Back Office Process“Key” Distribution Process at
WSU Engineering Business Office
Abishek Anand Shruti Baug
Joel Fortgang Kara Wandrie Parag Kapile
Engineering Business Office (EBO)• Key Distribution Process to give key to open
engineering rooms consists of 2 employees: 1. Kathryn- Primary contact with the system. 2.Eman- Student assistant. She is responsible for placing keys on and off the rack, maintaining inventory and filling in spreadsheets.• 10 keys are requested per week.• Heavy load during the commencement of
semester.
Purpose of the Project
• Kathryn who is the primary contact with the system has to spend too much time and too much effort on the system.
• The purpose of the project is find the root cause of the problem, find the appropriate solution for the problem and to make Kathryn work easy and efficient.
Flow Chart for “Key” Process
Process Overview
New Key Request• Completed Key Request Form is submitted to
EBO. (10 mins)• Information from the form is filled in the EBO
system, excel sheet and print out is taken and maintained in a file.(15 mins)
New Request cont..• Tag # is obtained by entering the room # from
the system. (2 mins)• Tag # is located in the key box.(10 mins)
New Key Request cont...
• Corresponding key from the Tag # is selected.• Key is put in the envelope.• Key # is filled in the form, and envelope is
stapled to the request form and passed to front desk. (5 mins)
• Customer is emailed to pick up the key.• Customer must show ID and sign request at
pick up.
Current State Value Stream MapSupplier/Customer
Receive Form Review One Card Information
Custom Software
Enter information into Software
Print Out Docs
Excel
Enter Key into Spreadsheet
Find Tag Take Key Return Tag Give Student Key File Paperwork
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
360 Seconds
600 Seconds
180 Seconds
0 Seconds
360 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
120 Seconds
3600 Seconds
5 Sets of Paperwork
Value Added Time = 1710 Seconds
Total Lead Time = 18600 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
Production Control
Intermittent when problems
Daily
De l
iver
y of
Key
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Current State Value Stream Map
Supplier/Customer
Receive Form Review One Card Information
Custom Software
Enter information into Software
Print Out Docs
Excel
Enter Key into Spreadsheet
Find Tag Take Key Return Tag Give Student Key File Paperwork
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
360 Seconds
600 Seconds
180 Seconds
0 Seconds
360 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
120 Seconds
3600 Seconds
5 Sets of Paperwork
Value Added Time = 1710 Seconds
Total Lead Time = 18600 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
Production Control
Intermittent when problems
Daily
De l
ive r
y o f
Ke y
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Supplier/Customer
Receive Form Review One Card Information
Custom Software
Enter information into Software
Print Out Docs
Excel
Enter Key into Spreadsheet
Find Tag Take Key Return Tag Give Student Key File Paperwork
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
360 Seconds
600 Seconds
180 Seconds
0 Seconds
360 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
120 Seconds
3600 Seconds
5 Sets of Paperwork
Value Added Time = 1710 Seconds
Total Lead Time = 18600 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
Production Control
Intermittent when problems
Daily
Del
ive r
y of
Key
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Supplier/Customer
Receive Form Review One Card Information
Custom Software
Enter information into Software
Print Out Docs
Excel
Enter Key into Spreadsheet
Find Tag Take Key Return Tag Give Student Key File Paperwork
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
360 Seconds
600 Seconds
180 Seconds
0 Seconds
360 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
120 Seconds
3600 Seconds
5 Sets of Paperwork
Value Added Time = 1710 Seconds
Total Lead Time = 18600 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
Production Control
Intermittent when problems
Dai ly
Del
i ver
y o f
Ke y
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Supplier/Customer
Receive Form Review One Card Information
Custom Software
Enter information into Software
Print Out Docs
Excel
Enter Key into Spreadsheet
Find Tag Take Key Return Tag Give Student Key File Paperwork
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
360 Seconds
600 Seconds
180 Seconds
0 Seconds
360 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
120 Seconds
3600 Seconds
5 Sets of Paperwork
Value Added Time = 1710 Seconds
Total Lead Time = 18600 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
Production Control
Intermittent when problems
Daily
Del
ive r
y o f
Key
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Supplier/Customer
Receive Form Review One Card Information
Custom Software
Enter information into Software
Print Out Docs
Excel
Enter Key into Spreadsheet
Find Tag Take Key Return Tag Give Student Key File Paperwork
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
360 Seconds
600 Seconds
180 Seconds
0 Seconds
360 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
120 Seconds
3600 Seconds
5 Sets of Paperwork
Value Added Time = 1710 Seconds
Total Lead Time = 18600 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
Production Control
Intermittent when problems
Daily
De l
ive r
y o f
Ke y
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
KPI Metrics
• Labor time spent per key– Total labor hours spent per keys issued in a week
= Total # of minutes spent/ #of keys issued per week = 15 minutes (from Gemba walk)
• Average Lead time– Total time taken from the time student drops off
form until receiving the key – Measured in minutes– Average lead time is 28.5 minutes
KPI Metrics
• Average number of keys issued– Number of keys issued per week
= Total # of keys issued / # of weeks = 131/13 = 10
KPI Metrics
Key Request per week
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 130
5
10
15
20
25
30
24
16
11
3
810
12
6
1513
6
1
6
Gemba WalkKey Request/Week
• Takt time– Available time / Customer demand
= 40 hours / 10 keys per week = 4 hours per key per week
KPI Metrics
• Kathryn and Eman utilize a lot of time distributing, ordering keys, and entering data into system. This consumes a lot of time for personnel in the engineering office. Current labor time spent per key is 15 minutes and the desired labor time is under 6 minutes.
Problem Statement
● 5 Hypotheses○ The physical access to the keys is challenging.○ The record keeping takes up a lot of valuable time.○ Keys are not returned so new keys must continually be
made.○ Takes too long to procure keys for the students.○ Wayne States key ordering process takes too much effort.
Plan – 5 WhysWhy are Kathryn and Eman are spending to much of their day working on distributing keys?
● 5 Hypotheses○ The physical access to the keys is challenging.○ The record keeping takes up a lot of valuable time.○ Keys are not returned so new keys must continually be
made.○ Takes too long to procure keys for the students.○ Wayne States key ordering process takes too much effort.
● Evidence○ Value Stream: Record keeping is where most of the active
time is spent.● Controllable: No
Plan – 5 WhysWhy are Kathryn and Eman are spending to much of their day working on distributing keys?
● 4 Hypotheses○ The Paper work is not uniformed○ The recording system is convoluted○ Paper Binders are hard to work with○ Inaccurate Paper Work
Plan – 5 WhysWhy does the record keeping take so much time?
● 4 Hypotheses○ The Paper work is not uniformed○ The recording system is convoluted○ Paper Binders are hard to work with○ Inaccurate Paper Work
● Evidence○ Gemba Walk: Operators complain about software system
● Controllable: No
Plan – 5 WhysWhy does the record keeping take so much time?
● 3 Hypotheses○ There are multiple systems being used○ The excel spreadsheet is too complicated○ The software design is confusing
Plan – 5 WhysWhy is the recording system problematic?
● 3 Hypotheses○ There are multiple systems being used○ The excel spreadsheet is too complicated○ The software design is confusing
● Evidence○ Flow Chart-The same work is done three times
● Controllable - Yes
Plan – 5 WhysWhy is the recording system problematic?
Plan - 4S for Excess Time Consumption
Order
Skill Suppliers
SystemsSurrounding
s
Key manufacturer
Key delivery from the manufacturer
Unreadable Forms
Untrained Employee
Manpower Shortage
Software Duplication Software
Outdated
Sending Multiple Reminders/e-mails Concerned
customer not available
Disorganized key cabinet
Excess time consumption
Surrounding Suppliers
Systems
Delivering key without form
Customers Losing key
Customers returning key
Reordering new keys
Unassigned keysMismatch Keys
Untagged keys
Excess Cost
Plan- 3S for Excess Cost
Plan- Future State Value Stream MapSupplier/Customer
Receive Form Review One Card Information
Check software for Tag # and if Key is
AvailableCustom Software
Enter User info into Software
Find Tag Take Key Return Tag Give Student Key
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
60 Seconds
600 Seconds
120 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
Value Added Time = 870 Seconds
Total Lead Time = 15000 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
Production Control
Weekly
Daily
Del
iver
y of
Ke y
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Weekly
Plan- Future State Value Stream MapSupplier/Customer
Receive Form Review One Card Information
Check software for Tag # and if Key is
AvailableCustom Software
Enter User info into Software
Find Tag Take Key Return Tag Give Student Key
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
60 Seconds
0 Seconds
120 Seconds
0 Seconds
60 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
Value Added Time = 340 Seconds
Total Lead Time = 14400 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
Production Control
Weekly
Dail y
De l
ive r
y o f
Key
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Weekly
Supplier/Customer
Receive Form Review One Card Information
Check software for Tag # and if Key is
AvailableCustom Software
Enter User info into Software
Find Tag Take Key Return Tag Give Student Key
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
60 Seconds
0 Seconds
120 Seconds
0 Seconds
60 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
Value Added Time = 340 Seconds
Total Lead Time = 14400 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
Production Control
Weekly
Dail y
De l
ive r
y of
Key
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Weekly
Supplier/Customer
Receive Form Review One Card Information
Check software for Tag # and if Key is
AvailableCustom Software
Enter User info into Software
Find Tag Take Key Return Tag Give Student Key
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
60 Seconds
600 Seconds
120 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
Value Added Time = 870 Seconds
Total Lead Time = 15000 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
Production Control
Weekly
Dai ly
Del
ive r
y of
Key
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Weekly
Supplier/Customer
Receive Form Review One Card Information
Check software for Tag # and if Key is
AvailableCustom Software
Enter User info into Software
Find Tag Take Key Return Tag Give Student Key
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
60 Seconds
600 Seconds
120 Seconds
0 Seconds
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
Value Added Time = 870 Seconds
Total Lead Time = 15000 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
Production Control
Weekly
Dai ly
Del
i ver
y o f
Key
s
Daily
Del
iver
y of
App
licati
ons
Daily Delivery of Applications Daily Delivery of Keys
Intermittent when problems
Intermittent
Weekly
Plan- Improvements in Future State• Eliminated 2 process steps• Added 2 levels of status communication• Lead time
– Current State = 28.5 minutes– Future State = 14.5 minutes
• Labor time– Current State = 15 minutes– Future State = 3 minutes
Plan – Design Decisions To MergeRecording Processes
• Decision Variable– Time to Process Key– Cost in dollars– Training Requirements– Support / Stability– Data Import / Initial Data Entry– Oversight
Plan – Design Alternatives
• One System– Paper Only– Excel Spreadsheet Only– Existing Custom Software– New Software
Plan – New Software Alternatives
• Custom - $ Unknown• Key Wizard- $1200
– http://www.keywizard.net/• Tracer 9 - $900
– https://www.dlaco.com/tracerxt/• Key Organizer - $600
– https://www.aidex-software.com/en/key-organizer/
Plan – Evaluation Matrix
Criteria WeightPaper System
Spread Sheet
Existing Software
Custom Software
Key Wizard Tracer 9
Key Organizer
Process Time 5 1 2 2 4 4 3 3
Cost in dollars 8 4 4 4 1 3 3 2
Training 1 2 2 1 4 3 3 3
Support / Stability 2 1 1 2 2 3 2 4
Import / Initial 3 2 2 4 4 2 2 2
Oversight 3 1 1 1 4 3 4 3
Totals 50 55 61 68 77 69 70
Do - Method for Small Scale Test
• Obtain Key Wizard Trial Version• Train Eman (Student Assistant) in Key Wizard• For One Week • Enter Data into Both System• Record Time for Each System
Check - Small Scale Test• Compare Average Times to Process for Existing• Evaluation Time Savings per Week• Compute New KPI
– Average Labor Time Per Key• Determine ROI on Key Wizard• Present Findings to Lara (Office Manager)• Lara Determines if Plan should be
implemented, or go back to plan
Act - Full Implementation• Determine Week of Low Key Demand from
Historic Data• Convert Existing Data into Key Wizard• Train Staff (Kathryn, Lara and Eman)• Begin Processing Keys
Expected Results• Key Process Labor Time Reduction from 15
minutes to under 6 minutes• Greater Long Term Stability of System• Better Oversight for Office Manager (Lara)
Review/Loop-Do we need to Keep going• Ongoing
– Review Key Process Numbers Every Semester for Employee performance
– Contact Key Wizard Manufacturer for Updates Once a year
• Another PDCA Cycle– Look at all KPI’s – Revisit Customer Viewpoint– Determine if another Cycle is needed
A3- ReportProjected Business Performance Improvement Story [BPIS]
Prior State Problem Statement Process Analysis
Gemab Walk, Flow Chart, Current VSM Map
KPI Definitions, Key Performance Metrics 5 Why Analysis, Fishbone Diagram
Design Initiatives Implementation Results
Future Value Stream, Solution Criteria, Solution Alternatives, Evaluation Matrix
Do Explanation, Check Explanation, Act Explanation, Review and Loop
Expected Results Explanation, Process Labort Reduced 23 %
Questions• This is how we climb the Staircase
● Standardize Form● Place Forms On-Line● Review Software Alternatives with Staff for
better evaluation criteria● Organize Key Boxes● Replace Key Boxes
Appendix -Further Recommendations
● Develop Online Request System● Record phone number of student● Prevent graduation for non-return keys● Charge a deposit
Appendix -Further Recommendations
● http://www.prosystech.ca/overviewsk.aspx● http://www.keywizard.net/prices.html ● https://www.dlaco.com/tracerxt/tracer1.htm● http://www.instakey.com/key-control-software/● http://www.morsewatchmans.com/product/keywatcher/key-con
trol-software/● https://www.aidex-software.com/en/key-organizer/
https://www.keytracker.com/Product/Category/Key-Control-Software
● Software Written By Computer Science Class
Appendix - Software List
● Hypotheses○ The physical access to the keys is challenging.
■ Evidence - The key cabinet is hard to access and is very un-organized.○ The record keeping takes up a lot of valuable time.
■ Evidence - Value Stream: Record keeping is where most of the active time is spent.
○ Keys are not returned so new keys must continually be made.■ Evidence - They have a set process to follow if a key is requested and
cannot be found because someone else didn’t return it after use.○ Takes too long to procure keys for the students.
■ Evidence - They make the students come to the office just to fill out paper work then leave and make them come back when the key is ready.
○ Wayne States key ordering process takes too much effort.■ Evidence -he students have to come in to fill out forms and then later
have to come back to pick it up.
Appendix – 5 WhysWhy are Kathryn and Eman are spending to much of their day working on distributing keys?
● Hypotheses○ The Paper work is not uniformed
■ Evidence - Gemba Walk: Inspection of Paperwork○ The recording system is convoluted
■ Evidence- Gemba Walk: Operators complain about software system
○ Paper Binders are hard to work with■ Evidence- Gemba Walk: Photos of binders
○ Inaccurate Paper Work■ Evidence - Gemba Walk: Interview with Kathryn
Appendix – 5 WhysWhy does the record keeping take so much time?
● Hypotheses○ There are multiple systems being used
■ Evidence - Flow Chart: The same work is done three times
○ The excel spreadsheet is too complicated■ Evidence - Gemba Walk: Example of the spreadsheet
○ The software design is confusing■ Evidence - Gemba Walk: Photos of interface
Appendix– 5 WhysWhy is the recording system problematic?
Appendix- Key Order Flowchart
Appendix- Current Value Stream Map of all Processes
Value Added Time = 30065 Seconds
Total Lead Time = 7200 Seconds
30 Seconds
0 Seconds
30 Seconds
0 Seconds
60 Seconds
0 Seconds
Supplier
Online Form External Processing Key is Ready Email Key Pick Up
Key
Nee
ds
to b
e m
ade
Enter Key into Software
Enter Key into Spreadsheet
For S
tock
Put Key in EnvelopeFor Handing Out
Send Pick Up Email Pick up of Key
Key Exists
Receive Key After Use
Enter Key into Software
Enter Key into Spreadsheet
Find Tag Put Tag on Key Return Tag with Key
Key
Retu
rn
Go to Key Request Loop
Key D
oesn
’t Ex
ist
Find Tag Put Tag on Key Return Tag with Key
300 Seconds
14400 Seconds
28800 Seconds
0 Seconds
5 Seconds
0 Seconds
600 Seconds
3600 Seconds
120 Seconds
3600 Seconds
120 Seconds
0 Seconds
30 Seconds
0 Seconds
60 Seconds
0 Seconds
120 Seconds
14400 Seconds
Value Added Time = 30155 Seconds
Total Lead Time = 21600 Seconds
30 Seconds
14400 Seconds
120 Seconds
7200 Seconds
120 Seconds
0 Seconds
60 Seconds
0 Seconds
30 Seconds
0 Seconds
30 Seconds
0 Seconds
Value Added Time = 390 Seconds
Total Lead Time = 21600 Seconds
C/T 30 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 7200 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
C/T 600 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 28800 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 300 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
File Paperwork
120 Seconds
3600 Seconds
120 Seconds
3600 Seconds
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
File Paperwork
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
File Paperwork
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
120 Seconds
3600 Seconds
Customer
PC = Manager
Intermittent
Intermittent
Intermittent
Find Tag Take Key Return Tag Give Student Key File Paperwork
600 Seconds
0 Seconds
30 Seconds
0 Seconds
20 Seconds
0 Seconds
5 Seconds
0 Seconds
120 Seconds
3600 Seconds
5 Sets of Paperwork
Value Added Time = 1710 Seconds
Total Lead Time = 18600 Seconds
C/T 60 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 5 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 3600 Seconds
U/P 100%
Shifts 1
Receive Form Review One Card Information
Custom Software
Enter information into Software
Print Out Docs
Excel
Enter Key into Spreadsheet
30 Seconds
0 Seconds
5 Seconds
14400 Seconds
360 Seconds
600 Seconds
180 Seconds
0 Seconds
360 Seconds
0 Seconds
C/T 5 Seconds
W/T 14400 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 30 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
C/T 120 Seconds
W/T 0 Seconds
U/P 100%
Shifts 1
Intermittent
Daily
Del
iver
y of
Key
s
Daily
Del
iver
y of
App
licati
ons
Intermittent When there is a Problem Intermittent When there is a Problem
Key
Requ
este
d
• Returned keys per week– Number of keys that are returned back to the
office per week • Keys ordered per week
– Number of keys ordered per week by back office when the keys requested are either unavailable or inventory for the key is low
Appendix - KPI Metrics