Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming College, Emeritus, Stephen N. Chapman, Ph.D., CFPIM, North Carolina State University, Lloyd M. Clive, P.E., CFPIM, Fleming College Operations Management for Competitive Advantage, 11th Edition, by Chase, Jacobs, and Aquilano, 2005, N.Y.: McGraw-Hill/Irwin.

Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Embed Size (px)

Citation preview

Page 1: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Lecture 7

Production Planning System (Revisited)

Books• Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

College, Emeritus, Stephen N. Chapman, Ph.D., CFPIM, North Carolina State University, Lloyd M. Clive, P.E., CFPIM, Fleming College

• Operations Management for Competitive Advantage, 11th Edition, by Chase, Jacobs, and Aquilano, 2005, N.Y.: McGraw-Hill/Irwin.

Page 2: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Objectives

• Manufacturing Planning and Control System• Sales and operations planning (SOP)• Making production plan• Developing production plan• Market to stock production plan• Market to order production plan• Production planning hierarchy• Inventory cost• Type of inventory• Production settings

Page 3: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing’s Objectives

• The goal of manufacturing is to produce

– The right goods

– Of the right quality

– In the right quantities

– At the right time

– At minimum cost

Page 4: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Four Basic Questions

What must we get?

What do wealreadyhave?

What doesit take tomake it?

What arewe goingto make?

Page 5: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Priority

The APICS Dictionary defines priority as “the relative importance of jobs, i.e., the sequence in which jobs should be worked on.” Priority refers to what is needed, how much is needed, and when it is needed.

Page 6: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Capacity

The APICS Dictionary defines capacity as “the capability of a worker, machine, work center, plant or organization to produce output per time period.”

Page 7: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Production Plan

Master ProductionSchedule (MPS)

Material RequirementsPlan (MRP)

Production ActivityControl (PAC)

ResourceRequirements

Plan (RRP)

Rough-CutCapacity

Plan (RCCP)

CapacityRequirements

Plan (CRP)

Input/Output Control

Operation Sequencing

Strategic BusinessPlan

Pri

orit

y M

anag

emen

t Tec

hniq

ues C

apacity Managem

ent Techniques

Page 8: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing Planning and Control System

• Strategic Business PlanA statement of the major goals and objectives the company

expects to achieve over the next 2-10 years or more.– broad/general direction– low level of detail– long-range forecasts– responsibility of senior management– includes participation from Marketing, Finance, and

Production– usually reviewed every six months to a year

Page 9: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing Planning and Control System

• Production Plan Concerns– Quantities of each product group required to be

produced– The desired inventory levels– The resources of equipment, labor, and material needed

in each period– The availability of resources needed

Page 10: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing Planning and Control System

• Production Plan must– Satisfy market demand within resources available– Assist the implementation of the strategic business plan– Be based upon families of products– Be fairly low level of detail– Address a planning horizon of six to 18 months– Be reviewed each month or quarter

Page 11: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing Planning and Control System

• Master Production ScheduleA plan for the production of individual end items (finished

goods). – breaks down production plan– list the quantity of each end item to be made– level of detail is higher than the production plan -

developed for individual end items– planning horizon extends three to 18 months– reviewed and changed weekly or monthly

Page 12: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing Planning and Control System

• Material Requirements PlanA plan for the production and purchase of the components

used in making the items in the MPS– Production control and purchasing use MRP to decide

the purchase or manufacture of specific items– Level of detail is high– Determines when the components and parts are needed – Planning horizon is at least as long as the combined

purchase and manufacture lead times (3 to 18 months)– Usually reviewed daily or weekly

Page 13: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing Planning and Control System

• Production Activity Control and Purchasing– Represents the implementation and control phase of the

production planning and control system– Purchasing is responsible for establishing and

controlling the flow of raw materials into the factory– PAC is responsible for planning and controlling the

flow of work through the factory– Planning horizon is very short, a day to a month– Level of detail is high– Reviewed and revised daily

Page 14: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing Planning and Control System

– What are the priorities - how much of what is to be produced and when?

– What is the available capacity - what resources do we have? • Can we outsource?

– How can differences between priorities and capacity be resolved?

2 At each level in the MPCS, three questions must be answered:

Page 15: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Manufacturing Resource Planning (MRP II)

• Manufacturing resource planning (MRP II) is a method for the effective planning of all resources of a manufacturing company. Ideally, it addresses operational planning in units, financial planning in dollars, and has a simulation capability to answer “what if” questions. It is made up of a variety of functions, each linked together: business planning, sales and operations planning, production planning, master production scheduling, material requirements planning, capacity requirements planning, and the execution support systems for capacity and material. Output from these systems is integrated with financial reports such as the business plan, purchase commitment report, shipping budget, and inventory projections in dollars.

APICS Dictionary, 8th edition, 1995

Page 16: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Sales and operations planning (SOP)

• Medium time range• Benefits:

– Provides a means of updating the strategic business plan

– Provides a means of managing change– Permits better management of production, inventory

and backlog

Page 17: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making the Production Plan

• Purpose

Production planning is

. . . setting the overall level of manufacturing output . . . and other activities to best satisfy the current planned levels of sales . . . while meeting general business objectives of profitability, productivity . . . etc., as expressed in the overall business plan.

APICS Dictionary, 8th edition, 1995

Page 18: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making the Production Plan

• Production planning is concerned with– The quantities of each product group in each period. – The desired inventory levels.– The resources of equipment, labor, and material needed in

each period.– The availability of needed resources.

• Why are plans made for product groups?• What should the product groups be based on?

Page 19: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making the Production Plan

• Production planning characteristics– The time horizon may be more or less than 12

months, depending on the manufacturing cycle.– Demand is seasonal for many products, but not for

all. Seasonal demand is the worst-case scenario.– A plan is made for families or groups.– Management will have a variety of objectives.

• What might be some management objectives?

Page 20: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

• Three Basic Strategies – Chase (Demand Matching) Strategy: Produce the

amounts that are demanded at any one time– Production Leveling Strategy: Continuously

produce an amount equal to the average demand– Subcontracting: Meeting additional demand

through subcontracting.

• Hybrid Strategy: Combination of any of the above strategies

Page 21: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

Chase (demand matching) StrategyThe goal is to produce the amounts demanded at any

given time. Inventory levels remain stable while production varies to meet demand

Uni

ts

1 2 3 4 5 6 7 8 9 10 11 12Periods

Page 22: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

• Chase Strategy Disadvantages– As production increases, workers must be hired and

trained. Extra shifts may be needed, and overtime may be necessary. These requirements all increase cost.

– As production decreases, people are laid off and morale suffers,

– When production starts to increase again, the best workers may have other jobs and their skills will not be available.

Page 23: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

• Chase Strategy Disadvantages (continued)– Manufacturing must have enough plant capacity to

produce at the highest capacity needed.

• What industries use a chase strategy?

Page 24: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

• Production Leveling Strategy

The goal of this strategy is to continuously produce an amount equal to the average demand.

1 2 3 4 5 6 7 8 9 10 11 12

Uni

ts

Periods

Page 25: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

• Production Leveling Strategy– This strategy avoids the disadvantages of demand

matching. However, inventory builds up.

• What are some examples of industries that could use this strategy?

Page 26: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

• Subcontracting Strategy– Subcontracting means always producing at the level

of minimum demand and meeting any additional demand through subcontracting

• Major Advantage– Costs associated with excess capacity are avoided– Since production is leveled, there are no costs

associated with changing production levels

Page 27: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

• Subcontracting Strategy - Disadvantage– The cost of purchasing may be greater than if the

item were made in the plant– Certain core skills or technologies may be lost

Page 28: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing the Production Plan

• Hybrid Strategy– Combination of any of the three previous strategies– Production management is responsible for finding the

combination of strategies that minimizes the sum of all costs involved, providing the level of service required, and meeting the objectives of the financial and marketing plans

Page 29: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing a Make-to-Stock Production Plan

• Under a make-to-stock production plan, goods are put into inventory and sold from inventory. It is used when– Demand is fairly constant and predictable– Only a few product options exists– Required delivery times are shorter than the time

needed to make the product– Product has a long shelf life

Page 30: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

• Information needed for a make-to-stock production plan includes– A forecast by time period for the planning horizon– Opening inventory– Desired ending inventory

• The objective in developing a production plan is to minimize the costs of carrying inventory, changing production levels, and stocking out (not supplying the customer what is wanted when it is wanted).

Developing a Make-to-Stock Production Plan

Page 31: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making a Level Production Plan

• Procedure for Level Production– Total the forecast demand for the planning horizon– Determine the opening inventory and the desired

ending inventory– Calculate the total production– Calculate the production required each period by

dividing the total production by the number of periods

– Calculate the ending inventory for each period

Page 32: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making a Level Production Plan

Period 1 2 3 4 5 Total Forecast Demand 110 120 130 120 120 Production Ending Inventory

Example Problem: (Pg. 29/33)

Opening inventory (OI) = 100 unitsDesired ending inventory (EI) = 80 units

Total production needed = total forecast demand + EI - OI = _____ + _____ - _____ = _______ units

Production each period = 5

units

Page 33: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making a Level Production Plan

Ending Inventory for Period 1 = OI + production - forecast demand= ______ + ______ - ______ = ______ units

Page 34: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making a Level Production Plan

• How much should be produced each period?• What is the ending inventory for each period?• If the cost of carrying inventory is $5 per case per period

based on ending inventory, what is the total cost of carrying inventory?

• What will be the total cost of the plan?

Page 35: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making a Level Production Plan

Answer:a. Total production required = 600 + 80 - 100 = 580 cases

b. Ending inventory = OI + production - demand

Ending inventory after the first period = 100 + 116 - 110

= 106 cases

Ending inv. for period 1 becomes the opening inv. for period 2

Ending inventory (period 2) = 106 + 116 - 120 = 102 cases

Production each period = 5805

= 116 cases

Page 36: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Making a Level Production Plan

Answer: (continued)

c. The total cost of carrying inventory would be:

(106 + 102 + 88 + 84 + 80)($5) = $2300

d. There were no stockouts and no changes in the level of production, $2300 is the total cost of the plan:

Period 1 2 3 4 5 Total Forecast (cases) 110 120 130 120 120 600 Production 116 116 116 116 116 580 Ending Inventory / 100 106 102 88 84 80

Page 37: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing a Make-to-Order (Chase Strategy) Production Plan

Using preceding example, suppose that changing the production level by one case costs $20.

A change from 50 to 60 would cost

(60 - 50)($20) = $200

Opening inventory is 100 cases, and the company wishes to bring this down to 80 cases in the first period

110 - (100 - 80) = 90 cases

Page 38: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing a Make-to-Order (Chase Strategy) Production Plan

Cost of changing production level = (60)($20) = $1200

Cost of carrying inventory = (80 cases)(5 periods)($5) = $2000

Total cost of the plan = $1200 + $2000 = $3200

Period 0 1 2 3 4 5 Total Demand (cases) 110 120 130 120 120 600 Production 100 90 120 130 120 120 580 Change in Production 10 30 10 10 0 60 Ending Inventory 100 80 80 80 80 80

Page 39: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Assemble to Order

• Assemble-to-order is a subset of make-to-order– several product options exists– customer is not willing to wait until the product is made– manufacturers assemble the component parts from

inventory according to the order– Examples: automobiles and computers

Page 40: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing a Make-to-OrderProduction Plan

• Information needed for make-to-order products– Forecast by period for the planning horizon– Opening backlog of customer orders– Desired ending backlog

• BacklogUnfilled customer orders that will be delivered in the future.

Page 41: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Resource Requirements Planning

• The preliminary production plan must be compared with the existing resources of the company. Two questions must be answered:– Are the required resources available?– If not, how will the differences be reconciled?

• Helpful tool is the resource bill or bill of resources

Page 42: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Resource Requirements Planning

• Resource bill or Bill of Resources– shows the quantity of critical resources (materials,

labor, and “bottleneck” operations) needed to make one average unit of the product group

Product Wood(board feet)

Labor(standard hours)

Tables 20 1.31Chairs 10 0.85Stools 5 0.55

Bill of Resources

Page 43: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Production Planning Hierarchy

Master Production Scheduling

Production Planning and Control Systems

Pond DrainingSystems

Aggregate Planning

PushSystems

PullSystems

Focusing onBottlenecks

Long-Range Capacity Planning

Page 44: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Production Planning Horizons

Master Production Scheduling

Production Planning and Control Systems

Pond DrainingSystems

Aggregate Planning

PushSystems

PullSystems

Focusing onBottlenecks

Long-Range Capacity PlanningLong-Range

(years)

Medium-Range(6-18 months)

Short-Range(weeks)

Very-Short-Range(hours - days)

Page 45: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Production Planning: Units of Measure

Master Production Scheduling

Production Planning and Control Systems

Pond DrainingSystems

Aggregate Planning

PushSystems

PullSystems

Focusing onBottlenecks

Long-Range Capacity PlanningEntire

Product Line

ProductFamily

SpecificProduct Model

Labor, Materials,Machines

Page 46: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Aggregate Planning

Page 47: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Why Aggregate Planning Is Necessary

• Fully load facilities and minimize overloading and underloading

• Make sure enough capacity available to satisfy expected demand

• Plan for the orderly and systematic change of production capacity to meet the peaks and valleys of expected customer demand

• Get the most output for the amount of resources available

Page 48: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Inputs

• A forecast of aggregate demand covering the selected planning horizon (6-18 months)

• The alternative means available to adjust short- to medium-term capacity, to what extent each alternative could impact capacity and the related costs

• The current status of the system in terms of workforce level, inventory level and production rate

Page 49: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Outputs

• A production plan: aggregate decisions for each period in the planning horizon about– workforce level– inventory level– production rate

• Projected costs if the production plan was implemented

Page 50: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Medium-Term Capacity Adjustments

• Workforce level– Hire or layoff full-time workers– Hire or layoff part-time workers– Hire or layoff contract workers

• Utilization of the work force– Overtime– Idle time (undertime) – Reduce hours worked

• . . . more

Page 51: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Medium-Term Capacity Adjustments

• Inventory level– Finished goods inventory– Backorders/lost sales

• Subcontract

Page 52: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Approaches

• Informal or Trial-and-Error Approach• Mathematically Optimal Approaches

– Linear Programming– Linear Decision Rules

• Computer Search• Heuristics

Page 53: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Pure Strategies for the Informal Approach

• Matching Demand• Level Capacity

– Buffering with inventory– Buffering with backlog– Buffering with overtime or subcontracting

Page 54: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Matching Demand Strategy

• Capacity (Production) in each time period is varied to exactly match the forecasted aggregate demand in that time period

• Capacity is varied by changing the workforce level• Finished-goods inventories are minimal• Labor and materials costs tend to be high due to the

frequent changes

Page 55: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing and Evaluating the Matching Production Plan

• Production rate is dictated by the forecasted aggregate demand

• Convert the forecasted aggregate demand into the required workforce level using production time information

• The primary costs of this strategy are the costs of changing workforce levels from period to period, i.e., hirings and layoffs

Page 56: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Level Capacity Strategy

• Capacity (production rate) is held level (constant) over the planning horizon

• The difference between the constant production rate and the demand rate is made up (buffered) by inventory, backlog, overtime, part-time labor and/or subcontracting

Page 57: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing and Evaluating the Level Production Plan

• Assume that the amount produced each period is constant, no hirings or layoffs

• The gap between the amount planned to be produced and the forecasted demand is filled with either inventory or backorders, i.e., no overtime, no idle time, no subcontracting

• . . . more

Page 58: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Developing and Evaluating the Level Production Plan

• The primary costs of this strategy are inventory carrying and backlogging costs

• Period-ending inventories or backlogs are determined using the inventory balance equation:

EIt = EIt-1 + (Pt - Dt )

Page 59: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Aggregate Plans for Services

• For standardized services, aggregate planning may be simpler than in systems that produce products

• For customized services,– there may be difficulty in specifying the nature and

extent of services to be performed for each customer

– customer may be an integral part of the production system

• Absence of finished-goods inventories as a buffer between system capacity and customer demand

Page 60: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Preemptive Tactics

• There may be ways to manage the extremes of demand:– Discount prices during the valleys.... have a sale– Peak-load pricing during the highs .... electric

utilities, Nucor

Page 61: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Time Horizon in Production PlanningStatic Vs. Dynamic Environments

• Models used for production planning are either static or dynamic• Static

– Constant through time– Assume same plan acceptable in each period for the

foreseeable future• Dynamic

– Explicitly consider changes in demand and resource availability to determine what should be done through time over a planning horizon

– Require stochastic data – Require great effort to build and solve

61

Page 62: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

The Role of Inventory

• Inventory consists of physical items moving through the production system

• Originates with shipment of raw material and parts from the supplier

• Ends with delivery of the finished products to the customer• Costs of storing inventory accounts for a substantial

proportion of manufacturing cost– Often 20% or more

• Optimal level of inventory– Allows production operations to continue smoothly

• A common control measure is Inventory Turnover62

Page 63: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Inventory Turnover

• The ratio of annual cost of goods sold to average inventory investment.

• It indicates how many times a year the inventory is sold.

• Higher the ratio, the better, because it implies more efficient use of resources.

• Higher the profit margin and longer the manufacturing lead time, the lower the inventory turns.

• Example: Supermarkets (low profit margins) have a fairly high turnover rate

63

Page 64: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Inventory Definitions and Decisions

• Batch or order size, Q– Batch size is the number of units released to the shop floor

to be produced• Reorder point, r

– Specifies the timing for placing a new order• Inventory Position

Inventory Position = Inventory On Hand + On Order – Backorders

• Units on order – Have been ordered but not yet arrived

• Backorders – Items promised to customers but not yet shipped – New units are shipped out to cancel backorders64

Page 65: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Types of Inventory

• Raw Materials– Essential to the production process– Often kept in large quantities on site

• Finished Goods– Completed products awaiting shipment to customers

• Work-in-Process (WIP)– Batches of semi finished products currently in production– Batches of parts from time of release until finished goods

status• Pipeline

– Goods in transit between facilities– Raw materials being delivered to the plant– Finished goods being shipped to warehouse or customer65

Page 66: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Types of Inventory

66

Page 67: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Justification of Inventory

67

Inventory will always exist Competitive pressure to supply common products

quicker than they can be produced imply finished goods inventory must be kept near the customer

Price breaks are common when large quantities of material and parts are purchased

We may store inventory in periods of low demand and consume them in periods of large demand to smooth production rate (seasonal demand)

Speculation

Page 68: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Inventory Costs and Tradeoffs

• Holding inventory is costly• In constructing economic models for choosing the

optimal levels of inventory, trade of the costs caused by:

1. Ordering or set up of machines

2. Investing and storing the goods

3. Shortages (not having inventory available when needed)

68

Page 69: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Ordering Costs

69

A fixed ordering cost can be associated with each replenishment when parts are ordered from suppliers• Identifying the need to order• Execute the order• Prepare the paperwork• Place the order• Delivery cost fixed component• Receiving inspection• Transportation to place of use• Storage

Page 70: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Setup Costs

70

For parts produced in-house, we must:• Check status of raw material• Possibly place an order• Create route sheets with instructions for each stage of

the production process• Store routing data in a database• Check routing data for compatibility with shop status

and engineering changes• Make routing instructions with raw material• Deliver to production workers• Machine set up

Page 71: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Inventory Carrying Costs

71

Carrying inventory incurs a variety of costs• Space heated and cooled• Move inventory occasionally because it blocks access

to other goods• Construct and maintain information system to track

location• Pay taxes based on value• Insurance costs• Some will be lost, damaged, or perished• Cost of capital invested in inventory

Page 72: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

72

Shortage Costs

When customer demands an out of stock item• May decide to wait for delivery - backorders• May cancel the order – lost sales• May look elsewhere next time – lost customer• May pay expedite charges

Within the plant, if material is unavailable to start production• Work center may lack work• Schedule may have to be modified• Completion of products may be delayed• Result in late deliveries or lost sales

Page 73: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Information Flow for Various Production Systems

73

I I

Order Entry

RawMaterial

I

a. Materials Requirements Planning (MRP)

RawMaterial

b. Just-In-Time (KANBAN)

IProcessorInformation Flow

Material FlowFinite Capacity Inventory Buffer

Infinite Capacity Inventory Buffer

Page 74: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

KANBAN control

• Kanban control uses the levels of buffer inventories in the system to regulate production. When a buffer reaches its preset maximum level, the upstream machine is told to stop producing that part type. This is often implemented by circulating cards, the kanbans, between a machine and the downstream buffer.

• The machine must have a card before it can start an operation. It can then pick raw materials out of its upstream (or input) buffer, perform the operation, attach the card to the finished part, and put it in the downstream (or output) buffer.

74

Page 75: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

KANBAN control

• Kanban control ensures that parts are not made except in response to a demand.

• The analogy is to a supermarket: Only the goods that have been sold are restocked on the shelves.

75

Page 76: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Information Flow for Various Production Systems

76

I

Limit onTotal

Inventory

RawMaterial

I

c. Constant Work-In-Process (CONWIP)

RawMaterial

d. Hybrid CONWIP-KANBAN

IProcessorInformation Flow

Material FlowFinite Capacity Inventory Buffer

Infinite Capacity Inventory Buffer

Page 77: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

CONWIP Control

• CONWIP stands for Constant Work-In-Process.• a control strategy that limits the total number of

parts allowed into the system at the same time. • Once the parts are released, they are processed as

quickly as possible until they fill up the last buffer as finished goods.

• Once the consumer removes a part from the finished goods inventory, the first machine in the chain is authorized to load another part.

77

Page 78: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

CONWIP Control

• Like KANBAN, the CONWIP system only responds to actual demands, so it is still a ``pull'' type system.

• But unlike kanban, the buffers for all downstream machines are empty, except finished goods, which is full.

• This occurs because any part released to the system will move to finished goods. New parts will not be released if the finished goods buffer is full.

78

Page 79: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Inventory is Needed to Support Production

• Recent years claim a goal of zero inventory– But some is necessary to meet needs – Economically practical to maintain some WIP to facilitate

production scheduling– Variability in processing time and job arrival rates

• Inventory should not be used to cover problems– Wasteful practice all too common– Prevents the system from improving– Defects not detected until later

• Lean companies– Operate with reliable processes, quick changeovers, low

inventories, small space, low scrap and rework, closer communication

79

Page 80: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Large Inventories Imply Long Throughput Times

• Throughout time (manufacturing Lead Time)– The span of time from when the part enters a system

until it leaves• Little’s Law I = X · T

– Relates average throughput time (T) to the level of average inventory (I) and the production rate (X) for any stationary process

• Stationary process– Probability of being in a particular state is

independent of time

80

Page 81: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

To reduce throughput time

Eliminate unnecessary, non-value added operations:– Reduce waiting time– Reduce transfer time– Reduce quality inspection time– Increase process rates– Reduce batch size

81

Page 82: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Capacity Balancing

82

1 2 3 4 5Flow In Flow Out

Desire to have same number of units produced in each work center

Capacity is measured by number of units that can be made per time period

Total production is limited by the workstation with the smallest capacity (bottleneck station)

Excess capacity reduces cycle time

Page 83: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

Theory of Constraints (TOC)

A management philosophy developed by Dr. Eliyahu Goldratt.

The goal of a firm is to make money.

Page 84: Lecture 7 Production Planning System (Revisited) Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming

End of Lecture 7