LEASEHOLD IMPROVEMENTS AND CONSTRUCTION COSTS IN TODAY’S MARKET: Current Issues and Management Challenges in a Greening Market

LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

LEASEHOLD IMPROVEMENTS AND

CONSTRUCTION COSTS IN TODAY’S MARKET:

Current Issues and Management Challenges in

a Greening Market

Page 2: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Today’s Discussion

• Market Influences

•Being Ready on Time

• Managing Construction Costs

• Delivery Dates

• Penalties

Page 3: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Market InfluencesRising Costs

• Leasing Costs- Less multi-floor contiguous space

- Base Building: rising taxes and fuel costs - higher density space

- Extreme growth

- Staff attraction and retention

- Construction costs remain at 2007 levels

• Technology change every 6 months – i.e. wireless

• Churn rates 100%

• Reduced credit = volatile marketplace

Page 4: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Building Search / Feasibility Planning

• Preliminary space planning, often of several buildings

• LEED Certified buildings – LEED CI Commercial Interiors

Being Ready on Time Managing Construction Costs Delivery Dates

- 10,000 sq. ft. requires approximately 4 days for planning

- 20,000 sq. ft. requires approximately 1 to 1 ½ weeks for planning

- 60,000 sq. ft. requires approximately 1 ½ weeks for planning

- 120,000 sq. ft. requires approximately 2 weeks for planning

• Schedule:

• The more lead time you have the better the costs and schedule are controlled

Page 5: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Building Search / Feasibility Planning

High Level Generic Preliminary Budget Pricing

• Existing Buildings- Level of existing finishes and architectural

detailing have a significant affect on the bottom line

- 13,000 sq. ft. comparison is $60,000 different

• New Buildings- Building Efficiency:

Building A - 127,000 sq. ft.Building B - 147,000 sq. ft.

Being Ready on Time Managing Construction Costs Delivery Dates

Page 6: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

ProgrammingBase Building Delivery• New buildings under construction:

- no elevators:schedule extensionhigher costs access to complete space

- loading dock not accessible

- base building occupancy permit

- no phone service

- no air conditioning or cannot be balanced

Being Ready on Time Managing Construction Costs Delivery Dates

Page 7: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Programming• Construction Managers

- Experience in buildings you are considering- Over 15 years in the Calgary marketplace; loyalty from the subtrades- Has experience with LEED projects

• Landlord work to be completed by the Landlord- Incorporate electrical and mechanical systems and interconnecting stair

openings based on a Tenant’s plan layout = significant savings in construction costs

Being Ready on Time Managing Construction Costs Delivery Dates

Page 8: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Detailed Planning

• Identify types of planning expectations

• Open planning is typically less construction cost

Being Ready on Time Managing Construction Costs Delivery Dates

- 10,000 sq. ft. requires approximately 2 weeks for planning

- 20,000 sq. ft. requires approximately 3 weeks for planning

- 60,000 sq. ft. requires approximately 4 weeks for planning

- 120,000 sq. ft. requires approximately 5 weeks for planning

• Schedule:

Page 9: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Modular Planning

Law Firm, Downtown Calgary

• Modular planning = future flexibility = lower renovation / reconfiguration costs

Being Ready on Time Managing Construction Costs Delivery Dates

Page 10: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Design DevelopmentSustainability

• Materials should be analyzed for their lifecycle, not just initial cost

• Materials need to be:- durable over a long period of time- made from recycled material- recyclable- reused on site- designs need to use less new materials = reduced cost

Being Ready on Time Managing Construction Costs Delivery Dates

• Professional fees on a 127,000 sq. ft. project = $1.00 sq. ft. for interior design fees

Most Sustainable Materials have little or NO cost increase

Page 11: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Design Development• Pre-ordering of long delivery

items

Being Ready on Time Managing Construction Costs Delivery Dates

- 10,000 sq. ft. project start 6 to 8 months prior to move-in

- 20,000 sq. ft. project start 9 months prior to move-in

- 60,000 sq. ft. project start 1 year prior to move-in

- 120,000 sq. ft. project start 2 years prior to move-in

• Schedule:

Page 12: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Design Development• Shortage of materials:

- drywall vs. moveable wall systems - less credit = manufacturers carry less inventory = longer delivery time- less credit = risk of manufacturer closing, plan B and C alternative materials

• Shortage of labour:- millwork – 6 weeks manufacturing time- modular kitchens - less time to manufacture- systems furniture instead of millwork – less time and less expensive- modular walls, doors, hardware and glass are being used for wall construction

or office fronts to reduce costs and installation time

Being Ready on Time Managing Construction Costs Delivery Dates

Page 13: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Contract Documentation /Working Drawings

• Construction employees in training

• The tighter the drawings, the more controlled the cost of construction

Being Ready on Time Managing Construction Costs Delivery Dates

- 10,000 sq. ft. requires approximately 3 weeks for Working Drawings

- 20,000 sq. ft. requires approximately 3 weeks for Working Drawings

- 60,000 sq. ft. requires approximately 4 weeks for Working Drawings

- 120,000 sq. ft. requires approximately 8 to 10 weeks for Working Drawings

• Schedule:

Page 14: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Building Permits

• Process ranges from 5 to 7 weeks

• If no permit is posted, the job site can be shut down, resulting in the schedule being compromised

• Fines add cost to the project

Being Ready on Time Managing Construction Costs Delivery Dates

Page 15: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Tender / Final PricingIn the Calgary marketplace, we recommend:

• Working with construction managers to ensure quality, cost control and meeting of schedules

• Using the industry standard stipulated price CCDC 2 2008 contract

Being Ready on Time Managing Construction Costs Delivery Dates

Page 16: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Tender / Final PricingCost per square foot in the Calgary marketplace:

New Construction

Basic space: $80.00 per sq. ft.

Being Ready on Time Managing Construction Costs Delivery Dates

Page 17: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Tender / Final PricingCost per square foot in the Calgary marketplace:

New Construction

More typical: $100.00 to $120.00 per sq. ft.

Being Ready on Time Managing Construction Costs Delivery Dates

Page 18: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Tender / Final PricingCost per square foot in the Calgary marketplace:

New Construction

High-end: up to $200.00 per sq. ft.

Being Ready on Time Managing Construction Costs Delivery Dates

Page 19: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Tender / Final PricingCost per square foot in the Calgary marketplace:

Renovation

Depending on the quality of the existing space, pricing can range from

$40.00 per sq. ft. to $80.00 per sq. ft.

Being Ready on Time Managing Construction Costs Delivery Dates

Page 20: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Construction / Field Review

New Construction

Renovations

- 10,000 sq. ft. one floor – 8 to 10 weeks

- 20,000 sq. ft. one floor – ranging from 10 to 12 weeks

- 60,000 sq. ft. three floors – 16 to 20 weeks

- 120,000 sq. ft. – 8 to 10 months depending on the extent of architectural detailing

- Similar to new full floor construction depending on the extent of the work

- Up to 30% more time required if the space is occupied

Being Ready on Time Managing Construction Costs Delivery Dates

• Schedule:

Page 21: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Contract Administration / Cost Control

• Get everything in writing!

• Document daily materials being shipped, stored in warehouses delivered to site and installed on site

• Penalties / Bonuses

• Furniture Installation:

Being Ready on Time Managing Construction Costs Delivery Dates

- 10,000 sq. ft. one floor – 3 to 4 days

- 20,000 sq. ft. one floor – ranging from 5 to 7 days

- 60,000 sq. ft. three floors – 3 weeks

- 120,000 sq. ft. – 6 weeks depending on the extent of systems furniture

Page 22: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

• Follow instructions in maintenance manuals to ensure the warranty does not become void

Project Closeout

• Establish yearly service agreement for equipment. i.e., air conditioners

• One-year warranty walkthrough

Being Ready on Time Managing Construction Costs Delivery Dates

Page 23: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Schedule Summary

- 10,000 sq. ft. project approximately 3 to 4 months to complete

- 20,000 sq. ft. project approximately 6 to 7 months to complete

- 60,000 sq. ft. project approximately 7 to 8 months to complete

- 120,000 sq. ft. project approximately 1 year to 1.5 years to complete

Being Ready on Time Managing Construction Costs Delivery Dates

• Lease Negotiations / Design Process through to Furniture Installation

Page 24: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

Benefits of Using an Interior Design Consultant

• Cost control and savings• Market knowledge / benchmarking

/ future trends• Experience and strength in

accurate scheduling• Have long-term relationships with

Construction Managers and subtrades

• Client can focus on their core business

Page 25: LEASEHOLD IMPROVEMENTS AND …...In the Calgary marketplace, we recommend: • Working with construction managers to ensure quality, cost control and meeting of schedules • Using

SHAPING THE WAY

YOU WORKONE SQUARE FOOT AT A TIME

DISCUSSION