36
Energy Management Systems (EMS) Dr M S R Murty

Lecture 49 EMS

Embed Size (px)

Citation preview

Page 1: Lecture 49 EMS

Energy Management Systems (EMS)

Dr M S R Murty

Page 2: Lecture 49 EMS

SCADA System• Supervisory Control and Data Acquisition (SCADA)

Supervisory Control => Remote Control of Field DevicesData Acquisition => Monitoring of Field Conditions

• SCADA System ComponentsMaster Station => System “Nerve Center” Located inElectric Utility Energy Control Center (ECC);Dispatchers Use to Monitor and Control Power System

• Field Devices => Needed Wherever There is Data to be Sent to Master Station (Substations, Lines or Feeders)

• Communications => Links Master Station with Field Devices; Continuous 24 by 7 Operation

Page 3: Lecture 49 EMS

SCADA SYSTEM CONFIGURATION

Page 4: Lecture 49 EMS

Energy Control Center

Page 5: Lecture 49 EMS

Energy Management System (EMS) Primary Functions

• Network Configuration / Topology Processor• State Estimation• Contingency Analysis• Three Phase Balanced Operator Power Flow• Optimal Power Flow• Dispatcher Training Simulator

Page 6: Lecture 49 EMS

• Voltage Reduction• Load Management• Power Factor Control• Two‐Way Distribution Communications• Short‐Term Load Forecasting• Fault Identification / Fault Isolation / Service Restoration

• Interface to Intelligent Electronic Devices (IEDs)

Distribution Automation System (DAS)Primary Functions

Page 7: Lecture 49 EMS

Energy Management System: Applications

Operations Training

LoadManagement Energy

Management

SCADA AutomaticGeneration

Control

Training Simulator

SecurityControl

EMS Functions

Power System Simulation

Instructional System

DataAcquisition

Supervising Control

Page 8: Lecture 49 EMS

SCADA Functions

• Data acquisition.• Supervisory Control.• Tagging: Identifying a device that should not be operated.• Alarms: Analysis, Chronology.• Logging.• Load Shedding• Trending.

Page 9: Lecture 49 EMS

SCADA Computer

• Downloading RTV files.• Conversion of engineering units.• Management of communication circuit configuration.• Detection & ciation of alarms.• Sequence of events recording.• Respond to operator requests for information display,

execution of control action, etc.

Page 10: Lecture 49 EMS

Automatic Generation Control (AGC)

• Major functions:a) Load Frequency Control (LFC).b) Economic Dispatch (ED).

• Objectives of Load Frequency Control:

i) To maintain frequency at scheduled value.ii) To maintain net power inter-changes with

neighboring control areas at scheduled values.iii) To maintain power allocation among generated

units at economic values.

Page 11: Lecture 49 EMS

Economic Dispatch

• Minimum cost dispatch : Equal incremental cost criteria

• ED Algorithm(Thermal) considers : Generator incremental

Costs- Penalty factorsTransmission loss factors

• For Hydro : ‘Water worth’ concept is used.

Page 12: Lecture 49 EMS

LFC and ED functions in real time:

• LFC : Every few seconds

• ED : Every few minutes

• Conflict : Unit control Errors (UCE) in different directions by LFC & ED

• Logic : Permissive Control : Follow loadMandatory control : Follow Economics

Page 13: Lecture 49 EMS

Energy Management Functions• System load forecast : Every hour for a period of 1-7 days.

• Unit Commitment : Start up & shut down times for most economic operation of thermal units for each hour.

• Fuel Scheduling : Economic choice, fuel purchase contracts.

• Transaction evaluation : Purchase & sale of energy with neighboring companies.

• Transmission loss minimization : Controller actions for minimization of loss.

• Security constraineddispatch : Ensuring eco dispatch without violating network

security.• Production cost

calculation : Actual & economical for each generated unit on hourly basis.

Page 14: Lecture 49 EMS

Real-time Network Analysis Sequence

SCADA NetworkTopology

State Estimator

ContingencyAnalysis

SecurityEnhancement

OptimalPower Flow

Preventive Action

Bus LoadForecast

Transmission Loss Factors

Study Network Analysis: Based on postulated state

Power Flow Contingency Analysis

Optimal Power Flow

Short CircuitAnalysis

Page 15: Lecture 49 EMS

Security Control

• Starts with ‘current state’ and executes programs sequentially.

• Contingency:Event that causes important component to

be removed from service (eg:tr-line, generator, transformer).

• A list of contingencies are processed as applicable to current state.

Page 16: Lecture 49 EMS

• Topology Processing:Building a network model based

on real-time measurements.

• State Estimator:Determining “best” estimate from real-time

measurements.• Power Flow:

Load flow analysis (Voltages, Phase angles).• Contingency Analysis:

Impact of a set of contingencies to identify harmful ones.

Page 17: Lecture 49 EMS

• Optimal Power Flow:Optimization of a specified objective

function (with constraints).• Preventive Action:

To prevent contingency.• Short Circuit Analysis:

Determines the fault currents for 1-ø & 3-ø faults for fault locations across the power system network.

Page 18: Lecture 49 EMS

Power System

SubstationSubstation

SubstationSubstation

G G G GGeneration

Transmission

Distribution

RTU

RTU RTU

SCADA

RTU

SCADA

NationalSCADA/EMS

RegionalSCADA/EMS

RegionalSCADA/EMS

Page 19: Lecture 49 EMS

SCADA/EMS/DMS Architecture

ProcessCommunication

UnitRTU

Measurements

Controls

SCADA EMS DMS

HMI

Measurements

SCADA

EMS

DMS

Data points

100 – 1 000 000

10 000 – 100 000

Sub stations

1 – 10 000

100 – 10 000

10 000 – 1 000 000 1000 – 100 000

Approximate sizes High loadevents per second

10 – 10 000

Updatedanalogs per second

10 – 10 000

Page 20: Lecture 49 EMS

DMS Functions

• Three Phase Unbalanced Operator Power Flow• Map Series Graphics• Interface to Automated Mapping / FacilitiesManagement (AM/FM) or Geographic Information System (GIS)

• Interface To Customer Information System (CIS)

• Interface to Outage Management

Page 21: Lecture 49 EMS

Intelligent Electronic Device (IED)

• IED – Building Block of Substation Integration and Automation

• Any device incorporating one or more processors with the capability to receive or send data/control from or to an external source (e.g., electronic multifunction meters,digital relays, controllers)

Page 22: Lecture 49 EMS
Page 23: Lecture 49 EMS

Some time scales in grid management• There are four levels in grid management.– Unit commitment – which works 

on a scale of days– Scheduling needed on a day 

upon day basis– Load following which has a time 

scale of minutes to hours– Regulation which happen over 

seconds to minutes

• We need to understand that it is a complex issue and needs detailed analysis either to accept or reject an idea.

Page 24: Lecture 49 EMS

SR

WR

NR

ER

NER

Freq ‐ 1

Freq ‐ 2

INDIA CURRENTLY OPERATING AT

“TWO” FREQUENCIES – NORTH & SOUTH

‐ 5 Regional Networks in the Country

‐ Currently 4 Regional Networks merged

Evacuation – The big picture –Northern & Southern GridsEvacuation – The big picture –Northern & Southern Grids

Page 25: Lecture 49 EMS

INTER‐REGIONAL EXISTING CAPACITIESINTER‐REGIONAL EXISTING CAPACITIES

Page 26: Lecture 49 EMS

SOUTHERN REGION

WESTERN REGION

NORTHERN REGION

NORTH-EASTERN REGION

13450 MW

1000 MW6450 MW

4600 MW

1300 MW3700 MW

30,000 MWOF INTER‐REGIONAL POWER  BY 2011 ‐12

EASTERN REGION

ER

“NO Augmentation” proposed between “Southern & Northern” Grids 

INTER‐REGIONAL PROPOSED CAPACITIES BY 2011‐12INTER‐REGIONAL PROPOSED CAPACITIES BY 2011‐12

SOURCE : CEA

Weak link

Page 27: Lecture 49 EMS
Page 28: Lecture 49 EMS
Page 29: Lecture 49 EMS
Page 30: Lecture 49 EMS
Page 31: Lecture 49 EMS
Page 32: Lecture 49 EMS
Page 33: Lecture 49 EMS
Page 34: Lecture 49 EMS
Page 35: Lecture 49 EMS
Page 36: Lecture 49 EMS