Lecture 6-Delivery Systems Payment&Award

Embed Size (px)

Citation preview

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    1/34

    Project Management Course

    Alberto De Marco 1

    Project Management

    Delivery systems

    Payment &Award

    Instructor:

    Alberto De Marco

    IV School of Management EngineeringDept. of Production Systems and Business Economics

    Preliminaries

    Long- term project calendar and groups

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    2/34

    Project Management Course

    Alberto De Marco 2

    Interview

    John Stewart, former McKinsey & Co. director

    Project organization

    When does a usual business needs a projectmanagement organization?

    What are the cost and benefits of project

    management organization

    RISK/KNOW

    HOW

    100% CONTRACTOR

    100% OWNER

    TRADITIONAL DBB

    DESIGN/BUILD

    TURN-KEY

    B.O.T.

    CM at RISK

    Delivery systems - Summary

    AGENCY CM

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    3/34

    Project Management Course

    Alberto De Marco 3

    Project Organization Outline

    9 Project Management Organizations

    9 Contract Organization9 Project Delivery Systems

    Payment Schemes Time&Material

    Unit prices

    Cost plus kinds

    Guaranteed Maximum Price

    Lump-sum

    Award Methods Bidding

    Negotiation

    Key Idea for Saving: Risk Sharing

    Different parties have ability to manage ortolerate different types of risk Owner (or big contractor) often better: Geotechnical

    risk, weather risk

    Contractor better: Risk of slow teams, equipmentquality, procurement, quality of supervision

    Divide risks within an agreement to Save money on contract price

    Provide incentive to contractors to finish early, inbudget, good quality

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    4/34

    Project Management Course

    Alberto De Marco 4

    Fundamental Ideas Contractors are often highly risk averse

    Recall risk premiums: Contractor willing to pay owner(charge less for contract) if owner takes on risk if have to

    For risks that contractor cantcontrol, may be willing topay a risk premium to owner to take over

    Contractor here will lower costs if owner assumes certain risk(essentially, paying the owner a risk premium)

    For risks that contractors cancontrol, cheaper for a

    contractor to managerisk than to pay a risk premium

    Fundamental Ideas II

    Structure contract so that

    Risks contractor can better handle are imposed on

    contractor (i.e. contractor will lose $ if dont control)

    To be competitive, will have to managethese Risks owner can better handle are kept by owner

    Risk can be better handled by A vs. B heremeans that the risk premium that would becharged by the A for taking on this risk issmaller than would be charged by B

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    5/34

    Project Management Course

    Alberto De Marco 5

    Risk allocation

    RIS

    K/KNOWH

    OW

    100% CONTRACTOR

    100% OWNER

    TRADITIONAL DBB

    DESIGN/BUILD

    TURN-KEY

    B.O.T.

    CM at RISK

    AGENCY CM

    ??? payment

    Fundamental Balance

    Impose highenough risk incentive to get contractor do

    job efficiently within the specifications of the contract

    E.g. Incentive to finish on time, incentive to stay withinbudget

    E.g. better team assignment, equipment provision, mgmt

    Impose lowenough risk to have reasonably low bid

    Impose according to contractor ability to tolerate

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    6/34

    Project Management Course

    Alberto De Marco 6

    Derivative Results of Risks:

    Accountability/Monitoring

    Consider parties A and B in an agreement

    The greater the risk on party A

    The more incentive on party A to manage this risk

    The less incentive on party B to manage this risk

    More incentive on A to monitor the relevant factorsso B cant claim the risk is responsible for a problem

    More incentive on B to make sure that As means of

    riskmanagementfall within the agreement

    E.g. that not cutting corners or otherwise cheating toshield from risk

    Derivative Results of Risks:

    Impact on Construction Timing More risk on contractor, the longer will delay construct.

    Given uncertainty, contractor will charge more up front

    Owner doesnt want to pay a huge amount up front

    As uncertainty is lessened in design, prices converge

    Owner can expedite by paying higher price (risk

    premium) to contractor or by shouldering risk

    Remember; delay can have major costs but so canwrangling over change orders!

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    7/34

    Project Management Course

    Alberto De Marco 7

    Note on Change Orders

    Changes contract (cost/schedule/scope/etc.)

    Can lead to costs beyond contract specification

    Anticipated costs incorporated in contingency

    Often 1-5% on top of agreed upon price

    Often only paid for additional direct costs

    Big problem if disruption in work Source of very large risk

    ontractua s

    Allocation

    100 %RISK Allocation

    Lump-Sum (Fixed Price)

    0 %

    100 %

    CONTRACTORSR

    ISK

    0 %

    OWNERSRISK

    RISK SHARING METERModified from Kerzner, 2000

    Fixed-Price w/ Economic Price Adjustments

    Fixed-Price Incentive

    Cost-Plus Incentive

    Cost-Plus Award Fee

    Cost-Plus Fixed Fee

    Cost-Sharing

    Cost-Plus Percentage

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    8/34

    Project Management Course

    Alberto De Marco 8

    Project Organization Outline9 Project Management Organizations

    9 Contract Organization9 Project Delivery Systems

    Payment Schemes Time & Material

    Unit prices

    Cost plus

    Guaranteed Maximum Price

    Lump-sum

    Award Methods Bidding

    Negotiation

    Time&Material Contract price = Value of work + material*(1+%fee)

    Price of working hour according to unionized prices oragreed upon on contract

    %fee represents contractor overhead

    Work Specialized worker 75 $/h ; 50 hours Worker 50 $/h ; 100 hs

    Material Equipment rental 5,000 $ Construction commodities3,000 $ 30% overhead

    Contract value: 75 * 50 + 50 * 100 + (5,000 + 3,000) * 1.3 = 19,150

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    9/34

    Project Management Course

    Alberto De Marco 9

    Time&Material

    Risk on owner

    Actual contract value defined at the end

    Small works (repair & maintenance)

    Project Organization Outline

    9 Project Management Organizations

    9 Contract Organization9 Project Delivery Systems

    Payment Schemes9 Time & Material

    Unit prices

    Cost plus

    Guaranteed Maximum Price

    Lump-sum

    Award Methods Bidding

    Negotiation

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    10/34

    Project Management Course

    Alberto De Marco 10

    Unit Price Contract Agreement on the price chargedper unitbetween thecontractor and the owner If project is complex, it needs a detailed list of activities (bill of

    quantities) If project is linear/homogeneous, it can be described by one

    unit price which includes the amount of work packages e.g.: unit price per foot of completed tunnel, unit price per ft3 of

    poured concrete

    Interesting example of risk sharing Owner: risk for uncertainty in quantity

    Contractor: risk for unit price (efficiency, procurement) Contractor overhead must be integrated in the unit price Necessity of an owner presence on site to measure the

    actual quantities (quantity surveyor) Typically renegotiate if quantity 20% off

    Quantity influences price b/c economies of scale

    Unit prices

    Activities:

    Footings 80 $/sq ft

    Columns 1,550 $/unit

    Scheduled quantities: Footings 100 sq ft

    Columns 9 units

    Contract initial value:

    80 * 100 + 1,550 * 9 = 14,750

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    11/34

    Project Management Course

    Alberto De Marco 11

    Unit Price Contract Highly dependent on the accuracy of the

    estimation of the quantities given by theOwner/Designer Risk of unbalanced bidding

    If contractor believes actual quantity will differ, caseincrease and/or decrease the unit price

    Contractor can make profit because payment is based onactual quantities but he can also lose money in the same

    wayA contractor can be excluded if its bid is very

    unbalanced

    The total cost for the owner can be greater thanplanned

    Example: Pile Driving

    Too risky to just charge fixed price

    Geotechnical uncertainties make length of piles

    uncertain

    Piles can be highly expensive

    Risk allocation

    Price risk more under contractor control (efficiency,crew and equipment selection): to contractor

    Length out of contractor control: to owner

    Owner must precisely monitor length used

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    12/34

    Project Management Course

    Alberto De Marco 12

    Project Organization Outline9 Project Management Organizations

    9 Contract Organization9 Project Delivery Systems

    Payment Schemes9 Time & Material

    9 Unit prices

    Cost plus

    Guaranteed Maximum Price

    Lump-sum

    Award Methods Bidding

    Negotiation

    Cost Plus Kinds

    Cost plus fixed %

    Incentive cost plus types:

    Cost plus fixed fee

    Target cost plus incentive fee

    Guaranteed maximum price

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    13/34

    Project Management Course

    Alberto De Marco 13

    Cost Plus Fixed %

    Owner is paying the actual cost plus a fixedpercentage

    Contractor agrees to do his best efforts toachieve the work

    Contractor shoulders very little risk Typically select contractors based on reputation

    and comfort (servicerather than commodity)

    Cost Vs. Price for Cost + Fixed %

    Macomber, 1989

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    14/34

    Project Management Course

    Alberto De Marco 14

    Cost Plus Fixed % - Example Estimated cost 100,000 $

    Fixed % fee 8 % Contractors Return on Cost ROC = 8%

    Actual contract value at completion Situation A

    Actual cost 90,000 $

    Price = 90,000 *(1+8%) = 97.200 $ Situation B

    Actual cost 110,000 $

    Price = 110,000 *(1+8%) = 118,800

    ROC = 8.0 %

    ROC = 8.0 %

    Cost Plus + Fixed %: Disadvantages

    Contractors have incentive to grow scope, price! Owner shoulders all risk

    Little incentive to reduce costs and overtime salaries

    can even increase costs Cost unknown until contract completes

    Owner needs to oversee construction closely Speed up slow crews

    Identify management problems

    Terrible with turnkey delivery type!

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    15/34

    Project Management Course

    Alberto De Marco 15

    Cost Plus + Fixed %: Advantages Maximum flexibility to the Owner

    No fighting over change orders contractor getspaid for any extra work required

    Permits collaboration at early project stages Minimal negotiation time

    Minimal fear of commitment by contractor

    Only have to pay for what actually costs

    If manage closely, can save moneyvs. fixed-price

    Applicability

    Requires sophisticated owner to manage

    Use if the pricing could not be performed in anyother way and if it is urgent

    Emergencies (civil, military) Examples

    Either scope or construction method unknown e.g. historic building renovation with unknown cond. Unknown technologies

    Confidential projects (limit public knowledge)

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    16/34

    Project Management Course

    Alberto De Marco 16

    Incentive policy

    Owner needs to incentive contractor to

    reduce cost

    May reduce speed of work because contractordoesnt use overtime, extra equipment, etc.

    Cost Plus Fixed Fee (Fixed Fee)

    Cost may vary but the fee remains firm The fee is independent of the duration of the

    project Like Cost + fixed % except some shared risk

    Less time risk: High incentive to finish early Less risk of contractor

    Growing size of project to make more Cutting corners to make a buck

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    17/34

    Project Management Course

    Alberto De Marco 17

    Cost Plus Fixed Fee Example Estimated cost 100,000 $

    Fixed fee 8,000 $ Estimated Return on Cost ROC = 8%

    Actual contract value at completion Situation A

    Actual cost 90,000 $

    Price = 90,000 + 8,000 = 98.000 $ Situation B

    Actual cost 110,000 $

    Price = 110,000 + 8,000 = 118,000

    ROC = 8.9 %

    ROC = 7.3 %

    Target Cost Plus Incentive Fixed Fee

    Target cost 100,000 $

    Fixed fee 8,000 $

    Saving/extra cost share 30% Estimated Return on Cost ROC = 8%

    Actual contract value at completion Situation A

    Actual cost 90,000 $

    Price = 90,000 + 10.000 * 0.30 + 8,000 = 101,000 $

    Situation B Actual cost 110,000 $ Price = 110,000 - 10.000 * 0.30 + 8,000 = 115,000

    ROC = 12.2 %

    ROC = 4.5 %

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    18/34

    Project Management Course

    Alberto De Marco 18

    Project Organization Outline9 Project Management Organizations

    9 Contract Organization9 Project Delivery Systems

    Payment Schemes9 Time & Material

    9 Unit prices

    9 Cost plus

    Guaranteed Maximum Price

    Lump-sum

    Award Methods Bidding

    Negotiation

    Guaranteed Maximum Price or GMP

    Variation of the Cost Plus a Fee but GMPcan be a cap on costs

    After a certain point, the floor or ceiling,

    the contractor assumes any additional costs Best: GM Shared Savings: Below Guaranteed

    Maximum, savings shared (60-30% or sliding) Very good for turnkey, well-defined scope

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    19/34

    Project Management Course

    Alberto De Marco 19

    GMP with Incentive Fixed Fee GMP 112,000 $

    Target cost 100,000 $

    Fixed fee 8,000 $

    Saving share 30% Estimated Return on Cost ROC = 8%

    Actual contract value at completion Situation A (savings) = cost + incentive fixed fee

    Actual cost 90,000 $ Price = 90,000 + 10.000 * 0.30 + 8,000 = 101,000 $

    Situation B (extra costs) Actual cost 110,000 $ Price = 110,000 + 8,000 = 118,000 > 112,000 $

    ROC = 12.2 %

    ROC = 1.8 %

    Cost Versus Price for GMP

    Macomber, 1989

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    20/34

    Project Management Course

    Alberto De Marco 20

    GMP: Advantages

    Permits easier financing

    Can fast-track

    Owner keeps savings below GMP

    Often can get started quickly on construction

    Particularly if contractor already involved w/design

    Contract may be higher than for fixed price b/cdesign often not complete when contract set

    GMP: Disadvantages

    Contractors may still spend lots

    Owner must monitor contractor spending

    Bad if unclear scope after GMP agreed to (mustrenegotiate)

    Just as for C+FF, quality may be sacrificedwhereas without GMP, cost and/or schedulewould have increased

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    21/34

    Project Management Course

    Alberto De Marco 21

    Project Organization Outline9 Project Management Organizations

    9 Contract Organization9 Project Delivery Systems

    Payment Schemes9 Time & Material

    9 Unit prices

    9 Cost plus

    9 Guaranteed Maximum Price

    Lump-sum

    Award Methods Bidding

    Negotiation

    Cost Versus Price for Lump Sum

    Macomber, 1989

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    22/34

    Project Management Course

    Alberto De Marco 22

    Lump Sum (Fixed Price) Contractor required to achieve the project at

    the negotiated contract value All risk of cost, schedule fall on contractor The owner knows the actual cost of the

    project before it begins Minimizes risk for the owner if the project is

    well estimated, contractual documentsaccurate and project clearly defined

    High incentive for contractor to finish Early (so can move on to other jobs)

    Low cost (so can make a profit)

    Lump Sum

    Required for many public projects P3 also

    Good for some well-defined projects

    Good price competition in commodity metric Bad for ill-defined projects

    Adversarial relationship over responsibility andpayment for of changes

    High contractor risk means typically start late Very different from typical meaning of Fixed fee!

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    23/34

    Project Management Course

    Alberto De Marco 23

    Ways to Save Money:

    Effect on Owners

    Helps: Efficiency within construction Best teams

    Appropriate equipment

    Careful management

    Quality workmanship (to avoid risk of rework)

    Hurts: Cutting corners, distortion, charge orders

    Substitution of materials Distortion of quantities used

    Distortion of progress

    Project Organization Outline

    9 Project Management Organizations

    9 Contract Organization9 Project Delivery Systems

    Payment Schemes9 Time & Material

    9 Unit prices

    9 Cost plus

    9 Guaranteed Maximum Price

    9 Lump-sum

    Summary

    Award Methods Bidding

    Negotiation

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    24/34

    Project Management Course

    Alberto De Marco 24

    Conclusion When market is not very good, clients insists on

    fixed price bids whereas when the project offersare numerous, it is more difficult to obtain thoseconditions

    The contract type choice must depend on:The accuracy of the estimation

    The ultimate cost known since the beginning or at

    least the maximumThe desired risk

    If quick completion of work is wanted

    What payment scheme would you

    choose?

    RISK/KNOW

    HOW

    100% CONTRACTOR

    100% OWNER

    TRADITIONAL DBB

    DESIGN/BUILD

    TURN-KEY

    B.O.T.

    CM at RISK

    AGENCY CM

    ?

    ?

    ?

    ?

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    25/34

    Project Management Course

    Alberto De Marco 25

    Summary

    Relative Costs of Construction Contracts

    E= contractor's original estimate of the direct job cost at the time of contractaward

    M = amount of markup by the contractor in the contract

    B = estimated construction price at the time of signing contract

    A = contractor's actual cost for the original scope of work in the contract

    U = underestimate of the cost of work in the original estimate (with negativevalue of U denoting an overestimate)

    C = additional cost of work due to change orders

    P = actual payment to contractor by the owner

    F = contractor's gross profit

    R = basic percentage markup above the original estimate for fixed fee contract

    Ri = premium percentage markup for contract type i such that the totalpercentage markup is (R + Ri), e.g. (R + R1) for a lump sum contract, (R + R2)for a unit price contract, and (R + R3) for a guaranteed maximum cost contract

    N = a factor in the target estimate for sharing the savings in cost as agreed uponby the owner and the contractor, with 0 N 1.

    Chris Hendrickson, 2000

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    26/34

    Project Management Course

    Alberto De Marco 26

    Original Estimated Contract Prices

    Chris Hendrickson, 2000

    Type of Contract Markup Contract Price

    Lump sum M = (R +R1)E B = (1 + R + R1)E

    Unit price M = (R + R2)E B = (1 + R + R2)E

    Cost plus fixed % M = RA = RE B = (1 + R)E

    Cost plus fixed fee M = RE B = (1 + R)E

    Guaranteed max cost M = (R + R3)E B = (1 + R + R3)E

    Owners Actual Payment with

    Different Contract Provisions

    Chris Hendrickson, 2000

    Type of Contract Change Order Payment Owner's Payment

    Lump sum C(1 + R + R1) P = B + C(1 + R + R1)

    Unit price C(1 + R + R2) P = (1 + R + R2)A + C

    Cost plus fixed % C(1 + R) P = (1 + R)(A + C)

    Cost plus fixed fee C P = RE + A + C

    Guaranteed max cost 0 P = B

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    27/34

    Project Management Course

    Alberto De Marco 27

    Contractors Gross Profit with

    Different Contract Provisions

    Chris Hendrickson, 2000

    Type of Contract Profit from Change Order Contractor's Gross Profit

    Lump sum C(R + R1) F = E - A + (R + R1)(E + C)

    Unit price C(R + R2 F = (R + R2)(A + C)

    Cost plus fixed % CR F = R (A + C)

    Cost plus fixed fee 0 F = RE

    Guaranteed max cost -C F = (1 + R + R3)E - A - C

    Project Organization Outline

    9 Project Management Organizations

    9 Contract Organization

    9 Project Delivery Systems

    9 Payment Schemes

    Award Methods

    Competitive Bidding

    Cap

    Negotiation

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    28/34

    Project Management Course

    Alberto De Marco 28

    Bidding method A contractor is selected by the lowest price

    proposal, in market competition

    Fixed price - low bid is win-lose

    Typically associated with lump-sum contract

    Qualifications critical

    Variants: multi-parameter bidding

    Low bid plus arithmetic combination of other factors

    Low bid divided by ranking of other factors

    Bidding Main Variants

    Contractor is competitively selected based on

    Qualification and price proposal

    Time and price proposal

    Qualification, time and price proposal

    Design and price proposal

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    29/34

    Project Management Course

    Alberto De Marco 29

    Bidding Tradeoffs Time provided to bidders to review documents

    Too long: Construction delayed

    Too short: Bids low-quality because too little time to review contract

    docs (incorporate high risk premium or unrealisticallylow)

    Few bidders willing to participate

    Bid countToo many bidders: Scare away best contractors

    Too few bidders: Bid not competitive

    Bidding Tradeoffs

    Advantages Can get good price

    Transparency

    Disadvantages Can set up win-lose situation

    Competitive pressures can eliminate profit from bidTry to make up with change orders, cutting corners

    Can lead to dispute-oriented relationships

    Insufficient consideration of design before pricing

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    30/34

    Project Management Course

    Alberto De Marco 30

    Issues with Bids Low bidders can be unreliable

    Prequalify aggressively!

    To allow for fast-tracking may bid early (30%)

    Dont try to force delivery from low bid

    Growing Frequency: innovative bidding method

    Pressure for lowest bid can create

    Cutting corners

    Low-quality personnel

    Bad feelings

    Bidding Process

    A/E oversight typical

    Publicity (specifies qualification requirements)

    Provide bid documents

    Typically include fair cost estimate, sample contract

    Answer RFIs

    Pre-bid conference

    Explain scope, working conditions, answer

    questions, documented in writing)

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    31/34

    Project Management Course

    Alberto De Marco 31

    Public vs. Private Bidding

    Public Bidding

    Must be publicly advertised (posting in newspapers,

    public building, etc.)

    Qualification occurs after submission of bids

    Typically 60 day period in which can submit bids

    Private Bidding

    May be by invitation only

    Qualification occurs before submission of bids

    Qualifications Common items for qualifications

    Bonds/Insurance (bid, performance, payment)

    Safety record

    Reputation

    Financial strength Total/Spare capacity

    Licensing

    Background in type of work

    Experience in local area/labor market

    Management system (QA, planning, estimation, control)

    Interest, adaptability shown

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    32/34

    Project Management Course

    Alberto De Marco 32

    CAP

    A fixed price (lump-sum) is set by the owneragainst which contractors propose a level ofquality and options for the project

    Negotiation

    Typically selected based on reputation, qualifications

    Typically used for two cases

    Very simple

    Use trusted, familiar party

    Very complex/big

    Get contractor involved in design, start work early

    Requires relatively savvy owner

    Evaluate proposals, monitor performance

    Important even for DBB for post-bid changes

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    33/34

    Project Management Course

    Alberto De Marco 33

    Negotiation Considerations

    Can get win-win because of differences in

    Risk preferences

    Relative preferences for different attributes

    Goal is to find a Pareto optimal agreement

    Key skill in negotiation: Ability to find win-win

    options

    Conclusion

    Scope

    Delivery system

    Payment scheme

    Award method

  • 7/28/2019 Lecture 6-Delivery Systems Payment&Award

    34/34

    Project Management Course

    Business cases