Upload
kevlyn
View
29
Download
0
Embed Size (px)
DESCRIPTION
LCLS-II Undulator Installation Sequence and Expansion. M. Rowen 1-18-2012. Goals. Goal Installation Plans: Expansion planning is to minimize changes as undulator segments and seeding mono’s are planned. 1) Keep source point fixed. 2) Keep mono position fixed, once installed. - PowerPoint PPT Presentation
Citation preview
LCLS-II Undulator Installation Sequence and Expansion
M. Rowen1-18-2012
LCLS-II Und. Installation & Expansion, 1-18-12
Goals
Slide 2LCLS-II Und. Installation & Expansion, 1-18-12
• Goal Installation Plans:• Expansion planning is to minimize changes as undulator segments
and seeding mono’s are planned. 1) Keep source point fixed. 2) Keep mono position fixed, once installed.
• HXR line the source should be as far from the end stations as possible to get maximum defocused spot.
• SXR line the source should be down stream as far as possible to limit over filling of mirrors at low energies. This does increase power density on absorbers. If branch lines have limited energy ranges, i.e. low energy and high
energy branches, then mirror angles on low energy line can be increased reducing the over filling and the source can be further away.
• Two Cases: 198 & 255m undulators.
HXU Expansion Plan
Slide 3LCLS-II Und. Installation & Expansion, 1-18-12
Tapered Und. Seg. 12-57202.4m
Seed Und. Seg. 1-1148.4m M
on o4.
4m
0 48.4 52.8 255.2
TW Taper to 13keV, No Contingency, In Longer Tunnel:
Source Point 92-138
Drift4.4mM
on o4.
4m
0 39.6 44.0 198.0
TW Taper to 8keV, No Contingency, in CD-1 Tunnel:
Source Point 83-130
Drift8.8m
Seed Und. Seg. 1-730.8m
Tapered Und. Seg. 8-41149.6m
8.8 193.6
Drift8.8m
0
Base Und. Seg. 7-32114.4m
20% 1-626.4m
35.2 149.6 255.2
Drift105.6m
Source Point 108-139
SASE in Longer Tunnel:
8.8
0
Base Und. Seg. 7-32114.4m
20% 1-626.4m
26.4 140.8 198.0
Drift57.2m
Source Point 99-130
CD-1 Scope, SASE:
SXU Expansion Plan
Slide 4LCLS-II Und. Installation & Expansion, 1-18-12
Seed Und. Seg. 1-939.6m
Tapered Und. Seg. 10-2461.6mM
ono 8.
8m
0 127.6 136.4 198.0
350 GW Taper to 1keV, No Contingency, in CD-1 Tunnel:
Source Point 1 keV, ~161m
88.0
Drift88.0m
0 255.2
350 GW Taper to 1keV, No Contingency, In Longer Tunnel:
Tapered Und. Seg. 10-2461.6m
193.6
Drift145.2m
Seed Und. Seg. 1-939.6m
Mo
no 8.8m
184.8145.2 Source Point 1 keV, ~218m
Drift13.2m
0
20% 1-417.6m
105.6 123.2 198.0
Drift105.6m
Source Point 153-175m
CD-1 Scope, SASE:
Base Und. Seg. 5-1861.6m
184.4
0 255.2
SASE in Longer Tunnel:
Drift162.8m
20% 1-417.6m
162.8 180.4 Source Point 210-233m
Drift13.2m
Base Und. Seg. 5-1861.6m
242.0
Assumption and Conclusions
Slide 5LCLS-II Und. Installation & Expansion, 1-18-12
• Assumptions:• Post saturation taper the source point is ~1/2 distance from saturation point
to end undulator. For strong taper Juhao provided more exact estimate for 8,10 and 18 keV.
(Assumed observation point was 150m from end HXR undulator & 110m end SXR.)
Extrapolated strong taper sto date. ource point to 4keV. Only 1 point for SXR at 1keV
• Conclusions:• The HXR undulators should be pushed to the upstream end of the
tunnel.• The SXR undulator should be pushed to the downstream end of the
tunnel.• This will have implications on spacing and number service
buildings.