Lecture 11 - Process Economics I

Embed Size (px)

Citation preview

  • 8/11/2019 Lecture 11 - Process Economics I

    1/12

    Process economics IProcess economics IProcess economics IProcess economics I

    H82PLD - Plant Design Econ I - 2

    Lecture outlineLecture outlineLecture outlineLecture outline

    Capital cost for new design

    Operating cost

    Depreciation

    Pre-tax and after-tax earning

    Profitability analysis

    H82PLD - Plant Design Econ I - 3

    IntroductionIntroductionIntroductionIntroduction Purpose of chemical processes: to make $$

    3 basic roles of process economics in processdesign: Evaluation of design options

    Process optimisation

    Overall project profitability

    Capital cost for new design (focus in this lecture): Battery limits investment (next slide)

    Utility investment

    Off-site investment

    Engineering fees Working capital

    H82PLD - Plant Design Econ I - 4

    Battery limits investmentBattery limits investmentBattery limits investmentBattery limits investment Battery limits: geographical boundary that defines process

    manufacturing area (converting raw materials products)

    Battery limits investment requires the purchase ofindividual plant items & their installation to form the

    working process. Cost for equipment is often quoted as FOB (Free On Board):

    Manufacturer pays for loading charges onto a shipping truck,railcar, barge or ship, but not freight or unloading charges

    Delivered cost = 5~10% added to the FOB cost

    Cost of equipment is a function of: Size

    Material of construction

    Design pressure Design temperature

  • 8/11/2019 Lecture 11 - Process Economics I

    2/12

    H82PLD - Plant Design Econ I - 5

    Battery limitsBattery limitsBattery limitsBattery limits

    ( Seider et al., 2003)

    H82PLD - Plant Design Econ I - 6

    Cost vs. capacity chartsCost vs. capacity chartsCost vs. capacity chartsCost vs. capacity charts

    Seider et al. (2003)

    H82PLD - Plant Design Econ I - 7

    Cost vs. capacity chartsCost vs. capacity chartsCost vs. capacity chartsCost vs. capacity charts

    Seider et al. (2003)

    H82PLD - Plant Design Econ I - 8

    Cost vs. capacity chartsCost vs. capacity chartsCost vs. capacity chartsCost vs. capacity charts

    Seider et al. (2003)

  • 8/11/2019 Lecture 11 - Process Economics I

    3/12

    H82PLD - Plant Design Econ I - 9

    Cost vs. capacity chartsCost vs. capacity chartsCost vs. capacity chartsCost vs. capacity charts

    Seider et al. (2003)

    H82PLD - Plant Design Econ I - 10

    Equipment purchase costEquipment purchase costEquipment purchase costEquipment purchase cost Cost data can be expressed as power law of capacity:

    where

    CE = equipment cost with capacity Q;

    CB = known base cost for equipment with capacity QB;

    M= constant depending on equipment type

    Published data available from public literature are often old,can be brought up-to-date using cost indices:

    where C1 = equipment cost in year 1; C2 = equipment cost inyear 2; I1 = cost index in year 1; I2 = cost index in year 2

    M

    Q

    QCC

    =

    B

    BE

    =

    2

    1

    21 I

    ICC

    H82PLD - Plant Design Econ I - 11

    Equipment purchase costEquipment purchase costEquipment purchase costEquipment purchase cost Commonly use cost index:

    Chem Eng (CE) Indices (Ibase = 100 @ 1958; ChemicalEngineering magazine) Most useful, covering heat exchangers, tanks, pipe, valve &

    fittings, process instruments, pump & compressors, structuralsupport, etc.

    Different indexes are combined CE Index of Equipment

    Marshall & Swift (MS) Indices (Ibase = 100 @ 1926;Chemical Engineering magazine)

    Nelson-Farrar (NF) Refinery Cost Indices (Ibase = 100@ 1946; Oil & Gas Journal)

    H82PLD - Plant Design Econ I - 12

    Capital cost correlations (CECapital cost correlations (CECapital cost correlations (CECapital cost correlations (CEindex = 585.7 @ Annual 2011)index = 585.7 @ Annual 2011)index = 585.7 @ Annual 2011)index = 585.7 @ Annual 2011)

  • 8/11/2019 Lecture 11 - Process Economics I

    4/12

    H82PLD - Plant Design Econ I - 13

    Capital cost correlations (CECapital cost correlations (CECapital cost correlations (CECapital cost correlations (CEindex = 585.7 @ Annual 2011)index = 585.7 @ Annual 2011)index = 585.7 @ Annual 2011)index = 585.7 @ Annual 2011)

    H82PLD - Plant Design Econ I - 14

    A comparison between indexesA comparison between indexesA comparison between indexesA comparison between indexes

    US Consumer PriceIndex (measurementof inflation rate)

    Engineering News-Record Construction cost

    index average for allindustrial construction

    Seider et al. (2003)

    H82PLD - Plant Design Econ I - 15

    Example 1 : Heat exchangerExample 1 : Heat exchangerExample 1 : Heat exchangerExample 1 : Heat exchanger A new heat exchanger is to be installed as part of a

    large project.

    Preliminary sizing of the exchanger has estimated

    its heat transfer area to be 500 m2

    . Material of construction: low grade stainless steel

    (ignore)

    Pressure rating: 5 bar (ignore)

    CE Index of Equipment: 441.9

    Estimate the purchase cost of the heat exchanger.

    H82PLD - Plant Design Econ I - 16

    Example 1Example 1Example 1Example 1 solutionsolutionsolutionsolution Capital cost estimation using power law:

    Up-to-date costing using CE Index:

    =

    1

    1E I

    ICC E

    M

    Q

    QCC

    =

    B

    BE

    468.0

    401x4.11$

    80

    50001x82.3 =

    =

    44 10x3.15$8.4357.58510x4.11 =

    =

  • 8/11/2019 Lecture 11 - Process Economics I

    5/12

    H82PLD - Plant Design Econ I - 17

    Equipment purchase costEquipment purchase costEquipment purchase costEquipment purchase cost Material of construction

    influences significantly

    equipment capital costcorrection factorfM is used

    Cost factors for shell-and-tube heat exchanger aremore complex.

    Typical equipment materialsMaterial fMCarbon steel 1.0

    Aluminium 1.3Stainless steel (low grades) 2.4Stainless steel (high grades) 3.4Hastelloy C 3.6Monel 4.1Nickel & inconel 4.4Titanium 5.8

    Pressure vessel & columnsMaterial fMCarbon steel 1.0

    Stainless steel (low grades) 2.1Stainless steel (high grades) 3.2Monel 3.6Inconel 3.9Nickel 5.4Titanium 7.7

    Shell-and-tube heat exchangerMaterial fMCS shell and tubes 1.0CS shell, aluminium tubes 1.3

    CS shell, monel tubes 2.1

    CS shell, SS (low grade) tubes 1.7

    SS (low grade) shell and tubes 2.9

    H82PLD - Plant Design Econ I - 18

    Equipment purchase costEquipment purchase costEquipment purchase costEquipment purchase cost

    Influence of operating

    pressure: thicker vesselwalls to withstand increasedpressure pressurecorrection factorfP

    Influence of operatingtemperature: decrease in

    allowable stress astemperature increasestemp correction factorfT

    Correction factor for pressure

    Design pressure (bar absolute) fP

    0.01 2.00.1 1.3

    0.5 7 1.0

    50 1.5

    100 1.9

    Correction factor for temp

    Design temperature (C) fT

    0 100 1.0

    300 1.6

    500 2.1

    H82PLD - Plant Design Econ I - 19

    Equipment purchase costEquipment purchase costEquipment purchase costEquipment purchase cost In addition to purchase cost, investment is needed for

    equipment installation, include: Cost of installation

    Piping & valves

    Control systems Foundations

    Structures

    Insulation fine proofing

    Electrical

    Painting engineering fees

    Contingency

    Total capital cost (installed equipment within batterylimits) = 2 ~ 4 times of equipment purchase cost.

    H82PLD - Plant Design Econ I - 20

    Utility investmentUtility investmentUtility investmentUtility investment The cost of utilities is considered from their sources within

    the site to the battery limits of the chemical process served

    Capital investment in utility plant include equipment for: Electricity generation

    Electricity distribution Steam generation

    Steam distribution

    Process water

    Cooling water

    Firewater

    Effluent treatment

    Refrigeration

    Compressed air Inert gas (nitrogen)

  • 8/11/2019 Lecture 11 - Process Economics I

    6/12

  • 8/11/2019 Lecture 11 - Process Economics I

    7/12

  • 8/11/2019 Lecture 11 - Process Economics I

    8/12

    H82PLD - Plant Design Econ I - 29

    Operating costOperating costOperating costOperating cost1. Raw materials cost:

    The largest individual operating cost

    Depends on whether the materials are being bought & sold: Under a contractual arrangement

    Raw materials might be purchased & products sold below orabove the open market price

    Long-term contractual agreement may reduce profit

    A degree of certainty over the project life

    In open market

    Fluctuate considerably with time.

    Give the best purchase & selling prices

    Uncertain economic environment. Values of raw materials & products are found in trade journals:

    Chemical Marketing Reporter

    European Chemical News

    Asian Chemical News

    H82PLD - Plant Design Econ I - 30

    Operating costOperating costOperating costOperating cost2. Catalysts & chemicals consumed in manufacturing

    (other than raw materials): Catalysts: Need to be replaced or regenerated though the life of process

    Homogeneous catalysts: replacement on continuous basis

    Heterogeneous catalysts:

    Regeneration/replacement is often carried out on anintermittent basis

    Replaced continuously if deteriorate rapidly & when

    regeneration does not fully reinstate the catalyst activity

    Chemicals consumed: Chemicals used that do not form part of the final product

    Example: acids & alkalis consumed to adjust pH of streams

    H82PLD - Plant Design Econ I - 31

    Operating costOperating costOperating costOperating cost3. Utility operating cost:

    Most significant after raw material costs, especiallyfor commodity chemicals production.

    Utility operating cost includes: Fuel

    Electricity

    Steam

    Cooling water

    Refrigeration

    Compressed air

    Inert gas

    H82PLD - Plant Design Econ I - 32

    Operating costOperating costOperating costOperating cost3. Utility operating cost (continue):

    Electricity: More stable price than fuel costs under long-term contract

    Hot countries: more expensive in the summer due to air

    conditioning Cold countries: more expensive in winter due to demandfrom space heating

    Cooling water: Low relative to fuel & electricity

    Depends on power for cooling tower fans & water circulationpump

    Refrigeration: to account for power of refrigerationcycle

  • 8/11/2019 Lecture 11 - Process Economics I

    9/12

    H82PLD - Plant Design Econ I - 33

    Operating costOperating costOperating costOperating cost3. Utility operating cost (continue):

    Low pressure (LP) steam: Estimated from fuel costs assuming an efficiency ofgeneration & distribution losses

    Generation efficiency (~85 - 90%) depends on the boilerefficiency & steam consumed in boiler feed water production

    Losses from the steam distribution system include:

    Heat losses from steam distribution

    Condensate return pipework to the environment

    Steam condensate lost to drain & not returned to theboilers and steam leaks

    Efficiency loss ~10% overall efficiency for steamgeneration & distribution ~ 75 - 80%

    H82PLD - Plant Design Econ I - 34H82PLD - Plant Design

    Operating costOperating costOperating costOperating cost3. Utility operating cost (continue): High pressure (HP) steam: Related to power generation capacity in steam turbine

    HP steam: generated in the utility boilers

    LP steam: generated by reducing P through steam turbinesto produce power.

    Simple way for cost calculation:

    Cost for HP steam = cost of fuel required to generate the HPsteam (including any losses)

    Cost for LP mains = (high-pressure

    mains) (power generated in thesteam turbine)

    Power generated is calculated using

    isentropic efficiency:

    21

    '

    21IS

    HH

    HH

    =

    S

    H

    X = 1.0

    X = 0.8X = 0.85

    P2

    P1H1

    H2

    H2

    Realexpansion

    H82PLD - Plant Design Econ I - 35

    Operating costOperating costOperating costOperating cost4. Labour cost:

    Difficult to estimate

    Decision factors: Batch or continuous processing

    Level of automation

    Number of processing steps

    Level of production

    5. Maintenance:

    Solid handling: increase maintenance cost

    Highly corrosive fluids: increase maintenance cost

    Average: ~6% of fixed capital investment

    H82PLD - Plant Design Econ I - 36

    Example 2: Steam costExample 2: Steam costExample 2: Steam costExample 2: Steam cost High pressure (HP) steam is generated in boilers at 41 barg

    & superheated to 400oC.

    Medium pressure (MP, 10 psig) & low pressure (LP, 3 psig)steam are generated by expanding HP steam through a

    steam turbine with 80% of isentropic efficiency. Cost:

    Fuel: $4/GJ

    Electricity: $0.07/kW.h

    Boiler feed water (BFW): 100oC; Cp = 4.2 kJ/kg.K

    Steam generation: Efficiency: 75%

    Distribution losses: 10%

    Estimate steam cost for all 3 levels.

  • 8/11/2019 Lecture 11 - Process Economics I

    10/12

    H82PLD - Plant Design Econ I - 37

    Example 2: Steam costExample 2: Steam costExample 2: Steam costExample 2: Steam cost

    H82PLD - Plant Design Econ I - 38

    Example 2Example 2Example 2Example 2 SolutionSolutionSolutionSolution Costing for 41 barg steam @ 400oC

    Steam enthalpy (from steam table): 3212 kJ/kg Enthalpy for BFW: 4.2(100 - 0) = 420 kJ/kg

    Heat duty to generate steam: 3212 420 = 2792 kJ/kg

    Cost for steam generation:

    steamHP/ton89.14$75.0

    1042792 6=

    H82PLD - Plant Design Econ I - 39

    Example 2Example 2Example 2Example 2 SolutionSolutionSolutionSolution Costing for 10 barg steam:

    41 barg steam is expanded to 10 barg in a steam turbine

    Inlet condition from steam table: H1 = 3212 kJ/kg

    S1 = 6.747 kJ/kg.K

    Outlet condition for isentropic expansion to 10 barg: H2 = 2873 kJ/kg

    S2 = 6.747 kJ/kg.K

    For single stage expansion with 80% efficiency:

    H2 = H1 (H1 H2) = 2941 kJ/kg

    Power generation (steam turbine): 3212 2941 = 271 kJ/kg

    Value of generated power: 271/3600 x 0.07 = $5.27/ton

    Steam cost = 14.89 5.27 = $9.62/ton

    H82PLD - Plant Design Econ I - 40

    Example 2Example 2Example 2Example 2 SolutionSolutionSolutionSolution Costing for 3 barg steam:

    10 barg steam is expanded to 3 barg in another steam turbine

    Inlet condition from steam table:

    H1 = 2941 kJ/kg

    S1 = 6.88 kJ/kg.K Outlet condition for isentropic expansion to 3 barg:

    H2 = 2732 kJ/kg

    S2 = 6.88 kJ/kg.K

    For single stage expansion with 80% efficiency:

    H2 = H1 (H1 H2) = 2774 kJ/kg

    Power generation (steam turbine): 2941 2774 = 167 kJ/kg

    Value of generated power: 167/3600 x 0.07 = $3.25/ton

    Steam cost = 9.62 3.25 = $6.37/ton

  • 8/11/2019 Lecture 11 - Process Economics I

    11/12

    H82PLD - Plant Design Econ I - 41

    Example 2Example 2Example 2Example 2 SolutionSolutionSolutionSolution Additional note:

    It is generally preferred to use saturated steam forprocess heating

    However, if saturated steam is fed to the main, heatlosses from the main will cause undesirablecondensation in the main.

    Standard practise: feed steam with a superheat of atleast 10oC to avoid condensation.

    For MP steam, steam table shows the outlet T of251oC, i.e. a superheat of 67oC

    For LP steam, outlet T of 160oC, i.e. a superheat of16oC

    H82PLD - Plant Design Econ I - 42

    DepreciationDepreciationDepreciationDepreciation Depreciation, D is often confusing due to several

    definitions and applications.

    For use with approximate profibility measurements,depreciation is estimated as constant percentage (%) of thetotal depreciable capital, CTDC (also known as straight-linedepreciation).

    Direct plant (onsite) depreciation: 8% of (CTDC 1.18Calloc)

    Allocated plant (offsite) depreciation (utilities andrelated facilities): 6% of 1.18 Calloc

    where 1.18 factor accounts for the share of the contigencyand contractors fee.

    H82PLD - Plant Design Econ I - 43

    Total Depreciable CapitalTotal Depreciable CapitalTotal Depreciable CapitalTotal Depreciable Capital Total depreciable capital, CTDC = Cost of direct

    permanent investment, CDPI + cost of contingencies.

    Direct permanent investment, CDPI is referred to thetotal costs of total bare-module investment (C

    TBM), site

    preparation or development (Csite), service facilities(Cserv) and allocated cost of off-site facilities (Calloc).

    Contingencies are unanticipated costs incurred duringconstruction.

    Cost of contingencies: 15% of CDPI

    Constractor fee: 3% of CDPI

    H82PLD - Plant Design Econ I - 44

    PrePrePrePre----tax & Aftertax & Aftertax & Aftertax & After----tax Earningstax Earningstax Earningstax Earnings

    Pre-tax earning or profit also know as grossearning or profit.

    Gross earning or profit = Sales revenue, S Annualproduction cost, C

    After-tax earning or profit also know as netearning or profit.

    Net earning or profit = (1 t) Gross earning

    where t is the income tax.

  • 8/11/2019 Lecture 11 - Process Economics I

    12/12

    H82PLD - Plant Design Econ I - 45

    Total capital investmentTotal capital investmentTotal capital investmentTotal capital investment

    Total capital investment, CTCI is also known as totalfixed capital.

    CTCI is the total cost of total depreciable capital,CDPI and non-depreciable items: Cost of land

    Cost of royalties (use of processes patented by others)

    Cost plant startup

    H82PLD - Plant Design Econ I - 46

    Profitability AnalysisProfitability AnalysisProfitability AnalysisProfitability Analysis Return of Investment (ROI) Annual interest rate

    made by the profit based on total capitalinvestment (CTCI)

    Payback Period (PBP) Time that required to

    breakeven.

    TCI

    earningnetROI

    C=

    ( )ondepreciatiannualearningnetPBP TDC

    +

    =C

    H82PLD - Plant Design Econ I - 47

    Profitability AnalysisProfitability AnalysisProfitability AnalysisProfitability Analysis Venture Profit (VP) Annual net earnings in

    excess of a minimum acceptable return oninvestment, imin

    Annualised cost (CA) Summation of theproduction cost (CProd) and a reasonable return(imin) on the total capital investment (CTCI)

    TCIminearningsnetVP Ci=

    TCIminProdA CiCC +=