Lec6a Process Piping Design Part2

Embed Size (px)

Citation preview

  • 8/7/2019 Lec6a Process Piping Design Part2

    1/25

    Piping Design Engineer

    Engineer must understand certain process basics

    When handling utilities

    the designer knows that steam cools and forms condensate

    he is aware that this condensate must be drained off

    How the condensate is removed??

    Possibly with a steam trap at selected low points in the steam system

    Design engineer

    also should know how to handle two-phase flow

    equilibrium liquids

    hot vapor by-passes

  • 8/7/2019 Lec6a Process Piping Design Part2

    2/25

    Phase Equilibrium Liquids

    Equilibrium liquids require the piping designers attention

    Small amount of pressure drop

    EL will start flashing

    resulting in two-phase flow

    increased line velocity

    fluid that is difficult to control and impossible to measure

    although flashing doesnt do any harm

    Piping designer must first recognise

    what liquids are in equilibrium?

    when flashing can be tolerated?

  • 8/7/2019 Lec6a Process Piping Design Part2

    3/25

    Phase Equilibrium Liquids

    Where do you find equilibrium liquids??

    any tray draw-off

    tower bottoms

    two phase flow

    reboiler liquid draw-off biggest piping problems occur at reboiler liquid drawoffs

  • 8/7/2019 Lec6a Process Piping Design Part2

    4/25

    Incorrect Piping of Reboiler Liquid

    Problem of routing the reboiler

    liquid from the area behind theweir

    Through a pair of orifice flanges

    (meter run)

    Through a level control valve

    Into the main pipeway or rack

  • 8/7/2019 Lec6a Process Piping Design Part2

    5/25

    Incorrect Piping of Reboiler Liquid

    Liquid is drawn @ nozzle A runshorizontally

    Rises @B (here the liquid must pushagainst the head of liquid in the riserB)

    Press drop is induced in the system

    Flashing will start

    The meter run, C can not properlymeasure two-phase flow

    The control valve can not controlproperly

    Piping fabricated and installed in thismanner

    would have to be dismantled andrebuilt in the field

    COSTLY MISTAKE

    Nozzle

    Riser

    Orifice meter

    Control

    valve

  • 8/7/2019 Lec6a Process Piping Design Part2

    6/25

    Correct Method of Piping Equilibrium Liquid

    Liquid is drawn through nozzleA stays horizontal through

    meter run B and the controlvalve

    Then rises vertically at C.

    Flashing still occurs but aftermeasuring and control

    functions

    If excessive flashing occurswhat one must do??

    Line size can be increased tokeep the velocity low

    By keeping both the meter runand the control valve below theliquid level in the reboiler

    flashing is prevented in this

    method

  • 8/7/2019 Lec6a Process Piping Design Part2

    7/25

    Two-phase Flow Scenario (improper)

    Two-phase flow causes piping

    designers the most problems

    Pipes friction reacts more on the

    liquid portion, as the vapor tends to

    flow at a greater velocity.

    Real problem occurs when two-phase

    flow must be divided into separate

    piping systems

    Major portion of flow would be routed to B

    This would cause exchanger A to have less

    pressure drop and exchanger B to have

    more pressure drop

    (although both HEs are designed for same

    duty and pressure drop)

  • 8/7/2019 Lec6a Process Piping Design Part2

    8/25

    Two-phase Flow Scenario (improper)

    Since A has less pressure drop, the

    liquids velocity will direct it to B

    vapor will take the path of least resistance

    and will go to exchanger A

    the net result is

    A is getting vapor

    B is getting liquid

    HTR of HEs is designed for equal flow

    of liquid and vapor

    Consequences: Exchangers will not perform as designed, the process unit

    will not perform and must be shut down for correction

    If piping designer does not recognise that the piping was for two-phase

    flow, then these problems are likely to prevail.

    How to modify??

    (to make it proper)

  • 8/7/2019 Lec6a Process Piping Design Part2

    9/25

    Two-phase Flow Scenario (proper)

    Two-phase flow enters the horizontal pipe

    midway between the exchangers

    Pressure drop is same to either one

    Absence of a path of least resistance

    Flow will be equal to both exchangers

    Features

  • 8/7/2019 Lec6a Process Piping Design Part2

    10/25

    Piping at Fired Heaters (proper)

    This a very common piping system

    The heater inlet is all liquid flow

    and the outlet is two-phase flow

    In majority of the cases (nine out of

    ten cases), this installation

    completely unnecessary

    excessively expensive

    WHY???

  • 8/7/2019 Lec6a Process Piping Design Part2

    11/25

    Piping at Fired Heaters The liquid heater feed (item1) is divided into 4 streams

    to match the four passes of

    heater tubes

    each stream has a globe valve

    (item 2) and flow indicator

    (item 3, orifice)

    each heater pass outlet has atemperature indicator

    To operate the heater

    flow is regulated with

    the globe valve to ensure

    that each pass has the

    same flow

    T indicates the desired

    outlet temperature

    The piping is correct up to

    this point

  • 8/7/2019 Lec6a Process Piping Design Part2

    12/25

    Piping at Fired Heaters

    Where is the inaccuracy in this

    installation??

    In the downstream of the TI located

    in each pass outlet

    Someone has coined the magic

    term two-phase flow and decided tohave symmetrical piping

    symmetrical piping means

    money and piping problems

    can be doubly expensive if

    the heater outlet is alloy

    material

    Symmetrical piping is necessary

    for two-phase flow if there is no

    method of control and distribution

    must be made

  • 8/7/2019 Lec6a Process Piping Design Part2

    13/25

    Piping at Fired Heaters

    In this installation distribution made

    while the fluid is all liquid, controlled by

    the globe valve and metered by the flow

    indicator

    to ensure that streams A, B, C, and D are

    all equal flow.

    If the flow is equal going into the heater

    it must be equal coming out

    Where to consider symmetrical piping??

    Low pressure systems (such as a

    crude charge heater service)

    High pressure installations

    the outlets should be combined in

    the most economical manner and

    routed on its way

    outlet pass differential pressure

    drop is minor and no consequence

  • 8/7/2019 Lec6a Process Piping Design Part2

    14/25

    Hot Vapor By-pass

    Tower overhead is routed to an air cooler (fin-fan)

    Condensed vapor is directed to the accumulator

    To maintain pressure on the accumulator, a hot

    vapor by-pass will be installed

    Hot vapor is by-passed around the cooler and isrouted to the pressure control valve, which allows

    pressure to enter the accumulator as required

    Hot vapor by-passes should never be pocketed

    The pressure control valve should be installedabove the top of the accumulator

    The by-pass piping must continuously drain from

    point A to point B

  • 8/7/2019 Lec6a Process Piping Design Part2

    15/25

    Hot Vapor By-pass

    As this by-passed vapor cools due to rainfall on

    the line or cool air cooling the line, condensate

    will form

    With small amount of differential pressure

    between points A and B

    a pocket of liquid head might not be

    overcome

    the hot vapor by-pass may not work.

    Generally, there is less than 10 psig differential

    between A and B

    Pressure control valve (butterfly type) is specified

    to keep the pressure drop to minimumbut this will consume 2-3 psig

    Line loss will consume another 2-3 psig

    leaving about 4 psig

    this will not overcome much liquid head

  • 8/7/2019 Lec6a Process Piping Design Part2

    16/25

    Static Head or Pressure Head or Head

    Liquids at rest causes a pressure equal in all directions and perpendicularto any surfaces in contact with liquid

    This pressure is due to the weight of the liquid

    Plus the pressure at the top level of the liquid

    The liquid height is called Static Head or Pressure Head or Head

    Head is important when calculating

    hydrostatic pressure of vessels

    Piping systems

  • 8/7/2019 Lec6a Process Piping Design Part2

    17/25

    Impact of water head

    A tower system designed for 50 psig

    This tower requires a hydrostatic

    pressure of 75 psig and this test pressure

    must be measured at the highest point in

    the system (point A)

    To attain this pressure at A the fieldbrings in a hydrotest pump and fills the

    system full of water.

    Piping designer knows this pump is

    located located at grade.

    Engineer should calculate the height

    from the pumps pressure gauge to point

    A and add this to the required test

    pressure.

  • 8/7/2019 Lec6a Process Piping Design Part2

    18/25

    Impact of water head

    In this case 54 psig must be added to 75

    psig, totalling 129 psig

    Which is the pressure that must be

    obtained at which pressure gauge to

    satisfy the 75 psig hydrostatic

    conditions

    The vessel designer must also considerthe static head

    While calculating the tower head and

    shell thickness.

    This additional weight is considered inthe design of the support for the tower.

    This can be critical when vessels are

    located high in a steel or concrete

    structures

  • 8/7/2019 Lec6a Process Piping Design Part2

    19/25

  • 8/7/2019 Lec6a Process Piping Design Part2

    20/25

    Flow of Oil in a Branched Pipeline

    The pipeline handles an oil with specific gravity of 0.92 and kinematic viscosity

    of 5 centistokes (cS) at a total rate of 12,000 cuft/hr. All three pumps have the

    same output pressure. At point 5 the elevation is 100 ft and the pressure is 2 atm

    gage. Elevations at the other points are zero. Line dimensions are presented in

    Table 1.

    Table Line dimensions

    Line L (ft) D (ft)

    14

    24

    34

    45

    1000

    2000

    1500

    4000

    0.4

    0.5

    0.3

    0.75

    Using the schematic for branched pipeline network shown in Figure 1, calculate

    the flow rates in each of the lines and the total power requirement.

    1

  • 8/7/2019 Lec6a Process Piping Design Part2

    21/25

    Branched pipeline

  • 8/7/2019 Lec6a Process Piping Design Part2

    22/25

  • 8/7/2019 Lec6a Process Piping Design Part2

    23/25

    Branched pipeline

  • 8/7/2019 Lec6a Process Piping Design Part2

    24/25

    Branched pipeline

  • 8/7/2019 Lec6a Process Piping Design Part2

    25/25