessary resources to perform jobIdentification & organization of the resources responsible with carrying out activities associated with the projectUsed to keep track of specific work assignments & resource allocations
Organization Breakdown StructureProject resourcesProject management teamProject managerConstruction superintendentField superintendentOffice managerSchedulerAccounter/controllerField engineerConstruction forceWorkerSubcontractorElectricalPlumbingInsulationTankageRoads
OBS/WBS LinkagesSource: Shtub et al., 1994
Outline Planning Hierarchical Project StructuresWork Breakdown StructureOrganization Breakdown StructureCost Breakdown Structure
Cost Breakdown Structure (CBS)Breakdown of the costs of the various components of the structure including all work done by the subcontractorsServes as a basis for subsequent monthly pay requests by the contractorUsed to continuously compare costs as they actually occur with the budget
Cost Breakdown Structure (CBS)Source: Shtub et al., 1994
Two Main ApproachesCBS = WBSCBS is the project cost control structureCBS WBSCBS is the corporate multi-project cost control structureUsually the case of a firm that has an integrated cost control system
Diverse CombinationsWBS + OBS: Task assignmentsCBS + OBS: Budget monitoring of crews, etc.OBS + Schedule: Time-specific crew assignmentsCBS + Schedule: Cost monitoring