Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
11/3/2017
1
Lecture 5Part 1
Construction MethodsEngineering for the Las Vegas
High Roller Ferris Wheel
Tom Zieman, P.E., S.E.
Principal
Zieman Engineering, LLC
BSCES SEI BOSTON – 2017 LECTURE SERIESConstruction Aspects of Structural Engineering – “If You Design
It, Can They Build It?”
Zieman Engineering, LLCStamford, CT
Project Participants
• Owner – Caesars Entertainment
• Permanent Structure Designer – Arup
• Contractor – American Bridge Company
• Construction Methods Engineer– American Bridge Company
– Zieman Engineering, LLC
Construction started 2012, open to public April 2014
11/3/2017
2
Structure Dimensions• 550’ tall• 460’ diameter wheel• 28 cabins
Major Components• Legs• Hub/Spindle• Wheel• Cabins
Construction Engineering Criteria
• Partially completed structure capable of withstanding loadsspecified in ASCE 37 “Design Loads on Structures DuringConstruction”– Goal – the same structural reliability as the permanent structure, but
based on the exposure duration of construction
• Wind speed of 80 MPH
• Seismic load assumed less than wind based on duration ofconstruction
• Permanent structure to have dead load force distribution andfinal geometry specified by the EOR within the tolerancesspecified by the EOR
11/3/2017
3
Construction phases
1. Legs
2. Hub/Spindle
3. Wheel
4. Cabins
Leg Construction
11/3/2017
4
Legs Dimensions
• Total Height 282’• Pipe 94”-110” Diameter• 1.38”-2.36” Wall Thickness• Fabricated Lengths 26’-75’• Erected Lengths 75’-109’• 3 Levels of Erection
11/3/2017
5
11/3/2017
6
11/3/2017
7
11/3/2017
8
11/3/2017
9
Hub/Spindle Construction
11/3/2017
10
Hub• 14’-9” Diameter• 1.57” Wall• 108’ Long
Spindle• 9’-10” O.D.• 1.18” Wall• 108’ Long
Spherical Bearing
11/3/2017
11
11/3/2017
12
11/3/2017
13
11/3/2017
14
11/3/2017
15
Wheel Construction
Wheel Configuration• Compression ring 79”
diameter pipe with 1” thickwall
• 460 feet diameter• 28 rim segments with internal
flanged connections• 112 cables – 3” diameter
11/3/2017
16
Rim 3062 k CompressionCable Tension 152 kips
Rim 3958 kips Compression
Cable Tension 199 kips
Cable Tension 254 kips
Wheel Final Force Configuration
Wheel Construction Objectives Specified by EOR
• Force objective – All cables at a load of 254 kips +/- 5% whenat the 6:00 position prior to installing cabins (maximum 267kips, minimum 241 kips)
• Geometry Objective– Wheel radius at 6:00 position must be the same value for any rotation
of the wheel +/- 1” (0.036% of the radius)
– Wheel transverse location at the 6:00 position must not vary fromtheoretical centerline by more than 1” for any rotation of the wheel.
11/3/2017
17
Camber Calculation
• Determine the fabrication dimensions (unstressed condition)which will result in the correct geometry in the final (stressed)condition
• The wheel has to be made 2” larger in diameter
• The cables have to be made about 3” shorter than their finallength
General Construction Procedure Development
• The rim does not function as acompression ring until complete.Therefore, radial struts would benecessary to hold the rim in place duringconstruction.
• No piece of equipment could reasonablyplace the rim segments at the top of thewheel. Therefore, all rim segmentswould be installed at the 6:00 positionand the wheel rotated duringconstruction.
11/3/2017
18
11/3/2017
19
11/3/2017
20
11/3/2017
21
11/3/2017
22
11/3/2017
23
Construction Decision AffectingProcedure and Modeling – CableInstallation Method
• Install to calculated force• Requires extremely accurate
force measurements• Requires more complex
structural model that accuratelypredicts the forces in the realstructure
• Install to calculated geometry• Requires accurate as-built
information (includingtolerances) of all structuralcomponents
Solution:• Install cable to calculated
geometry, but also measureforce to compare to predictions
11/3/2017
24
Staged Construction Analysis Model Objective
• Determine the member forces at each stage of constructionto verify the permanent structure members are withincapacity
• Determine required design capacities for all temporarycomponents
• Verify the feasibility of the assumed construction sequenceand make refinements
• Determine anticipated forces during each stage for thepurpose of monitoring during construction
• Determine anticipated deflections during each stage for thepurpose of monitoring during construction.
SAP2000 Model
• 147 construction stages• All components in model, but
only those that are present in astage are turned on
• Gravity direction is rotated toaccount for different positionsof wheel
• All dead loads input asmembers with mass so that theload direction will correspondto gravity direction
11/3/2017
25
Model Detail at Rim
Model Detail at Hub
11/3/2017
26
TypicalStageOutput
TypicalStageOutput –Deflections
11/3/2017
27
Typical StageOutput -Moments
Temporary Support Structures
• Radial Struts
• Hydraulic Rotating Mechanism
• Holdback Tower
11/3/2017
28
Radial Struts
Radial Struts• 224 feet long each• 18 struts – 4032 feet total length• Interior segments 6’-9” x 6’-9” x 45’-0” long• Interior segments intended to be usable for future projects
11/3/2017
29
11/3/2017
30
Hydraulic Rotating Mechanism
11/3/2017
31
11/3/2017
32
Holdback Tower
11/3/2017
33
11/3/2017
34
11/3/2017
35
11/3/2017
36
Holdback Tower
11/3/2017
37
As-Built Survey of Components Affecting RadialDimensions
• Survey of holes on hub
• Survey of end hardware on cables
• Survey of holes on rim sections
• Survey of ends of each rim section
All surveys were made in the shop using very accurate totalstation equipment (accuracy 0.1mm), then an as-builtrepresentation of the structure was created in 3D cad todetermine the adjusted cable setting dimensions.
11/3/2017
38
11/3/2017
39
11/3/2017
40
11/3/2017
41
11/3/2017
42
Rim Closing Plan
• Lower rim sections adjacent to final section by looseningcables so that the gap opens up
• Insert last rim section
• Pull rim back into shape by jacking cables
11/3/2017
43
Rim Closing Reality
• Gap 9” less than anticipated
• Reasons– 3” due to oversize of radial strut holes
– Remaining 6” unaccounted for – assumed fabrication tolerance orcumulative error of shop survey error
• Solution– Remove 3” of adjustment shims between last two segments
– Hang weights from segments adjacent to last segment to open the gapmore
– Check structural model for hanging weights and forcing in longsegment to verify no overload in rim, cables or radial struts
11/3/2017
44
Gap when segment near finalelevation
Gap when segment at final elevation
11/3/2017
45
Final Cable Installation Reality – Higher ForcesThan Anticipated
• As radial struts were removed and final cable were installedbased on geometry, measured cable force becameprogressively larger than anticipated – up to 30% larger.
• The forces required to unload the radial struts were also muchhigher than predicted by the model.
• Likely cause – geometric error. Possible reasons:– Rim fabricated larger than it was supposed to be
– Cables fabricated shorter than they were supposed to be
– Cumulative as-built survey error during progressive assembly of rim
– Dimensional calculation error
• Actual cause –unknown – but the solution for all possibilitiesis the same – change the cable setting geometry
11/3/2017
46
Solution to Achieve Correct Cable Forces
• Assume that from a modeling viewpoint, the problem can be representedas an imposed elongation of the rim circumference.
• Determine the imposed elongation that best fits the force measurementsalready done:– Retrieve data for cables already installed, and measure tension in additional
accessible cables – 21 data points total.– For each data point, run the SAP model stage corresponding to the point in
time the measurement was taken, and through trial and error determine theimposed elongation of the rim that will reproduce the measured force. Thisgave imposed elongation values between 3” and 10”
– Take a weighted average of the data points based on the assumed reliability ofthe force measurement. Result – rim is 6.6” bigger in circumference than it issupposed to be.
• Adjust the model for all future stages to reflect the increase in rim size.• Adjust the cable setting measurements for all future cables to reflect the
increase in rim size
Result of Geometric Cable Setting Corrections
• After making the correction to the cable setting lengths tocorrect for the larger rim, all future cables matched thepredicted forces generally within 5%. A few cables weremore than 5% off – at worst 10%.
11/3/2017
47
Final Wheel Construction Steps
• A cable tension survey was done at night when temperaturegradients in the structure were lowest. The tension in allcables was measured at the 6:00 position.
• A rim position survey was done simultaneously with thetension survey
• After the survey, approximately 10% of the cables wereoutside the 5% tension tolerance. The model was used todetermine how to adjust the tension in these cables so thatthey would have minimal effect on adjacent cables
• The cables outside the 10% tolerance were adjusted andtension remeasured
11/3/2017
48
Cabin Installation
11/3/2017
49
11/3/2017
50
Project Conclusion
Highly Successful Project for All Parties
• The project was delivered to the owner on time and onbudget
• The contractor and the EOR worked together to solve anydesign issues
• The required force and geometric tolerances were met
• The quality of construction was high
• Through extensive planning, the contractor’s field labor costwas significantly less than anticipated
Questions?
11/3/2017
1
BSCES SEI BOSTON – 2017 LECTURE SERIESConstruction Aspects of Structural Engineering– “If You Design It, Can They Build It?”
Lecture 5Part 2
Assembly and FieldErection of Larger GirderAssemblies for the New
Tappan Zee Bridge
Tom ZiemanPrincipalZieman Engineering, LLCStamford, CT
Video or photography is not allowed during thispresentation. The information (electronic or hardcopy)contained in this presentation is intended for the exclusiveuse of this presentation and may contain information thatis confidential or sensitive. Dissemination, forwarding,printing, or copying is strictly prohibited. Informationregarding the New NY Bridge Project that can be circulatedis available on NewNYBridge.com Photos courtesy of NewYork State Thruway Authority.
To comply with the above restrictions only this trimmeddown portion of the presentation is allowed to bedistributed.
11/3/2017
2
Load-OutBarge
TrestleRunway
Girder Assembly AreaTower Crane
Land Runway
Barge Delivery Slip
Assembly Area
Assembly Line Stations
Girder/CrossframeAssembly
Catwalk/MiscellaneousInstallation
Electrical Installation
Connection Painting,Inspection, Load-Outto Barge
ConnectionPainting
ASSEMBLY LINE STATIONS
11/3/2017
3
Intermediate Grillages for Girder Assembly (Duringassembly +/- 100’ spacing)
Tower Crane
Assembly Support Grillages (After assembly 260’ spacing)
Girder Transporters
Land Runways
Trestle Runways
Winch System
Barge Grillage
Straddle crane Trestle
ASSEMBLY LINE COMPONENTS
• Structural Analysis of Girder Assemblies
• Design of Lifting Frame
• Photos of Field Erection
FIELD ERECTION OF GIRDER ASSEMBLIES
11/3/2017
4
Girder AssemblyLifting Frame• 175’ long x 42’ wide• Supported on crane
with 14” diameterwire rope slings
• Adjustable girderconnections toaccommodatedifferent types ofassemblies
• Hydraulicallyadjustable to slopeframe to matchassemblysuperelevation,longitudinal slope andcenter of gravitylocation
11/3/2017
5
11/3/2017
6