Upload
ibrahim-mesfin
View
216
Download
0
Embed Size (px)
Citation preview
7/28/2019 Lecture 6-Delivery Systems Payment&Award
1/34
Project Management Course
Alberto De Marco 1
Project Management
Delivery systems
Payment &Award
Instructor:
Alberto De Marco
IV School of Management EngineeringDept. of Production Systems and Business Economics
Preliminaries
Long- term project calendar and groups
7/28/2019 Lecture 6-Delivery Systems Payment&Award
2/34
Project Management Course
Alberto De Marco 2
Interview
John Stewart, former McKinsey & Co. director
Project organization
When does a usual business needs a projectmanagement organization?
What are the cost and benefits of project
management organization
RISK/KNOW
HOW
100% CONTRACTOR
100% OWNER
TRADITIONAL DBB
DESIGN/BUILD
TURN-KEY
B.O.T.
CM at RISK
Delivery systems - Summary
AGENCY CM
7/28/2019 Lecture 6-Delivery Systems Payment&Award
3/34
Project Management Course
Alberto De Marco 3
Project Organization Outline
9 Project Management Organizations
9 Contract Organization9 Project Delivery Systems
Payment Schemes Time&Material
Unit prices
Cost plus kinds
Guaranteed Maximum Price
Lump-sum
Award Methods Bidding
Negotiation
Key Idea for Saving: Risk Sharing
Different parties have ability to manage ortolerate different types of risk Owner (or big contractor) often better: Geotechnical
risk, weather risk
Contractor better: Risk of slow teams, equipmentquality, procurement, quality of supervision
Divide risks within an agreement to Save money on contract price
Provide incentive to contractors to finish early, inbudget, good quality
7/28/2019 Lecture 6-Delivery Systems Payment&Award
4/34
Project Management Course
Alberto De Marco 4
Fundamental Ideas Contractors are often highly risk averse
Recall risk premiums: Contractor willing to pay owner(charge less for contract) if owner takes on risk if have to
For risks that contractor cantcontrol, may be willing topay a risk premium to owner to take over
Contractor here will lower costs if owner assumes certain risk(essentially, paying the owner a risk premium)
For risks that contractors cancontrol, cheaper for a
contractor to managerisk than to pay a risk premium
Fundamental Ideas II
Structure contract so that
Risks contractor can better handle are imposed on
contractor (i.e. contractor will lose $ if dont control)
To be competitive, will have to managethese Risks owner can better handle are kept by owner
Risk can be better handled by A vs. B heremeans that the risk premium that would becharged by the A for taking on this risk issmaller than would be charged by B
7/28/2019 Lecture 6-Delivery Systems Payment&Award
5/34
Project Management Course
Alberto De Marco 5
Risk allocation
RIS
K/KNOWH
OW
100% CONTRACTOR
100% OWNER
TRADITIONAL DBB
DESIGN/BUILD
TURN-KEY
B.O.T.
CM at RISK
AGENCY CM
??? payment
Fundamental Balance
Impose highenough risk incentive to get contractor do
job efficiently within the specifications of the contract
E.g. Incentive to finish on time, incentive to stay withinbudget
E.g. better team assignment, equipment provision, mgmt
Impose lowenough risk to have reasonably low bid
Impose according to contractor ability to tolerate
7/28/2019 Lecture 6-Delivery Systems Payment&Award
6/34
Project Management Course
Alberto De Marco 6
Derivative Results of Risks:
Accountability/Monitoring
Consider parties A and B in an agreement
The greater the risk on party A
The more incentive on party A to manage this risk
The less incentive on party B to manage this risk
More incentive on A to monitor the relevant factorsso B cant claim the risk is responsible for a problem
More incentive on B to make sure that As means of
riskmanagementfall within the agreement
E.g. that not cutting corners or otherwise cheating toshield from risk
Derivative Results of Risks:
Impact on Construction Timing More risk on contractor, the longer will delay construct.
Given uncertainty, contractor will charge more up front
Owner doesnt want to pay a huge amount up front
As uncertainty is lessened in design, prices converge
Owner can expedite by paying higher price (risk
premium) to contractor or by shouldering risk
Remember; delay can have major costs but so canwrangling over change orders!
7/28/2019 Lecture 6-Delivery Systems Payment&Award
7/34
Project Management Course
Alberto De Marco 7
Note on Change Orders
Changes contract (cost/schedule/scope/etc.)
Can lead to costs beyond contract specification
Anticipated costs incorporated in contingency
Often 1-5% on top of agreed upon price
Often only paid for additional direct costs
Big problem if disruption in work Source of very large risk
ontractua s
Allocation
100 %RISK Allocation
Lump-Sum (Fixed Price)
0 %
100 %
CONTRACTORSR
ISK
0 %
OWNERSRISK
RISK SHARING METERModified from Kerzner, 2000
Fixed-Price w/ Economic Price Adjustments
Fixed-Price Incentive
Cost-Plus Incentive
Cost-Plus Award Fee
Cost-Plus Fixed Fee
Cost-Sharing
Cost-Plus Percentage
7/28/2019 Lecture 6-Delivery Systems Payment&Award
8/34
Project Management Course
Alberto De Marco 8
Project Organization Outline9 Project Management Organizations
9 Contract Organization9 Project Delivery Systems
Payment Schemes Time & Material
Unit prices
Cost plus
Guaranteed Maximum Price
Lump-sum
Award Methods Bidding
Negotiation
Time&Material Contract price = Value of work + material*(1+%fee)
Price of working hour according to unionized prices oragreed upon on contract
%fee represents contractor overhead
Work Specialized worker 75 $/h ; 50 hours Worker 50 $/h ; 100 hs
Material Equipment rental 5,000 $ Construction commodities3,000 $ 30% overhead
Contract value: 75 * 50 + 50 * 100 + (5,000 + 3,000) * 1.3 = 19,150
7/28/2019 Lecture 6-Delivery Systems Payment&Award
9/34
Project Management Course
Alberto De Marco 9
Time&Material
Risk on owner
Actual contract value defined at the end
Small works (repair & maintenance)
Project Organization Outline
9 Project Management Organizations
9 Contract Organization9 Project Delivery Systems
Payment Schemes9 Time & Material
Unit prices
Cost plus
Guaranteed Maximum Price
Lump-sum
Award Methods Bidding
Negotiation
7/28/2019 Lecture 6-Delivery Systems Payment&Award
10/34
Project Management Course
Alberto De Marco 10
Unit Price Contract Agreement on the price chargedper unitbetween thecontractor and the owner If project is complex, it needs a detailed list of activities (bill of
quantities) If project is linear/homogeneous, it can be described by one
unit price which includes the amount of work packages e.g.: unit price per foot of completed tunnel, unit price per ft3 of
poured concrete
Interesting example of risk sharing Owner: risk for uncertainty in quantity
Contractor: risk for unit price (efficiency, procurement) Contractor overhead must be integrated in the unit price Necessity of an owner presence on site to measure the
actual quantities (quantity surveyor) Typically renegotiate if quantity 20% off
Quantity influences price b/c economies of scale
Unit prices
Activities:
Footings 80 $/sq ft
Columns 1,550 $/unit
Scheduled quantities: Footings 100 sq ft
Columns 9 units
Contract initial value:
80 * 100 + 1,550 * 9 = 14,750
7/28/2019 Lecture 6-Delivery Systems Payment&Award
11/34
Project Management Course
Alberto De Marco 11
Unit Price Contract Highly dependent on the accuracy of the
estimation of the quantities given by theOwner/Designer Risk of unbalanced bidding
If contractor believes actual quantity will differ, caseincrease and/or decrease the unit price
Contractor can make profit because payment is based onactual quantities but he can also lose money in the same
wayA contractor can be excluded if its bid is very
unbalanced
The total cost for the owner can be greater thanplanned
Example: Pile Driving
Too risky to just charge fixed price
Geotechnical uncertainties make length of piles
uncertain
Piles can be highly expensive
Risk allocation
Price risk more under contractor control (efficiency,crew and equipment selection): to contractor
Length out of contractor control: to owner
Owner must precisely monitor length used
7/28/2019 Lecture 6-Delivery Systems Payment&Award
12/34
Project Management Course
Alberto De Marco 12
Project Organization Outline9 Project Management Organizations
9 Contract Organization9 Project Delivery Systems
Payment Schemes9 Time & Material
9 Unit prices
Cost plus
Guaranteed Maximum Price
Lump-sum
Award Methods Bidding
Negotiation
Cost Plus Kinds
Cost plus fixed %
Incentive cost plus types:
Cost plus fixed fee
Target cost plus incentive fee
Guaranteed maximum price
7/28/2019 Lecture 6-Delivery Systems Payment&Award
13/34
Project Management Course
Alberto De Marco 13
Cost Plus Fixed %
Owner is paying the actual cost plus a fixedpercentage
Contractor agrees to do his best efforts toachieve the work
Contractor shoulders very little risk Typically select contractors based on reputation
and comfort (servicerather than commodity)
Cost Vs. Price for Cost + Fixed %
Macomber, 1989
7/28/2019 Lecture 6-Delivery Systems Payment&Award
14/34
Project Management Course
Alberto De Marco 14
Cost Plus Fixed % - Example Estimated cost 100,000 $
Fixed % fee 8 % Contractors Return on Cost ROC = 8%
Actual contract value at completion Situation A
Actual cost 90,000 $
Price = 90,000 *(1+8%) = 97.200 $ Situation B
Actual cost 110,000 $
Price = 110,000 *(1+8%) = 118,800
ROC = 8.0 %
ROC = 8.0 %
Cost Plus + Fixed %: Disadvantages
Contractors have incentive to grow scope, price! Owner shoulders all risk
Little incentive to reduce costs and overtime salaries
can even increase costs Cost unknown until contract completes
Owner needs to oversee construction closely Speed up slow crews
Identify management problems
Terrible with turnkey delivery type!
7/28/2019 Lecture 6-Delivery Systems Payment&Award
15/34
Project Management Course
Alberto De Marco 15
Cost Plus + Fixed %: Advantages Maximum flexibility to the Owner
No fighting over change orders contractor getspaid for any extra work required
Permits collaboration at early project stages Minimal negotiation time
Minimal fear of commitment by contractor
Only have to pay for what actually costs
If manage closely, can save moneyvs. fixed-price
Applicability
Requires sophisticated owner to manage
Use if the pricing could not be performed in anyother way and if it is urgent
Emergencies (civil, military) Examples
Either scope or construction method unknown e.g. historic building renovation with unknown cond. Unknown technologies
Confidential projects (limit public knowledge)
7/28/2019 Lecture 6-Delivery Systems Payment&Award
16/34
Project Management Course
Alberto De Marco 16
Incentive policy
Owner needs to incentive contractor to
reduce cost
May reduce speed of work because contractordoesnt use overtime, extra equipment, etc.
Cost Plus Fixed Fee (Fixed Fee)
Cost may vary but the fee remains firm The fee is independent of the duration of the
project Like Cost + fixed % except some shared risk
Less time risk: High incentive to finish early Less risk of contractor
Growing size of project to make more Cutting corners to make a buck
7/28/2019 Lecture 6-Delivery Systems Payment&Award
17/34
Project Management Course
Alberto De Marco 17
Cost Plus Fixed Fee Example Estimated cost 100,000 $
Fixed fee 8,000 $ Estimated Return on Cost ROC = 8%
Actual contract value at completion Situation A
Actual cost 90,000 $
Price = 90,000 + 8,000 = 98.000 $ Situation B
Actual cost 110,000 $
Price = 110,000 + 8,000 = 118,000
ROC = 8.9 %
ROC = 7.3 %
Target Cost Plus Incentive Fixed Fee
Target cost 100,000 $
Fixed fee 8,000 $
Saving/extra cost share 30% Estimated Return on Cost ROC = 8%
Actual contract value at completion Situation A
Actual cost 90,000 $
Price = 90,000 + 10.000 * 0.30 + 8,000 = 101,000 $
Situation B Actual cost 110,000 $ Price = 110,000 - 10.000 * 0.30 + 8,000 = 115,000
ROC = 12.2 %
ROC = 4.5 %
7/28/2019 Lecture 6-Delivery Systems Payment&Award
18/34
Project Management Course
Alberto De Marco 18
Project Organization Outline9 Project Management Organizations
9 Contract Organization9 Project Delivery Systems
Payment Schemes9 Time & Material
9 Unit prices
9 Cost plus
Guaranteed Maximum Price
Lump-sum
Award Methods Bidding
Negotiation
Guaranteed Maximum Price or GMP
Variation of the Cost Plus a Fee but GMPcan be a cap on costs
After a certain point, the floor or ceiling,
the contractor assumes any additional costs Best: GM Shared Savings: Below Guaranteed
Maximum, savings shared (60-30% or sliding) Very good for turnkey, well-defined scope
7/28/2019 Lecture 6-Delivery Systems Payment&Award
19/34
Project Management Course
Alberto De Marco 19
GMP with Incentive Fixed Fee GMP 112,000 $
Target cost 100,000 $
Fixed fee 8,000 $
Saving share 30% Estimated Return on Cost ROC = 8%
Actual contract value at completion Situation A (savings) = cost + incentive fixed fee
Actual cost 90,000 $ Price = 90,000 + 10.000 * 0.30 + 8,000 = 101,000 $
Situation B (extra costs) Actual cost 110,000 $ Price = 110,000 + 8,000 = 118,000 > 112,000 $
ROC = 12.2 %
ROC = 1.8 %
Cost Versus Price for GMP
Macomber, 1989
7/28/2019 Lecture 6-Delivery Systems Payment&Award
20/34
Project Management Course
Alberto De Marco 20
GMP: Advantages
Permits easier financing
Can fast-track
Owner keeps savings below GMP
Often can get started quickly on construction
Particularly if contractor already involved w/design
Contract may be higher than for fixed price b/cdesign often not complete when contract set
GMP: Disadvantages
Contractors may still spend lots
Owner must monitor contractor spending
Bad if unclear scope after GMP agreed to (mustrenegotiate)
Just as for C+FF, quality may be sacrificedwhereas without GMP, cost and/or schedulewould have increased
7/28/2019 Lecture 6-Delivery Systems Payment&Award
21/34
Project Management Course
Alberto De Marco 21
Project Organization Outline9 Project Management Organizations
9 Contract Organization9 Project Delivery Systems
Payment Schemes9 Time & Material
9 Unit prices
9 Cost plus
9 Guaranteed Maximum Price
Lump-sum
Award Methods Bidding
Negotiation
Cost Versus Price for Lump Sum
Macomber, 1989
7/28/2019 Lecture 6-Delivery Systems Payment&Award
22/34
Project Management Course
Alberto De Marco 22
Lump Sum (Fixed Price) Contractor required to achieve the project at
the negotiated contract value All risk of cost, schedule fall on contractor The owner knows the actual cost of the
project before it begins Minimizes risk for the owner if the project is
well estimated, contractual documentsaccurate and project clearly defined
High incentive for contractor to finish Early (so can move on to other jobs)
Low cost (so can make a profit)
Lump Sum
Required for many public projects P3 also
Good for some well-defined projects
Good price competition in commodity metric Bad for ill-defined projects
Adversarial relationship over responsibility andpayment for of changes
High contractor risk means typically start late Very different from typical meaning of Fixed fee!
7/28/2019 Lecture 6-Delivery Systems Payment&Award
23/34
Project Management Course
Alberto De Marco 23
Ways to Save Money:
Effect on Owners
Helps: Efficiency within construction Best teams
Appropriate equipment
Careful management
Quality workmanship (to avoid risk of rework)
Hurts: Cutting corners, distortion, charge orders
Substitution of materials Distortion of quantities used
Distortion of progress
Project Organization Outline
9 Project Management Organizations
9 Contract Organization9 Project Delivery Systems
Payment Schemes9 Time & Material
9 Unit prices
9 Cost plus
9 Guaranteed Maximum Price
9 Lump-sum
Summary
Award Methods Bidding
Negotiation
7/28/2019 Lecture 6-Delivery Systems Payment&Award
24/34
Project Management Course
Alberto De Marco 24
Conclusion When market is not very good, clients insists on
fixed price bids whereas when the project offersare numerous, it is more difficult to obtain thoseconditions
The contract type choice must depend on:The accuracy of the estimation
The ultimate cost known since the beginning or at
least the maximumThe desired risk
If quick completion of work is wanted
What payment scheme would you
choose?
RISK/KNOW
HOW
100% CONTRACTOR
100% OWNER
TRADITIONAL DBB
DESIGN/BUILD
TURN-KEY
B.O.T.
CM at RISK
AGENCY CM
?
?
?
?
7/28/2019 Lecture 6-Delivery Systems Payment&Award
25/34
Project Management Course
Alberto De Marco 25
Summary
Relative Costs of Construction Contracts
E= contractor's original estimate of the direct job cost at the time of contractaward
M = amount of markup by the contractor in the contract
B = estimated construction price at the time of signing contract
A = contractor's actual cost for the original scope of work in the contract
U = underestimate of the cost of work in the original estimate (with negativevalue of U denoting an overestimate)
C = additional cost of work due to change orders
P = actual payment to contractor by the owner
F = contractor's gross profit
R = basic percentage markup above the original estimate for fixed fee contract
Ri = premium percentage markup for contract type i such that the totalpercentage markup is (R + Ri), e.g. (R + R1) for a lump sum contract, (R + R2)for a unit price contract, and (R + R3) for a guaranteed maximum cost contract
N = a factor in the target estimate for sharing the savings in cost as agreed uponby the owner and the contractor, with 0 N 1.
Chris Hendrickson, 2000
7/28/2019 Lecture 6-Delivery Systems Payment&Award
26/34
Project Management Course
Alberto De Marco 26
Original Estimated Contract Prices
Chris Hendrickson, 2000
Type of Contract Markup Contract Price
Lump sum M = (R +R1)E B = (1 + R + R1)E
Unit price M = (R + R2)E B = (1 + R + R2)E
Cost plus fixed % M = RA = RE B = (1 + R)E
Cost plus fixed fee M = RE B = (1 + R)E
Guaranteed max cost M = (R + R3)E B = (1 + R + R3)E
Owners Actual Payment with
Different Contract Provisions
Chris Hendrickson, 2000
Type of Contract Change Order Payment Owner's Payment
Lump sum C(1 + R + R1) P = B + C(1 + R + R1)
Unit price C(1 + R + R2) P = (1 + R + R2)A + C
Cost plus fixed % C(1 + R) P = (1 + R)(A + C)
Cost plus fixed fee C P = RE + A + C
Guaranteed max cost 0 P = B
7/28/2019 Lecture 6-Delivery Systems Payment&Award
27/34
Project Management Course
Alberto De Marco 27
Contractors Gross Profit with
Different Contract Provisions
Chris Hendrickson, 2000
Type of Contract Profit from Change Order Contractor's Gross Profit
Lump sum C(R + R1) F = E - A + (R + R1)(E + C)
Unit price C(R + R2 F = (R + R2)(A + C)
Cost plus fixed % CR F = R (A + C)
Cost plus fixed fee 0 F = RE
Guaranteed max cost -C F = (1 + R + R3)E - A - C
Project Organization Outline
9 Project Management Organizations
9 Contract Organization
9 Project Delivery Systems
9 Payment Schemes
Award Methods
Competitive Bidding
Cap
Negotiation
7/28/2019 Lecture 6-Delivery Systems Payment&Award
28/34
Project Management Course
Alberto De Marco 28
Bidding method A contractor is selected by the lowest price
proposal, in market competition
Fixed price - low bid is win-lose
Typically associated with lump-sum contract
Qualifications critical
Variants: multi-parameter bidding
Low bid plus arithmetic combination of other factors
Low bid divided by ranking of other factors
Bidding Main Variants
Contractor is competitively selected based on
Qualification and price proposal
Time and price proposal
Qualification, time and price proposal
Design and price proposal
7/28/2019 Lecture 6-Delivery Systems Payment&Award
29/34
Project Management Course
Alberto De Marco 29
Bidding Tradeoffs Time provided to bidders to review documents
Too long: Construction delayed
Too short: Bids low-quality because too little time to review contract
docs (incorporate high risk premium or unrealisticallylow)
Few bidders willing to participate
Bid countToo many bidders: Scare away best contractors
Too few bidders: Bid not competitive
Bidding Tradeoffs
Advantages Can get good price
Transparency
Disadvantages Can set up win-lose situation
Competitive pressures can eliminate profit from bidTry to make up with change orders, cutting corners
Can lead to dispute-oriented relationships
Insufficient consideration of design before pricing
7/28/2019 Lecture 6-Delivery Systems Payment&Award
30/34
Project Management Course
Alberto De Marco 30
Issues with Bids Low bidders can be unreliable
Prequalify aggressively!
To allow for fast-tracking may bid early (30%)
Dont try to force delivery from low bid
Growing Frequency: innovative bidding method
Pressure for lowest bid can create
Cutting corners
Low-quality personnel
Bad feelings
Bidding Process
A/E oversight typical
Publicity (specifies qualification requirements)
Provide bid documents
Typically include fair cost estimate, sample contract
Answer RFIs
Pre-bid conference
Explain scope, working conditions, answer
questions, documented in writing)
7/28/2019 Lecture 6-Delivery Systems Payment&Award
31/34
Project Management Course
Alberto De Marco 31
Public vs. Private Bidding
Public Bidding
Must be publicly advertised (posting in newspapers,
public building, etc.)
Qualification occurs after submission of bids
Typically 60 day period in which can submit bids
Private Bidding
May be by invitation only
Qualification occurs before submission of bids
Qualifications Common items for qualifications
Bonds/Insurance (bid, performance, payment)
Safety record
Reputation
Financial strength Total/Spare capacity
Licensing
Background in type of work
Experience in local area/labor market
Management system (QA, planning, estimation, control)
Interest, adaptability shown
7/28/2019 Lecture 6-Delivery Systems Payment&Award
32/34
Project Management Course
Alberto De Marco 32
CAP
A fixed price (lump-sum) is set by the owneragainst which contractors propose a level ofquality and options for the project
Negotiation
Typically selected based on reputation, qualifications
Typically used for two cases
Very simple
Use trusted, familiar party
Very complex/big
Get contractor involved in design, start work early
Requires relatively savvy owner
Evaluate proposals, monitor performance
Important even for DBB for post-bid changes
7/28/2019 Lecture 6-Delivery Systems Payment&Award
33/34
Project Management Course
Alberto De Marco 33
Negotiation Considerations
Can get win-win because of differences in
Risk preferences
Relative preferences for different attributes
Goal is to find a Pareto optimal agreement
Key skill in negotiation: Ability to find win-win
options
Conclusion
Scope
Delivery system
Payment scheme
Award method
7/28/2019 Lecture 6-Delivery Systems Payment&Award
34/34
Project Management Course
Business cases