Lead-Based PaintRenovation, Repair, and Painting

Overview of Final RuleMarch 11, 2010

Page 2: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview2

The Renovation, Repair, and Painting Rule (RRP)

On March 31, 2008, EPA issued a final rule under the authority of § 402(c)(3) of the Toxic Substances Control Act (TSCA) to address lead-based paint hazards created by renovation,repair, and painting activities that disturb lead-based paint.

Delegable program. Lawsuit settlement.

Page 3: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview3

Where does it apply?

Applies to renovations of:– Target housing. – Child occupied facilities.

Excludes:– Renovations that affect only components determined to be free of lead-based

paint. – Activities that disturb under 6 ft2 interior or 20 ft2 exterior (this excludes window

replacement, demolition, and projects involving prohibited practices).– Work done by individuals in housing they own and occupy.

Opt out:– Owners may choose to opt out of the rule requirements if they meet the following

criteria: they occupy the housing to be renovated, the housing is not a child-occupied facility, and no child under age 6 or pregnant woman lives there.

Page 4: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview4

What does it require?

Changes to pre-renovation education. Effective Now!

Accreditation of training providers. Began in April ’09.

Certification of firms, renovators, and dust sampling technicians. Began in October ’09.

Work practice standards . Effective April ’10.

Page 5: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview5

Pre-Renovation Education Changes

New brochure “Renovate Right.”– “Protect Your Family”

brochure is not being retired. It will still be used for real estate disclosure, and general outreach.

Page 6: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview6

Pre-Renovation Education Changes

Adds requirements for child occupied facilities (COF). Before renovating a firm must:

– Provide “Renovate Right” to building owner and adult representative.

– Provide information about the renovation to parents & guardians of children under age 6 using facility by mail, hand-delivery or informational signs.

Change to requirements in common areas of target housing. – Firms may post informational signs in lieu of delivering information

directly to each dwelling. Informational signs must:

– Be posted where they will be seen.– Describe nature, locations, and dates of renovation. – Be accompanied by “Renovate Right” or info on how to get a free

copy.

Page 7: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview7

Accreditation of Training Providers

Trainers must be accredited to provide renovator or sampling technician training, to become accredited they must submit an application and fee to EPA.

Must be re-accredited every 4 years. EPA developed model renovation

training. Training providers must notify EPA of

individuals who complete training.

Page 8: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview8

Certification of Firms

To be certified to perform renovation or dust sampling firms must submit an application and fee to EPA.

Certifications are good for 5 years.

Page 9: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview9

Certification of Renovators and Sampling Technicians

Must take 8-hour accredited training course.

– Individuals with certain previous training can take a 4-hour accredited refresher course.

– Course certificate serves as certification (no application to EPA required) .

Refresher training is required every 5 years.

Page 10: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview10

Work Practice Standards Firm Responsibilities

Ensure all individuals performing renovation activities are appropriately trained.

A certified renovator is assigned to each renovation.

All renovations are performed in accordance with the lead-safe work practice standards.

Comply with pre-renovation education requirements prior to starting the work.

Ensure the recordkeeping requirements are met.

Page 11: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview11

Work Practice Standards Renovator Responsibilities

Perform or direct work to ensuring the work practices are followed.

Be physically present at the work site:– When warning signs are posted, while containment is

established, and during final work area cleaning.– Be available, either on-site or by telephone, at all other times.

Provide on the job training to uncertified workers. When requested, use a test kit to determine if LBP is not

present. Perform cleaning verification. Prepare required records.

Page 12: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview12

Work Practice StandardsGeneral

Post signs defining the work area. Certain practices are prohibited:

– open-flame burning or torching.– operating a heat gun above 1100°F.– machines that remove lead-based paint through

high speed operation such as sanding, grinding, power planing, needle gun, abrasive blasting, or sandblasting, unless used with HEPA exhaust control.

Ensure that all personnel, tools, and other items including waste are free of dust and debris when leaving the work area.

Waste must be sealed in bags or plastic sheeting. Dispose of waste in accordance with Federal, State, and Local requirements.

Page 13: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview13

Work Practice StandardsInteriors

Remove or cover all objects from the work area. Close and cover all ducts in the work area. Close all windows, and cover all doors in the work

area. Cover the floor surface of the work area with plastic

sheeting.

Page 14: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview14

Work Practice StandardsExteriors

Close all doors and windows within 20 feet of the renovation.

Cover the ground with plastic sheeting extending out from the edge of the structure a sufficient distance to collect falling paint debris.

Page 15: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview15

Work Practice StandardsCleaning

Pick up paint chips and debris. Remove all protective sheeting. Clean all objects and surfaces in and around the

work area.– Clean walls with a HEPA-equipped

vacuum or with a damp cloth.– HEPA vacuum all remaining surfaces

and objects in the work area.– Wipe all remaining surfaces in the

work area with a damp cloth.– Mop uncarpeted floors.

Page 16: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview16

Cleaning Verification

Wipe floors, countertops, and windowsills with wet cleaning cloth.

If the cloth does not match the verification card, re-clean that surface and then re-wipe with a wet cleaning cloth.

If this cloth does not match the cleaning verification card, allow the surface to dry completely and wipe with a dry cleaning cloth.

Note: Laboratory dust sampling is an option where the contract or another Federal, State, or local regulation requires dust sampling by a certified professional and requires the renovation firm to clean the work area until it passes clearance.

Page 17: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview17

Recordkeeping and Enforcement

Documents demonstrating compliance with the rule must be retained for 3 years following the completion of a renovation.

– Pamphlet acknowledgment forms, owner opt-out forms, and documentation of work practices.

EPA may suspend, revoke, or modify a firm’s certification if firm is found to be in non-compliance.

Non-compliant contractors may be subject to civil and criminal penalties up to $37,500 for each violation, imprisonment, or both.

Page 18: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview18

State/Tribal Program Authorization

RRP is a delegable program. Programs must be at least “as protective as”

EPA requirements, and have “adequate enforcement.”

Reciprocity will be encouraged. On October 20th, Wisconsin became the first

state authorized to administer and enforce an RRP program.

Page 19: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview19

Important Dates

April 2009:– EPA began administering the program in

unauthorized states.– Training providers began applying for accreditation.

October 2009:– Renovation firms began applying for certification.

April 2010:– Renovation firms must be certified.– Renovators and dust sampling technicians must be

certified.– Work practices must be followed.

Page 20: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview20

RRP Lawsuit Settlement

EPA recently settled a lawsuit with several public interest groups. In the settlement the Agency agreed to propose to:

– By October 2009 (final rule by April 2010) Eliminate the opt out. Require the renovator provide post renovation information to

the homeowner.– By April 2010 (final rule by July 2011)

Require work area testing, and the elimination of lead hazards when certain tasks are undertaken.

– Expand the scope of the rule to include public and commercial buildings within the next 6 years.

Page 21: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview21

Need for Large Marketing Campaign for Lead

People need to know that lead poisoning can happen to them, not just other people

We need to emphasize that lead poisons children

We must motivate people to take action to prevent lead poisoning of children

Page 22: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview22

Outreach Vehicles

Specialty and Critical Audiences Parents & Do-It-YourselfersAfrican American & Hispanic CommunitiesLandlordsProperty ManagersHardware Stores, Schools, DaycaresHealthcare ProfessionalsStates, Tribes, Federal GovernmentTraining FirmsContractors and Firms

Ad CouncilCreate overall awareness of lead hazards and poisoning prevention, including potential renovation hazards

Marketing FirmWill take Ad Council message and tailor to specific audiences

General Audiences

General PublicPregnant WomenRenovatorsRenters

Page 23: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview23

Messages for Outreach

Messages – Lead is still a health problem– Children can be poisoned by lead dust from

improperly conducted renovations– Encourage use of certified contractors for

renovations

Page 24: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview24

Current Marketing Projects

Tool Box Retail Chains (Home Depot, Lowes) Trade Unions/Associations Trade Print PSAs (Ads for trade publications) State and City Licensing Agencies Web Site Enhancements

Page 25: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview25

Information ResourcesNational Lead Information Center (NLIC)

Contact NLIC with questions, to receive a general information packet, or to order documents.

– By Phone: call and speak with a specialist Monday through Friday, 8:00 am to 6:00 pm eastern time (except federal holidays) at 1(800) 424-LEAD.

– On the web at www.epa.gov/lead/nlic.htm Use the online form to send your comments and questions. Use our online document request to order documents

electronically.

Page 26: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview26

Information ResourcesLead Website

www.epa.gov/lead

Page 27: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview27

Information ResourcesRenovator Toolbox

Follow link from the lead home page to find: – Application and

instructions for firm certification.

– Sample forms.– Helpful publications.

Page 28: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview28

Information ResourcesCompliance Guide

Handbook for contractors, property managers, and maintenance personnel working in homes, child care facilities, and schools built before 1978.

Contains detailed information and flow charts outlining the RRP requirements.

Page 29: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview29

Information ResourcesSteps Brochure

A guide to lead-safe renovation, repair and painting.

Covers basic lead-safe practices.

Can be used as a training guide for on-the-job training.

Page 30: Lead-Based Paint Renovation, Repair, and Painting Overview of Final Rule March 11, 2010

January 2010 RRP Final Rule - Overview30

Thank You for Your Time!

Wallace Reid

Team Leader – Asbestos & Lead Programs

U.S. EPA Region 10 - Seattle

206-553-6389

[email protected]

www.epa.gov/lead