Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking, May 2015

Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

Embed Size (px)

Citation preview

Page 1: Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

Leadership Profile Programme

March 12, 2013

Securing Financial CloseRapdly and Cost Effectivley

Luis DuranEnergy and Clean Technologies

Business Banking, May 2015

Page 2: Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

Process Overview

Page 3: Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

Phase 1 – Initial Proposal

aa

Bank:• Meet us early on in the process. i.e. at least 6 months• Understand what’s in scope and what isn’t• Seek Indicative Term Sheet - what can the Bank do for you?

Advisors:• Appoint early on• Seek credentials• Seek compromise on payment terms• Allow for seaonality – e.g. BES

Turbine: • Peace of mind is paramount• Are you comparing apples with apples?

Page 4: Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

The term sheet is a non-binding document. It will give you a good indication of project terms. Remember it is subject to Credit Committee approval!!

Phase 2 – Secure A Term Sheet

We stress test your projections in our own PF model

We prepare a brief project summary- Project is graded

Head of business unit sign off

Term sheet is issued

Includes Pricing, C.P.s, Security, events of default etc.

Process can take 2-3 weeks from first meeting

Page 5: Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

Securing a Term Sheet – Phase 2How do we stress test a project? How much debt can the project withold?

Stress testing – Some things we look at :

Term: Construction plus 15 yrs

Wind Resource Bank case - always P90

Leverage Driven by DSCR of 1.2 (can be sculpted)

BES Repayment must be evident

Supplier Lite Reserve Account required– REFIT Price Only

Contingency At least 3% - Depending on level of advancement

Page 6: Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

Credit Approval and Drawdown – Phase 3

Creditt Committe:

Independent body

May seek clarifications

Formal Approval

Letter of Sanction Includes

a long list of C.P.s

Appoint Legal & Tech Advisors Initiate due

diligence Process

Review and prep key docs

Due Diligence Complete All C.Ps met Project Docs Finalised Security docs

in Place

Drawdown

1 week 1 week 3-5 weeks 1 week

Page 7: Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

Drawdwown: Securing a Satisfactory Outcome Completeness: Upoload everything on to data room ASAP- This is typically

the biggest delay

Timing: Allow time for Bank Lawyers and Technical Advisers to review and

input into key documents early on in the process

Quick Turnaround: Insist on weekly update calls same day turn around –

all parties involved

Cost Effciencies: Avoid dupplication - costs can be greatly reduced

Page 8: Leadership Profile Programme March 12, 2013 Securing Financial Close Rapdly and Cost Effectivley Luis Duran Energy and Clean Technologies Business Banking,

Thank You!

Any Questions?