Upload
fahad-mahmood
View
226
Download
0
Embed Size (px)
Citation preview
8/7/2019 Lec6a Process Piping Design Part2
1/25
Piping Design Engineer
Engineer must understand certain process basics
When handling utilities
the designer knows that steam cools and forms condensate
he is aware that this condensate must be drained off
How the condensate is removed??
Possibly with a steam trap at selected low points in the steam system
Design engineer
also should know how to handle two-phase flow
equilibrium liquids
hot vapor by-passes
8/7/2019 Lec6a Process Piping Design Part2
2/25
Phase Equilibrium Liquids
Equilibrium liquids require the piping designers attention
Small amount of pressure drop
EL will start flashing
resulting in two-phase flow
increased line velocity
fluid that is difficult to control and impossible to measure
although flashing doesnt do any harm
Piping designer must first recognise
what liquids are in equilibrium?
when flashing can be tolerated?
8/7/2019 Lec6a Process Piping Design Part2
3/25
Phase Equilibrium Liquids
Where do you find equilibrium liquids??
any tray draw-off
tower bottoms
two phase flow
reboiler liquid draw-off biggest piping problems occur at reboiler liquid drawoffs
8/7/2019 Lec6a Process Piping Design Part2
4/25
Incorrect Piping of Reboiler Liquid
Problem of routing the reboiler
liquid from the area behind theweir
Through a pair of orifice flanges
(meter run)
Through a level control valve
Into the main pipeway or rack
8/7/2019 Lec6a Process Piping Design Part2
5/25
Incorrect Piping of Reboiler Liquid
Liquid is drawn @ nozzle A runshorizontally
Rises @B (here the liquid must pushagainst the head of liquid in the riserB)
Press drop is induced in the system
Flashing will start
The meter run, C can not properlymeasure two-phase flow
The control valve can not controlproperly
Piping fabricated and installed in thismanner
would have to be dismantled andrebuilt in the field
COSTLY MISTAKE
Nozzle
Riser
Orifice meter
Control
valve
8/7/2019 Lec6a Process Piping Design Part2
6/25
Correct Method of Piping Equilibrium Liquid
Liquid is drawn through nozzleA stays horizontal through
meter run B and the controlvalve
Then rises vertically at C.
Flashing still occurs but aftermeasuring and control
functions
If excessive flashing occurswhat one must do??
Line size can be increased tokeep the velocity low
By keeping both the meter runand the control valve below theliquid level in the reboiler
flashing is prevented in this
method
8/7/2019 Lec6a Process Piping Design Part2
7/25
Two-phase Flow Scenario (improper)
Two-phase flow causes piping
designers the most problems
Pipes friction reacts more on the
liquid portion, as the vapor tends to
flow at a greater velocity.
Real problem occurs when two-phase
flow must be divided into separate
piping systems
Major portion of flow would be routed to B
This would cause exchanger A to have less
pressure drop and exchanger B to have
more pressure drop
(although both HEs are designed for same
duty and pressure drop)
8/7/2019 Lec6a Process Piping Design Part2
8/25
Two-phase Flow Scenario (improper)
Since A has less pressure drop, the
liquids velocity will direct it to B
vapor will take the path of least resistance
and will go to exchanger A
the net result is
A is getting vapor
B is getting liquid
HTR of HEs is designed for equal flow
of liquid and vapor
Consequences: Exchangers will not perform as designed, the process unit
will not perform and must be shut down for correction
If piping designer does not recognise that the piping was for two-phase
flow, then these problems are likely to prevail.
How to modify??
(to make it proper)
8/7/2019 Lec6a Process Piping Design Part2
9/25
Two-phase Flow Scenario (proper)
Two-phase flow enters the horizontal pipe
midway between the exchangers
Pressure drop is same to either one
Absence of a path of least resistance
Flow will be equal to both exchangers
Features
8/7/2019 Lec6a Process Piping Design Part2
10/25
Piping at Fired Heaters (proper)
This a very common piping system
The heater inlet is all liquid flow
and the outlet is two-phase flow
In majority of the cases (nine out of
ten cases), this installation
completely unnecessary
excessively expensive
WHY???
8/7/2019 Lec6a Process Piping Design Part2
11/25
Piping at Fired Heaters The liquid heater feed (item1) is divided into 4 streams
to match the four passes of
heater tubes
each stream has a globe valve
(item 2) and flow indicator
(item 3, orifice)
each heater pass outlet has atemperature indicator
To operate the heater
flow is regulated with
the globe valve to ensure
that each pass has the
same flow
T indicates the desired
outlet temperature
The piping is correct up to
this point
8/7/2019 Lec6a Process Piping Design Part2
12/25
Piping at Fired Heaters
Where is the inaccuracy in this
installation??
In the downstream of the TI located
in each pass outlet
Someone has coined the magic
term two-phase flow and decided tohave symmetrical piping
symmetrical piping means
money and piping problems
can be doubly expensive if
the heater outlet is alloy
material
Symmetrical piping is necessary
for two-phase flow if there is no
method of control and distribution
must be made
8/7/2019 Lec6a Process Piping Design Part2
13/25
Piping at Fired Heaters
In this installation distribution made
while the fluid is all liquid, controlled by
the globe valve and metered by the flow
indicator
to ensure that streams A, B, C, and D are
all equal flow.
If the flow is equal going into the heater
it must be equal coming out
Where to consider symmetrical piping??
Low pressure systems (such as a
crude charge heater service)
High pressure installations
the outlets should be combined in
the most economical manner and
routed on its way
outlet pass differential pressure
drop is minor and no consequence
8/7/2019 Lec6a Process Piping Design Part2
14/25
Hot Vapor By-pass
Tower overhead is routed to an air cooler (fin-fan)
Condensed vapor is directed to the accumulator
To maintain pressure on the accumulator, a hot
vapor by-pass will be installed
Hot vapor is by-passed around the cooler and isrouted to the pressure control valve, which allows
pressure to enter the accumulator as required
Hot vapor by-passes should never be pocketed
The pressure control valve should be installedabove the top of the accumulator
The by-pass piping must continuously drain from
point A to point B
8/7/2019 Lec6a Process Piping Design Part2
15/25
Hot Vapor By-pass
As this by-passed vapor cools due to rainfall on
the line or cool air cooling the line, condensate
will form
With small amount of differential pressure
between points A and B
a pocket of liquid head might not be
overcome
the hot vapor by-pass may not work.
Generally, there is less than 10 psig differential
between A and B
Pressure control valve (butterfly type) is specified
to keep the pressure drop to minimumbut this will consume 2-3 psig
Line loss will consume another 2-3 psig
leaving about 4 psig
this will not overcome much liquid head
8/7/2019 Lec6a Process Piping Design Part2
16/25
Static Head or Pressure Head or Head
Liquids at rest causes a pressure equal in all directions and perpendicularto any surfaces in contact with liquid
This pressure is due to the weight of the liquid
Plus the pressure at the top level of the liquid
The liquid height is called Static Head or Pressure Head or Head
Head is important when calculating
hydrostatic pressure of vessels
Piping systems
8/7/2019 Lec6a Process Piping Design Part2
17/25
Impact of water head
A tower system designed for 50 psig
This tower requires a hydrostatic
pressure of 75 psig and this test pressure
must be measured at the highest point in
the system (point A)
To attain this pressure at A the fieldbrings in a hydrotest pump and fills the
system full of water.
Piping designer knows this pump is
located located at grade.
Engineer should calculate the height
from the pumps pressure gauge to point
A and add this to the required test
pressure.
8/7/2019 Lec6a Process Piping Design Part2
18/25
Impact of water head
In this case 54 psig must be added to 75
psig, totalling 129 psig
Which is the pressure that must be
obtained at which pressure gauge to
satisfy the 75 psig hydrostatic
conditions
The vessel designer must also considerthe static head
While calculating the tower head and
shell thickness.
This additional weight is considered inthe design of the support for the tower.
This can be critical when vessels are
located high in a steel or concrete
structures
8/7/2019 Lec6a Process Piping Design Part2
19/25
8/7/2019 Lec6a Process Piping Design Part2
20/25
Flow of Oil in a Branched Pipeline
The pipeline handles an oil with specific gravity of 0.92 and kinematic viscosity
of 5 centistokes (cS) at a total rate of 12,000 cuft/hr. All three pumps have the
same output pressure. At point 5 the elevation is 100 ft and the pressure is 2 atm
gage. Elevations at the other points are zero. Line dimensions are presented in
Table 1.
Table Line dimensions
Line L (ft) D (ft)
14
24
34
45
1000
2000
1500
4000
0.4
0.5
0.3
0.75
Using the schematic for branched pipeline network shown in Figure 1, calculate
the flow rates in each of the lines and the total power requirement.
1
8/7/2019 Lec6a Process Piping Design Part2
21/25
Branched pipeline
8/7/2019 Lec6a Process Piping Design Part2
22/25
8/7/2019 Lec6a Process Piping Design Part2
23/25
Branched pipeline
8/7/2019 Lec6a Process Piping Design Part2
24/25
Branched pipeline
8/7/2019 Lec6a Process Piping Design Part2
25/25