LEASEHOLD IMPROVEMENTS AND
CONSTRUCTION COSTS IN TODAY’S MARKET:
Current Issues and Management Challenges in
a Greening Market
Today’s Discussion
• Market Influences
•Being Ready on Time
• Managing Construction Costs
• Delivery Dates
• Penalties
Market InfluencesRising Costs
• Leasing Costs- Less multi-floor contiguous space
- Base Building: rising taxes and fuel costs - higher density space
- Extreme growth
- Staff attraction and retention
- Construction costs remain at 2007 levels
• Technology change every 6 months – i.e. wireless
• Churn rates 100%
• Reduced credit = volatile marketplace
Building Search / Feasibility Planning
• Preliminary space planning, often of several buildings
• LEED Certified buildings – LEED CI Commercial Interiors
Being Ready on Time Managing Construction Costs Delivery Dates
- 10,000 sq. ft. requires approximately 4 days for planning
- 20,000 sq. ft. requires approximately 1 to 1 ½ weeks for planning
- 60,000 sq. ft. requires approximately 1 ½ weeks for planning
- 120,000 sq. ft. requires approximately 2 weeks for planning
• Schedule:
• The more lead time you have the better the costs and schedule are controlled
Building Search / Feasibility Planning
High Level Generic Preliminary Budget Pricing
• Existing Buildings- Level of existing finishes and architectural
detailing have a significant affect on the bottom line
- 13,000 sq. ft. comparison is $60,000 different
• New Buildings- Building Efficiency:
Building A - 127,000 sq. ft.Building B - 147,000 sq. ft.
Being Ready on Time Managing Construction Costs Delivery Dates
ProgrammingBase Building Delivery• New buildings under construction:
- no elevators:schedule extensionhigher costs access to complete space
- loading dock not accessible
- base building occupancy permit
- no phone service
- no air conditioning or cannot be balanced
Being Ready on Time Managing Construction Costs Delivery Dates
Programming• Construction Managers
- Experience in buildings you are considering- Over 15 years in the Calgary marketplace; loyalty from the subtrades- Has experience with LEED projects
• Landlord work to be completed by the Landlord- Incorporate electrical and mechanical systems and interconnecting stair
openings based on a Tenant’s plan layout = significant savings in construction costs
Being Ready on Time Managing Construction Costs Delivery Dates
Detailed Planning
• Identify types of planning expectations
• Open planning is typically less construction cost
Being Ready on Time Managing Construction Costs Delivery Dates
- 10,000 sq. ft. requires approximately 2 weeks for planning
- 20,000 sq. ft. requires approximately 3 weeks for planning
- 60,000 sq. ft. requires approximately 4 weeks for planning
- 120,000 sq. ft. requires approximately 5 weeks for planning
• Schedule:
Modular Planning
Law Firm, Downtown Calgary
• Modular planning = future flexibility = lower renovation / reconfiguration costs
Being Ready on Time Managing Construction Costs Delivery Dates
Design DevelopmentSustainability
• Materials should be analyzed for their lifecycle, not just initial cost
• Materials need to be:- durable over a long period of time- made from recycled material- recyclable- reused on site- designs need to use less new materials = reduced cost
Being Ready on Time Managing Construction Costs Delivery Dates
• Professional fees on a 127,000 sq. ft. project = $1.00 sq. ft. for interior design fees
Most Sustainable Materials have little or NO cost increase
Design Development• Pre-ordering of long delivery
items
Being Ready on Time Managing Construction Costs Delivery Dates
- 10,000 sq. ft. project start 6 to 8 months prior to move-in
- 20,000 sq. ft. project start 9 months prior to move-in
- 60,000 sq. ft. project start 1 year prior to move-in
- 120,000 sq. ft. project start 2 years prior to move-in
• Schedule:
Design Development• Shortage of materials:
- drywall vs. moveable wall systems - less credit = manufacturers carry less inventory = longer delivery time- less credit = risk of manufacturer closing, plan B and C alternative materials
• Shortage of labour:- millwork – 6 weeks manufacturing time- modular kitchens - less time to manufacture- systems furniture instead of millwork – less time and less expensive- modular walls, doors, hardware and glass are being used for wall construction
or office fronts to reduce costs and installation time
Being Ready on Time Managing Construction Costs Delivery Dates
Contract Documentation /Working Drawings
• Construction employees in training
• The tighter the drawings, the more controlled the cost of construction
Being Ready on Time Managing Construction Costs Delivery Dates
- 10,000 sq. ft. requires approximately 3 weeks for Working Drawings
- 20,000 sq. ft. requires approximately 3 weeks for Working Drawings
- 60,000 sq. ft. requires approximately 4 weeks for Working Drawings
- 120,000 sq. ft. requires approximately 8 to 10 weeks for Working Drawings
• Schedule:
Building Permits
• Process ranges from 5 to 7 weeks
• If no permit is posted, the job site can be shut down, resulting in the schedule being compromised
• Fines add cost to the project
Being Ready on Time Managing Construction Costs Delivery Dates
Tender / Final PricingIn the Calgary marketplace, we recommend:
• Working with construction managers to ensure quality, cost control and meeting of schedules
• Using the industry standard stipulated price CCDC 2 2008 contract
Being Ready on Time Managing Construction Costs Delivery Dates
Tender / Final PricingCost per square foot in the Calgary marketplace:
New Construction
Basic space: $80.00 per sq. ft.
Being Ready on Time Managing Construction Costs Delivery Dates
Tender / Final PricingCost per square foot in the Calgary marketplace:
New Construction
More typical: $100.00 to $120.00 per sq. ft.
Being Ready on Time Managing Construction Costs Delivery Dates
Tender / Final PricingCost per square foot in the Calgary marketplace:
New Construction
High-end: up to $200.00 per sq. ft.
Being Ready on Time Managing Construction Costs Delivery Dates
Tender / Final PricingCost per square foot in the Calgary marketplace:
Renovation
Depending on the quality of the existing space, pricing can range from
$40.00 per sq. ft. to $80.00 per sq. ft.
Being Ready on Time Managing Construction Costs Delivery Dates
Construction / Field Review
New Construction
Renovations
- 10,000 sq. ft. one floor – 8 to 10 weeks
- 20,000 sq. ft. one floor – ranging from 10 to 12 weeks
- 60,000 sq. ft. three floors – 16 to 20 weeks
- 120,000 sq. ft. – 8 to 10 months depending on the extent of architectural detailing
- Similar to new full floor construction depending on the extent of the work
- Up to 30% more time required if the space is occupied
Being Ready on Time Managing Construction Costs Delivery Dates
• Schedule:
Contract Administration / Cost Control
• Get everything in writing!
• Document daily materials being shipped, stored in warehouses delivered to site and installed on site
• Penalties / Bonuses
• Furniture Installation:
Being Ready on Time Managing Construction Costs Delivery Dates
- 10,000 sq. ft. one floor – 3 to 4 days
- 20,000 sq. ft. one floor – ranging from 5 to 7 days
- 60,000 sq. ft. three floors – 3 weeks
- 120,000 sq. ft. – 6 weeks depending on the extent of systems furniture
• Follow instructions in maintenance manuals to ensure the warranty does not become void
Project Closeout
• Establish yearly service agreement for equipment. i.e., air conditioners
• One-year warranty walkthrough
Being Ready on Time Managing Construction Costs Delivery Dates
Schedule Summary
- 10,000 sq. ft. project approximately 3 to 4 months to complete
- 20,000 sq. ft. project approximately 6 to 7 months to complete
- 60,000 sq. ft. project approximately 7 to 8 months to complete
- 120,000 sq. ft. project approximately 1 year to 1.5 years to complete
Being Ready on Time Managing Construction Costs Delivery Dates
• Lease Negotiations / Design Process through to Furniture Installation
Benefits of Using an Interior Design Consultant
• Cost control and savings• Market knowledge / benchmarking
/ future trends• Experience and strength in
accurate scheduling• Have long-term relationships with
Construction Managers and subtrades
• Client can focus on their core business
SHAPING THE WAY
YOU WORKONE SQUARE FOOT AT A TIME
DISCUSSION