Upload
donhu
View
215
Download
0
Embed Size (px)
Citation preview
LAYING AND ASSOCIATEDWORKS FOR ONGC BANTUMILLITO ULLAMPARU PIPELINE Project No. P.011947Document No. P..011947 R11050 101E - Tender No. 8000013032
GAIL (India) LimitedNoida | INDIA
PUBLIC
8 May 2018
TECHNICAL DOCUMENTATIONTechnical - General, Vol II A, Rev. 0
SCOPE OF WORK P.011947
D 10775
101
LAYING AND ASSOCIATED WORKS FOR ONGC
BANTUMILLI TO ULLAMPARU PIPELINE IN KG BASIN
TRACTEBEL ENGINEERING PVT. LTD.
SCOPE OF WORK
DOC. NO. P.011947 D 10775 101
0 01.05.2018 Issued for Procurement PP SK SKH
Rev. Date Subject of revision Prepared By Checked By Approved By
SCOPE OF WORK P.011947
D 10775
101
Rev. 0 ONGC Bantumilli To Ullamparu Pipeline Project Page 1 of 1
TABLE OF CONTENTS
1.0 PROJECT GENERAL DESCRIPTION ...................................................................................... 1
2.0 BRIEF SCOPE OF WORK OF CONTRACTOR ......................................................................... 5
3.0 FREE ISSUE MATERIALS (FIM) ........................................................................................... 7
4.0 ROUTE AND CROSSING DETAILS ........................................................................................ 8
5.0 ACTIVITIES INVOLVED IN THE SCOPE OF CONTRACTOR ................................................. 15
6.0 PIPELINE BURIAL ............................................................................................................. 19
7.0 DETAILED SCOPE OF WORK FOR CONTRACTOR ............................................................... 20
8.0 QUALITY ASSURANCE AND QUALITY CONTROL ............................................................... 60
9.0 PROJECT MANAGEMENT ................................................................................................... 61
10.0 INTERFACING & COORDINATION WITH SUB-CONTRACTORS / VENDORS
/SPECIALIZED AGENCIES ................................................................................................. 64
11.0 ORDER OF PRECEDENCE OF DOCUMENTS ........................................................................ 64
12.0 “AS BUILTS” ...................................................................................................................... 65
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 1 of 65
1.0 PROJECT GENERAL DESCRIPTION
1.1. Scope
The details provided in this section are Indicative only and are intended to provide a basic understanding of the Project
and the proposed 12” Pipeline system. However, for details, the contractor must refer the complete Tender Documents
especially all Specifications (including GTS and PTS), Design basis and all Project Drawings.
The scope of work in general includes scope of work specified in Technical Documents (including Design basis, PTS
GTS, drawings, datasheet etc.) And Schedule of Rates enclosed in the Tender Document. Section of the Bidding
Document. Further, it includes any other work not specifically mentioned but required to complete the work
as per specifications, drawings and instructions of Engineer-in-Charge.
Scope of work shall be read in conjunction with item description of Schedule of Rates and Contractor's scope
shall include all activities of work specified in the item description of Schedule of Rates. Rates shall include all cost
for the performance of the item considering all parts of the Bidding Document. In case any activity though specifically
not covered in description of item under `Schedule of Rates' but is required to complete the work which could be
reasonably implied/ informed from the content of Bidding Document, the cost for carrying out such activity of work
shall be deemed to be included in the item rate.
This document shall be read in conjunction with Design Basis, Schedule of Rates, Specifications including PTS and
GTS, Standards, Drawings, P&IDs and other Documents/ Drawings forming part of Tender Document.
Details of associated Civil, Structural, Architectural, Electrical, Mechanical, Instrumentation/Telecom, survey
drawings, etc. are covered elsewhere in the Tender document.
1.2. Introduction
GAIL India Limited (GAIL) is operating a network of Natural gas pipelines in the KG Basin area of Andhra Pradesh,
with total length spanning approx. 880 kms, for supplying gas to various customers in the region. GAIL receiving gas
from suppliers like ONGC, and transports it to various industrial customers / load centres, through its existing Pipeline
network.
GAIL will be receiving supply of 0.7 MMSCMD (approx.) of Natural Gas from ONGC Bantumilli field. GAIL is
planning to lay a new 12” NB dia x 38.0 kms length (approx.) Pipeline from ONGC Bantumilli to its existing station
at Ullamparu, for transporting this gas upto Ullamparu, where it will be fed into existing GAIL network.
The proposed 12” pipeline, with a flow capacity of 0.7 MMSCMD, will have a dispatch Terminal at Bantumilli, & a
Receipt cum Hook-up terminal at Ullamparu. The downstream of the new pipeline, at Ullamparu, will be hooked up
to the existing 18” NB Pipeline of GAIL, which passes through Ullamparu station premises, for feeding this gas into
the existing GAIL network.
The proposed 12’ Pipeline will be laid partly in new ROU (approx.. 21 Kms from Bantumilli to DPML,
Vendra) & balance in existing ROU of GAIL (approx.. 17 kms approx.. from DPML to Ullamparu). The proposed
gas pipeline route runs, through marshy soil, paddy fields and fish ponds on either side and crosses areas falling under
Location Class 1, 2 and 3 and 4 (area within the radius of 90 meters from railway ROU).
This document establishes the basis for Design and Detail Engineering for the proposed 12” inch x approx.. 38 km
Pipeline from Bantumilli to Ullamparu, and the associated equipment/ station facilities proposed to be installed, along
with the Pipeline.
The Project involves Laying, Testing and Commissioning of 12” diameter x approx. 38 km long Cross-country
pipeline system along with the associated Station facilities and hook-ups including installation of Barred tee on
existing 18”Pipeline with in station of Ullamparu /tap-offs including Civil, Structural, Mechanical, Piping, Electrical,
Control & Instrumentation, Telecom and Cathodic Protection works.
Work tendered as a part of this Tender Document consists transportation of Company supplied free issue materials to
worksite(s) including all intermediate storage; installation of new pipeline, testing, procurement and supply of all
materials (as per scope of supply); new pipeline/piping works at various terminals; tie-in/ hook-up of Pipeline and
Terminal facilities, preservation (if required), Electronic Geometric Pigging (EGP), pre-commissioning &
commissioning for the pipeline system of the project. The pipeline system includes Pipeline, Despatch Terminal,
Receipt Terminal, Sectionalising Valve (SV) Station and all associated facilities. The work includes installation of
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 2 of 65
pipeline and related piping works and all associated Civil, Structural, Architectural, Electrical, Mechanical,
Instrumentation/ Telecom etc.
Refer “Schematic Arrangement of Pipeline Facilities”. The Pipeline Schematic indicates the overall project details in
brief and is for reference purpose only. Contractor’s quotation shall be based on complete scope of work & all
documents/ drawings forming part of the Tender Document. All clauses mentioned in this document are applicable
to all pipelines unless specified otherwise.
The approx. width of ROU available to lay the new 12” pipeline is as under,
� Initial approx. 21 Kms from Bantumilli to DPML, Vendra (Chainage 0 km to 21 km) : New ROU of 20 Mtr
width
� Balance approx. 20 kms from DPML to Ullamparu: Existing ROU of 18 mtr width wherein 4” gas pipeline is
already laid at almost center of ROU i.e 8 to 10 mtr. The proposed 12” pipeline will be laid at 5 mtr either side
of 4” existing Gas pipeline. Contractor must have to take care of existing 4” pipeline during laying
of 12” proposed pipeline by providing a suitable protection to avoid damages of existing pipeline.
� The alignment of existing pipelines and proposed 12” pipeline is provided in the attached
alignment sheets enclosed with the tender document.
The above mentioned available width of ROU is approximation and based on survey report/as-built alignment sheet,
the actual available width may vary in positive or negative side. Contractors is requested to quote the price considering
the variations in ROU width and any extra amount will not be paid by GAIL on this account.
Contractor’s scope also include to arrange the working ROU to lay the new 12” diameter pipeline in the existing ROU
of GAIL, price incurred in the same shall be included in the quoted rate for Pipe laying work and no extra amount
will be paid to the contractor on this account.
The proposed trench cross section with pipeline location are shown in standard drawings.
Contractor throughout the execution of the contract shall take all necessary steps to maintain the safety and integrity
of any existing pipeline, utilities etc. in the ROU. All the materials / preparatory works/ safety measures as deemed
necessary by Owner for the protection of existing utilities / systems shall be arranged by contractor without any Cost
as well as time implications.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 3 of 65
1.3. Route Map
1.4. Pipeline Design Parameters and Facilities
Process Parameters:
• Pipeline Size : 12” Inch
• Pipe Line Length : 38 km (approx.)
• Design Flow : 0.7 MMSCMD
• Design Pressure : 72 bar g
• Design Temp : Underground Services = (-) 20 to 60 (min / max)
Aboveground Services – CS = (-) 20 to 65 (min / max)
Aboveground & Underground Services – LTCS = (-) 45 to
65 (min / max)
• Design Life : 25 Years
• Gas Supply Pressure : 40-50 barg (max. at ONGC Bantumilli)
• Gas Supply Temperature : 40-45 ° C (at Bantumilli)
• Material Grade of Mainline Pipe : API 5L Gr. X 70/60, PSL 2 (size = 12”).
• Material Grade of Station Piping : API 5L Gr. X 70/60, PSL 2 (for size 12”)
ASTM A 333, Gr.6 (Seamless) (for size ≤ 10”).
• Location Class : 1, 2, 3 and 4
o Location Class 1 & 2 and 3 shall be used for:
: Pipeline laying along the proposed Pipe route, which falls
in Location Class-1, 2 and 3 respectively.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 4 of 65
o Location Class-3 shall also be used for:
: All Station Piping
: All crossings by HDD
: Some crossing in Class-2 which require design factor of 0.5
o Location Class-4 shall be used for :
: Railway crossing, and for pipeline laid within the ‘risk
radius’ on both sides of Railway Crossing.
• Corrosion Allowance : ‘2.0’ mm for 12” Mainline Pipe
(API 5L Grade X 70 & Grade X 60 Pipes)
: ‘2.0’ mm for ASTM A 333, Grade 6 Piping
(all Station Piping 10” and below)
• External Coating : 3LPE as per PTS /GTS coating
• Internal coating : Yes, Liquid Epoxy Paint (for Mainline)
• Manufacturing Tolerance for Wall : ‘Zero’ Negative tolerance for 12” Mainline Pipe
Thickness (API 5L Grade X 70 Pipes)
: (+/-) 12.5% for ASTM A 333, Grade 6 Piping
(all Station Piping 10” and below)
Pipeline Facilities:
• Gas Supply Point : Bantumilli (ONGC Tap Off Point)
• Receiving Points : Ullamparu
• No. of Dispatch Station : 1 (at Bantumilli)
• No. of Receiving Station : 1 (at Ullamparu)
• Total No. of SV Stations : 1 no.
• Total No. of Tap Off Points : 2 nos. (at Ullamparu)
1.5. Pipeline System Configuration
The Pipeline System configuration was finalized based on Route Survey details and the number and location of SV
Station was determined based on ASME B 31.8 requirements, and tentative location of plot identified by GAIL at
approx. 21.6 KM for SV Station.
In addition to 12” diameter x 38 km( approx..) long pipeline, full-fledged Despatch Station at ONGC Bantumilli, 1
(One) SV station and Receiving Station at Ullamparru shall be constructed along with mechanical equipment
installation as defined in the tender documents.
The Table below summarizes the Location Chainage of each station, and a summary of equipment / facilities proposed
at each station, along the proposed Pipeline :
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 5 of 65
S. No. Station Description
Chainage
(km. - approx. from
Bantumilli)
Proposed Facilities
1 Dispatch Station,
Bantumilli 00.00
Dispatch Facility with hook up within premises
of ONGC, Pig Launcher, and Filtering,
Metering, Gas Chromatograph, Pressure &
Flow regulating skid
2 SV – 1 21.6 SV with 1 no. 12” Tap Off for future
3 Receiving Station,
Ullamparu 38
Receiving station with Pig Receiver, Check
Metering skid, and 2 nos. 12” future tap off
valves (one for future tap-off, & the other for
future connectivity with 8” and 12” Pipelines),
Hook-up with existing 18” Pipeline of GAIL by
installing of Barred tee
Note: The location & chainage of SV station shall be finalized, based on plot finalization by GAIL. The drawing
attached with the tender document is the indicative drawing which will be modified to suite the site condition after
finalisation of plot.
The detailed works of Civil, Structural, Mechanical, Piping, Electrical, Control & Instrumentation, Telecom and
Cathodic Protection works involves at the above stations are provided elsewhere in this document.
2.0 BRIEF SCOPE OF WORK OF CONTRACTOR
2.1 Mainline Work
The present specification envisages construction requirement for API5L Grade X70/X-60 line pipes.
Chainage-wise details of line pipes (Thickness-wise as per area classification) to be used in the mainline construction
is provided as annexure-1 of this scope of work. However the chainage-wise thickness may vary as per the decision
taken by GAIL/PMC during Construction. Contractor to construct the mainline accordingly and SOR rate will be
applicable as per the actual thickness of line pipe. Final detail of the same shall also be marked in the as-built
Alignment drawings to be prepared by contractor based on Alignment sheets provided with the tender document.
Alignment sheets provided with the tender document does not have thickness-wise details of line pipe, hence refer
the annexure-1 of this document for line pipe thickness of mainline.
While working out the cost of the SOR (as per tender documents), the contractor should take into consideration the
following:-
i) The number of crossings/obstacles encountered at site may differ from the one mentioned in Alignment
drawings/Crossing drawings/ crossing details provided in the tender document.
ii) The width, depth, nature of crossings/obstacles may differ from the one reported on alignment sheet and/or
crossing drawings.
iii) Based on the above, the contractor shall determine the characteristics, depth, width, nature of
crossing/obstacles, etc. based on site visit or any other evidences or materials he may have.
In addition to above, the contractor should take into account all such variations and must include it in the quoted price
of relevant SOR item. Payment will be made as per actual length executed (as per SOR) and in line with approved
crossing drawing by GAIL/PMC. Contractor will not be entitled for any compensation or raise extra cost for
discrepancies between what has been reported in scope of work, PTS & its annexure or reports/drawings and the
reality of the terrain.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 6 of 65
2.2 Main Line Pipes
• Material for 12” Main Line Pipe : API 5L X70/60, PSL 2
• Wall Thickness for 12” Line Pipe (API 5L X70, PSL 2) :
Location Class of
Pipeline Route
Selected
Wall Thickness
Wall Thickness required
for fabrication of hot
induction Bend
Location Class 1 6.4 mm 7.1 mm
Location Class 2 6.4 mm 7.1 mm
Location Class 3 7.1 mm 8.7 mm
Location Class 4 8.7 mm 9.5 mm
The following thickness shall be used for fabrication of hot induction bends:
• For Location Class – 1: Thickness to be used for fabrication of Hot bend – 7.1 mm
• For Location Class – 2: Thickness to be used for fabrication of Hot bend – 7.1 mm
• For Location Class – 3: Thickness to be used for fabrication of Hot bend – 8.7 mm
• For Location Class – 4: Thickness to be used for fabrication of Hot bend – 9.5 mm
All above pipes will be free issued to the Contractor. In some cases 9.5 mm thick pipes will be issued for fabrication
of induction bends for location class 1, 2 and 3 also.
• Wall Thickness for 12” Line Pipe (API 5L X60, PSL 2) :
Location Class of
Pipeline Route
Selected
Wall Thickness
Location Class 1/2/3/4 9.5 mm
2.3 Important remarks:
a) Unless otherwise stated in particular cross section drawings, the clear spacing between the gas pipeline and
utilities will be min. 0.30 m at the crossing point and min.3.0m when the pipeline is running parallel to the
utilities (OISD 141) Wherever it is possible, the minimum distance must be increased.
b) Unless otherwise stated, no trees shall be left at less than 4 meters from the axis of the pipeline.
c) If any crossing due to site conditions, statutory authority requirements or project schedule requirements (at sole
discretion & prior approval of Owner’s representative) shall be required to be done by trenchless method, it shall
be paid as per relevant SOR item.
d) Apart from this the pipeline may also cross existing pipelines at some locations; Contractor shall take necessary
precautions to protect the existing pipelines.
e) At some locations, where pipeline may have to cross the existing pipelines, large scale excavation may expose
existing pipeline and may cause damage due to land collapse. In such case, excavation and laying of pipeline
are to be done in separate phases. Contractor shall submit detail procedure for crossings the existing pipelines
for approval of Owner/Owner’s representative.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 7 of 65
f) In some areas due to several underground obstacles encountered during construction, mechanical trenching may
not be possible. In such cases Contractor shall perform the work by manual means without any cost as well as
time implications.
g) In urban areas where there are numerous underground utilities, the cover of 1.2m may not be sufficient,
Contractor will not raise any compensation for any such necessary deepening (refer to PTS _Construction of
pipeline and part 10 of GTS/502).
h) If any, hard rocks may be encountered, Control rock blasting method of trenching / back filling must be taken.
i) In Rocky area if backfilling material does not meet the condition specified in GTS (Part 10) & PTS, the
contractor must propose a suitable rock shield protection (6 mm thk.) to be approved by Owner and Engineer.
No extra cost or compensation for supply & placement of the rock shield will be raised by contractor. Special
precautions to be taken for controlled rock blasting which has to be done before hauling, storing and stringing
of pipes. The maximum particles velocity should be determined to avoid any damages on existing facilities
(Refer PTS/GTS Controlled rock blasting).
j) To comply with the agreed work schedule the contractor may have to work in shift or extended hours without
any cost implication.
k) The Contractor shall be deemed to have taken into account all variations as mentioned above at the time of
formulating his bid and no extra compensation either by way of time or cost shall be admissible.
l) Contractor’s scope also include to arrange the working ROU to lay the new 12” diameter pipeline in the existing
ROU of GAIL, price incurred in the same shall be included in the quoted rate for Pipe laying work and no extra
amount will be paid to the contractor on this account.
m) The rate for pipe laying shall be inclusive of excavation in all type of soil, soft and hard rocks and all depths,
pre & post padding.
2.4 Stations / Facilities on the Pipeline
Following is a summary of facilities planned at the stations:
o Dispatch station: It includes Pig launcher facilities, Hook-up with 12” Tap-Off Valve and 200 mtr piping along
with pipe support (to be provided by ONGC) from GAIL Despatch station to inside ONGC premises,
installation of a Filtering along with KOD, Metering, Pressure and Flow Regulating Skid with Gas
Chromatograph, all associated valves and Piping, Civil, Electrical with Cathodic protection, Instrumentation
and Controls, and facility to depressurize the pipeline, if necessary as defined in the tender documents.
o Sectionalizing Valve (SV) Station: SV Station shall be provided with bypass and venting arrangement. In
addition a 12” Tap Off shall be provided for Future. The location and plot for SV station shall be as finalized
by GAIL. It also includes Piping, Civil, and Electrical with Cathodic protection, Instrumentation and Controls
work as defined in the tender documents.
o Receiving station : Receiving station shall include Pig receiver facility, a Check metering skid, Hook-up with
existing 18” Pipeline of GAIL, which passes through the Ullamparu plot, for feeding the gas in existing GAIL
network, (the Hook-up to 18” Pipeline, shall be done with a barred tee, to ensure piggability of the 18”
pipeline), all associated, valves and Piping, Civil, Electrical with Cathodic protection, Instrumentation and
Controls, and facility to depressurize the pipeline, if necessary, as defined in the tender documents.
o Future Tap Off Points : 3 Nos. 12” NB Tap Off Points (TOP) shall be provided on the pipeline, 1 at SV station,
and 2 nos at Ullamparu Receiving Station, (one for future connectivity, and the other for future interconnection
of 12” and 8” pipelines running parallel to 18” Pipelines.
3.0 FREE ISSUE MATERIALS (FIM)
The following items shall be issued to the EPC contractor as ‘Free Issue Item (FIM), for installation at stations, as
part of the project.
S. No. Item
1 12” Mainline 3 LPE Coated Line Pipes API 5L Gr. X-70 (6.4 mm/ 7.1 mm/ 8.7 mm/ 9.5
mm and API 5L Gr. X-60 (9.5 mm)
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 8 of 65
2 Ball, Globe , Plug and Check Valve above 2” diameter
3 Insulating Joints
4. Pig Launcher/Receiver ( Scrapper Trap ) for 12” dia Pipeline including handling system &
Jib Crane and Pig signaller
5. Fittings and Flanges above 2” diameter including barred / Flow tee
6. Skids ( Filtering along with KOD, Metering, Pressure and Flow Regulating Skid with Gas
Chromatograph for Despatch station at ONGC Bantumilli and Check metering skid for
Receiving station at Ullamparu
With respect to the Free Issue Materials issued to the Contractor, the scope of work includes loading, un-loading,
handling, storage, preservation, transportation and installation. Civil Works including foundations, piping
interconnections, co- ordination with system vendors etc. to render system completely functional is also included in
the scope of Contractor.
All other items, not listed in the Table of FIM above, shall all be included in Contractors scope of Supply.
4.0 ROUTE AND CROSSING DETAILS
4.1 General
The details provided in this section are Indicative only and are intended to provide a basic understanding of the
proposed route of 12” ONGC Bantumilli to Ullamparu Pipeline. The contractor must refer the “: Detailed Route
Survey Report” attached with the Tender Document.
The proposed Pipeline is a 12” NB dia, approx. 38 Kms. long high pressure cross-country Natural Gas Pipeline.
Which will be laid partly in new ROU (21 Kms from Bantumilli to DPML, Vendra) & balance in existing ROU
of GAIL (17 kms approx.. from DPML to Ullamparu). 20 mtr width of new ROU from ONGC Bantumilli to DPML,
Vendra and 18 mtr width of existing ROU wherein 4” existing pipeline is already laid from Ullamparu to DPML
4.2 Location of the Project
The proposed Pipeline shall be laid from ONGC Bantumilli to Ullamparu (which is existing station of GAIL). The
details of Starting and end points are as below:
4.3 Pipeline Route Profile
The proposed Pipeline will be laid partly in new ROU (21 Kms from Bantumilli to DPML, Vendra) & balance
in existing ROU of GAIL (17 kms approx.. from DPML to Ullamparu) and will cross though areas falling under
Location Class 1, 2, 3 and 4 (pipeline under risk radius of Railway ROU). The proposed gas pipeline route runs cross-
country, between take off point and terminal.
As per the route survey, Route Map, Alignment sheets attached with the tender document, the Pipeline route is approx.
38 Km. The Proposed route Take off from ONGC Bantumilli at Ch. 0.0 km in Bantumilli village of Krishna District,
Andhra Pradesh and Terminal point proposed at existing station at Ullamparu of West Godavari District of Andhra
Pradesh.
The Proposed pipeline ROU details to lay the new 12” pipeline is as under,
� Initial approx. 21 Kms from Bantumilli to DPML, Vendra (Chainage 0 km to 21 km) : New ROU of 20 Mtr
width
� Balance approx. 17 kms from DPML to Ullamparu: Existing ROU of 18 mtr width wherein 4” gas pipeline is
already laid at almost center of ROU i.e 8 to 10 mtr. The proposed 12” pipeline will be laid at 5 mtr either side
Particulars Ch. (Km) Location Village District State
Take-off Point 0.00 ONGC,
Bantumilli Bantumilli West Godavari Andhra Pradesh
Terminal Point 38 Ullamparu Ullamparu West Godavari Andhra Pradesh
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 9 of 65
of 4” existing Gas pipeline. Contractor must have to take care of existing 4” pipeline during laying
of 12” proposed pipeline by providing a suitable protection to avoid damages of existing pipeline.
� The alignment of existing pipelines and proposed 12” pipeline is provided in the attached
alignment sheets enclosed with the tender document
The proposed ONGC Bantumilli to Ullamparu pipeline runs in Bhimavaram in West Godavari district of Andhra
Pradesh. Pipeline generally runs in west to east direction. The proposed route from ONGC Bantumilli,
Nagendrapuram village, Bhimavaram runs in west to east in west Godavari district and crosses the major crossing
Asphalted Road ( From NaHodupalom - To SH-113 ) at Ch. 419.97, Kommatippa Branch Channel at Ch. 2896.92,
Asphalted Road (From Kotha Pusalamarru - To SH-113 ) at Ch. 5193.38, Enamadurru Channel at Ch. 6790.22, State
Highway-113 ( From Kalipatnam - To Bhimavaram ) at Ch. 7008.66, Uppukodu Drain at Ch. 7327.93, Unlined Drain
at Ch. 8036.21, Asphalted Road ( From Bhimavaram - To Dirusumarr ) at Ch. 9116.55, Metalled Road ( From
Enamadurru - To Chinna Haruvu ) at Ch. 9447.81, Unlined Drain at Ch. 10193.9, Unlined Drain at Ch. 10607.36,
Hunupudi Drain at Ch. 10792.05, Unlined Drain at Ch. 12136.13, Metalled Road ( From Field - To Yamunepalle )
at Ch. 12141.63, Matsyapuri Road(ASP) ( From Bhimavaram - To Matsyapuri ) at Ch. 12679.33, Vissakoderu
Channel at Ch. 13099.62, Unlined Drain at Ch. 14208.73, Vissakoderu Channel at Ch. 14333.74, Unlined Drain at
Ch. 15191.22, Asphalted Road ( From HoraHanamudai - To Bhimavaram EnH.Co ) at Ch. 16489.16, Tallikodu
Channel at Ch. 16509.76, South Central Railwa ( From Bhimavaram RS - To Pennadapalem RS(N ) at Ch. 16921.24,
Unlined Channel at Ch. 17559.95, Metalled Road ( From Pennadapalem - ) at Ch. 17800.04, National HiHhway-65
( From Bhimavaram - To Viravasaram ) at Ch. 18085.64, Unlined Channel at Ch. 19707.32, Metalled Road ( From
Vendra - To Pennada ) at Ch. 19711.36, Metalled Road ( From Fish Pond - To Pennada ) at Ch. 20198.53, Adarikodu
Channel at Ch. 20212.57, Viravasaram West Channel at Ch. 20539.37Metalled Road ( From Fish Pond - To Pennada
) at Ch. 20198.53, Adarikodu Channel at Ch. 20212.57, Viravasaram West Channel at Ch. 20539.37.
The proposed route from Ullamparu village runs in east to west direction in West Godavari district and
crosses the major crossing SH-41 at Ch. 669.75, Narsapur Unlined Canal at Ch. 689.73, MOHALLURU DRAIN at
Ch. 1987.41, Asphalted Road at Ch. 2272.6, Jnnuru Unlined Channel at Ch. 2792.01, Asphalted Road at Ch. 3627.06,
Bhaieswae Drain at Ch. 4158.91, Asphalted Road at Ch. 5170.9, Koderu No.1 Branch Canal at Ch. 5475.26, RCC
Road at Ch. 5720.61, Asphalted Road at Ch. 5829.34, RCC Road at Ch. 6146.21, Asphalted Road at Ch. 7209.99,
Drain-Rapaka Channel-drain at Ch. 7842.37, Asphalted Road at Ch. 7904.56, Asphalted Road at Ch. 8519.96,
Asphalted Road at Ch. 9257.68, Gonteru Drain at Ch. 9793.9, Basavaraju kodu Drain at Ch. 10588.26, Asphalted
Road at Ch. 11676.66, Unlined Canal at Ch. 11932.24, Canal at Ch. 11946.36, Field Chanal at Ch. 13348, Field
Chanal at Ch. 13862.96, Asphalted WBM Road at Ch. 14490.12, Asphalted Road at Ch. 15718.75, Field Chanal at
Ch. 15725.56, Gostanadi Canal at Ch. 18394.02, Vraw Hara Canal at Ch. 18157.26.
ELEVATIONS:-
Terrain along the pipeline is Flat its entire length. The elevation at start point is 6.4 m above MSL and end point is
6.04 m. The highest elevation is 8.21 m at approx. route Ch. 17571.68 m and the lowest elevation is 3.15 m at approx
route Ch. 11397.01 M
FOREST LANDS:-
The proposed pipeline route passes through protected forest for about 0.002 Ha areas.
WILDLIFE SANCTUARY / NATIONAL PARKS:-
The proposed pipeline route does not passes through any Wild Life Sanctuary / national Park.
EXTENT OF VEGETATION AND LAND USE PATTERN:
The proposed route of pipeline from Take-off point at ONGC Bantumilli at Ch.00+000.00 Km to Terminal point at
Ullamparu mainly passes through the agricultural land, Fish Pond and Paddy field.
4.4 Major Crossings
All major crossings like State Highways, National Highways, Railways, Lined Canals etc. shall be laid by Boring or
whenever imposed by concerned authority. Cased crossing is mandatory for Lined canals, State Highways, National
Highways & Railroad crossing.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 10 of 65
At all crossings where Carrier / Casing pipe is installed by using Boring & Jacking method, and for all HDD crossings,
a separate 6” Casing Pipe (API 5L Grade-B, 6.4 mm thk, external epoxy coated, 500 micron thick) shall be installed,
with 2 nos. 50 mm HDPE ducts laid inside the casing, 1 housing the main OFC cable inside it, and the other spare,
for future OFC blowing. The 6” Casing pipe shall be installed through separate boring as shown in the standard
drawings.
The Wall Thickness of Pipes to be used at all the crossings shall be as given in the tender document.
All the crossings mentioned in detailed route survey shall be classified as per PNGRB, as shown in the table below.
Type of Crossing as per Detailed
Survey Report Crossing Classification -
as per PNGRB Regulation ‘Table-1’ S.No
Crossing
Code
Crossing
Description
Uncased Crossing (Open Cut)
1 AR Asphalted Road Uncased - Road, Highway, Public Street with Hard Surface
2 MR Metalled Road Uncased - Road, Highway, Public Street with Hard Surface
3 ODR Other District
Road Uncased - Road, Highway, Public Street with Hard Surface
4 MDR Major District
Road Uncased - Road, Highway, Public Street with Hard Surface
5 MUR Mud Road Uncased - Un-improved Public Roads or Private Roads
Cased Crossing (Boring + Casing)
6 SH State Highway Cased - Road, Highway, Public Street with Hard Surface
7 NH National
Highway Cased - Road, Highway, Public Street with Hard Surface
8 Ry Railway Cased - Railway Crossing – considering Location Class-4
(As Per Railway requirement)
9 LC Lined Canal Cased Crossing
10 RCC RCC Road Cased - Road, Highway, Public Street with Hard Surface
Open Cut/HDD
11 NL Nala River Crossing -Open Cut
12 DR Drain Uncased Crossing - Open Cut
13 Rl River River Crossing -Open Cut
Crossing list provided with Annexure-1 shall be referred for Type of crossing and its chainages.
4.5 Railway & Highway Crossings
Rail crossing shall comply with the requirements of API RP 1102 and Indian Railway Authorities recommended
guidelines (Report No. BS-105 and Addendum Slip-4 dated 08.04.2014). Pipeline at rail crossings shall be provided
with casing pipe, which shall extend min. 1500 mm on either side of railway ROW unless specified otherwise by
Railway Authorities. In any case, the minimum length of Casing Pipe for Railway Crossings, shall be 60 meters. The
casing pipe shall be installed by boring/jacking method.
Carrier pipe shall be electrically insulated from the casing pipe and casing ends shall be sealed using durable,
electrically non-conducting materials. Suitable measures (epoxy coating, 500 micron) shall be taken for anti-corrosive
coating/painting of Casing pipes and/or as directed by concerned authorities. Annular space between casing and
carrier pipe shall be filled with bentonite.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 11 of 65
Casing pipe size for 12” Mainline shall be 18” NB. However, Final size and Thickness of the Casing Pipe shall be
determined , based on requirements of Statutory Authorities. All applicable Statutory Authorities’ codes and
requirements shall be complied.
Road crossing shall comply with the requirements of API RP 1102 and the requirements of the concerned road
authorities. In general for major road crossing, crossing shall be done by boring & casing method.
Pipeline at State highway / National Highway road crossings shall be provided with casing pipe, which shall extend
min. 1500 mm beyond the drainage ditch on either side of road/ROW, unless specified otherwise by concerned
authorities.
The casing pipe shall be installed by boring/jacking. Suitable measures (epoxy coating, 500 micron) shall be taken
for anti-corrosive coating/painting of Casing pipes and/or as directed by concerned authorities. Annular space between
casing and carrier pipe shall be filled with bentonite.
Casing pipe size for 12”NB (Main Line) shall be 18”NB. However. All applicable Statutory Authorities’ codes and
requirements shall be complied.
Provisions shall be kept for additional length/ increased width of crossing lengths of jacking + boring lengths to take
care of restricted ROU’s or land issues.
The Material and Wall Thickness to be used for Casing Pipe, for housing 12” NB Carrier shall be as summarized
below :
Crossing Chainages are listed at Annexure-1 of this document.
4.6 River / Canal Crossings and HDD
Minor water crossings and unlined canals shall be installed by open cut method. All lined Canals shall be crossed by
Boring & Casing method. River Crossing shall be done by open cut method with concrete coating or Gabions/
geotextiles Major water crossings like major canals shall be installed by open cut/Horizontal Directional Drilling
(HDD) method. The banks shall be protected by using gravel and boulders filled embankment mattresses of
galvanized iron wire to be laid over the backfilled, compacted and graded banks.
The protection of the banks shall be carried out across the ROU width plus three meters on either side of ROU or
actual distributed bank during construction whichever is higher. All lined canal/drains/nala will be restored to the
original condition.
Based on the above, the following methods may be used for major crossings along the proposed route of pipeline.
Crossing Type
Details of Casing Pipe to be Used
Casing Pipe
Size
(inch NB)
Casing Pipe
Material
Casing Pipe
Wall Thickness
(mm)
Railway Crossing 18” API 5L, Grade B 7.0
Highway Crossing 18” API 5L, Grade B 7.0
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 12 of 65
Sr.
No. Crossing Detail
Location
Class
Center
line
Chainage
in (M)
Design
Cumulative
Chainage
(M)
Method
of
Crossing
Width
of
Crossing
/ HDD
(M)
ROU
Detail
1 Kommatippa Branch
Channel 3 2,896.92 2,896.92 B+C 32.01 New
2 Enamadurru Channel 3 6,790.22 6,790.22 B+C 27.74 New
3
State HiHhway-113 ( From
Kalipatnam - To
Bhimavaram )
3 7,008.66 7,008.66 B+C 14.67 New
4 Uppukodu Drain 3 7,327.93 7,327.93 OC 75.32 New
5 Hunupudi Drain 2 10,792.05 10,792.05 OC 51.52 New
6 Vissakoderu Channel 1 14,333.74 14,333.74 B+C 54.16 New
7
South Central Railway
(From Bhimavaram RS -
To Pennadapalem RS)
4 16,921.24 16,921.24 B+C 43.49 New
8
National Highway-65 (
From Bhimavaram - To
Viravasaram )
3 18,085.64 18,085.64 HDD 160* New
9 Basavarajukodu Drain 1 10,588.26 26,995.78 HDD 410* Existing
10 Gonteru Drain 1 9,793.90 27,790.14 HDD 200* Existing
11 Baggeswaram Drain 2 4,158.91 33,425.13 HDD 180* Existing
12 Narsapur Canal & SH-41 3 689.73 36,894.31 HDD 200* Existing
HDD : Horizontal Directional Drilling;
B+C : Boring and casing
OC+CC : Open Cut + Concrete Coating
Notes :
1. *The length mentioned for HDD crossings are tentative only, and shall be finalized based on actual site
requirements. However, Contractor may propose additional HDD including fish ponds and any other crossing
which shall be done without any cost implication and prior approval of Owner/Engineer. Contractor shall ensure
proper disposal arrangement of Bentonite during HDD operation. Any damages due to seepage or improper
handling of bentonite shall be borne by contractor.
2. The Chainage given are as per Alignment sheets for New and Existing ROU.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 13 of 65
3. The Chainages for new ROU are measured from ONGC Bantumilli, and increases towards DMPL
4. The Chainages for existing ROU are measured from Ullamparru, and increases towards DMPL
5. The Design Cumulative chainage are given for cross checking, and are measured from ONGC Bantumilli
towards Ulamparru.
The above methods proposed for the crossings are tentative. However, the actual method of crossing shall be
finalized based on actual site requirements.
In addition to the above, the initial 6.6 kms length (approx..) of proposed pipeline route, starting from TP-07 near
ONGC Bantumilli (chainage – 0.424 km), and upto TP-50 (chainage : 7.0463 km) has a very restricted width of
ROU available. This section of pipe route runs adjacent to existing road and State Highway-113. This section has
been considered as HDD section.
Since the length of the pipeline section is large, (approx. 6.6 kms), the pipeline laying shall be done using multiple
HDDs. The depth of HDD shall be kept adequate to safeguard the pipeline from effects of seepage, waterlogging
and earth loads. The following shall be considered:
a. The exact location, length and starting & end points of the HDD crossings shall be determined based on
actual site conditions, and availability of space and permissions for carrying out HDD operation, and ease
of installation and movement of required equipment.
b. To the extent possible, most of the portions of the above section shall be preferably installed by HDD
Method. The sections where major construction constraints are likely shall be included in crossings by HDD.
c. The no. and locations of HDD sections shall be decided based on site conditions and requirements,
availability of adequate space for carrying out the operation, movement and installation of equipment, and
ease of hooking up of different HDD sections.
d. The depth, routing and exact profile of the HDD shall be finalized based on site conditions and actual site
requirements.
e. The sections where it is possible to lay the pipeline by trenching, shall be carefully evaluated and agreed by
the client / PMC. All such sections shall be hooked-up with adjacent HDD sections, ensuring a smooth
pipeline profile for ensuring that all pipeline stresses are within design limits.
f. Adequate protection against earth/vehicular loads in form of concrete slabs etc. and adequate anti-buoyancy
measures like concrete-coating, saddle bags or pre-cast concrete weight blocks etc. shall be provided, as per
site requirements, for pipeline sections which are executed by normal trenching method.
g. The pipeline laying in this entire section, including all HDDs shall be planned and designed very carefully,
considering site conditions, existing constraints, presence of large water bodies and a running state highway
adjacent to the route with traffic. The planning and design shall ensure safe operation, construction and
installation of pipeline, without affecting the highway traffic and in view of the safety of public, adjacent
structures and installations and water bodies.
h. In view of the above, the entire HDD operation, including design, engineering, and execution and testing
shall be performed by a specialist HDD Contractor, with adequate experience and proven track record of
similar operations.
The Design of all HDD operations, including design of all materials, all engineering calculations, execution,
installation and testing etc. shall be carried out in full compliance to all applicable codes and standards, statutory
requirements and in line with project specifications and requirements. Best practices from the industry shall be
considered and followed where deemed suitable.
Design and engineering of HDD operation shall also ensure that no seepage of bentonite takes place from the HDD
into the adjoining soil / fields / fisheries / ponds etc. In case, any seepage happens, the compensation for the same
shall be done by the contractor.
4.7 Anti-Buoyancy requirements
Anti-buoyancy measures shall be provided, over and above Pipe External Coating, in marshy lands, areas prone to
flooding or waterlogging, at water body crossings and other areas requiring anti-buoyancy measures.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 14 of 65
Anti-Buoyancy shall be provided by means of continuous Concrete Coating, use of Geo Textile Bags or pre-cast
concrete weight blocks. The preferred method for providing anti-buoyancy is by use of saddle bags and or concrete
blocks. Use of concrete coating shall be avoided and shall be followed only where use of saddle bags or concrete
blocks is difficult or not possible, due to restricted space, small ROU width or other limitations.
For Rocky River (if any) anti-buoyancy measures shall be provided with gabion arrangement.
The size & spacing of saddle bags and concrete blocks shall be determined during detail engineering. The thickness
of concrete coating required for each location class, is tabulated below. The size, weight and spacing of saddle bags
or concrete blocks shall be such that it provides equivalent weight and anti-buoyancy effect as provided by concrete
coating thickness (for each location class) mentioned below:
Based on Buoyancy calculations carried out for the Pipeline, the Concrete Coating thicknesses, to be used for 12” NB
x 38.0 km long Main Pipe Line, from Bantumilli to Ullamparru, shall be as below:
Crossing Location Class Wall Thickness of
Pipeline to be used
Thickness of Concrete
Coating Required
Location Class 1 & 2 API 5L X-70 6.4 mm 40 mm (Note – 1)
Location Class 3 API 5L X-70 7.1 mm 35 mm (Note – 1)
Location Class 4 API 5L X-70 8.7 mm 30 mm (Note – 1)
Note – 1 : Final Thickness of Concrete Coating or anti buoyancy weight for geo textile bags shall be determined,
during detail engineering, based on requirements at site.
For Rocky River / Fish pond area and any other area where anti buoyancy is required, concrete coating or geo textile
bags shall be provided as instructed by EIC.
4.8 Other Crossings
Foreign Pipeline Crossing
In case any existing pipeline needs to be crossed, the new pipeline shall be laid at least 500 mm below such existing
pipeline, and a physical barrier in the form of 75 mm thick concrete slab shall be provided. The existing pipeline shall
be properly supported during and after the construction.
Over Head Power Transmission Line Crossing
Where overhead Power Transmission line equal to and above 11KV and less than 66KV needs to be crossed, plastic
grating of minimum 8 mm thickness shall be provided. For 66 KV and above power line crossings, concrete slab of
thickness 75 mm shall be provided over pipe trench.
4.9 Route Survey and Verification by Contractor
The Details provided above, and elsewhere in the tender document are based on preliminary survey/observation and
given for information only. In any case, the Contractor shall carry out detailed site survey, collect and record all the
findings and update Survey data / drawings based on his own detailed site verification survey.
The contractor must acquaint himself well with the existing / prevailing site conditions and requirements, proposed
route and terrain, land use and crossings etc. Further, the contractor shall determine the exact quantum of work
required for each activity, including the quantity for each item, based on his detailed site survey including soil
investigation report, bore hole reports, site visits or any evidence or material he may have or required to be collected
by them.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 15 of 65
5.0 ACTIVITIES INVOLVED IN THE SCOPE OF CONTRACTOR
5.1 General
In order for the tender to be valid, the bidder must forward to the Owner at least the following documents, correctly,
completely filled in and clearly legible:
a) A detailed methodology of the works drawn up on the basis of the start and end dates for the works as stipulated
in the special condition of contract (SCC). The various phases of the work must be included in this programme
in so far as they are applicable to the works.
b) An explanatory note must be attached describing the organisation of the Construction Site, as well as the methods
and phases of execution, the complete inspection plan that the Bidder intends to follow, the qualitative and
quantitative description of the means of execution, the installations, the equipment, the material, the tools and the
personnel that he is to employ in each phase in order to complete the Works within the planned schedule.
• The Contractor must draw up working methodologies including equipment, man power and material needed
for all phases of the construction of the pipeline and Natural Gas stations.
• The Contractor must draw HSE execution plan for all phases of construction of the pipeline and natural gas
stations as illustrated in HSE document provided in the tender document and requirement of the site.
• All working methodology must get approved by the Owner and the Engineer before starting work.
• Only approved working methodology will be strictly implemented at site during all construction stages.
• The Contractor shall deploy all equipment and material required to achieve the work as per his detailed
methodology and agreed schedule.
• Contractor shall mobilise (equipment, manpower) simultaneously for (a)main line (b) all crossings and (c)
Natural Gas Stations in order to achieve pre-commissioning activities in due time as specified in the SCC
(Special condition of contract). Deployment of equipment shall be done as defined in the tender document.
• The minimum equipment to be deployed are listed with S.C.C. If equipment pertaining to a particular activity
which has been completed, those particular equipment may be demob provided that request made by the
contractor has been approved by Owner/Owner’s representative.
• If deemed necessary as per the working methodology and/or at the request of the Owner, Contractor must
deploy extra equipment without being entitled to raise any compensation.
• The Bidder must provide a detailed organisational chart indicating the organisation or personnel and
equipment for each phase of the Works.
• Key persons shall be deployed during the entire duration of the work till completion of all works. Non
deployment of key persons will be subject to recovery as elsewhere defined in bid.
• There will be separate in charges for mainline and station works.
This description is only binding upon the Contractor. He must provide, at his own expense, all the necessary
equipment, machinery and personnel even in addition to those indicated in the offer.
5.2 Main Activities
The Contractor scope of work shall consist, but not limited to the following. However, all such works, which are not
listed below but are otherwise required to complete the work in all respects shall form part of the Contractor’s scope
of work. In addition to this, the scope indicated below shall be read in conjunction with the price schedules, drawings,
PTS and GTS etc. forming part of the contract document. In case of contradiction the most stringent shall be applicable
in consent with Owner/Owner’s representative:
• Construction & maintenance and dismantling of the site camp, site offices for contractor’s workshops etc.
• Marking out and clearing out of the ROU
• The ROU will be provided by the Owner. If for some unforeseen reason which is not attributable to contractor,
the pipeline has to be re-routed it will be the sole responsibility of Contractor to make all arrangement to provide
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 16 of 65
new ROU. Contractor shall carry out all necessary survey work as per requirements of site conditions. It will be
the responsibility of the Contractor to maintain the ROU until completion of the work. Liasoning with Owner,
villagers, land Owners and concerned authority etc. for ROU related activities shall be in the scope of Contractor.
• ROU may not be available in the required width in certain stretches, in such cases the work shall be carried out in
the available ROU width.
In case of encroachment on the ROU or extra land needed during construction, it will be the sole responsibility of
the Contractor to relocate all issues (including any compensation) with the relevant land Owner, tenant or
authorities. All related cost will be borne by the Contractor within the quoted rate of mainline work.
• All other permissions, permits and licenses necessary for the performance of the work shall be obtained by the
Contractor at his own cost and initiative. In so far as any such permission, permit or license required for the
performance of the work by the contractor can only be granted at the request or recommendation of the Owner,
the Owner shall at the request of the Contractor, provide recommendatory letters to the contractor to obtain or
procure the same.
• For access route to the working strip the Contractor will be responsible to negotiate with the relevant Owner,
tenant or authorities. Any deemed compensation will be borne by the Contractor and no extra payment will be
given by the OWNER.
• Fabrication, testing, coating/painting of Induction bends from Owner supplied bare coated line pipes. In case of
coated line pipes, contractor will be borne the cost for striping of external coating of line pipes and no extra
payment will be given by the OWNER.
• All civil work for cross country pipeline like soil investigation (if deemed necessary), levelling, fencing,
architectural works, access road construction, sewerage, etc. (Refer PTS Construction – Civil and Design Basis*-
Civil).
• All works for cross country pipeline related to material handling, stringing of pipes, trenching, welding, testing,
inspection of welds, coating, earthworks, lowering-in and ballasting, Crossings (Including HDD), site restoration,
etc.
• All safety practices/standards as illustrated in Present PTS and GTS Building site regulation (70000/740/0503)
shall be strictly followed during construction.
Station Works
• All natural gas stations for this pipeline are to be constructed as indicated in the tender drawings.
• All civil work for Natural Gas Stations like soil investigation if deemed necessary, levelling, fencing, architectural
works, access road construction, sewerage, etc. (Refer PTS Construction – Civil.)
• All works at Natural Gas Station related to material handling, bending, welding, inspection of welds, testing,
coating, painting, earthworks, preparation of shop/assembly/as – built drawing etc.
• Contractor shall carry out displacement / relocation of various existing equipments such that fencing, Gas detector,
electrical Poles, etc. if required for installation of new facilities without any extra cost implication. Contractor
shall also carry out restoration work which has been dismantled / damaged during work such as RCC pavements,
shifting / relocation of Electrical / Instrumentation cabling, etc. including testing. Re – Commissioning of such
equipment/facility to the satisfaction of Owner is in scope of Contractor.
• Providing Portable fire extinguisher at stations as detailed in the tender document.
• Dismantling of existing fencing, providing provisional fencing for existing facilities and installation of new
fencing shall be in the scope of Contractor as mentioned in the drawings.
• The instrumentation/Electrical panel shall be provided in all existing control rooms, if applicable and in new
control room. Contractor shall obtain all necessary permits/approvals viz. work permit, hot permit,
equipment/machine movement permit from the concerned authority. Contractor Scope also includes obtaining
necessary work permits for all existing stations.
• The contractor shall lay, test, clean and dry the pipeline before inserting (SV) or connecting the natural gas stations
to the main pipeline.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 17 of 65
• All natural gas stations will be tested, cleaned and dried prior to be golden tie-in joints with the pipeline.
• Geo textile membrane of 8 mm thk or PE sheet (1000 micron thk) shall be provided below the gravel filled in
process area mainly at SV stations for protecting the grasses growing.
• Lightening arrestor shall be provided at the stations wherever earthing is not provided.
• Safety sign boards displaying use of extinguisher, first aid, emergency procedure etc. shall be provided at control
rooms at each station. Also refer GTS 70000/740/0503 Building site regulations.
• The Contractor will also carry out the testing, cleaning & drying of the pipeline (Pre-commissioning activities as
detailed in PTS).
• Receiving and taking over of Owner’s supplied free issue materials.
• Contractor shall supply items such as ball valves (2””and below), Globe & Check Valves (2””and below), fittings
and flanges (2””and below), Assorted Pipes (10” and below), Welding Consumables, Fasteners, Gaskets,
foundation bolts/holding down bolts/nuts, Warning tape, rock shield, OFC & HDPE Duct, end seals, casing
insulators etc., as per specifications enclosed in bid document. Contractor shall procure all supply items only from
manufacturer/suppliers listed in approved vendor list, enclosed with bid document.
• In principle most of the statutory permissions from the concerned authority have already been obtained by Owner.
However, all activities related to liaison, co-ordination etc. with authorities needed to achieve the work as per
schedule will be under Contractor’s scope including work permit before commencement of work. In case, some
of the permissions are not received by Owner, Contractor to take necessary action for obtaining the same.
Contractor shall also refer to provisions of Commercial part of the tender.
• Obtaining all necessary approvals and work permits from concerned local authorities having jurisdiction including
hot work permit as applicable for performing the work in existing station facilities. Arranging of adequate fire
fighting equipment viz. fire brigade, fire extinguisher, shielding from existing facilities, oxygen mask etc. for
carrying out the work safely to the satisfaction of Owner.
• The Contractor will assure the interface and the coordination of his approved sub-contractors and also other
contractors who may be working on different packages..
• During Pre-commissioning a gauging electronic device (GED) will be used to ascertain the physical integrity of
the pipeline.
• Pipe laying Contractor scope shall also include commissioning. Commissioning of pipeline shall be from Despatch
to receiving station.
• Removal/displacement of existing ROU boundary marker and providing the new boundary markers.
• Fabrication & Installation of new Pipeline markers for proposed pipe line. Removal of existing ROU boundary
markers and fabrication, installation of new ROU boundary marker is in scope of Contractor.
• Supply and installation of HDPE duct & OF cable as per present PTS and PTS-Instrumentation
• 6” Mild steel pipe (API 5L Gr. B, 6.4 mm thk, epoxy coated, 500 micron thk) for housing HDPE duct and OFC
at crossings.
• Providing Concrete slabs or HDPE sheet (6 mm thk) at road crossings as per approval of concerned
authority/Owner’s representative.
• Providing Concrete coating as per requirement
• The Contractor will also submit as built documents/drawings for the entire work under his scope as indicated by
Consultant. Any modification in the drawing after issuance of RFQ drawings shall not cause any cost implication.
• Supply, Installation, Testing, Inspection, transportation& Commissioning of Electrical Equipment (SFU, MEDB,
OLDB, ILDB, SSDB, AC UPS system with UPSDB and Battery Bank, DG set with AMF Panel etc.), Lighting,
Earthing& Lightning Protection, Trenching, Cabling and all the electrical works related to stations. (Refer SLD
and PTS- Electrical).
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 18 of 65
• TCP (Temporary Cathodic Protection) and PCP (Permanent Cathodic Protection). Supply, Installation, Testing,
Commissioning of TCP and PCP including all civil works associated with CP i.e. cable trenches, foundation for
equipment and all test stations.
5.3 Other activities:
• Soil investigation (If required)
• HDD
HDD to be carried out for crossings as listed in above clause 4.6 of this document. However, Contractor may
propose additional HDD for other crossing, which shall be done without any cost implication and prior approval
of Owner/Engineer.
Contractor shall ensure proper disposal arrangement of Bentonite during HDD operation. Any damages due to
seepage of bentonite shall be borne by contractor.
• Controlled rock blasting (Refer PTS/GTS - Controlled rock blasting, if applicable)
• Transition piece requirement
• Contractor shall take very special precaution while stringing of the pipes. However extent of thickness-wise
material use shall be intimated to successful bidder.
• Transition piece requirement other than those indicated above if deemed necessary by the Contractor during
construction stage, shall be subject to approval of Owner/Engineer.
• The contractor shall develop “Pipeline information system” including terrain mapping, land holder records,
welding report (welding log book), as built alignment sheet, entire pipeline route video report, length profile for
the as built pipeline utilities mapping. The pipeline information system must be approved by Owner prior to
commencement of work.
• Digitized map to be used for as built documentation.
• For all supports, neoprene sheet shall be provided.
• Design, supply and installation of electronic markers and locators (for OFC) duly approved by Owner/Engineer
shall be executed by contractor.
5.4 Other Work Packages (Not in the scope of contractors) :
• SCADA work package
5.5 Particular Instructions:
• For access route to the working strip the Contractor will be responsible to negotiate with the relevant Owner,
tenant or authorities. Any deemed compensation will be borne by the Contractor.
• Since the crossing activities are to be started immediately, the acquisition of additional ROU for approach to
crossing locations and additional working strip to be acquired by the laying contractor without any extra time
and cost implication. The pipe laying contractor shall not insist on opening of ROU for crossing. Further, all
necessary actions including providing additional ROU for approach for crossing is in scope of Contractor at no
additional time and cost to Owner.
• Contractor proponent shall have to take prior approval of providing of concrete coating or geotextile bags as
anti-buoyancy for any locations.
• Contractor proponent shall have to take prior approval of concerned Government agencies while carrying out
blasting wherever required.
• Contractor proponent shall have to preserve top soil dug and shall be restored to original condition on completion
of the work. The excavated soil may be stored over the existing pipelines after written approval from the Owner.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 19 of 65
• Contractor proponent shall have to obtain clearance from the Forest Department for the portion of pipeline
passing through reserve forest or any other type of Forest or wild life sanctuary, national park of other prohibited
areas.
• Contractor may propose additional HDD for other crossing, which shall be done without any cost implication
and prior approval of Owner/Engineer. If HDD is proposed for crossing of fish ponds or any other crossings,
Contractor shall ensure proper disposal arrangement of Bentonite during HDD operation. Any damages and
implication of cost due to seepage of bentonite shall be borne by contractor.
• For the waste generated from the pigging and any other operation contractor proponent shall have to provide
sludge collection storage and disposal facility complying EPA-1986 with Hazardous Waste (M&H) Rules 1989
amended further in 2000 and 2003 and rules made there under as amended from time to time.
• The applicant shall have to submit the returns in prescribed form regarding water consumption and shall have
to make payment of water cess to the Board under the Water Cess Act – 1974.
• Contractor proponent shall construct the pipeline and other infrastructure, and adopt safety measures as per the
standards & specification laid down by the concerned agencies from time to time.
• Contractor proponent shall comply with the Costal Regulation Zone Notification 1991 if applicable.
• Contractor proponent is required to comply with the manufacturing, Storage and Import of Hazardous Chemicals
Rules-1989 framed under the Environment (Protection) Act-1986.
• On completion of all temporary work structures, surplus materials and wastes shall be suitably disposed off.
• An Onsite-Offsite Emergency plan shall be prepared & submitted to Disaster Management Authorities under
intimation to respective state authorities.
• The contract shall act as per recommendation of the concerned authorities regarding safety measures and
OHSAS-18002.
6.0 PIPELINE BURIAL
The minimum ROW requirement for laying of pipeline shall be of 20 M width.
Pipeline burial depth shall be appropriate for the route, surface, and use of land, terrain features and external loads
imposed. In areas likely to have an increased risk of impact damage or third party interference, the pipeline shall be
buried with a minimum depth of cover as given below:-
Location Minimum Cover (m)
a) Normal terrain 1.2
b) Industrial, Commercial and Residential areas 1.2
c) Rocky terrain 1.2
d) Minor stream crossing/Canal (lined/unlined) 1.5
e) Drainage, ditches at roads/railway crossings 1.5
f) Uncased road crossings 1.2
g) Cased road crossings 1.5
h) Cased railway crossings 1.7
i) River Crossings (Below lowest scour depth) 2.5
j) HDD (Below lowest scour depth) (also see Note-ii) 2.5
k) Marshy and Creek Area 1.5
l) Terrain with Sandy clay (See Note vi) 1.2
m) Terrain with Sand Dunes (See Note vi) 1.5
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 20 of 65
n) Others 1.2
1) The minimum cover may further be increased based on the safety and risk assessment.
NOTES:
(i) Cover shall be measured from the top of coated pipe to the top of the undisturbed surface of soil or the
top of graded working strip, whichever is lower. The fill material in the working strip shall not be considered in
the depth of cover.
(ii) For river / watercourses that are prone to scour and / or erosion, the specified cover shall be measured from
the expected lowest bed profile after scouring / erosion. Where scour level is not known, the scour depth
shall be assumed at least 5 meters below the existing bed of the river/water course, except in case of Rocky bed.
The cover, as mentioned in the Table above, shall be provided in addition to this, from bottom of this assumed
scour level.
(iii) Whenever the above provisions of cover cannot be provided due to site constraints, additional protection
in form of casing/ concreting, soil bags, etc. shall be provided.
(iv) When insisted by authorities, the depth shall be maintained as per the directions of the concern authorities.
(v) For areas of brick kiln, the minimum cover of 1.5 m shall be measured from the current level or below predicted
excavation level, whichever is lower.
(vi) For terrain with sandy clay and / or with sand dunes, the minimum cover of 1.2 / 1.5 m shall be measured from
sound & compact ground level. The compact ground level shall be determined based on site data and actual site
conditions.
As per PNGRB requirements, when a cluster of buildings intended for human occupancy, indicates that a basic mile
(1600m) of pipeline should be identified as location class 2 or location class 3, the location class 2 or location class
3 may be terminated 200 m from the nearest building in the cluster on either side (i.e. at start of cluster and at end of
cluster). The boundary between location class 1 and location class 2 or location class 3 shall be at least 200m away
from the building closest to the boundary.
In case, any private dwelling, industrial building or place of public assembly falls within 15 M of pipeline,
additional cover of minimum 300 mm shall be provided over and above the cover indicated in the Table above, up
to a distance of 15 M from last building on either side
Where buried pipes come above ground, the anti-corrosion coating on the buried pipe will continue for a length of
at least 500 mm above ground.
All the details provided above are Indicative in nature. Contractor shall conduct the detailed Route Survey for details
of the proposed route including terrain, land use, crossings and other data.
7.0 DETAILED SCOPE OF WORK FOR CONTRACTOR
The scope of work detailed herein shall be read in conjunction with the Design Basis, Schedule of Rates,
Specifications including PTS and GTS, Standards, Drawings, P&IDs and other Documents/ Drawings forming part
of Tender Document.
Details of associated Civil, Structural, Architectural, Electrical, Mechanical, Instrumentation/Telecom, survey
drawings, etc. are covered elsewhere in the Tender document.
The Contractor's Scope of Work for the pipeline shall consist of, but not limited to mobilization/Demobilization, Site
Survey, locating existing pipelines & other facilities before excavation, Transportation of Company supplied free
issue materials to Worksite(s) including storage, procurement and supply of all materials (as per scope of supply),
installation, tie-in/ hook-up with existing facilities; preservation (if required), fabrication, installation, testing,
swabbing, EGP, pre-commissioning and commissioning of the new proposed pipeline systems including terminal
piping works and hook-up works at terminal along with all associated mechanical, civil, structural, architectural,
electrical, telecom &instrumentation works. Scope of work and details for Civil, Structural, Architectural, Electrical,
Mechanical, Instrumentation/ Telecom etc. are covered elsewhere in the Tender Document. All such works that are
not indicated herein below but are required to complete the work in all respects shall form part of Contractor's Scope
of Work.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 21 of 65
7.1 Site Survey &Validation:
Route Survey, Topographical / Geotechnical/ Hydrological Studies
Owner has performed the Surveys for the entire pipeline route, pipeline Crossings Surveys. These survey details are
incorporated in Alignment & Crossing Drawings enclosed with the Tender Document for reference. However,
contractor shall carry out further verification/detailing survey of available Alignment & Crossing Drawings. The
scope of work shall cover & but not limited to the following detailed surveys,
• Detailed Pipeline Route Survey: Carrying and/or verification of pipeline route surveys & detailing the same
covering topography, type of land, strata details, details of surface features and UG utilities, cadastral survey,
village maps. Any new/forthcoming crossing not identified in the crossing list but necessary for laying the
pipeline shall be surveyed.
• Topographic, Hydrographic & Geotechnical Survey for water Crossings: shall cover the extent of water
crossing, identification of HFL/Flood Plains, River bed scour depth.
• Soil Investigation for Pipeline Route: Boring/Sampling survey along the pipeline to ascertain the surface/sub-
surface strata and soil resistivity /Corrosively for Design of Cathodic Protection system.
• Topographical and Geotechnical investigation for Station plots: Includes detailing, contouring for new
station plots and extension of existing plots. The scope also includes carrying out bore logs, performing field
and lab tests for design of civil /structural foundations.
Following are included in the Contractor’s scope of work
• Collect & record all required details / information, validate information provided in DERS and update / revise
the same where required
• Visit all crossings locations and finalize type of crossings, acquaint himself well with all existing / prevailing
conditions at site and site specific requirements
• Understand the hook-up requirements with existing facilities, and
• Update alignment sheets, crossing drawings, Survey data based on the same.
7.2 Engineering:
• Residual and procurement Engineering for materials in the scope of contractor based on the tender specification
and PTS, Datasheet , QAP provided in the tender document.
• Preparations of Procedures, Fabrication & Construction drawings & Documents
• Pre-commissioning & Commissioning procedures.
• Preparation of all As-Built Drawings and Documents
• Contractor shall submit a detailed schedule for preparation and submission of drawings during the kick-off
meeting or latest within one week thereof which shall be reviewed by Owner/ Consultant.
• Contractor shall prepare and submit a complete list of drawings/documents for review by Owner/ Consultant.
• Contractor shall incorporate all the comments, if any without any cost implication. Such review by Owner/
Consultant shall, however, not relieve the Contractor of his responsibilities to comply with the requirements as
per Contract and requirements arise out of statutory permissions on grant of permission.
7.3 Procurement :
• Procurement of all bought out items required for the project and mentioned in the SOR including ordering and
supply, inspection, testing, expediting, custom clearance wherever applicable, transportation to site.
• Procurement of all Civil and Structure related supplies including steel, paving blocks, cement, bricks, etc. for
civil works
• Procurement of all items required for execution of project including consumables / non- consumables / spares
etc.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 22 of 65
• Procurement and supply of mandatory spares, special tools and tackles and commissioning spares necessary for
commissioning is also in the scope of the Contractor.
• Preservation and storage of equipment and materials in covered shed and open storage and insurances of material
including transit insurance.
• Before ordering, clearances shall be obtained from Owner/ Consultant. However, it shall be Contractor’s
responsibility to ensure that the ordering is in accordance with the data sheets, drawings, standard, specifications
and vendor list. Any item ordered which does not conform to the contractual requirements, identified at any
stage of the Project shall be rejected. Replacement/ modification and the cost impact, project delay arising out
of such rejection shall be solely on account of the Contractor.
7.3.1 Procurement Management
Contractor shall, as part of his detailed Project Execution Plan (PEP) submit a detailed Procurement Execution
strategy document which, as a minimum, shall cover the activities listed below, but shall also address all other areas
of Procurement, which the Contractor will require to be carried out to successfully execute the Work.
• Identify procurement interfaces with Owner (both Project office and field)
• Management of Owner Free Issue Materials
• Provide the following details to Owner for approval :
o Organization charts
o Procurement Procedures - including Procurement Systems, Procurement Evaluations
o Details of Sub Contracts
In Addition, The Contractor Shall:
• Ensure that all Procurement and subcontracting activities on the project are carried out in an ethical and
transparent manner.
• Procure materials and services only from those vendor listed in Owner’s Approved Vendor
• Contractor may propose additional vendor in case listed vendors are not in a position to meet the Project
requirement. Contractor proposal shall be supported by justification, including PTR of vendor, copies of
QA Plans, international certifications, technical references and other prequalification data requested.
• Carry out Technical evaluations for all equipment and materials to be purchased for the Work.
• Submit to Owner a schedule of Procurement Milestones (including any proposed subcontract activity) that
Contractor shall meet in order to support Contractor’s overall Project schedule.
• With the exception of Owner s up p l i ed Free Issue Material, Contractor shall be responsible for procurement of
all materials and equipment and services, both temporary and permanent, required to complete the Work.
• Expediting shall be carried out by Contractor in an effective and proactive manner in order to ensure timely
deliveries from suppliers adhering to Project schedule.
• Contractor shall hire Third Party Inspection Agency (TPIA) from the approved TPIA list for carrying out the
inspection at their supplier’s works as per approved QAP based on attached Data sheets / PTS / QAP /
Specifications with the tender document. TPIA charges shall be borne by the Contractor.
Spares:
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 23 of 65
• Contractor shall procure all spare parts as specified in the bid document.
• Procurement of construction, pre-commissioning, commissioning spare parts.
• Spare parts shall be suitably packed / preserved for storage in the climate at Site. The estimated storage period
shall be three (3) years. Each part shall be marked with its description and purpose and stock number on the outside
of the packaging. Packaging shall be for long term outdoor storage.
Mandatory Spares:
• Contractor shall also supply mandatory spares as indicated in the SORs attached with the Bid Package. All
associate spares shall also be supplied by the Contractor.
• This quantity shall be procured as surplus material only, not as contingency with the scope of supply.
• Mandatory Spares shall be procured and stored by the Contractor in Contractor’s store till commissioning &
subsequently the same shall be transported by the Contractor to Owner’s store.
• Storage & proper upkeep of the mandatory spares shall be the responsibility of the Contractor till it is handed over
to Owner.
7.3.2 Scope of Supply for - Pipeline Construction
This section lists the major items required to be procured for Construction of proposed Pipeline and associated Station
Facilities. The List is Indicative only, and is not exhaustive. Contractor shall identify and procure all necessary items
required for successful completion of the job, without any time and cost implications:
• Ball, Globe and Check Valves upto 2” diameter
• Transition piece, if required
• All fittings and flanges upto 2” diameter
• Station Pipes 10” and below (The pipes for all other station piping of size 10” and below, shall be LTCS Seamless
pipes of material ASTM A 333 Gr. 6. All LTCS Pipes shall be Charpy Impact tested at -45 °C)
• The wall Thickness for all Station Piping (10” and below) shall be as summarized below :
o Material for Station pipes (10” & below) : ASTM A333, Grade 6.
o Wall Thickness for Station pipes (10” & below) :
� Pipe sizes ½” to 2” NB Pipe - Schedule 160
� Pipe Sizes 3” to 10” NB - Schedule 80
The following Table summarizes the Wall Thickness and Material requirements for all Station Piping:
Thickness Summary for Station Piping
Station Pipe Detail
Location
Class
considered
for WT
Material for Station
Piping
Wall Thickness
Selected
12” NB - Mainline Pipe at Stations Class-3 API 5L, Grade X-70, PSL-2 7.1 mm
12” NB - Hot Induction Bends at
Stations Class-4 API 5L, Grade X-70, PSL-2 8.7 mm
Station Piping - 3” NB to 10” NB Class-3 ASTM A 333, Grade 6 Sch. 80
Station Piping - 1/2” NB to 2” NB Class-3 ASTM A 333, Grade 6 Sch. 160
• Fabrication of Hot Induction Bends -API 5L Gr. X 70, PSL 2 (size = 12”) as per Specifications
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 24 of 65
Pipe Thickness for fabricating Hot Induction Bends – 128” Mainline
Location of Bend Location Class of
Pipeline Route
Pipe Wall Thickness to be used,
for fabricating Hot Induction
bends #
Along Pipeline route :
12”NB Main line Location Class-1 API 5L Gr. X-70 7.1 mm
(Class-2 thickness)
12”NB Main line Location Class-2 API 5L Gr. X-70 7.1 mm
(Class-3 thickness)
12”NB Main line Location Class-3 API 5L Gr. X-70 8.7 mm
(Class-4 thickness)
12”NB Main line Location Class-4
(within Railway ‘risk radius’) API 5L Gr. X-70 9.5 mm
At Station Locations :
12” NB Hot Induction
Bends at Stations
All Stations considered as
Location Class-3
API 5L Gr. X-70 8.7 mm
(Class-4 thickness)
#Wherever required 9.5 mm thick pipes will be issued for fabrication of Hot induction bends in case of calss-1, 2,
3 also.
• Casing Pipe -API 5L Gr. B, PSL 2 (Size = 18”) with thickness indicated as below :
o For Railway Crossings - Wall thickness = 7.0 mm
o Highway / Other Cased Crossings - Wall thickness = 7.0 mm
However, the actual Wall Thickness shall be finalized, as per Railway, Highway authority & other applicable
statutory requirements & codes. Casing Pipe shall be supplied with casing vents & drains, end seals, casing
insulators,
• Continuous Concrete Weight Coated Pipes / geo textile bags, for installation at Water body Crossings, marshy
/ water logged areas / fish ponds arae, as per Specifications. However, Contractor shall have to take prior
approval of providing of concrete coating or geotextile bags as anti-buoyancy for any locations.
• Pipeline & Piping test medium (Water/air as applicable), complete with test headers, corrosion inhibitors, oxygen
scavengers, biocides & Pigs (Cleaning, gauging, swabbing & calliper pigs).
• All Consumables (including Welding & NDT Consumables, Field Joint Coating material etc.).
• OFC cables, along with 2” HDPE Duct, Jointing closures, FTC and other accessories.
• 6” Steel Casing (API 5L Grade-B, 6.4 mm thk, external epoxy coated, 500 micron thk) for housing Spare
OFC/HDPE Duct at crossings, along with required accessories.
• Pipeline markers/Warning signs, Warning tape/ribbon.
• Rock shield, Pre-cast Concrete Slabs, HDPE Sheet, trench padding/soft padding, select backfill material etc. for
Pipeline Laying
• Stud Bolts, Nuts & gaskets as per requirement
• Paint and Coatings as required for Station Piping
• All required Instrumentation and Controls for Station facilities and Pipeline
• Fire Suppression system for Control Room Building.
• Pre-cast Inspection Chambers, electronic markers and locators (for OFC).
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 25 of 65
• Supply of all Equipment’s, materials & consumables for related to Electrical/ Instrumentation/ Cathodic Protection
packages etc. as specified in corresponding PTS.
• All other items including Instrumentation and Controls, Electrical Lightings, fixtures, cables & Cable Trays, OFC
and Communication Cables, Civil construction material, structural steel, concrete slabs etc., material required for
installation of PCP and TCP etc. i.e. all material required for construction of Pipeline along with associated Station
facilities, complete in all respects, as per Tender requirements, shall all be included in EPC Contractors scope of
Supply.
• All materials for all types of pipeline markers including cement, sand, reinforcements, structural steel, etc.
• Supply of Warning Tape. The details of warning tape shall be as per PTS-Warning mats (Doc No. P.011947 D
11097 104)
• Supply of all materials (except Owner supplied materials), consumables, labour and other incidental works; return
of the surplus free issue materials to the Owner's designated stockyard(s); carrying out all temporary, ancillary,
auxiliary works, assistance for hook-up works at both end with adjacent pipeline required to make the entire
pipeline including pipeline section laid by normal open cut method,
• All safety tools, tackles, devices, apparatus, equipment etc. including ladders and scaffolding complete as required.
Other Supplies
- All Consumables required in the project (including Electrodes, Joint Coating materials etc.) & utilities whatever
are required for complete execution, testing and completion of the project.
- All civil, structural, steel material required to complete the buildings, roads, plumbing system etc.
- All Nuts, Bolts including Foundation Bolts, Galvanized Bolts, Gaskets (as per specifications), Copper jumpers
etc.
- Paint /coating for above ground and underground piping and steel structure.
Material for Electrical/Instrumentation/Civil Works:
The above list is indicative only. Contractor shall refer to other sections of these documents for Discipline wise Scope
and Work and Supply, and all required items for the project, mentioned elsewhere in this document and the Tender,
shall be included in Contractors scope of Supply.
7.4 Contractor MTO
Based on Tender requirements and Site survey / requirements, the Contractor shall prepare detailed MTO for all
items required for the Project, from the drawings, specifications, contract documents and field measurements.
Contractor shall also identify any shortfall or future potential shortfall of Owner Free Issue Materials and shall
promptly advise Owner of such shortfall.
7.5 Pipeline Construction
• Construction of 12” NB buried natural gas pipeline along with associated facilities at Dispatch station at ONGC
Bantumilli, SV station and Receiving station at Ullamparu..
• Survey and Site preparation including Cleaning, Grading, Trenching, Pipeline Laying, Backfilling & Restoration
• Pipeline Stringing, Welding, FJ Coating, Radiography and NDT testing.
• Carry out all Crossings along the route as per Project Specifications / Drawings and Tender requirements.
• Provide Special Measures such as Casing, Concrete Coating, Concrete Slabs and other Protective Measures, as
per Project Specifications & tender requirements
• Hydro testing, dewatering, swabbing, caliper pigging
• Mechanical Completion of Pipeline and all associated Station Facilities.
• Hook –up at Dispatch & receiving Terminals, as per Tender requirements.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 26 of 65
• Pre commissioning and commissioning.
• For details of activities included in Mechanical Completion, Pre-commissioning and Commissioning, Refer PTS
– Construction of Natural Gas Pipelines.
7.5.1 Details of Pipeline Construction
i. Surveying, marking-out of existing pipeline centre line and ROU width,
ii. Right of Way (ROU):Clearing /grading/cutting/filling for entire width of ROU for the new ROU.
iii. Fencing, barricading, display of appropriate warning signs/notices as applicable.
iv. It will be the responsibility of the Contractor to maintain the ROU in motorable condition until completion of
the work. The ROU damaged especially due to movement of crawler mounted heavy equipment shall be
regularly graded, levelled & sprinkled with water for dust suppression.
v. Liaisoning with Owner, villagers, land Owners and concerned authority etc. for ROU related activities shall
be in the scope of Contractor.
vi. The ROU will be provided by the Owner. It may be noted that Owner shall provide documentary evidence of
acquisition of ROU. However, Owner shall not be responsible for any obstruction/hindrance by any individual
or group in laying of pipelines by contractor. Responsibility to clear the obstruction is in contractor’s scope
without any time & cost compensation.
vii. Any extra land needed during construction beyond stipulated width of ROU, it will be the sole responsibility
of the Contractor to arrange the same and to relocate all issues (including any compensation) with the relevant
land Owner, tenant or authorities. All related cost will be borne by the Contractor.
viii. ROU may not be available in the required width in certain stretches, in such cases the work shall be carried
out in the available ROU width. Any additional working strip if required shall be arranged by contractor with
no cost to Owner.
ix. If pipeline to be laid in the limited space of restricted ROU, if required soaring to be carried out by the
contractor to lay the pipeline at the required depth.
x. Removal and reinstatement of construction survey markers as installed by survey agency engaged by Owner.
Installation of ROU boundary markers for new ROU.
xi. Top-soil preservation: Contractor shall have to preserve top soil dug and shall be restored to original condition
on completion of the work. The top-soil excavated during trenching /stripped during grading for entire width
of ROU shall be stored separately to avoid mixing with subsurface strata and reused for reinstatement at later
stage.
xii. Controlled rock blasting if required (Refer PTS/GTS - Controlled rock blasting).
xiii. Trenching in all types of soils & strata (sand/clay/rock, soft/hard etc. complete) to the design depth and width
and in all types of terrains (flat/undulating/sand-dunes etc. complete with side-cutting, as required).
xiv. The Contractor shall exercise extreme caution while trenching/excavation in areas, where possibility of
presence of other pipelines/utilities in the ROU is expected / indicated in documents / drawings /survey data.
This may also involve manual trenching/barricading/trench wall protection/shoring as well as trenched-spoil
management to enable access/inspection/maintenance of existing utilities
xv. Hauling & Transport of Bare/Coated line pipes from the different Owner store to Contractor’s pipe storage
yard.
xvi. Transportation of Pipes to site for laying. Complete repairs to damage of the line pipe coatings after transfer
of Pipes to site, as per the Owner approved repair and QA/QC procedures.
xvii. Stringing of line pipes, cold & hot bends (side/sag/over type) edge preparation aligning, fit-up,
cutting/bevelling, and as required.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 27 of 65
xviii. Cold Field Bending: Provide cold bending equipment at the on-site locations. The Contractor shall
arrange/mobilize the pipe bending machine of adequate size and capacity for fabrication of cold-field-bends,
as required.
xix. Contractor shall provide concrete coating or geotextile bags as anti-buoyancy based on prior approval from
PMC / Owner.
xx. Complete all cold bends using 12” Coated line pipe.
xxi. Idle time preservation by filling Nitrogen at a positive pressure of 2 bar (g) as per specification, if required,
including supply of Nitrogen.
xxii. Induction Bends: Fabrication, shifting, testing, coating/painting of Induction bends using bare 12” line pipes.
xxiii. Carrying out Welding ONLY as per WPS (Welding Procedure Specification) duly approved by
Owner/Owner’s representative
The brief scope covers manual welding of all types (root pass, filler pass, reinforcement welds, as applicable)
and all methods (electric arc/TIG/MIG etc. as applicable) as per approved documents and approved
welder/welding qualifications requirements (WPS/WQT) including welding of all
types/sizes/rating/edge/material of pipes/fittings/flanges/valves etc. as applicable.
The welding works shall also include the applicable weld-spool protection against external environment
(air/moisture/dust/wind/rapid cooling etc.) by provision of surrounding flux and/or controlled environment
(welding chambers/thermal blankets), as applicable. If required, the welding works shall also include pre-
treatment/pre-heating/drying of welding electrodes to avoid damage to electrodes due to environmental
degradation. The welding works shall also include stress-relieving of weld/parent metal, as required.
xxiv. 100% Non-Destructive-Testing (NDT) of welds including providing all types of
consumables/equipment/testing facilities. The inspection and test results of the NDT of welds shall be
evaluated/recorded and the Contractor shall remove/rectify the defects, as applicable.
xxv. Safe and licensed storage and movement of radiographic material including radio isotopes / cameras etc. for
field radiography jobs under statutory regulations including safe disposal.
xxvi. Cutting/removal of defects, re-working, as approved by Owner.
xxvii. Surface preparation for application of external Field Joint Coatings (FJC).
xxviii. External Field Joint Coating (E-FJC) of the girth welds including provision of all
equipment/consumable/resources. The external field joint coating shall include a proven system (e.g. heat
shrink sleeves) to ensure its effectiveness for the design life of the facilities and compatible with the adjoining
steel/anti-corrosion coatings and operating parameters. The Contractor shall evaluate and submit the proposal
for the proposed external field joint coating system for approval of the Owner.
xxix. External Field Joint Coating of anti-buoyancy type (Concrete Weight Coating) for the applicable sections of
water/MFL crossing.
xxx. Inspection of trench (trench bottom/side walls) to ensure that it is free from sharp objects which may damage
the pipelines/coatings. The trench inspection shall also cover the levelling of the trench bottom to avoid any
free spans in the pipeline. Any such anomalies shall be corrected before lowering-in so as to have continuous
resting of pipeline in the trench.
xxxi. Providing soft/sand padding as required to required depth and extent.
xxxii. Holiday detection and repair of damaged coating of pipelines prior to lowering.
xxxiii. Lowering of pipeline inside the trench including Tie-ins / jointing of either ends at the respective crossings so
as to make the pipeline continuous complete with external field joint coatings at such locations.
xxxiv. Laying of Optic Fibre Cable (OFC) buried in the same 12” pipeline trench complete with jointing of ends so
as to make it a continuous cable. The jointing testing, Commissioning and termination of OFC cable shall be
as per approved scheme.
xxxv. Installation of warning tapes. The size/material of tape and the information to be inscribed shall be approved
by Owner.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 28 of 65
xxxvi. Backfilling the trench to required depth and compactness including backfilling with special/select/engineered
back-fill material at specific locations as may be required (e.g. station approach, fault crossings etc.). The
backfilling shall be performed uniformly in layers to ensure continuous backfill free from voids and pockets
which could be potential harmful leading to subsidence and collapse of backfill. The backfilling shall be
provided in such a manner that it leaves a reinforcement crown at the top of the trench to allow for future
settlement of the backfill. The top layer of the soil which was earlier stored separately for re-use, shall be
replaced while backfilling the top layers of trench. The surplus material shall be removed from the site and
disposed-off appropriately.
xxxvii. For Backfilling in rocky areas, Contractor to propose the innovative / mechanized solution such as padding
machines for carrying out loading, crushing screening of excavated material. (viz. ALLUVIAL BUCKET or
equivalent)
xxxviii. Backfilling in Seismic Areas shall be as per provision given in the PTS_ Construction of natural gas pipelines.
xxxix. Install all Pipeline signage and markers: Fabrication & Installation of new Pipeline markers as per Alignment
sheets & as per specifications.
xl. Testing & Pre-commissioning of 12” Cross-country pipeline and associated Above Ground Installations shall
be carried out as per Hydrotest Procedure and Pre-Commissioning plan as proposed by contractor and duly
approved by owner/Owner’s representative. The Brief scope of Hydrotest shall be as below,
• Installation of test headers for the fabricated assemblies/sections at the crossings as well as for continuous
pipeline sections complete with associated pumping equipment with adequate capacity to pump the test water
to required pressure/duration, pressure and temperature recorders and associated instruments.
• The Contractor shall prepare all documents/drawings/reports/sketches/procedures/method statements for
cleaning/flushing/gauging/filling/hydrotesting/dewatering / Swabbing of the pipeline complete with
identification/repair/rectification of leaks and bursts and submit for Owner approval prior to performing such
activities.
• The Underground pipeline sections shall be hydrotested after backfilling only. Cleaning, flushing of the
pipeline for removal of construction debris, gauging to ensure the pipeline free from any anomalies
(dents/buckles etc.) and to have an unobstructed pigging run.
• Filling the pipeline/piping sections with test water duly mixed with approved dosages of corrosion
inhibitors/biocides/oxygen scavengers.
• Hydrotesting of the pipeline/piping sections to the required test pressure/duration including holding the
pressure for specified duration. (Separate 24 Hours Hold duration for Strength and Leak Tests) Inspection
during test and repair/rectification of leaks/defects as per Hydrotest Specifications (PTS: Construction of
Natural Gas Pipeline).
• Dewatering/Swabbing of Hydrotest water after successful hydrotesting, removal of test apparatus and
appurtenances and making the pipeline system ready for tie-in/hook-up/jointing with the respective
sections/pre-commissioning.
xli. During Hydrotesting gauge plate to be inserted to ascertain the geometrical deformation of the pipeline. During
Pre-commissioning a gauging electronic device (GED) will be used to ascertain the physical integrity of the
pipeline.
xlii. In addition to above, all above ground/ underground piping of terminals (despatch/receipt) & SV station shall
be pneumatically tested with nitrogen at 7 bar (g). Functional test of valves shall also be carried out during
pneumatic testing. The contractor shall lay, test, clean and dry the pipeline before inserting (SV) or connecting
the natural gas stations to the main pipeline.
xliii. Golden-Tie-ins: All natural gas stations will be tested, cleaned, dewatered and dried prior to be golden tie-in
joints with the pipeline.
xliv. Hook-up/tie-in of the buried/above ground system so as to make the system continuous for pre-commissioning.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 29 of 65
xlv. Any modification works required at the stations : The modification work refers to possible modifications to
existing structures which may be required for Hook-up, installation and construction of proposed Pipeline
system, or as a result of statutory requirements if any.
xlvi. Final Drying shall be carried out using the continuous supply of super-dry air (having temp. significantly below
dew point) with the repeated cycle of operations from one scrapper trap to another till the pipeline is dried up
to acceptable conditions of -8 degree C.
xlvii. Nitrogen Purging (Inertization) shall be carried out if the final drying is achieved by using the super-dry air.
Contractor shall submit the Final Drying & Inertization procedure in line with bid specifications and Owner’s
guidelines.
xlviii. Pre-commissioning Audits: Contractor shall participate and provide all assistance to Owner for carrying out
Pre-commissioning Audits. The scope of contractor also includes closure/compliance of all audit observations.
Any alteration in design/ modification in already constructed facility if necessitated by statutory authorities
shall be carried out by Contractor without any additional cost implication to Owner.
xlix. Commissioning and Gas-in: Contractor scope shall include commissioning of pipeline from DT to RT station.
l. Carrying out Magnetic Cleaning (pigging with the help of magnetic pig to remove steel debris), Electronic
Geometric Pigging (EGP).
li. Carrying out repair of all defects found during Electronic Geometric Pigging including locating, digging,
cutting, welding, NDT, etc.
lii. Restoration/Reinstatement: Reinstate & make good all areas used for Construction, Storage, and transportation
purposes to original condition. Contractor shall reinstate the entire ROU. Reinstatement shall be performed in
accordance with all measures and recommendations as well as the Project HSE Construction Requirements
and specific requirements stipulated by the regulatory authorities / government bodies.
7.5.2 Crossings
Where HDD is required, the Contractor shall be responsible for complete design of HDD Crossing including
performance of requisite surveys, performing of calculations, profiling, pull load calculations and hook-up of the
crossing pipe on upstream and downstream. Any additional land required for execution of HDD shall be in the firm
scope of contractor.
The change of Crossing Methodology especially for Major river/canal crossing (from open-cut to HDD) is subject to
approval from Owner/PMC and does not entitle contractor for claiming any additional time and cost implications.
The Contractor is deemed to have made due provisions in his bid for all such works.
a. Foreign Pipeline Crossing
In case any existing pipeline needs to be crossed, the new pipeline shall be laid at least 500 mm below such
existing pipeline, and a physical barrier in the form of 80 mm thick concrete slab shall be provided. The existing
pipeline shall be properly supported during and after the construction.
b. Over Head Power Transmission Line Crossing
Where overhead Power Transmission line equal to and above 11KV and less than 66KV needs to be crossed,
plastic grating of minimum 6 mm thickness shall be provided. For 66 KV and above power line crossings,
concrete slab of thickness 100 mm shall be provided over pipe trench.
c. The supply & installation of all special measures at Crossing such as Concrete Coating, Concrete Slabs, Gabions,
Casing Pipes, Steel Conduit, HDPE Sheet, Gabion wall / Gabion mattress etc. shall be carried out as per
approved Crossing methodology and shall be the scope of contractor.
d. The details shown in crossing list such as Crossing methodology, Overall Crossing length, quantity of special
measures are indicative. However, contractor is required to carry out detailed survey, obtain local information,
verify geotechnical/hydrological soundings and submit the working drawing based on detailed engineering
before the start of crossing execution.
e. Contractor shall note that the “Limits of Crossings” shall be as per the crossing width finalized after detailed
survey by Contractor and as approved by the statutory authorities/Owner/PMC. The “Limits of Crossings” shall
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 30 of 65
broadly include the “Width of RoW of the facility to be crossed + Installation Allowances + any additional
length as suggested by the authorities”. Execution of crossings within the approved “Limits of Crossings” will
constitute firm Scope of Work of Contractor.
f. Pre-Hydrotesting/ Post-Hydrotesting of pipeline section as per bid specification for major
River/Waterway/Canal Crossing and all Cased Crossing shall be in scope of contractor.
g. Since the crossing activities are to be started immediately, the acquisition of Land/ Approach if required to
crossing locations and additional working strip to be acquired by contractor without any extra time and cost
implication. The contractor shall not insist on opening of ROU for crossing.
h. After crossing construction, the site shall be restored to the satisfaction of authorities having jurisdiction & NOC
to be obtained from respective authorities.
i. Installation of spare 6” CS conduits, HDPE duct & OFC for the entire Crossing length at all crossings executed
by Boring & Casing, for the purpose of future use by Owner. Accordingly, the Contractor shall implement
additional trenching/backfilling works and/or trenchless construction and associated works at such locations for
installation of spare casings/conduits/ducts while maintaining the specified gaps.
j. After crossing execution, the spare conduits, duct & OFC shall be adequately cleaned, preserved and capped at
the ends. Contractor shall supply and install the pre-cast chambers and electronic locator for the termination of
6” CS conduits, HDPE & OFC at crossing extremities (beyond which the pipeline follows the normal cover).
7.5.3 Cathodic Protection (CP)
a. Key deliverable
Supply &Installation of TCP and PCP system for 12” NB x approx.. 38 km Natural gas Pipeline from ONGC
Bantumilli to Ullamparu including requirements at Station facilities, as per Project specifications and Tender
requirements.
b. Scope Of Work
• TCP (Temporary Cathodic Protection): Scope of work includes Survey, Design Supply, Installation, Testing &
Commissioning of TCP including all civil works associated with CP i.e. cable trenches, foundation for equipment
and all test stations. (Refer PTS: CP for detailed scope of work).
• PCP (Permanent Cathodic Protection) : Scope shall include collection of Cathodic protection related data along
right of use, design, detailed engineering, supply of materials, Computerized Test Station unit (CTSU), quality
assurance (QA) and quality control (QC), installation, testing and commissioning of PCP system. Bonding of the
pipeline to the existing pipelines if applicable, interference detection, mitigation, post-commissioning survey such
as such as CIPL (computerized on & off) and coating conductance measurements along the pipeline ROW,
followed by Pearson survey along the ROW & DCVG (for defect classification) at defect locations indicated by
Pearson & CIPL & AC/DC interference survey surveys. Contractor has to hand over the interference free PCP
system to Owner as per the specification. (Refer PTS: CP for detailed scope of work).
For Details, Please refer to the following:
1. Design Basis – Cathodic Protection (CP) – Doc No : P.011947 E 11017 102
2. PTS – Cathodic Protection (CP) – Doc No : P.011947 E 11017 101
7.6 Scope Of Work - Station Facilities
Total 3 number (Despatch. SV and Receiving) stations are required to be developed for proposed pipeline project
which are hereunder. Station-wise facilities are as under,
At Despatch terminal (ONGC Bantumilli)
• Construction of Dispatch Terminal, along with all associated station piping and facilities at ONGC Bantumilli, as
per drawings, specifications (PTS & GTS) & design basis including :
o Hook-up with 12”existing tap off Point available in ONGC premises with 200 mtr piping and supports
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 31 of 65
o Supply (in Contractor’s scope) &Installation of all associated Valves with /without Actuators as per PIDs
o Supply (in Contractor’s scope) &Installation of all Station Piping with Fittings and Flanges, Stud, Bolts &
Gaskets
o Installation of all free issue skids, IJs and Pig Launcher with Pig handling system
o Integration of with the overall Station Piping.
o All associated works including required Civil, Mechanical, Electrical with Cathodic Protection ,
Instrumentation & Control, Cathodic Protection work and associated activities required for successful
completion of the project.
At SV Station :
• Construction of following sectionalizing Valve (SV)stations as per drawings, specifications (PTS & GTS) &
design basis with all associated facilities and Tap Off Points (TOPs) as listed below : a
o Supply (in Contractor’s scope) & Installation of all associated Valves with /without Actuators as per PIDs
o Supply (in Contractor’s scope) & Installation of all Station Piping with Fittings and Flanges, Stud, Bolts &
Gaskets
o Integration of with the overall Station Piping.
o All associated works including required Civil, Mechanical, Electrical with Cathodic Protection ,
Instrumentation & Control, Cathodic Protection work and associated activities required for successful
completion of the project.
At Receiving Terminal (Ullamparu) :
Construction of Receiving Terminal, along with all associated station piping and facilities at Ullamparu as per
drawings, specifications (PTS & GTS) & design basis including:
o Hook-up with existing 18” dia existing pipeline by providing of barred / flow tee after shut down.( During Shut
down / installation of barred tee with existing 18”pipeline, Contractor to supply all the required materials,
tools & tackles, consumables including Nitrogen for purging & coating materials for underground installations
, equipment / machineries including cold cutter, manpower etc in scope of contractor)
o Supply (in Contractor’s scope) & Installation of all associated Valves with /without Actuators as per PIDs
o Supply (in Contractor’s scope) & Installation of all Station Piping with Fittings and Flanges, Stud, Bolts &
Gaskets
o Installation of all free issue skids, IJs and Pig Launcher with Pig handling system
o Integration of with the overall Station Piping.
o All associated works including required Civil, Mechanical, Electrical, Instrumentation & Control, Cathodic
Protection work and associated activities required for successful completion of the project.
Similarly, Contractor shall provide full co-operation and support for Integration of the new Piping Installations
with existing systems / installations.
7.6.1 Key Deliverables- Station wise
At Despatch terminal (ONGC Bantumilli)
a. Construction of Dispatch Terminal, along with all associated station piping and facilities at ONGC Bantumilli,
as per drawings , specifications, design basis and Tender Requirements, including supply ( in Contractor’s scope)
& Installation of all associated Valves, Station Piping, IJs, Skids (FIM by Owner) and Pig Launcher/Receivers
b. All associated works including required Civil, Mechanical, Electrical, Instrumentation & Control, Cathodic
Protection work and associated activities required for successful completion of the project.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 32 of 65
At SV Station :
a. Construction of sectionalizing Valve(SV)stations, with all associated facilities and Tap Off Points (TOPs), as per
drawings , specifications, design basis and Tender Requirements, including supply( in Contractor’s scope) &
installation of Valves & all required Piping items at each location.
b. All associated works including required Civil, Mechanical, Electrical, Instrumentation & Control, Cathodic
Protection work and associated activities required for successful completion of the project.
At Receiving Terminal (Ullamparu) :
a. Construction of Receiving Terminal, along with all associated station piping and facilities at Ullamparu as per
drawings , specifications, design basis s and Tender Requirements, including supply( in Contractor’s scope) &
Installation of all associated Valves, Station Piping, Skids (FIM by Owner ), IJs and Pig Launcher/Receivers.
b. All associated works including required Civil, Mechanical, Electrical, Instrumentation & Control, Cathodic
Protection work and associated activities required for successful completion of the project.
c. The scope includes the modification and extension of existing control room building.
7.6.2 Station-Wise Discipline Wise Scope Of Work
The Scope of Work for Station facilities has been further divided in the following Sections, based on
Disciplines, for clarity & better understanding:
a. Civil Scope of Work
b. Piping and Mechanical Scope of Work
c. Electrical Scope of Work
d. Cathodic Protection System Scope of work
e. Instrumentation & Control Scope of Work
Please refer the relevant sections for Details on Scope of work for each Discipline. These sections will follow.
7.6.2.1 Civil - Scope Of Work
The purpose of this document is to provide basis of design / design criteria for detailed design the buildings, pipeline
supports & various facilities needed for different types of stations. This design basis covers general requirements and
conditions needed for the design of architectural works, reinforced cement concrete structures & structural steel
works for different facilities to be built at each station. However, all the structures will be designed for satisfactory
performance and intended usage.
The scope of major civil /structural/ Architectural works including supply and installation at each station are
given in the table 7.6.2.1
Table 7.6.2.1: civil /structural works at each station
S.NO. STATION SCOPE
• Layout Plan
• Topographical & contour Survey, soil investigation.
• Plot area of Clearing and stripping
• Site grading, Cutting & filling ( Earth and Sand), green
Belt development & Signage
• Structural materials including steel etc.
• Architectural materials
• Control room building with RO system
• Guard room
• RCC Pavement
• Boundary wall with Concertina fence
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 33 of 65
1.0
DESPATCH STATION
(Ullamparu)
• Earthworks, RC works etc.
• Process area with pipe & valve support, Gavel Filling/
RCC Pavement
• Approach and internal RCC roads & Footpaths
• Transformer area development with chain-link fencing
and Gravel filling
• DG foundation with shed
• Pig Launcher / Receiver, Pig handling system along with
Jib Crane foundation
• Skids foundation ( whichever applicable)
• Inspection chamber, septic tank & soak pit
• Footpaths
• Box / pipe culverts
• Boundary wall, chain link fencing
(if required near transformer or other equipment)
• Bore well
• U/G RCC water tank and HDPE Water Storage Tank
• Water drainage system (Storm Water Drain)
• Sewerage System
• Drinking water system with uPVC pipe and fittings
• Main gate (sliding) & wicket gate
• ERC / IRC
• Valve Operating Platforms and Crossovers.
• cable trenches
• Recharge well & Water harvesting system
• Raw Water System for Horticulture
• Windsock
• Door / windows
• Rubble Pitching
• Painting
• Misc. RCC work
• Disposal of Surplus earth
• Restoration of Civil works at Gas-in / Source facilities
• Misc work
2.0
SV STATION (at ch
21.6 KM)
• Layout Plan
• Topographical & contour Survey, soil investigation.
• Plot area of Clearing and stripping
• Site grading, Cutting & filling ( Earth and Sand), green
Belt development & Signage
• Structural materials including steel etc.
• Architectural materials
• Control room building with RO system
• Guard room
• RCC Pavement
• Boundary wall with Concertina
• Earthworks, RC works etc.
• Process area with pipe & valve support, Gavel Filling/
RCC Pavement
• Approach and internal RCC roads & Footpaths
• Transformer area development with chain-link fencing
and Gravel filling
• DG foundation with shed
• Inspection chamber, septic tank & soak pit
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 34 of 65
• Footpaths
• Box / pipe culverts
• Boundary wall, chain link fencing
(if required near transformer or other equipment)
• Bore well
• U/G RCC water tank and HDPE Water Storage Tank
• Water drainage system (Storm Water Drain)
• Sewerage System
• Drinking water system with uPVC pipe and fittings
• Main gate (sliding) & wicket gate
• ERC / IRC
• Valve Operating Platforms and Crossovers.
• Cable trenches
• Recharge well & Water harvesting system
• Raw Water System for Horticulture
• Windsock
• Door / windows
• Rubble Pitching
• Painting
• Misc. RCC work
• Disposal of Surplus earth
• Restoration of Civil works at Gas-in / Source facilities
• Misc work
3.0
Receiving Station at
Ullamparu
• Layout Plan
• Topographical & contour Survey, soil investigation.
• Plot area of Clearing and stripping
• Site grading, Cutting & filling ( Earth and Sand), green
Belt development & Signage
• Structural materials including steel etc.
• Architectural materials
• Control room building with RO system
• Guard room
• RCC Pavement
• Boundary wall with Concertina fence
• Dismantling of existing Boundary wall
• Earthworks, RC works etc.
• Process area with pipe & valve support, Gavel Filling/
RCC Pavement
• Approach and internal RCC roads & Footpaths
• Transformer area development with chain-link fencing
and Gravel filling
• DG foundation with shed
• Pig Launcher / Receiver, Pig handling system along with
Jib Crane foundation
• Skids foundation ( whichever applicable)
• Inspection chamber, septic tank & soak pit
• Footpaths
• Box / pipe culverts
• Boundary wall, chain link fencing
(if required near transformer or other equipment)
• Bore well
• U/G RCC water tank and HDPE Water Storage Tank
• Water drainage system (Storm Water Drain)
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 35 of 65
• Sewerage System
• Drinking water system with uPVC pipe and fittings
• Main gate (sliding) & wicket gate
• ERC / IRC
• Valve Operating Platforms and Crossovers.
• cable trenches
• Recharge well & Water harvesting system
• Raw Water System for Horticulture
• Windsock
• Door / windows
• Rubble Pitching
• Painting
• Misc. RCC work
• Disposal of Surplus earth
• Restoration of Civil works at Gas-in / Source facilities
• Misc work
• Miscellaneous works such as breaking and making good the existing roads; RCC works etc. wherever
pipe/electrical/instrumentation cable crossings are envisaged. Dismantling of existing masonry structures,
concrete and steel structures, road, fence & other related civil structures in such a fashion that site becomes
suitable for construction activity. All trees to be cut & stems uprooted from the site after obtaining approval
from statutory body.
• All the associated Equipment Foundations & Civil / Structural works will be carried out as per the relevant
standard specifications listed in General Technical Specifications.
• Please refer Drawings, design basis, PTS and GTS provided with the tender for details for detailed scope of
work.
7.6.2.2 Station Piping & Mechanical - Scope Of Work
a. Key Deliverables
• Dispatch station (ONGC Bantumilli): The Gas shall be taken from ONGC Terminal existing Tap-Off Valve
available at ONGC terminal. The Following Equipment/Facilities are planned at ONGC Bantumilli Dispatch
Station :
i. The Pipeline is a Piggable Line. Accordingly, Pig Launcher to be installed at Dispatch Station for
Launching the Pigs.
ii. Hook-up Piping: Hook-up Piping from existing 12”Tap-Off valve including 200 mtr piping from GAIL
Despatch station to ONGC terminal upto the inlet of proposed 12” Pipeline, near Pig Launcher area.
iii. Associated Piping and Station Work: All Associated Piping and station works.
• Sectionalizing Valve (SV) Station : SV Stations shall be provided with bypass and venting arrangement. The
Following Equipment/Facilities are planned at SV Stations :
i. Sectionalizing Valve: Sectionalizing Valve with Bypass. The SV will be a Remote Operated, Gas Over
Oil Actuated (GOOAV), Full Bore Ball Valve, with Double Block and Bleed Arrangement and
Equalizing / Bypass Line.
ii. Associated Piping and Station Work : All Associated Piping and station works.
• Receiving station (Ullamparu) : The Gas supplied through 12” Pipeline shall be received at Ullamparu Station,
which will be the ‘Receiving Station’ for the Pipeline. Here, the Pipeline shall be hooked-up to a metering which
in turn will feed the gas to existing 18”Pipileline. The Following Equipment/Facilities are planned at Ullamparu
Station, as part of this Project,
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 36 of 65
i. Pig Receiver: The Pipeline is a Piggable Line, a Pig Receiver is to be installed at Receiving Station,
Ullamparu for receiving the Pigs after Pigging Operation.
ii. Hook-up Piping: Piping from proposed 12” pipeline shall be hooked-up to the Metering, which in turn will
supply the gas to 18”Existing pipeline..
iii. Associated Piping and Station Work: All Associated Piping and station works.
• Future Tap off Points (TOP): 3 Nos. 12” NB Tap Off Points (TOP) shall be provided on the pipeline, 1 at
SV station, and 2 nos at Ullamparru Receiving Station, (one for future connectivity, and the other for future
interconnection of 12” and 8” pipelines running parallel to 18” Pipelines for future connectivity.) The Tap Off
Points shall be provided from the 12” Main-Line. Both the Tap-off valves shall be provided in the non-piggable
portion of station piping, to ensure Piggability of the 12” mainline. The Tap-offs valves shall be 12” NB Full
Bore Ball Valve with Blind Flange installed at the Downstream. This shall be used for future connectivity /
interconnection of the Pipeline.
Contractor shall provide full co-operation and support for Integration of the new Piping Installations at
stations with existing systems / installations.
b. Detailed Scope Of Work – Piping & Mechanical
i. Receiving and taking over of Owner’s supplied free issue materials. All cost incurred in taking deliveries,
unloading/handling/storage etc. shall be in scope of contractor.
ii. Installation of all ‘Free Issue’ items as per the installation requirements, under the supervision of
PMC/Owner.
iii. Delivery of all items and consumables in Contractor’s scope including Welding Consumables, Fasteners,
Gaskets, foundation bolts, holding down bolts/nuts etc. complete at worksite including
loading/unloading/handling/hauling/inspection/storage/safe management etc. complete. The items shall be
protected from corrosion/environmental degradation.
iv. Preparation of shop/assembly& Isometric drawings Preparation of drawings/sketches for proposed
Hydrotest packs.
v. Pre-fabricate pipe work for all Above Ground Installations. This is required exclusively for Installation of
piping for SV stations.
vi. Measurement/cutting/edge & surface preparation/fabrication and welding/ 100% NDT and other
inspections/testing, as applicable, of piping spools and runs, complete with associated testing and removal
of defects.
vii. Erection of piping / mechanical items and equipment including erection/installation of all equipment
&accessories/mountings, erection of package items/skids, construction/installation of scraper
launcher/receiver, pig handling systems, actuated and non-actuated valves and equipment and all such
items included in the Scope of Work, Approved for Construction (AFC) drawing and as required for project
completion.
viii. Cutting/removal/reinstallation/reinstatement of designated piping and utilities so as to ensure applicable
hook-up & tie-ins. The Contractor shall minimize the waste/scrap. The cut/removed/disused/waste/scrap
material shall be removed from the site as instructed by Owner’s Representative.
ix. Hook-up at the designated battery limits with existing facilities/utilities/facilities to be installed by others.
x. Cleaning/flushing of piping and conducting all types of pneumatic/hydrostatic tests as per approved
procedure/pressure/duration/acceptance criteria including provision of all test equipment and consumables
and safe disposal of test medium after testing.
xi. In addition to above, all above ground/ underground piping of terminals (despatch/receipt& SV station
shall be pneumatically tested with nitrogen at 7 bar (g). Functional test of valves shall also be carried out
during pneumatic testing.
xii. All types of coating painting works including coating painting of piping, support structure, equipment,
buildings, boundary walls, gates & fixtures etc. complete with provision of associated materials/resources.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 37 of 65
xiii. Hook-up/tie-in of the buried/above ground piping system with existing Piping Systems, as per Tender
requirements, complete with Instrumentation& Controls.
xiv. Successful testing/pre-commissioning/commissioning of Pipeline system along with Station facilities in
the Scope of Work of Contractor.
xv. Reinstatement/Correcting/mitigating the damage to third party utilities/facilities while construction of
facilities forming part of this CONTRACT including displacing/reinstallation of all kinds of utilities &
obstructions as per requisite approvals and to the satisfaction of authorities having jurisdiction is included
in firm Scope of Work of Contractor.
xvi. Construction of above ground sections of the pipelines (from above/below ground transition point to further
upstream/downstream sections of piping until hook-up with existing/proposed facilities) including
installation of inline appurtenances (insulation joints/isolation valves/actuators etc.) complete with
associated civil/structural/electrical/instrumentation/control works. The corrosion protection coating of the
buried pipelines/piping shall extend (~ 1.0 m) in the above ground section to militate against wear/tear due
to displacements.
xvii. Contractor shall also carry out restoration work which has been dismantled / damaged during work such as
RCC pavements, shifting / relocation of Electrical / Instrumentation cabling, etc. including re-testing. Re–
Commissioning of such equipment/facility to the satisfaction of Owner is in scope of Contractor.
xviii. The scope of works also includes providing necessary manpower &equipment for commissioning.
Please refer Drawings, PTS and GTS provided with the tender for details for detailed scope of work.
7.6.2.3 ELECTRICAL - SCOPE OF WORK
A. GENERAL:
The Owner shall arrange the power supply from State Electricity Board (SEB) at each station however, liasioning and
approval part with SEB to be executed by contractor. SEB shall install and supply the power through Distribution
transformer up to each station.
Distribution Transformer shall be provided by State Electricity Board (SEB) and liaisoning activities for station’s
Power supply shall be done by EPC contractor.
The contractor shall supply, lay & terminate 1.1 KV grade power & control cable from SEB pole mounted transformer
to SFU (bidder to supply) to MEDB, including Earthing of all SEB supplied equipment.
Note- EPC/Contractor shall check and confirm at site for the existing transformer (SEB)/Fuse capacity whether it is
capable to cater new developed control building & process area’s electrical load for Ullamparu Receiving station. If
existing SEB facility are suitable existing feeders shall be utilized with permission of Owner. If the existing SEB
facility not capable to cater new electrical load new connection shall be taken by state Electricity Board (SEB).
Design, detailed Engineering of whole Electrical system and approval from PMC/client representative Including
formulae used, design calculations, BOQ, Technical Specifications and Job/Commissioning Methodology, Data
Recording Formats, Quality Assurance Control [QA/QC] methodology.
• Supply, installation, Testing and commissioning of SFU, MEDB, DG Set with AMF panel/Control panel as per
the tender specification. Contractor shall also responsible for interconnection cable laying between MEDB to
DG Set & AMF Panel/Control panel.
• Supply, installation, Testing and commissioning of Parallel Redudant UPS system with UPSDB and Battery
bank (2x50%- Two source of battery bank) as per the tender specification. UPSDB shall have special provision
for converting of 48 V and 24 V DC supply for instrument load. Refer SLD for further details.
• Supply, installation, Testing and commissioning of Indoor lighting system with Indoor lighting DB/Switch
socket DB/ACDB/Inverter for critical lighting/ LED lighting fixtures/switch socket /wiring & conduiting
/exhaust and ceiling fans etc. Refer PTS Electrical Package for further detail.
• Supply, installation, Testing and commissioning of Five star 1.5 Ton split AC with outdoor compressor unit.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 38 of 65
• Supply, installation, Testing and commissioning of Outdoor lighting system with Outdoor lighting DB/LED
lighting fixture for safe area /Hazardous area with 4.5 meter,9 meter & 11 meter lighting pole /Junction box.
• Supply, installation, Testing and commissioning of indoor earthing system & Outdoor earthing system with
plant /control building’s lightning protection system. Refer earthing layout for further details.
• Supply, installation/laying, Testing and commissioning of all Power & Control cable with required all
accessories like cable glands/copper lugs/ ferruling /route marker /WARNING TAPE/Cable tiles or bricks inside
& outside of control building /Process area.
• All civil works associated with the complete Electrical work shall be included in the scope of contractor. This
shall include providing cable trenches, Buried cable trenches/backfill /DG Set & AMF Panel/control panel’s
shed or foundation for Electrical equipment etc.
• Supply, installation of Structural steel, cable trays, other miscellaneous items etc.
• Electrical work associated at all the stations shall be consisting of (but not limited to):
� All cable work including earthing and system ground earth associated with the installation of the supplied
equipment.
� Any temporary electrical works associated with the installation and commissioning of the system.
� Testing and certification of all electrical works.
� Supply of mandatory spares as per below:
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 39 of 65
Sr.
No. tem description Unit Quantity
ELECTRICAL SPARES
E.1
Spares for UPS (One set for each UPS as supplied for DT at Bantumilli Station , SV-1&
RT-Ullamparu are to be supplied)
(Note- Quantities mentioned against each item are for one set only)
1 System Control Card of each type Nos. 1
2 SMPS Card of each type Nos. 1
3 1-phase Charger Card of each type Nos. 1
4 Gate Drive Card of each type Nos. 1
5 Thyrsitor (Charger) of each rating and each type Nos. 1
6 Thyristor (Static Switch) of each type Nos. 1
7 DC capacitor of each rating and each type Nos. 1
8 AC capacitor of each rating and each type Nos. 1
9 Free Wheeling Diode (Charger) of each rating and each
type Nos. 1
10 IGBT of each rating and type Nos. 1
11 Rectifier Input Fuses (Fast acting) of each rating and
each type Nos. 1
12 DC Fuses of each rating and each type Nos. 1
13 By pass fuses of each rating and each type Nos. 1
14 Choke of each rating and each type Nos. 1
15 Cooling Fan Nos. 1
16 Indication LED Lamp of each type Nos. 1
0
E.2
Spares for DG Set (One set for each DG Set as supplied for DT at Bantumilli Station ,SV-
1 and RT-Ullamparu are to be supplied).
(Note- Quantities mentioned against each item are for one set only)
1 Generator relay each type and each make Nos. 1
2 DVR- all control card of each type Set 1
3 Automatic Voltage Regulator of each type Nos. 1
4 Engine Safety -- for Lube oil Nos. 1
5 Rotating Rectifier Assembly with surge suppressor set 1
E.1.4
Spares for Electrical Switch Board / MEDB (One Set for Each Switch Board / MEDB as
supplied for DT at BANTUMILLI Station, SV-1 and RT-ULLAMPARU are to be
supplied).
(Note- Quantities mentioned against each item are for one set only)
1 MCCB of Each Rating Nos. 1
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 40 of 65
�
•
2 Power Contactor of Each Rating Nos. 1
3 Indicating lamp of each type Nos. 1
0 4 Push button & switches (Set) of each type Nos. 1
0 5 MCB of each rating Nos. 1
6 ELCB/RCBO of each rating Nos. 1
7 Timer Switch of each type Nos. 1
8 Switches of each rating Nos. 1
9 HRC Fuses of each rating and each type Nos. 1
0 10
Mulitification Meter Nos. 1
11 Megger – 500V Nos. 1
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 41 of 65
Sr.
No. Item description Unit Quantity
CATHODIC PROTECTION SYSTEM
A DC Links of each rating Nos. 6
B Resistor of each rating Nos. 6
C
Transformer Rectifier Unit (One Set for each equipment as supplied, to be supplied)
(Note- Quantities mentioned against each item are for one set only)
1 Input MCB ( A.C. Circuit breaker) Nos. 2 Nos. Or 20%
whichever is higher
2 Ammeter - DC Nos. 2 Nos. Or 20%
whichever is higher
3 Ammeter - AC Nos. 2 Nos. Or 20%
whichever is higher
4 Voltmeter - DC Nos. 2 Nos. Or 20%
whichever is higher
5 Voltmeter - AC Nos. 2 Nos. Or 20%
whichever is higher
6 Diodes Nos. 2 Nos. Or 20%
whichever is higher
7 SCR's Nos. 2 Nos. Or 20%
whichever is higher
8 D.C. Fuses for output side Nos. 2 Nos. Or 20%
whichever is higher
9 A.C. fuses for input side Nos. 2 Nos. Or 20%
whichever is higher
10 HRC fuse for Diodes Nos. 2 Nos. Or 20%
whichever is higher
11 D.C. Lightening arrestor Nos. 2 Nos. Or 20%
whichever is higher
12 Filter circuit capacitor Nos. 2 Nos. Or 20%
whichever is higher
13 Signal light assembly for annunciation Nos. 2 Nos. Or 20%
whichever is higher
14 R.C. Surge Diverter Nos. 2 Nos. Or 20%
whichever is higher
15 Control transformer Nos. 2 Nos. Or 20%
whichever is higher
16 Coarse voltage control switch Nos. 2 Nos. Or 20%
whichever is higher
17 Coarse current control switch Nos. 2 Nos. Or 20%
whichever is higher
18 Fine voltage control switch Nos. 2 Nos. Or 20%
whichever is higher
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 42 of 65
19 Fine current control switch Nos. 2 Nos. Or 20%
whichever is higher
20 Toggle switches Nos. 2 Nos. Or 20%
whichever is higher
21 Assorted Glass cartridge fuses Nos. 2 Nos. Or 20%
whichever is higher
22 Selector Switch (Auto Manual Mode
selector switch)
Nos. 2 Nos. Or 20%
whichever is higher
23 Synchronized Interrupter switch Nos. 2 Nos. Or 20%
whichever is higher
24 Pulse Drivers Card Nos. 2 Nos. Or 20%
whichever is higher
25 Control Amplifier Card ( Electronic
Control Cards each type)
Nos. 2 Nos. Or 20%
whichever is higher
26 Power supply card Nos. 2 Nos. Or 20%
whichever is higher
27 Relay Card Nos. 2 Nos. Or 20%
whichever is higher
28 Indicating Lamp Nos. 2 Nos. Or 20%
whichever is higher
29 Reference cell Selector Switch Nos. 2 Nos. Or 20%
whichever is higher
30 4-20 ma Convert Module (for PSP reading) Nos. 2 Nos. Or 20%
whichever is higher
• Please refer SLD, Drawings, PTS Electrical and GTS provided with the tender for details for detailed scope
of work.
B. The following electrical equipment / systems are envisaged in this project for despatch terminal at ONGC
Bantumilli but not limited as per below:
(i) Main Electrical Distribution Board (MEDB)
(ii) 415 V , TPN, SFU
(iii) 415 V (3 Ph, N & 4W) 50 Hz Main Power Supply shall be from SEB arranged by M/s GAIL & Emergency
Power supply shall be feed by DG Set.
(iv) **KVA ,415V, 50 Hz, 0.8 PF, 3P & N Silent Diesel Generator Set, with AMF Panel, Air Cooled type,
Auto /manual start facility from local / through SCADA upon grid failure. Rating to be finalized during
detail engineering.
(v) Min. 7 KVA,230V AC output, 50 Hz parallel redundant UPS with static stabilizer for by pass supply and
with Ni-Cd VRPP battery (02 Nos. of Battery Bank) & UPS Distribution Board (UPS DB)
(vi) OLDB,ILDB,SSDB, ACDB
(vii) Bore Well Pump
(viii) Power & Control FRLS Cables
(ix) Indoor /Outdoor Lighting system
(x) Earthing, Bonding and lightning protection system
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 43 of 65
(xi) Split AC system
(xii) 2KVA Invertor with battery & distribution board
(xiii) Structural steel, cable trays, miscellaneous items etc.
(xiv) Conduit and associated hardware for concealed /surface mounting & wire (to be laid in the concrete
slab/other civil construction) for electrical system.
c. The following Electrical equipment / systems are envisaged in this project for SV Station at ch 21.6 Km, but not
limited as per below:
(i) Main Electrical Distribution Board (MEDB)
(ii) 415 V , TPN, SFU
(iii) 415 V (3 Ph, N & 4W) 50 Hz Main Power Supply shall be from SEB arranged by M/s GAIL & Emergency
Power supply shall be feed by DG Set.
(iv) **KVA ,415V, 50 Hz, 0.8 PF, 3P & N Silent Diesel Generator Set, with AMF Panel, Air Cooled type,
Auto /manual start facility from local / through SCADA upon grid failure. Rating to be finalized during
detail engineering.
(v) Min.5 KVA,230V AC output, 50 Hz parallel redundant UPS with static stabilizer for by pass supply and
with Ni-Cd VRPP battery (02 Nos. of Battery Bank) & UPS Distribution Board (UPS DB)
(vi) OLDB,ILDB,SSDB, ACDB
(vii) Bore Well Pump
(viii) Power & Control FRLS Cables
(ix) Indoor /Outdoor Lighting system
(x) Earthing, Bonding and lightning protection system
(xi) Split AC system
(xii) 2KVA Invertor with battery & distribution board
(xiii) Structural steel, cable trays, miscellaneous items etc.
(xiv) Conduit and associated hardware for concealed /surface mounting & wire (to be laid in the concrete
slab/other civil construction) for electrical system.
D. The following electrical equipment / systems are envisaged in this project for receiving terminal at Ullamparu,
but not limited as per below:
(i) Main Electrical Distribution Board (MEDB)
(ii) 415 V , TPN, SFU
(iii) 415 V (3 Ph, N & 4W) 50 Hz Main Power Supply shall be from SEB arranged by M/s GAIL & Emergency
Power supply shall be feed by DG Set.
(iv) **KVA ,415V, 50 Hz, 0.8 PF, 3P & N Silent Diesel Generator Set, with AMF Panel, Air Cooled type,
Auto /manual start facility from local / through SCADA upon grid failure. Rating to be finalized during
detail engineering.
(v) Min.5 KVA,230V AC output, 50 Hz parallel redundant UPS with static stabilizer for by pass supply and
with Ni-Cd VRPP battery (02 Nos. of Battery Bank) & UPS Distribution Board (UPS DB)
(vi) OLDB,ILDB,SSDB, ACDB
(vii) Bore Well Pump
(viii) Power & Control FRLS Cables
(ix) Indoor /Outdoor Lighting system
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 44 of 65
(x) Earthing, Bonding and lightning protection system
(xi) Split AC system
(xii) 2KVA Invertor with battery & distribution board
(xiii) Structural steel, cable trays, miscellaneous items etc.
(xiv) Conduit and associated hardware for concealed /surface mounting & wire (to be laid in the concrete
slab/other civil construction) for electrical system
7.6.2.4 Cathodic Protection - Scope Of Work
Supply &Installation of TCP and PCP system for 12” NB x 38 km (approx.)Natural gas Pipeline from Bantumilli to
Ullamparu, including requirements at Station facilities, as per Project specifications and Tender requirements.
Major activities covering complete scope of work include the following:
� Corrosion survey Methodology for site data generation and interpretation report and design basis for [TCP/ PCP]
system.
� Pre-design surveys
a. Soil resistivity survey.
b. Soil Ionic and microbial analysis.
� Design, detailed Engineering of TCP & PCP and approval from PMC/client representative. Including formulae
used, design calculations, BOQ, Technical Specifications and Post Commissioning Monitoring Methodology,
Data Recording Formats, Quality Assurance Control [QA/QC] methodology.
Procurement which includes supply, factory inspection, transportation , loading and unloading of CPTRU, anodes,
cables, junction boxes, reference cells and other materials for completing TCP and PCP work required for complete
PCP work on FOT- project site basis.
� Submission and obtaining approval of all documents (vendor documents) related to procurement of items as
mentioned above.
� Installation, testing, pre-commissioning and Commissioning of TCP and PCP work as defined in the tender
including job procedure for field testing, pre-commissioning and commissioning.
� All civil works associated with the complete Cathodic Protection work (TCP & PCP) shall be included in the
scope of CP contractor. This shall include providing cable trenches, foundation for equipment etc.
� Liaisoning with local authorities/statutory bodies/foreign utilities to obtain permissions for PCP work. However
Demand Notes/fees applicable to obtain permissions from concerned authorities/local bodies will be paid by
GAIL. For acquiring land for Anode Bed and for boring in case of deep well anode bed, CP Contractor has to
liaison with private land owner/ Govt body/ concerned authority and transfer the same in the name of M/s GAIL.
� Performing the following surveys, submission and obtaining approval of job procedures, reports for the
acceptance of PMC/client representative.
� Post Commissioning surveys
a. CIPL survey of pipeline network.
b. DCVG survey based on CIPL reports.
c. Coating Conductance survey.
d. AC/DC interference survey: Interference mitigation to be performed during PCP by contractor, without any
additional cost.
� CP Monitoring for three months from the date of commissioning with monthly progress reporting to PMC/
Client’s representative & mitigation of any anomaly required to tune up the functioning of the PCP system. This
includes monthly monitoring of PCP test station with data logger and weekly monitoring of CPTRU parameters.
� Progress reporting to PMC/client representative.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 45 of 65
a. As-Built Document submission including O&M manual and handing over the entire system with reports to
CLIENTS’S O&M.
b. Monitoring methodology, frequency and formats
7.6.2.5 Instrumentation & Control - Scope Of Work
The entire project is comprised of dispatch station, receiving station and remote operated SV stations along with
associated instrumentation and protection system. Refer P&ID for detail. The facilities in the Contractor’s scope is as
under,
A. SPECIAL INSTRUCTIONS TO CONTRACTOR
• Bidder shall submit their offer in a well-documented manner with all required documents.
• The language of bidder’s offer including catalogue, technical literature or any other documents or any software
shall be English language only. This shall be applicable for bought out items also.
• Scope of the bidder shall be as per the tender specification. Any other activities not specifically mentioned
/covered in the tender documents but otherwise required for satisfactory completion /safety of work has to be
carried out by the contractor within specified schedule at no extra cost to owner.
• Bidder shall strictly follow the Recommended Vendor List attached with the tender document for various items.
B. REFERENCE
• PTS – Instrumentation with appendices – P.011947-I-11097-101
o Appendix -1 – Spare capacity
o Appendix- II – Instrument Index
o Appendix – III – Instrument Data sheets
• Material Requisition – P.001947-I-11071-101
• PTS – Remote terminal unit – P.011947-I-11097-102
o Annexure – I- Input output List
o Annexure -II – I/O count
• PTS – Telecommunication system – P.011947-I-11097-103
• PTS – Optical fiber cable – P.011947-I-11097-104
• PTS – HDPE Duct – P.011947-I-11097-105
• Instrumentation operational philosophy- P.011947-I-11000-101
C. INSTRUMENTATION SYSTEM SUMMARY
• The entire project is comprised of dispatch station, receiving station and remote operated SV stations along
with associated instrumentation and protection system.
• Following facilities shall be provided at stations
1. DESPATCH STATION-BANTUMILLI
a. Field instruments as per P&ID.
b. Standalone local control panel in control room for monitoring the process parameters and GOOVA
operation.
c. Remote terminal unit (RTU). Make of RTU shall be “SYNERGY” as per existing
d. SHD Telecommunication system (STM4). Make of SDH shall be Nokia Siemens Network hiT
7025/Coriant supplied by M/s Commtel as per existing.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 46 of 65
e. CCTV cameras. One Fixed and one PTZ color cameras WP IP 65. Make of the cameras shall be
“PELCO” and integrated with existing NVR.
f. Analog telephones (one in control room, one in guard room and one Ex proof WP IP65 in field with
three side canopy) and FXS card. Make of the Telephones shall be “ALCATEL-LUCENT” and
integrated with existing EPABX.
g. Conventional type Fire detection including smoke and heat detector.
h. Addressable type Gas detection system with point gas detectors.
i. Corrosion monitoring system along with corrosion probe and corrosion coupon.
j. Armored 24 core optical fiber with FTC, joint chamber, joint closure, electronic router marker and
locator, manual route marker. OF cable shall be laid inside the HDPE duct from Bantumalli to
Ullamparru
k. New Optical fiber cable shall be connected at Ullamparru and interface with existing system.
l. SCADA system is not envisaged- all the new parameters shall be integrated in existing SCADA
system.
Metering system shall be consisting of following facility at Bantumilli (TO BE SUPPLIED BY
SEPARATE METERING SKID CONTRACTOR)
a. Single stream Demister type knock-out drum with instruments
b. Dual stream coalescent dual chamber filtration skid with instruments.
c. Dual stream ultrasonic gas metering skid with flow computers for each stream and metering cabinet.
d. Dual stream pressure reduction skid with active & monitor valve and slam shutoff valve.
e. Single stream gas chromatograph with field mounted analyzer, controller carrier gas cylinder and
calibration cylinder.
f. Single stream field mounted moisture analyzer
g. Single stream field mounted H2S analyzer.
h. HMI system with processor, monitor and printer.
2. SV STATION
a. Field instruments as per P&ID.
b. Standalone local control panel provided in control room for monitoring the process parameters and
GOOVA operation.
c. Remote terminal unit (RTU), make of RTU shall be “SYNERGY” as per existing
d. SHD Telecommunication system (STM4). Make of SDH shall be Nokia Siemens Network hiT
7025/Coriant supplied by M/s Commtel as per existing.
e. CCTV cameras. Fixed and PTZ color cameras shall be provided. Make of the cameras shall be
“PELCO” and integrated with existing NVR.
f. Analog telephone (one in control room and one in guard room) and one FXS cards. Make of the
Telephones shall be “ALCATEL-LUCENT” and integrated with existing EPABX.
g. Conventional type Fire detection including smoke and heat detector.
h. Addressable type Gas detection system with point gas detectors.
3. RECEIVING STATION-ULLAMPARRU
a. Field instruments as per P&ID as per recommended vendor list
b. Standalone local control panel in control room for monitoring the process parameters and GOOVA
operation.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 47 of 65
c. Existing Remote terminal unit (RTU) shall be used for integration of field instruments, make of RTU
is “SYNERGY”. Contractor shall supply a 32 channel DI card, install in existing RTU in spare slot
and internal wiring in existing panel upto terminal block.
d. Existing SHD Telecommunication system (STM4) shall be used, Make of SDH is Nokia Siemens
Network hiT 7025/Coriant supplied by M/s Commtel.
e. CCTV Fixed and PTZ color cameras. Make of the cameras shall be “PELCO” and integrated with
existing NVR.
f. Analog telephones (one in control room, one in guard room and one Ex Proof WP IP65 in field with
three side canopy) and one number FXS card & one number FXO card. Make of the Telephones shall
be “ALCATEL-LUCENT” and integrated with existing EPABX.
g. Conventional type Fire detection including smoke and heat detector.
h. Addressable type Gas detection system with point gas detectors.
i. Corrosion monitoring system along with corrosion probe and corrosion coupon.
j. SCADA system is not envisaged- all the new parameters shall be integrated in existing SCADA
system.
Dual stream ultrasonic gas metering skid with flow computer and metering cabinet ((TO BE SUPPLIED BY
SEPARATE METERING SKID CONTRACTOR)
D. SCOPE OF WORK
• The Contractor’s scope of work shall include but not limited to the following:
o This document shall read in conjunction with material requisition and other specification enclosed with
tender document.
o Scope of work shall comprise of Total Project Management and execution including, System Design, Detail
Engineering, Procurement of Materials, manufacturing or fabrication, Supply, Installation, Inspection &
Factory Acceptance Testing (total Equipment & System Integration) & Testing of system, Packaging,
forwarding, Insurance, Shipping related all formalities, Inland Transportation to site, and Supply of all
related goods including Mandatory, Commissioning consumables spares, Handling, Storage & Safe
custody, Supply of all type of Erection Items, site engineering, Pre-Commissioning activity, Testing,
Interconnection and interfacing with Telecommunication System, Trial Run, Commissioning, Training,
support and Warranty Including any civil works etc., & documentation of total system, Testing certificates,
calibration certificates of equipment required to complete in all respect.
o Contractor shall collect all the necessary existing system documents and information require for interfacing
with their system. It is contractor’s responsibility to interact or co-ordinate with existing equipment supplier
for technical details require for interface with existing system and RTU/local control panel/gas detection
system etc.
o Contractor shall carry all the required Tools and Tackles require for installation, erection, testing and
commissioning of system. Quantities of all the tools and tackles shall be adequate and certified as per the
quantum and quality to work. These quantities may require to enhance as and when required by Client to
achieve the project schedule or to expedite the progress.
o Contractor shall also carry all the calibration equipment/ testing equipment like multi-meter, hand held
calibrator, 4-20mA simulator, modbus simulators, diagnostic tools etc.
o Supply and laying of power, signals, control and communication cables, earthing cables. Including supply,
laying of cable tray including terminations, ferruling, cable numbering, marking, testing including hot &
cold loop testing. Branch cable shall be laid in cable tray and cable from Junction box or field local panel
shall be buried.
� Tentative distance between field instruments to junction box as per site requirement.
� Tentative average aerial distance between Junction box to control room is 60 mtrs.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 48 of 65
� Tentative average aerial distance between local control panel to RTU is 30 mtrs.
� Tentative average aerial distance between gas detection system to RTU is 30 mtrs
� Tentative average aerial distance between Fire detection system to RTU is 30 mtrs
� Tentative average aerial distance between RTU and Telecommunication Panel is 15 Mtrs.
� Tentative average aerial distance from DCDB to equipment cabinet is 50 mtrs
Note –Contractor shall choose the cable size and type according to requirement but cable size and type of the
cables shall be according to PTS- Instrument cables only.
o Required masonry works for installation of systems and all associated equipment etc. shall be in
contractor’s scope of supply.
o Any other equipment /material not specifically mentioned herein but required to complete the work (i.e. to
install, commission and successfully run the Installation) shall be in contractor’s scope.
o Contractor shall prepare, maintain and submit inspection reports, erection/installation progress reports,
material log etc. periodically.
o Daily/Weekly progress report, Documentation like procedure preparation and approval, furnish of
inspection reports, handing over the documents after completion of project etc shall be done by contractor
at their cost.
o Preparation of cable drum cutting schedule, cable schedule/interfacing wiring diagram, branch cable tray
routine is in contractor scope.
o Supply, Fabrication and installation of MS base frames, supports, pipes, plates etc. for local control
Panels/RTU/GDS/FDS/Metering panels including welding, bolting, riveting, supply of necessary anchor
bolts, grouting etc., supply of paint and applying one coat of anti-rust primer and two finished coats of
approved synthetic enamel paint, breaking walls, floors etc. for structures as required and supply of all GI
hardware materials as required
o Contractor shall supply the material as per recommended vendor list. If any item is not covered under
recommended vendor list, shall take written approval of CLIENT/CLIENT’S REPRESENTATIVE before
supply of material.
o Unloading of material/equipment related to works received at site shall be in the contractor’s scope.
o Inspection of received material by unpacking/opening boxes at site including spares & material to be
received at site in presence of CLIENT/CLIENT’S REPRESENTATIVE in charge/OEM.
o Contractor shall follow Quality and Safety requirement during construction phases of the Project.
o Any special training for height work, electrical/mechanical safety, Scaffolding work, special toolbox, etc.,
for workers, promotional programs, motivational programs etc., shall be in contractor’s scope.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 49 of 65
o Scope matrix
� Part A
� Station - Bantumilli Despatch station
Sr.
No
Equipment/Packages Contractor’s Scope of work Free issue items/ GAIL /
Other Scopes
1 Field Instruments- as
per P&IDs
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, installation of field
instruments (including supply, fabrication of canopies,
mounting stands, supports etc as per situ conditions),
testing, integration with System,
configuration/programming, commissioning as per user
requirement, test run, and handover to Client as per “PTS-
Instrumentation with Appendices” and other tender
documents.
Scope also includes supply and installation all the erection
hardware such as impulse tubing, fittings, protection
shed/canopy, SS tag plates with SS Chain, mounting
bracket as applicable, mounting stands including associated
civil works
None
2 Local Control Panel
(Floor mounted
cabinet) (LCP)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of LCP and integration with Field instrument, RTU
etc ,configuration/programming as per user requirement,
commissioning, test run, SAT and handover to Client as per
PTS – “PTS-Instrumentation with Appendices” and other
tender documents.
Erection, installation of LCP inside the station control room
including supply of all the required erection materials,
fabrication and civil works.
None
3 Gas detection system
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of addressable gas detection system and integration
with RTU, configuration /programming as per user
requirement, commissioning, test run, SAT and handover
to Client as per PTS-Instrumentation with Appendices”
and other tender documents.
None
4 Fire Detection
System(FDS)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of conventional type fire detection system and
integration with RTU, configuration /programming as per
user requirement, commissioning, test run, SAT and
handover to Client as per PTS-Instrumentation with
Appendices” and other tender documents.
None
5 Corrosion Monitoring
system (CMS)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of corrosion coupon, corrosion probe, digital
indicator, etc and configuration /programming as per user
requirement, commissioning, test run, SAT and handover
None
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 50 of 65
CMS shall be mounted
in LCP
to Client as per PTS-Instrumentation with Appendices”
and other tender documents.
6 Remote terminal Unit
(Floor Mounted))
Refer IO count for RTU
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of RTU and integration with LCP / GDS/ FDS/ CP
etc ,configuration/programming as per user requirement,
commissioning, test run, FAT, SAT and handover to Client
as per PTS – “PTS-Remote Terminal Unit” and other tender
documents.
Erection, installation of RTU inside the station control
room including supply of all the required erection materials,
fabrication and civil works.
None
7 Telecommunication
System
(Floor mounted)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of Telecom system and integration with RTU
,configuration/programming as per user requirement,
commissioning, test run, FAT, SAT and handover to Client
as per PTS – “PTS-Telecommunication system” and other
tender documents.
Erection, installation of Telecom cabinet inside the station
control room including supply of all the required erection
fabrication and civil materials.
Integration and configuration of new Optical fiber cable
and SDH equipment with existing SDH telecom network
and NMS.
None
8 SCADA System Providing the all required information, documents and
technical supports while integration
Integration of New parameters
in existing SCADA system
9 Cables (Single cable,
Power & control cable,
communication cable,
LAN cable
Supply and Cable laying, glanding, termination, ferruling,
lugging, tagging, clamping, route marker etc. Scope
includes supply of cable gland, cable tag plates, Cable
ferrule, clamps and all the required items to complete the
laying works as per PTS-Instrumentation with
Appendices” and other tender documents .
• Field Instruments to field mounted junction in cable
tray.
• Field junction box to Control cabinet is buried
• Cabinet to cabinet inside the control room in cable
trench
RTU & Telecom communication cable (Ethernet), serial
cables (GDS/FDS) etc.
For LAN cable Contractor shall supply conduit of proper
size and lay cable inside the conduit.
None
10 Junction Boxes Supply, installation of weather proof and Explosion proof
junction including fabrication of supports
None
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 51 of 65
PTS-Instrumentation with Appendices” and other tender
documents
11 Cable Tray with cover-
branch tray
Supply, installation and laying of instrument cable tray
(branch and main) including fabrication of supports
PTS-Instrumentation with Appendices” and other tender
documents
None
12 Earthing pits Preparation of system and power earthing pit. Supply and
laying of earthing cable and earthing strip.
None
13 Optical Fiber cable. Supply and laying of armored Optical fiber cable inside the
HDPE duct along with pipeline from Bantumalli, SV
station and Ullamparru and inside each station control
room, including supply of FTC, electronic route marker &
locator, manual route marker, joint/splicing chamber, joint
closure, etc as per “PTS- Optical Fiber cable” and other
documents.
None
14 HDPE duct Supply and laying of HDPE duct along with pipeline from
Bantumalli, SV station and Ullamparru and inside each
station control room as per “PTS- HDPE duct” and other
documents
None
15 CCTV Supply and Installation of CCTV cameras along with power
cable and communication cable and integration with
existing NVR system
Providing the all required
information regarding existing
system, documents and
technical supports while
integration.
16 Analog Phones Supply and Installation of Analog phones along with
telephone cables, connectors, FXS card and integration
with existing EPABX system.
Providing the all required
information regarding existing
system, documents and
technical supports while
integration.
17 KOD, Filtration skid,
Metering skid, PRS
skid, Gas
chromatograph,
Moisture analyzer, H2S
analyzer.
Installation of all the skids under the supervision of skid
supplier, cable laying and terminal of cable from skid
junction box to metering system cabinet according to skid
supplier cable schedule. Etc. including supply of all the
required erection , fabrication and civil materials.
Erection, installation of Metering cabinet inside the station
control room, Gas chromatograph system, moisture
analyzer system, H2S Analyzer system including supply of
all the required erection , fabrication and civil materials.
Supply of all the skids along
with cabinet and required
accessories.
Supply of cables (Power,
signals, control and
communication) from skid
instruments to junction box
and junction box to cabinet
including cable glands.
Supervision of installation
work
Installation of all the skids
instruments including laying of
cable from skid instrument to
junction box.
Providing the all required
information, documents and
technical supports while
integration.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 52 of 65
� Station - SV station
Sr.
No
Equipment/Packages Contractor’s Scope of work Free issue items/
GAIL / Other
Scopes
1
Field Instruments- as
per P&IDs
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, installation of field
instruments (including supply, fabrication of canopies,
mounting stands, supports etc as per situ conditions), testing,
integration with System, configuration/programming,
commissioning as per user requirement, test run, and handover
to Client as per “PTS-Instrumentation with Appendices” and
other tender documents.
Scope also includes supply and installation all the erection
hardware such as impulse tubing, fittings, protection
shed/canopy, SS tag plates with SS Chain, mounting bracket as
applicable, mounting stands including associated civil works
None
2 Local Control Panel
(Floor mounted
cabinet) (LCP)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of LCP and integration with Field instrument, RTU etc
,configuration/programming as per user requirement,
commissioning, test run, SAT and handover to Client as per
PTS – “PTS-Instrumentation with Appendices” and other
tender documents.
Erection, installation of LCP inside the station control room
including supply of all the required erection materials,
fabrication and civil works.
None
3 Gas detection system Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of addressable gas detection system and integration with
RTU, configuration /programming as per user requirement,
commissioning, test run, SAT and handover to Client as per
PTS-Instrumentation with Appendices” and other tender
documents.
None
4 Fire Detection
System(FDS)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of conventional type fire detection system and
integration with RTU, configuration /programming as per user
requirement, commissioning, test run, SAT and handover to
Client as per PTS-Instrumentation with Appendices” and
other tender documents.
None
5 Corrosion Monitoring
system (CMS)
CMS shall be mounted
in LCP
None None
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 53 of 65
6 Remote terminal Unit
(Floor Mounted)
Refer IO count for RTU
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of RTU and integration with LCP / GDS/ FDS/ CP/ etc
,configuration/programming as per user requirement,
commissioning, test run, FAT, SAT and handover to Client as
per PTS – “PTS-Remote Terminal Unit” and other tender
documents.
Erection, installation of RTU inside the station control room
including supply of all the required erection materials,
fabrication and civil works.
None
7 Telecommunication
System
(Floor mounted)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection, installation,
testing of Telecom system and integration with RTU
,configuration/programming as per user requirement,
commissioning, test run, FAT, SAT and handover to Client as
per PTS – “PTS-Telecommunication system” and other tender
documents.
Erection, installation of Telecom cabinet inside the station
control room including supply of all the required erection
materials, fabrication and civil works.
Integration and configuration of new Optical fiber cable and
SDH equipment with existing SDH telecom network and NMS.
None
8 SCADA System Providing the all required information, documents and
technical supports while integration
Integration of New
parameters in existing
SCADA system
9 Cables (Single cable,
Power & control cable,
communication cable,
LAN cable
Supply and Cable laying, glanding, termination, ferruling,
lugging, tagging, clamping, route marker etc. Scope includes
supply of cable gland, cable tag plates, Cable ferrule, clamps
and all the required items to complete the laying works as per
PTS-Instrumentation with Appendices” and other tender
documents .
• Field Instruments to field mounted junction in cable tray.
• Field junction box to Control cabinet is buried
• Cabinet to cabinet inside the control room in cable trench
RTU & Telecom communication cable (Ethernet), serial cables
(GDS/FDS) etc.
For LAN cable Contractor shall supply conduit of proper size
and lay cable inside the conduit.
None
10 Junction Boxes Supply, installation of weather proof and Explosion proof
junction including fabrication of supports
PTS-Instrumentation with Appendices” and other tender
documents
None
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 54 of 65
11 Cable Tray with cover-
branch tray
Supply, installation and laying of instrument cable tray (branch
and main) including fabrication of supports
PTS-Instrumentation with Appendices” and other tender
documents
None
12 Earthing pits Preparation of system and power earthing pit. Supply and
laying of earthing cable and earthing strip.
None
13 CCTV Supply and Installation of CCTV cameras along with power
cable and communication cable and integration with existing
NVR system
Providing the all
required information
regarding existing
system, documents
and technical supports
while integration.
14 Analog Phones Supply and Installation of Analog phones along with telephone
cables, connectors, FXS card and integration with existing
EPABX system.
Providing the all
required information
regarding existing
system, documents
and technical supports
while integration.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 55 of 65
� Station - Ullamparru Receiving station
Sr. No Equipment/Packages Contractor’s Scope of work Free issue items/ GAIL /
Other Scopes
1 Field Instruments- as
per P&IDs
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, installation of
field instruments (including supply, fabrication of
canopies, mounting stands, supports etc as per situ
conditions), testing, integration with System,
configuration/programming, commissioning as per user
requirement, test run, and handover to Client as per
“PTS-Instrumentation with Appendices” and other
tender documents.
Scope also includes supply and installation all the
erection hardware such as impulse tubing, fittings,
protection shed/canopy, SS tag plates with SS Chain,
mounting bracket as applicable, mounting stands
including associated civil works
None
2 Local Control Panel
(Floor mounted
cabinet) (LCP)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection,
installation, testing of LCP and integration with Field
instrument, RTU etc ,configuration/programming as per
user requirement, commissioning, test run, SAT and
handover to Client as per PTS – “PTS-Instrumentation
with Appendices” and other tender documents.
Erection, installation of LCP inside the station control
room including supply of all the required erection
materials, fabrication and civil works.
None
3 Gas detection system
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection,
installation, testing of addressable gas detection system
and integration with RTU, configuration /programming
as per user requirement, commissioning, test run, SAT
and handover to Client as per PTS-Instrumentation with
Appendices” and other tender documents.
None
4 Fire Detection
System(FDS)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection,
installation, testing of conventional type fire detection
system and integration with RTU, configuration
/programming as per user requirement, commissioning,
test run, SAT and handover to Client as per PTS-
Instrumentation with Appendices” and other tender
documents.
None
5 Corrosion Monitoring
system (CMS)
CMS shall be mounted
in LCP
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection,
installation, testing of corrosion coupon, corrosion
probe, digital indicator, etc and configuration
/programming as per user requirement, commissioning,
test run, SAT and handover to Client as per PTS-
None
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 56 of 65
Instrumentation with Appendices” and other tender
documents.
6 Remote terminal Unit
(Floor Mounted))
Refer IO count for RTU
Supply and installation of 32 channel digital input cards
of “Synergy make” at Ullamparrau and do the panel
internal wiring upto terminal block and interface with
local control panel as per PTS – “PTS-Remote Terminal
Unit” and other tender documents.
Location of Local control is in new control room,
contractor shall lay signals cables from local control
panel (new control room) to RTU (existing control
room)
None
7 Telecommunication
System
(Floor mounted)
Design, Detail Engineering, Procurement of Materials,
manufacturing or fabrication, Supply, erection,
installation, testing of Telecom system and integration
with RTU ,configuration/programming as per user
requirement, commissioning, test run, FAT, SAT and
handover to Client as per PTS – “PTS-
Telecommunication system” and other tender
documents.
Erection, installation of Telecom cabinet inside the
station control room including supply of all the required
erection fabrication and civil materials.
Integration and configuration of new Optical fiber cable
and SDH equipment with existing SDH telecom
network and NMS.
None
8 SCADA System Providing the all required information, documents and
technical supports while integration
Integration of New
parameters in existing
SCADA system
9 Cables (Single cable,
Power & control cable,
communication cable,
LAN cable
Supply and Cable laying, glanding, termination,
ferruling, lugging, tagging, clamping, route marker etc.
Scope includes supply of cable gland, cable tag plates,
Cable ferrule, clamps and all the required items to
complete the laying works as per PTS-Instrumentation
with Appendices” and other tender documents .
• Field Instruments to field mounted junction in cable
tray.
• Field junction box to Control cabinet is buried
• Cabinet to cabinet inside the control room in cable
trench
RTU & Telecom communication cable (Ethernet), serial
cables (GDS/FDS) etc.
For LAN cable Contractor shall supply conduit of
proper size and lay cable inside the conduit.
None
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 57 of 65
10 Junction Boxes Supply, installation of weather proof and Explosion
proof junction including fabrication of supports
PTS-Instrumentation with Appendices” and other
tender documents
None
11 Cable Tray with cover-
branch tray
Supply, installation and laying of instrument cable tray
(branch and main) including fabrication of supports
PTS-Instrumentation with Appendices” and other
tender documents
None
12 Earthing pits Preparation of system and power earthing pit. Supply
and laying of earthing cable and earthing strip.
None
13 Optical Fiber cable. Supply and laying of armored Optical fiber cable inside
the HDPE duct along with pipeline from Bantumalli, SV
station and Ullamparru and inside each station control
room, including supply of FTC, electronic route marker
& locator, manual route marker, joint/splicing chamber,
joint closure, etc as per “PTS- Optical Fiber cable” and
other documents.
None
14 HDPE duct Supply and laying of HDPE duct along with pipeline
from Bantumalli, SV station and Ullamparru and inside
each station control room as per “PTS- HDPE duct” and
other documents
None
14 HDPE duct Supply and laying of HDPE duct along with pipeline
from Bantumalli, SV station and Ullamparru and inside
each station control room as per “PTS- HDPE duct” and
other documents
None
15 CCTV Supply and Installation of CCTV cameras along with
power cable and communication cable and integration
with existing NVR system
Providing the all required
information regarding
existing system, documents
and technical supports
while integration.
16 Analog Phones Supply and Installation of Analog phones along with
telephone cables, connectors, FXS & FXO cards and
integration with existing EPABX system.
Providing the all required
information regarding
existing system, documents
and technical supports
while integration.
17 Metering skid Installation of all the skid under the supervision of skid
supplier, cable laying and terminal of cable from skid
junction box to metering system cabinet according to
skid supplier cable schedule. Etc. including supply of
all the required erection , fabrication and civil materials.
Erection, installation of Metering cabinet inside the
station control room, including supply of all the required
erection , fabrication and civil materials.
Supply of all the skid along
with cabinet and required
accessories.
Supply of cables (Power,
signals, control and
communication) from skid
instruments to junction box
and junction box to cabinet
including cable glands.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 58 of 65
Supervision of installation
work
Installation of all the skids
instruments including
laying of cable from skid
instrument to junction box.
Providing all required
information, documents
and technical supports
while integration.
� Part B
Scope
Sr.
No.
Item Description Contractor Client Remarks
1 Unloading the material/equipment received from
vendors to site, shifting of equipmens/material
from store to installation location etc.
YES
3 Staff and labor transportation YES
4 Labor accommodation. YES
5 Labor license. YES
6 Wooden sleeper as required. YES
7 Office container YES
8 Required material for preparation of platform YES
9 Obtaining statutory approval (if any) for
instrumentation system of project.
YES
10 Preparation of Job Planning and schedule and
DPR
YES
11 All statutory compliance YES
12 All civil work for earthing pits, repairing of plaster
(If required during conceal wiring work).
YES
13 Scaffolding material and installation YES As per
requirement.
14 welding machines YES As per
requirement.
15 Documentation like procedure preparation, work
schedule, calibration reports, inspection report,
progress report, termination details etc. test
certificates compliance reports
YES
16 Temporary Illumination at work site YES
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 59 of 65
E. GENERAL TECHNICAL REQUIREMENTS
o General site equipment shall be suitable for operation under the following site conditions.
Sand & dust : With a built-up of dust on operational surface to a level
such as may occur because of imperfections in the
sealing of equipment, housing and conditions
prevailing in sub- tropical dust conditions.
Tropicalisation : The equipment shall be fully tropicalized.
Shock & vibration : The equipment shall withstand transportation and
handling by air, sea and road under packed conditions.
o The equipment shall also be resistant to termite, fungus, rodents and salty environment. Environmental
Specification of Equipment to be supplied.
o The equipment at Stations shall be designed for non-air conditioned environment.
o Area and zone classification
� All the control rooms wherever available are classified as Safe Areas.
� All the fields wherever available are classified as Hazardous area.
o Surge Protection, Transient Suppressors, RFI filters Equipments shall be designed with built-in safety to
protect against the effects of monitor induced high voltages.
o Earthing
� Transmitters, Junction box and control cabinets shall be provided with earthing lugs. All these lugs/
strips shall be properly secured to the electrical earthing bus.
� All system grounds of various cards and equipment, shields of instrument cables shall be connected to
system ground bus, which is electrically isolated from the AC mains earthing bus. The equipment shall
provide separate earthing strip for the same. The system ground bus shall be connected to independent
ground buses through insulated wires.
� The wire and cable shielding are required to prevent the equipment from propagating interference and
to protect the equipment from the effect of interference propagated by other devices. Shielding is
typically floating on the device end, tied to IE at the control console.
i. System grounding (earth resistance less than 1 ohm)
ii. Frame and AC mains grounding (earth resistance less than 5 ohms)
� Accordingly, the equipments shall provide separate earthing strips as mentioned above.
i. Instrument earth(IE)/system ground
IE earth shall be copper earth. IE ground protects sensitive electrical and electronic device,
circuit and wiring from electromagnetic interference (EMI) and radio frequency interference
(RFI). IE should be free from transient voltages and electromagnetic noise. It is, therefore,
normally isolated from PE ground. Instrument earth should be tied in the most direct possible
path to a common earth electrode.
IE grounds resistance is less than 1 ohm to ground
ii. Power Earth (PE)/AC mains grounding
PE ground provides a route to dissipate the power line transient to earth potential. PE should
be tied in the most direct possible path to a common earth electrode
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 60 of 65
PE grounds resistance is less than 5 ohm to ground
o Safety Requirements
� It is the intent of the CLIENT that operational hazards be reduced to a minimum. Contractor
shall use sound engineering judgment to complete installation that will perform the required
function without compromise of safety.
� All controls shall operate in a fail-safe mode. A fail-safe mode defines what a plant, equipment
or system will do when it fails, so as to ensure a safe condition.
� Provision shall be made to isolate all 230 V AC (If any) incoming signals to a cabinet, before
gaining access to cabinet internals. Shrouded terminals with warning labels shall be provided,
with these terminals being segregated from other incoming terminals.
o Electromagnetic Compatibility - EMC
� The equipment shall be efficiently screened against EMI, RFI and conductive interference and
shall not interfere with other equipment in the vicinity or installed in the same building.
� The equipment shall be required to meet one of the relevant EMC standards (IEC, MIL, VDE,
BS, IEEE etc.).
o The entire electronic component shall be protected from airborne contaminants as per ISA 71.04
environmental conditions for process measurement and control system.
o Civil Works
i. Civil works required for interconnecting cabling between various systems, equipments,
telecommunication system and the power supply unit along with cable routing and dressing.
ii. Associated foundation, grouting for installation of equipment.
iii. Providing and laying perforated trays etc. for point a) above.
iv. Any other masonry work associated with entry and installation of equipment, painting and
finishing etc.
v. Any other civil works not specifically mentioned in the tender but required as per site
requirement.
o Electrical Works
� Electrical work associated at all the stations shall be consisting of (but not limited to):
i. All cable work including earthing and system ground earth associated with the installation of
the supplied equipment.
ii. Any temporary electrical works associated with the installation and commissioning of the
system.
iii. Testing and certification of all electrical works.
iv. All power cabling works (including supply of cables, glanding, ferruling, termination etc.).
8.0 QUALITY ASSURANCE AND QUALITY CONTROL
o Contractor shall be fully responsible for their Quality Assurance and associated Quality Control process.
o Unless otherwise agreed by the PURCHASER, the Contractor’s quality system shall meet the requirements of
ISO 9001:2015 Quality System and shall be accredited by a recognized authority.
o Contractor is required to establish an acceptable Quality Plan, inclusive of quality manual and procedures that
cover all activities of the order, in order to comply with the Quality System requirements.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 61 of 65
o Contractor shall be responsible for arranging/liaising with the Third Party Inspection Agency and other agencies
for design appraisal, inspection, survey and certification requirements as required by the
specification/requisition.
o When required, waiver and acceptance of non-conformances shall be subjected to Third Party Inspection Agency
approval before COMPANY endorsement. These concession records shall be included in the Manufacturer’s
Final Documentation.
9.0 PROJECT MANAGEMENT
9.1 General Requirements
a. Contractor shall establish and maintain the Office (PMO) at site for this project for the entire contract duration.
b. Providing & mobilizing all project management resources, as required, for performance of works. The project
management team shall be fully equipped with planning / scheduling software and analysis tools and manned with
competent and experienced manpower complete with sound project management, reporting, and project control
system.
c. The document numbering philosophy and format shall be as per the approved procedure
d. Appraisal and taking cognizance of site-conditions, Indian Government/State government rules and regulations,
bye-laws, applicable codes and standards, requirements of authorities having jurisdiction over the work site(s),
environmental and pollution concerns including conditions / stipulations laid down by the concerned authorities
etc. The Contractor is deemed to have recognized any restrictive features of the site(s) and / or specific
requirements of the work and made due allowance for it in the work to be performed forming part of this Contract.
Specific consideration shall be given to fact that the project construction also involves necessary modifications /
replacement / hook-up / tie-in works at the existing stations and the construction of pipeline involves
trenching/laying in the existing corridor having other operating pipelines and utilities. The Contractor shall also
take cognizance of other contractor’s operating/working in the same terminal / RoU, and thus will plan its work
execution accordingly to minimize interference.
e. The Owner will acquired the RoU corridor for installation of proposed pipeline & associated facilities. The details
are included in the tender document. The Contractor shall optimally plan the construction methods and limit the
construction works within the land already acquired by Owner. Any additional land as necessitated by the
Contractor for execution of works (temporary/permanent/construction aid/storage yard etc.) shall be arranged by
the Contractor at Contractor’s sole risk and cost and is included in Scope of Work of Contractor. The Owner has
also initiated the approval process for obtaining timely statutory approvals for major crossings including
rails/roads/water/utility etc. (Approval shall be provided by owner, however liasioning / final permission for
execution of construction works shall be responsibility of Contractor).
f. The alignment sheets are enclosed with the Bid Document. The Contractor shall study all such information
contained in the Bid Document and if required, shall make a site visit to familiarise himself with the site conditions.
Gist of alignment and Crossing drawing is provided herewith as Annexure-1 of this document. Accordingly, the
Contractor shall identify and plan the access to site(s) as may be required for construction of project facilities.
Any encroachment to the adjoining agriculture/farm land, private/government properties and or other such access
routes including existing infrastructure of rail/roads etc. shall be managed and resolved by the Contractor including
but not limited to discussion with local / statutory authorities having jurisdiction, stakeholders, associated
compensations and grievance resolutions. The Contractor shall absolve Owner harmless from all such disputes,
grievances by effective resolution to the satisfaction of local / statutory authorities, having jurisdiction.
g. Obtaining all necessary approvals and work permits from concerned authorities having jurisdiction, as applicable
for performing the work including shifting/relocation of existing facilities and other utilities etc., as required by
local authorities and as directed by Owner. The Contractor shall pre-inform all local authorities in advance having
jurisdiction for crossing underground utilities/pipelines wherever encountered along the pipeline route. The
Contractor shall be required to carry out all the construction works as per applicable work permits. The Scope of
Work of Contractor shall also include implementation of all the planned & incidental approval conditions as laid-
out by the statutory authorities having jurisdiction
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 62 of 65
h. Statutory Permissions: Statutory permissions from the concerned authority will be provided by owner. However,
all activities related to liaison, co-ordination etc. with authorities needed to achieve the work as per schedule will
be under Contractor’s scope including work permit before commencement of work.
i. Review, interpretation and verification of data / information furnished by Owner in the Bid Document. The Owner
does not take responsibility for correctness / adequacy of the information provided in the Bid Document. The
Contractor shall assess the requirement for any additional data and surveys/investigations that may be required to
generate all data/information necessary to substantiate his Bid Proposal and to carry out detailed design &
engineering, procurement & supply, fabrication & installation, construction, testing & pre-commissioning, and
commissioning of the facilities (temporary and permanent) forming part of this Contract.
j. The Contractor shall co-ordinate with their sub-Vendors, Suppliers, Sub-contractors, Fabricators and shall perform
all activities, as required, including but not limited to expediting, inspection & testing as applicable, transportation,
loading/unloading and liaison with the authorities etc. complete so as to timely procure and deliver the materials.
The Contractor shall also be responsible for necessary testing, verifications and checks during various stages of
procurement including product design, fabrication & testing.
k. The Contractor shall be solely responsible for timely preparation, submission, comment resolution and necessary
revision of all the documents & deliverables required for execution of the project. Major types of deliverables are
specified in this document for Bidder’s Reference. However, it is not the intention of the Owner to identify and
include the listing of all the deliverables. The Contractor shall estimate and list all such deliverables for submission
to Owner. Any exclusion by Contractor in estimating the deliverables does not relieve the Contractor of his sole
responsibility for preparation and submission of all such deliverables, as required by Owner for granting approval
for execution of works.
l. The documents and deliverables shall include but not be limited to the Master Document Register (MDR) or
Document Deliverable Register (DDR), project progress plans & schedules,
plans/layouts/drawings/sketches/schematics/isometrics, construction procedures, method statements, inspection
& test plans, environment & safety plans, inspection and testing reports, routine progress reports, close-out report
of Action Tracker etc. complete.
m. The Contractor shall provide accommodation and camping facilities to its workforce.
n. The Contractor shall take due care of the surroundings and environment. It shall be ensured that the cutting of
trees/vegetation/crops etc. is avoided to the extent possible and such action would be initiated only after taking
appropriate permissions/approvals from the concerned authorities and/or Owner. The Contractor shall provide the
replacement of any such damages as per the guidelines issued by the statutory authorities. The damage to the
environment during construction/testing (e.g. air/water pollution, sanitation, sound/noise pollution etc.) shall be
minimised and any such complaints shall be resolved to the satisfaction of concerned authorities at sole risk &
cost of Contractor.
i. In case, cutting of Trees is unavoidable, the same shall be carried out by the Contractor without any cost
implication. Any permission if required for the same shall be obtained by the Contractor.
o. Review and approval by Owner of the works performed by the Contractor, shall in no way relieve the Contractor
of his sole responsibility for scheduled & safe execution of works.
9.2 Construction Management
a. Providing & mobilizing all construction resources, as required, for execution of project. The construction team
shall be fully equipped with all tools and tackles, support facilities, consumables, construction worthy equipment
of adequate number & capacity (to work under the prevailing site conditions and meeting the expected
construction performance) and manned with competent and experienced site construction team.
b. The construction team (construction supervision as well as construction engineering) shall primarily be
responsible for performing pre-construction activities, review of all the construction / fabrication drawings prior
to start of site construction and updating same as per actual site conditions, prepare of all the construction method
statements and procedures, resolution of site queries, managing the construction activities including storage and
issuance of materials, logistics, managing the Sub-Contractors, if any complete with routine reporting of the site
progress through Daily Progress Reports (DPRs) as well as weekly/monthly construction reports complete with
look-ahead and mitigation plans. It is required that the Contractor shall depute experienced and competent team
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 63 of 65
so as to work in-sync with the engineering & procurement team, project management team, local & statutory
authorities as well as liaison with Owner’s project management team, as required. All reports shall be uploaded
on PIMS on regular basis as agreed with EIC.
c. Demobilization from site after completion of construction/testing/hook-up/tie-in works and associated pre-
commissioning and commissioning activities including clearing and restoration of site and handing over to
authorities having jurisdiction or to Owner as the case may be.
d. Prepare and Implement all approved Construction Plans & Procedures. The construction of facilities shall be
carried out in accordance with applicable construction plans and procedures, method statements, sketches,
drawings etc., which shall be timely, prepared and submitted by the Contractor for review and approval by
Owner commensurate with execution / construction plan.
e. The construction plan shall specifically address the issues related to construction of pipelines in the vicinity of
existing operating pipelines including the risk assessment and mitigation plans. In addition to the risk of damage
to existing facilities, the construction methodology/plan shall specifically address the safety of men, materials,
equipment and machinery while working in the vicinity of existing Pipelines, OH power lines / OFC cables /
catholically protected pipelines against electrocution / flux interference / earthing leakages etc.
f. Construction, maintenance and dismantling contractor’s workshops, Stores, Yards, Warehouse etc. in vicinity
of pipeline route.
g. Prepare and maintain all pipe books, vendor data books, material receipt and issue records, inspection & testing
report
h. Ensure HSE compliance for all Works to meet or exceed Company Standards.
9.3 Store & Warehouse Management
a. Contractor shall set-up “Material Storage Yard” for storage & safe custody of all types of materials as per
manufacturer’s standards/approved project requirements and deploying adequate number/capacity of material
handling equipment for loading/unloading of materials.
b. Contractor shall arrange for land for Storage Yard near to pipeline ROU, adequate to store line pipes as per the
requirements stipulated. Contractor shall enter into lease agreement with the various land owners/authorities for
usage of land adequate as per the Storage Yard plan. The area of Storage Yard and number of layers for pipes
shall be chosen so as to ensure safe handling of pipes, free movement of trailers and stresses on pipe. Contractor
shall submit the Storage Yard location and layout plan for Company’s review/ approval prior to actual
acquisition of land for the said purpose.
Contractor shall develop the Storage Yard area required for stacking/ storing of specified quantity of coated/
bare pipes. Contractor shall carry out in this regard all civil works within the Storage Yard required for temporary
storage of pipes in all types of soils such as site grading, clearing, levelling, filling-up, providing temporary
internal roads duly compacted for movement of cranes/ trailers within the Storage Yard, providing temporary
fencing and gates/ barrier, cabins etc. as per the relevant drawings and other requirements indicated in the
Contract document. Contractor shall be responsible for temporary land acquisition for Storage Yard, making
approach road as required to the Storage Yard from the nearest main road including compensation to land
owner(s) for the approach road, permission for the approach road, etc. All internal access roads shall be dressed
and consolidated by means of power driven rollers to obtain maximum compaction. Contractor shall also provide
adequate drainage within the Storage Yard(s). All levelling, dressing and consolidation works shall be carried
out as per the instructions of Company Representative. Contractor shall develop a detailed development plan of
Storage Yard including approach road and obtain Company approval prior to acquisition of land and
commencement of Storage Yard development works. The area of Storage Yard shall be chosen so as to ensure
safe handling of pipes and free movement of trailers. Contractor shall provide adequate drainage within the
Storage Yard.
c. The material storage yard shall have all the provisions for storage of materials in open spaces / sheds / climate
controlled enclosures etc. as applicable, and shall provide protection to materials against degradation (e.g. heat,
rain, dust, corrosion etc.). The layout of the yard shall provide adequate space for handling of material and
equipment movement as well as safety and escape routes. The Contractor shall be responsible for maintaining
the storage yard including levelling/grading/cutting/filling as applicable, water drainage/slope protection,
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 64 of 65
lighting/fencing etc. complete as applicable so as to ensure uninterrupted work execution. The Contractor shall
maintain a logbook of the incoming and outgoing material to ensure material traceability. The formats shall be
agreed with Owner. Rejected/defective and other such items rendered not-usable by authorized representatives
of Owner or Contractor, shall not be mixed with usable items and shall be removed from the site.
a. The contractor shall be solely responsible for Free Issue material once taken over in his custody. With regard to
FIM, the scope of contractor includes but not limited to Receiving, Taking-over, transportation, protected
storage, preservation, watch & ward and Reconciliation. Contractor shall be responsible for any
damages/shortfall in FIM reconciliation and necessary recovery shall be imposed as per bid specifications.
b. Co-ordinate with their Vendors/Suppliers/Manufacturers/Fabricators to ensure delivery of materials at site
commensurate with construction activities.
c. Perform necessary inspections/verifications/checks for incoming and outgoing materials in accordance with
approved documents. The damaged/defective items shall be segregated separately for further review/approval
by Owner for seeking permissions for subsequent repair/rejection.
10.0 INTERFACING & COORDINATION WITH SUB-CONTRACTORS / VENDORS /SPECIALIZED
AGENCIES
In addition, the following are included in contractor’s scope of work:
a. The Contractor will assure the interface and the coordination of his approved sub-contractors and also other
contractors appointed by Owner who may be working on different packages. The contractor is solely responsible
and liable for interfacing & coordination between his subcontractors if any (Civil, Mechanical, Electrical,
Instrumentation, RTU, Telecom, TCP, PCP etc.), Equipment vendors and specialized agencies such as NDT,
Commissioning, Controlled Blasting etc.
b. Contractor shall prepare the interfacing/Tie-in List showing the description of existing facilities (Civil,
Mechanical, Electrical, Instrumentation, RTU, Telecom, TCP, PCP etc.) with relevant tie-in points.
c. Any variations required for interfacing between sub-contractors / vendors /specialized agencies for efficient
running of system will be carried out by the Contractor at no extra cost to the Owner/Owner’s representative.
d. Any other work not expressly identified above but necessary to complete the construction. of Proposed pipeline
and associated works to the satisfaction of Owner and authorities having jurisdiction.
11.0 ORDER OF PRECEDENCE OF DOCUMENTS
In case of an irreconcilable conflict between Indian or other applicable standards, General Conditions of Contract,
Special Conditions of Contract, Specifications, Drawings and/or Schedule of Rates, the following shall prevail to the
extent of such irreconcilable conflict in descending order of precedence:
� Contract Agreement
� Purchase Order
� Letter of Acceptance
� Schedule of Rate
� Instructions to Bidders
� Special Conditions of Contract
� General Conditions of Contract
� Scope of Work
� Technical Specifications
In case of conflict, discrepancy, inconsistency or dispute between various technical Specifications / documents, they
shall be specifically brought into the notice of Owner/Owner’s representative; the order of precedence of documents
shall be as given below, in decreasing order of priority:
� Statutory Regulations and applicable codes & Standard
� Scope of Work
� P & IDs / Line Schedule
� Piping Material Specification/ Data Sheets
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 65 of 65
� Design Basis
� Particular Technical Specifications (PTS)
� Project drawings
� Typical drawings
� General Technical Specification (GTS)
In case of conflict between the various requirements given in this document and the requirements of other
specifications enclosed with the tender document, the requirements specified in the scope of work document shall
govern.
In general the pipeline and stations have to be built in accordance with the best state of engineering practice and
commonly used by the worldwide industry.
If any dispute arises with regards to the interpretation of any of the clauses/ detail of the bid document, the decision
of the Owner/Owner’s representative shall be final.
In case of any conflict between various requirements of specifications and code requirements, the most stringent
requirement shall be followed and the decision of Owner/Owner’s representative in the resolution of the conflict shall
be final and shall be implemented by Contractor without any time and cost implication.
Latest edition of applicable codes/Standards/Statutory Regulations, referred in the Bid Document, shall correspond
to the edition as on the date of submission of bid.
Further, in case of any conflict or discrepancy between PTS and GTS for any activity/item, the requirements of the
PTS shall prevail.
12.0 “AS BUILTS”
Contractor shall develop “As-Built” procedure and obtain Owner/Owner’s representative approval on the same.
Contractor shall record and update all As-Built information including all the changes made to the proposed Pipeline
and associated stations facilities, during Construction, in the final “As-Built” documentation.
Subsequently the contractor shall include all design specifications, drawings, datasheets, reports, Vendor data,
equipment manuals, operating and maintenance manuals etc. in the As-Built Documentation.
As built document shall be provided in PDF & Native file (AutoCAD, Word, Excel etc.). All As-Built Documentation
shall be provided in both Electronic and Hard copies as per Tender requirements.
During preparation of as-built of stations, separate as-built GAD and Plot plan drawings shall be prepared including
the GAIL facilities of Ullamparu station.
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 1 of 1
ANNEXURE – 1
ANNEXURE – 1A
ALIGNMENT SHEET DETAILS
ONGC BANTUMALLI - ULLAMPARRU PIPELINE
1 GAIL-BUPL-ALN-001 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML0.00 m 1750.00 m 1750.00 m 1750.00 m GAIL-BUPL-ALN-001 0 1 of 13
2 GAIL-BUPL-ALN-002 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML1750.00 3500.00 m 1750.00 m 3500.00 m GAIL-BUPL-ALN-002 0 2 of 13
3 GAIL-BUPL-ALN-003 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML3500.00 5250.00 m 1750.00 m 5250.00 m GAIL-BUPL-ALN-003 0 3 of 13
4 GAIL-BUPL-ALN-004 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML5250.00 m 7000.00 m 1750.00 m 7000.00 m GAIL-BUPL-ALN-004 0 4 of 13
5 GAIL-BUPL-ALN-005 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML7000.00 m 8750.00 m 1750.00 m 8750.00 m GAIL-BUPL-ALN-005 0 5 of 13
6 GAIL-BUPL-ALN-006 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML8750.00 m 10500.00 m 1750.00 m 10500.00 m GAIL-BUPL-ALN-006 0 6 of 13
7 GAIL-BUPL-ALN-007 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML10500.00 m 12250.00 m 1750.00 m 12250.00 m GAIL-BUPL-ALN-007 0 7 of 13
8 GAIL-BUPL-ALN-008 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML12250.00 m 14000.00 m 1750.00 m 14000.00 m GAIL-BUPL-ALN-008 0 8 of 13
9 GAIL-BUPL-ALN-009 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML14000.00 m 15750.00 m 1750.00 m 15750.00 m GAIL-BUPL-ALN-009 0 9 of 13
10 GAIL-BUPL-ALN-010 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML15750.00 m 17500.00 m 1750.00 m 17500.00 m GAIL-BUPL-ALN-010 0 10 of 13
11 GAIL-BUPL-ALN-011 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML17500.00 m 19250.00 m 1750.00 m 19250.00 m GAIL-BUPL-ALN-011 0 11 of 13
12 GAIL-BUPL-ALN-012 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML19250.00 m 21000.00 m 1750.00 m 21000.00 m GAIL-BUPL-ALN-012 0 12 of 13
13 GAIL-BUPL-ALN-013 0ONGC BANTUMALLI -
ULLAMPARRU TOP VIA DPML21000.00 m 21084.04 m 84.04 m 21084.04 m GAIL-BUPL-ALN-013 0 13 of 13
14A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/10 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
16500.00 m 15750.00 m 750.00 21834.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/10 OF 11 0 10 of 11
15A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/09 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
15750.00 m 14000.00 m 1750.00 23584.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/09 OF 11 0 9 of 11
16A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/08 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
14000.00 m 12250.00 m 1750.00 25334.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/08 OF 11 0 8 of 11
17A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/07 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
12250.00 m 10500.00 m 1750.00 27084.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/07 OF 11 0 7 of 11
18A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/06 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
10500.00 m 8750.00 m 1750.00 28834.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/06 OF 11 0 6 of 11
19A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/05 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
8750.00 m 7000.00 m 1750.00 30584.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/05 OF 11 0 5 of 11
20A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/04 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
7000.00 m 5250.00 m 1750.00 32334.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/04 OF 11 0 4 of 11
21A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/03 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
5250.00 m 3500.00 m 1750.00 34084.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/03 OF 11 0 3 of 11
22A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/02 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
3500.00 m 1750.00 m 1750.00 35834.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/02 OF 11 0 2 of 11
23A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/01 OF 110
4" GAIL SV STATION
ULAMPARU TO DELTA PAPER
MILL
1750.00 m 0.00 m 1750.00 37584.04 m A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/01 OF 11 0 1 of 11
SheetReferance Drawing No.Rev
No.Total Length
Start Chainage End Chainage
Cumulative ChainageRev
No.
Comulative
LengthSr. No.
Alignment
Drawing No.Section
Page 1 of 1
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 1 of 1
ANNEXURE – 1B
CROSSING DETAIILS
ONGC BANTUMALLI - ULLAMPARRU PIPELINE
Center line Chainage In
(M)
(As per Alignment Sheet) Start ChainaHe (M) End ChainaHe (M)
1 CS-01Asphalted Road ( From NaHodupalom - To SH-
113 )AR 3 419.97 416.07 424.33 419.97 8.26 HAIL-BUPL-ALN-001
2 CS-02 Kommatippa Branch Channel LC 3 2896.92 2884.52 2916.53 2896.92 32.01 HAIL-BUPL-ALN-002
3 CS-03Asphalted Road (From Kotha Pusalamarru - To
SH-113 )AR 3 5193.38 5188.26 5198.09 5193.38 9.83 HAIL-BUPL-ALN-003
4 CS-04 Enamadurru Channel LC 3 6790.22 6776.42 6804.16 6790.22 27.74 HAIL-BUPL-ALN-004
5 CS-05State HiHhway-113 ( From Kalipatnam - To
Bhimavaram )SH 3 7008.66 7003.21 7017.88 7008.66 14.67 HAIL-BUPL-ALN-005
6 CS-06 Uppukodu Drain DR 3 7327.93 7289.51 7364.83 7327.93 75.32 HAIL-BUPL-ALN-005
7 CS-07 Unlined Drain DR 3 8036.21 8032.31 8039.81 8036.21 7.50 HAIL-BUPL-ALN-005
8 CS-08Asphalted Road ( From Bhimavaram - To
Dirusumarr )AR 2 9116.55 9110.06 9122.21 9116.55 12.15 HAIL-BUPL-ALN-006
9 CS-09Metalled Road ( From Enamadurru - To Chinna
Haruvu )MR 2 9447.81 9443.91 9451.27 9447.81 7.36 HAIL-BUPL-ALN-006
10 CS-10 Unlined Drain DR 2 10193.9 10178.93 10202.12 10193.9 23.19 HAIL-BUPL-ALN-006
11 CS-11 Unlined Drain DR 2 10607.36 10601.81 10615.19 10607.36 13.38 HAIL-BUPL-ALN-007
12 CS-12 Hunupudi Drain DR 2 10792.05 10765.61 10817.13 10792.05 51.52 HAIL-BUPL-ALN-007
13 CS-13 Unlined Drain DR 1 12136.13 12133.55 12145.27 12136.13 11.72 HAIL-BUPL-ALN-007
14 CS-14 Metalled Road ( From Field - To Yamunepalle ) MR 1 12141.63 12133.55 12145.27 12141.63 11.72 HAIL-BUPL-ALN-007
15 CS-15Matsyapuri Road(ASP) ( From Bhimavaram - To
Matsyapuri )AR 1 12679.33 12672.20 12687.07 12679.33 14.87 HAIL-BUPL-ALN-008
16 CS-16 Vissakoderu Channel LC 1 13099.62 13094.33 13107.55 13099.62 13.22 HAIL-BUPL-ALN-008
17 CS-17 Unlined Drain DR 1 14208.73 14204.90 14212.15 14208.73 7.25 HAIL-BUPL-ALN-009
18 CS-18 Vissakoderu Channel LC 1 14333.74 14313.34 14367.50 14333.74 54.16 HAIL-BUPL-ALN-009
19 CS-19 Unlined Drain DR 1 15191.22 15180.78 15203.34 15191.22 22.56 HAIL-BUPL-ALN-009
20 CS-20Asphalted Road ( From HoraHanamudai - To
Bhimavaram EnH.Co )AR 3 16489.16 16479.62 16523.93 16489.16 44.31 HAIL-BUPL-ALN-010
21 CS-21 Tallikodu Channel LC 3 16509.76 16479.62 16523.93 16509.76 44.31 HAIL-BUPL-ALN-010
22 CS-22South Central Railwa ( From Bhimavaram RS -
To Pennadapalem RS(N )RY 4 16921.24 16901.02 16944.51 16921.24 43.49 HAIL-BUPL-ALN-010
23 CS-23 Unlined Channel ULC 3 17559.95 17551.75 17577.68 17559.95 25.93 HAIL-BUPL-ALN-011
24 CS-24 Metalled Road ( From Pennadapalem - ) MR 3 17800.04 17796.09 17802.66 17800.04 6.57 HAIL-BUPL-ALN-011
25 CS-25National HiHhway-65 ( From Bhimavaram - To
Viravasaram )NH 3 18085.64 18080.60 18091.76 18085.64 11.16 HAIL-BUPL-ALN-011
26 CS-26 Unlined Channel ULC 1 19707.32 19702.49 19715.03 19707.32 12.54 HAIL-BUPL-ALN-012
27 CS-27 Metalled Road ( From Vendra - To Pennada )R MR 1 19711.36 19702.49 19715.03 19711.36 12.54 HAIL-BUPL-ALN-012
Drawing TitleType of
Crossing
Width of Crossing In
(M)Ref AliHnment DrawinH No.
AR=Asphalted Road, BR=Brick Road, CT=Cart Track, DR=Drain, EW=Express Way, LC=Lined Canal, MDR=Mejor District Road, MR=Metal Road, MUR=Mud Road, NH=Netional HiHhway, NL=Nala, ODR=Other Distric Road, OR=Other Road,
RCC=RCC Road, RI=River, RY=Railway, SH=State HiHhway, ST=Stream, ULC=Unlined Canal, UMR=Unmetal Road, VR=VillaHe Road, WBM=Bitumen Road
Class
Crossing Chainage Details
(As per Alignment Sheet)
Sr. No.
Design Cumulative
Chainage
(Starting from
Bantumilli)
Cross Section
No.
Page 1 of 3
Center line Chainage In
(M)
(As per Alignment Sheet) Start ChainaHe (M) End ChainaHe (M)
Drawing TitleType of
Crossing
Width of Crossing In
(M)Ref AliHnment DrawinH No.
AR=Asphalted Road, BR=Brick Road, CT=Cart Track, DR=Drain, EW=Express Way, LC=Lined Canal, MDR=Mejor District Road, MR=Metal Road, MUR=Mud Road, NH=Netional HiHhway, NL=Nala, ODR=Other Distric Road, OR=Other Road,
RCC=RCC Road, RI=River, RY=Railway, SH=State HiHhway, ST=Stream, ULC=Unlined Canal, UMR=Unmetal Road, VR=VillaHe Road, WBM=Bitumen Road
Class
Crossing Chainage Details
(As per Alignment Sheet)
Sr. No.
Design Cumulative
Chainage
(Starting from
Bantumilli)
Cross Section
No.
28 CS-28 Metalled Road ( From FishPond - To Pennada ) MR 1 20198.53 20195.05 20226.87 20198.53 31.82 HAIL-BUPL-ALN-012
29 CS-29 Adarikodu Channel LC 1 20212.57 20195.05 20226.87 20212.57 31.82 HAIL-BUPL-ALN-012
30 CS-30 Viravasaram West Channel LC 1 20539.37 20526.53 20550.76 20539.37 24.23 HAIL-BUPL-ALN-012
27 CS-27 Field Chanal FC 1 15725.56 15721.50 15726.80 21858.48 5.30
26 CS-26 Asphalted Road AR 1 15718.75 15715.40 15721.50 21865.29 6.10
25 CS-25 Asphalted WBM Road AR 1 14490.12 14487.04 14496.34 23093.92 9.30
24 CS-24 Field Chanal FC 1 13862.96 13852.60 13865.67 23721.08 13.07
23 CS-23 Field Chanal FC 1 13348 13340.00 13351.73 24236.04 11.73
22 CS-22 Canal ULC 1 11946.36 11940.82 11950.60 25637.68 9.78
21 CS-21 Unined Canal ULC 1 11932.24 11917.06 11940.82 25651.80 23.76
20 CS-20 Asphalted Road AR 1 11676.66 11666.29 11687.66 25907.38 21.37
19 CS-19 Basavarajukodu Drain DR 1 10588.26 10563.45 10633.44 26995.78 69.99
18 CS-18 Gonteru Drain DR 1 9793.9 9757.74 9824.00 27790.14 66.26
17 CS-17 Asphalted Road AR 2 9257.68 9248.33 9261.07 28326.36 12.74
16 CS-16 Asphalted Road AR 2 8519.96 8508.54 8530.33 29064.08 21.79
15 CS-15 Asphalted Road AR 3 7904.56 7893.14 7914.93 29679.48 21.79
14 CS-14 Drain-Rapaka Channel-drain ULC 3 7842.37 7830.95 7852.74 29741.67 21.79
13 CS-13 Asphalted Road AR 3 7209.99 7198.57 7220.36 30374.05 21.79
12 CS-12 RCC Road RCC 3 6146.21 6131.74 6155.80 31437.83 24.06
11 CS-11 Asphalted Road AR 3 5829.34 5824.78 5835.24 31754.70 10.46
10 CS-10 RCC Road RCC 3 5720.61 5711.65 5724.05 31863.43 12.40
9 CS-09 Koderu No.1 Branch Canal ULC 3 5475.26 5467.56 5481.81 32108.78 14.25
8 CS-08 Asphalted Road AR 3 5170.9 5164.60 5179.91 32413.14 15.31
7 CS-07 BhaHHeswae Drain DR 2 4158.91 4141.30 4176.39 33425.13 35.09
6 CS-06 Asphalted Road AR 2 3627.06 3618.85 3631.01 33956.98 12.16
5 CS-05 Jnnuru Unlined Channel ULC 3 2792.01 2780.59 2802.38 34792.03 21.79
4 CS-04 Asphalted Road AR 3 2272.6 2263.48 2280.75 35311.44 17.27
Page 2 of 3
Center line Chainage In
(M)
(As per Alignment Sheet) Start ChainaHe (M) End ChainaHe (M)
Drawing TitleType of
Crossing
Width of Crossing In
(M)Ref AliHnment DrawinH No.
AR=Asphalted Road, BR=Brick Road, CT=Cart Track, DR=Drain, EW=Express Way, LC=Lined Canal, MDR=Mejor District Road, MR=Metal Road, MUR=Mud Road, NH=Netional HiHhway, NL=Nala, ODR=Other Distric Road, OR=Other Road,
RCC=RCC Road, RI=River, RY=Railway, SH=State HiHhway, ST=Stream, ULC=Unlined Canal, UMR=Unmetal Road, VR=VillaHe Road, WBM=Bitumen Road
Class
Crossing Chainage Details
(As per Alignment Sheet)
Sr. No.
Design Cumulative
Chainage
(Starting from
Bantumilli)
Cross Section
No.
3 CS-03 MOHALLURU DRAIN DR 3 1987.41 1971.68 2005.75 35596.63 34.07
2 CS-02 Narsapur Unlined Canal ULC 3 689.73 36894.31
1 CS-01 SH-41 SH 3 669.75 658.47 717.16 36914.29 58.69
Page 3 of 3
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 1 of 1
ANNEXURE – 1C
ALIGNMENT SHEET WISE PIPE THICKNESS
ONGC BANTUMALLI - ULLAMPARRU PIPELINE
14,473.04 6,425.00 16,336.00 350.00 - 37.58
Start
Chainage
End
ChainageTotal Length
Start
Chainage
End
ChainageTotal Length
Start
Chainage
End
ChainageTotal Length
Start
Chainage
End
ChainageTotal Length Total Length
0.00 0.00 0.00 1,750.00 1,750.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
1 GAIL-BUPL-ALN-001 0.00 0.00 1,750.00 0.00 0.00 1,750.00 1.75
0.00 0.00 1,750.00 3,500.00 1,750.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
2 GAIL-BUPL-ALN-002 0.00 0.00 1,750.00 0.00 0.00 1,750.00 3.50
0.00 0.00 3,500.00 5,250.00 1,750.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
3 GAIL-BUPL-ALN-003 0.00 0.00 1,750.00 0.00 0.00 1,750.00 5.25
0.00 0.00 5,250.00 7,000.00 1,750.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
4 GAIL-BUPL-ALN-004 0.00 0.00 1,750.00 0.00 0.00 1,750.00 7.00
0.00 8,090.00 8,750.00 660.00 7,000.00 8,090.00 1,090.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
5 GAIL-BUPL-ALN-005 0.00 660.00 1,090.00 0.00 0.00 1,750.00 8.75
0.00 8,750.00 10,500.00 1,750.00 0.00 0.00 0.00
0.00 -60.00 -60.00 60.00 60.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
6 GAIL-BUPL-ALN-006 0.00 1,690.00 60.00 0.00 0.00 1,750.00 10.50
11,303.00 12,250.00 947.00 10,500.00 11,303.00 803.00 0.00 0.00 0.00
-24.00 -24.00 24.00 24.00 0.00 0.00 0.00
0.00 -84.00 -84.00 84.00 84.00 0.00 0.00
7 GAIL-BUPL-ALN-007 923.00 743.00 84.00 0.00 0.00 1,750.00 12.25
12,250.00 14,000.00 1,750.00 0.00 0.00 0.00 0.00
-48.00 -48.00 48.00 48.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
8 GAIL-BUPL-ALN-008 1,702.00 48.00 0.00 0.00 0.00 1,750.00 14.00
14,000.00 15,750.00 1,750.00 0.00 0.00 0.00 0.00
-96.00 -96.00 96.00 96.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
9 GAIL-BUPL-ALN-009 1,654.00 96.00 0.00 0.00 0.00 1,750.00 15.75
15,750.00 16,325.00 575.00 0.00 16,325.00 16,750.00 425.00 16,750.00 17,100.00 350.00 0.00
0.00 0.00 17,100.00 17,500.00 400.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
10 GAIL-BUPL-ALN-010 575.00 0.00 825.00 350.00 0.00 1,750.00 17.50
18,485.00 19,250.00 765.00 0.00 17,500.00 18,485.00 985.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
11 GAIL-BUPL-ALN-011 765.00 0.00 985.00 0.00 0.00 1,750.00 19.25
19,250.00 21,000.00 1,750.00 0.00 0.00 0.00 0.00
-156.00 -156.00 156.00 156.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
12 GAIL-BUPL-ALN-012 1,594.00 156.00 0.00 0.00 0.00 1,750.00 21.00
21,000.00 21,084.04 84.04 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
13 GAIL-BUPL-ALN-013 84.04 0.00 0.00 0.00 0.00 84.04 21.08
16,500.00 15,750.00 750.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
14 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/10 OF 11 750.00 0.00 0.00 0.00 0.00 750.00 21.83
15,750.00 14,000.00 1,750.00 0.00 0.00 0.00 0.00
-36.00 36.00 36.00 -36.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
15 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/09 OF 11 1,786.00 -36.00 0.00 0.00 0.00 1,750.00 23.58
14,000.00 12,250.00 1,750.00 0.00 0.00 0.00 0.00
-48.00 48.00 48.00 -48.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
16 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/08 OF 11 1,798.00 -48.00 0.00 0.00 0.00 1,750.00 25.33
12,250.00 10,500.00 1,750.00 0.00 0.00 0.00 0.00
-192.00 192.00 192.00 -192.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
17 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/07 OF 11 1,942.00 -192.00 0.00 0.00 0.00 1,750.00 27.08
10,500.00 9,600.00 900.00 9,600.00 8,750.00 850.00 0.00 0.00 0.00
0.00 -48.00 48.00 48.00 -48.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
18 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/06 OF 11 900.00 898.00 -48.00 0.00 0.00 1,750.00 28.83
0.00 8,750.00 8,000.00 750.00 8,000.00 7,000.00 1,000.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
19 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/05 OF 11 0.00 750.00 1,000.00 0.00 0.00 1,750.00 30.58
0.00 0.00 7,000.00 5,250.00 1,750.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
20 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/04 OF 11 0.00 0.00 1,750.00 0.00 0.00 1,750.00 32.33
20 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/04 OF 11
19 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/05 OF 11
18 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/06 OF 11
17 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/07 OF 11
15 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/09 OF 11
16 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/08 OF 11
14 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/10 OF 11
12 GAIL-BUPL-ALN-012
13 GAIL-BUPL-ALN-013
11 GAIL-BUPL-ALN-011
9 GAIL-BUPL-ALN-009
10 GAIL-BUPL-ALN-010
8 GAIL-BUPL-ALN-008
6 GAIL-BUPL-ALN-006
7 GAIL-BUPL-ALN-007
5 GAIL-BUPL-ALN-005
4 GAIL-BUPL-ALN-004
3 GAIL-BUPL-ALN-003
2 GAIL-BUPL-ALN-002
Class - IV (12"-X70 - 8.4 thk.)
For Station
(12"-X70 -
6.4 mm thk.)Total
Length in
Meters
Total
Chainage in
km.
1 GAIL-BUPL-ALN-001
CLASS - 1 TOTAL
LENGTH
CLASS - 2 TOTAL
LENGTH
CLASS - 3 TOTAL
LENGTH
CLASS - 4 TOTAL
LENGTH
Sr.
No.Referance Drawing No.
Class - I (12"-X70 - 6.4 mm thk.) Class - II (12"-X70 - 6.4 mm thk.) Class - III (12"-X70 - 7.1 mm thk.)
Page 1 of 2
Start
Chainage
End
ChainageTotal Length
Start
Chainage
End
ChainageTotal Length
Start
Chainage
End
ChainageTotal Length
Start
Chainage
End
ChainageTotal Length Total Length
Class - IV (12"-X70 - 8.4 thk.)
For Station
(12"-X70 -
6.4 mm thk.)Total
Length in
Meters
Total
Chainage in
km.
Sr.
No.Referance Drawing No.
Class - I (12"-X70 - 6.4 mm thk.) Class - II (12"-X70 - 6.4 mm thk.) Class - III (12"-X70 - 7.1 mm thk.)
0.00 4,800.00 3,500.00 1,300.00 5,250.00 4,800.00 450.00 0.00 0.00
0.00 -60.00 60.00 60.00 -60.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
21 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/03 OF 11 0.00 1,360.00 390.00 0.00 0.00 1,750.00 34.08
0.00 3,500.00 3,200.00 300.00 3,200.00 1,750.00 1,450.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
22 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/02 OF 11 0.00 300.00 1,450.00 0.00 0.00 1,750.00 35.83
0.00 0.00 1,750.00 0.00 1,750.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
23 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/01 OF 11 0.00 0.00 1,750.00 0.00 0.00 1,750.00 37.58
23 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/01 OF 11
22 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/02 OF 11
21 A645/GAIL/PRP2/T/ULMP-DMPL/PL/ALMT/03 OF 11
Page 2 of 2
SCOPE OF WORK P.011947
D 10775
101
Rev.0 ONGC Bantumilli To Ullamparu Pipeline Project Page 1 of 1
ANNEXURE – 1D
CROSSING METHOD DETAILS
ONGC BANTUMALLI - ULLAMPARRU PIPELINE
Ref
era
nce
Dra
win
g N
o.
Rev
. N
o
Cro
ss S
ecti
on
No
.
Det
ail
s o
f C
ross
ing
Ref
Cro
ssin
g D
raw
ing
No
.
Ty
pe
of
Cro
ssin
g
Cla
ss
Cen
ter
lin
e C
ha
ina
ge
In (
M)
Sta
rt C
ross
ing
Ch
ain
ag
e (M
)
En
d C
ross
ing
Ch
ain
ag
e
(M)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-1 (
12
"-
X7
0-
6.4
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-2 (
12
"-
X7
0 -
6.4
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-3 (
12
"-
X7
0 -
7.1
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-4 (
12
"-
X7
0 -
8.4
th
k.)
Len
gth
of
Cro
ssin
gs
(CL
-
2)
(12
"-X
70
- 6
.4 t
hk
.)
Len
gth
of
Cro
ssin
gs
(CL
-
3)
(12
"-X
70
- 7
.1 t
hk
.)
Len
gth
of
Cro
ssin
gs
(CL
-
4)
(12
"-X
70
- 8
.4 t
hk
.)
Ty
pe
of
Cro
ssin
g
Min
imu
m C
ov
er T
op
of
Pip
e (m
)
Len
gth
of
HD
D (
m)
Len
gth
of
Co
ncr
ate
Co
ati
ng
(m
)
Len
gth
of
Co
ncr
ate
Sla
b (
m)
Len
gth
of
Un
case
d (
m)
Len
gth
of
Ca
ssin
g p
ipe
(m)
Len
gth
of
Ca
ssin
g p
ipe
(m)
for
Ra
ilw
ay
Rem
ark
s
LEGEND:- B=BORING, C=CASSING, CC=COCRETE COATING, CS=CS CONDUIT CASING, OC=OPEN CUT, UC=UNCASED, COS=CONCRETE SLAB, HDD=HORIZONTAL DIRECTIONAL DRILLING, TB=THRUST BORING
Total Length in Metres 485.11 189.38 581.28 43.49 600.00 252.00 - - - 1,150.00 - 363.00 446.00 275.00 45.00 -
CS-01 Asphalted Road ( From NaHodupalom - To SH-113 ) HAIL-BUPL-CS-001 AR 3 419.97 416.07 424.33 - - 8.26 - - - - OC+COS 1.5 - - 9.00 - - -
- - - - - - - - - - - - -
Total Length - - 8.26 - - - - - - 9.00 - - -
CS-02 Kommatippa Branch Channel HAIL-BUPL-CS-002 LC 3 2896.92 2884.52 2916.53 - - 32.01 - - - - B+C 1.5 - - - - 34.00 -
- - - - - - - - - - - - -
Total Length - - 32.01 - - - - - - - - 34.00 -
CS-03 Asphalted Road (From Kotha Pusalamarru - To SH-113 ) HAIL-BUPL-CS-003 AR 3 5193.38 5188.26 5198.09 - - 9.83 - - - - OC+COS 1.5 - - 10.00 - - -
- - - - - - - - - - - - -
Total Length - - 9.83 - - - - - - 10.00 - - -
CS-04 Enamadurru Channel HAIL-BUPL-CS-005 LC 3 6790.22 6776.42 6804.16 - - 27.74 - - - - B+C 1.5 - - - - 30.00 -
- - - - - - - - - - - - -
Total Length - - 27.74 - - - - - - - - 30.00 -
CS-05 State HiHhway-113 ( From Kalipatnam - To Bhimavaram ) HAIL-BUPL-CS-007 SH 3 7008.66 7003.21 7017.88 - - 14.67 - - - - B+C 1.5 - - - - 17.00 -
CS-06 Uppukodu Drain HAIL-BUPL-CS-008 DR 3 7327.93 7289.51 7364.83 - - 75.32 - - - - OC 1.5 - - - 77.00 - -
CS-07 Unlined Drain HAIL-BUPL-CS-009 DR 3 8036.21 8032.31 8039.81 - - 7.50 - - - - OC 1.5 - - - 10.00 - -
Total Length - - 97.49 - - - - - - - 87.00 17.00 -
CS-08 Asphalted Road ( From Bhimavaram - To Dirusumarr ) HAIL-BUPL-CS-010 AR 2 9116.55 9110.06 9122.21 - 12.15 - - - 24.00 - OC+COS 1.5 - - 13.00 - - -
CS-09 Metalled Road ( From Enamadurru - To Chinna Haruvu ) HAIL-BUPL-CS-011 MR 2 9447.81 9443.91 9451.27 - 7.36 - - - 12.00 - OC+COS 1.5 - - 8.00 - - -
CS-10 Unlined Drain HAIL-BUPL-CS-012 DR 2 10193.9 10178.93 10202.12 - 23.19 - - - 24.00 - OC 1.5 - - - 25.00 - -
Total Length - 42.70 - - - 60.00 - - - 21.00 25.00 - -
CS-11 Unlined Drain HAIL-BUPL-CS-013 DR 2 10607.36 10601.81 10615.19 - 13.38 - - - 24.00 - OC 1.5 - - - 15.00 - -
CS-12 Hunupudi Drain HAIL-BUPL-CS-014 DR 2 10792.05 10765.61 10817.13 - 51.52 - - - 60.00 - OC 1.5 - - - 54.00 - -
CS-13 Unlined Drain HAIL-BUPL-CS-015 DR 1 12136.13 12133.55 12145.27 11.72 - - - 12.00 - - OC 1.5 - - - 14.00 - -
CS-14 Metalled Road ( From Field - To Yamunepalle ) HAIL-BUPL-CS-016 MR 1 12141.63 12133.55 12145.27 11.72 - - - 12.00 - - OC+COS 1.5 - - 12.00 - - -
Total Length 23.44 64.90 - - 24.00 84.00 - - - 12.00 83.00 - -
CS-15 Matsyapuri Road(ASP) ( From Bhimavaram - To Matsyapuri ) HAIL-BUPL-CS-017 LC 1 12679.33 12672.2 12687.07 14.87 - - - 24.00 - - B+C 1.5 - - - - 17.00 -
CS-16 Vissakoderu Channel HAIL-BUPL-CS-018 LC 1 13099.62 13094.33 13107.55 13.22 - - - 24.00 - - B+C 1.5 - - - - 15.00 -
Total Length 28.09 - - - 48.00 - - - - - - 32.00 -
CS-17 Unlined Drain HAIL-BUPL-CS-019 DR 1 14208.73 14204.9 14212.15 7.25 - - - 12.00 - - OC 1.5 - - - 9.00 - -
CS-18 Vissakoderu Channel HAIL-BUPL-CS-020 LC 1 14333.74 14313.34 14367.5 54.16 - - - 60.00 - - B+C 1.5 - - - - 56.00 -
CS-19 Unlined Drain HAIL-BUPL-CS-021 DR 1 15191.22 15180.78 15203.34 22.56 - - - 24.00 - - OC 1.5 - - - 25.00 - -
Total Length 83.97 - - - 96.00 - - - - - 34.00 56.00 -
GAIL-BUPL-ALN-001 0
GAIL-BUPL-ALN-002 0
GAIL-BUPL-ALN-003 0
GAIL-BUPL-ALN-004 0
GAIL-BUPL-ALN-005 0
GAIL-BUPL-ALN-006 0
GAIL-BUPL-ALN-007 0
GAIL-BUPL-ALN-008 0
GAIL-BUPL-ALN-009 0
Page 1 of 3
Ref
era
nce
Dra
win
g N
o.
Rev
. N
o
Cro
ss S
ecti
on
No
.
Det
ail
s o
f C
ross
ing
Ref
Cro
ssin
g D
raw
ing
No
.
Ty
pe
of
Cro
ssin
g
Cla
ss
Cen
ter
lin
e C
ha
ina
ge
In (
M)
Sta
rt C
ross
ing
Ch
ain
ag
e (M
)
En
d C
ross
ing
Ch
ain
ag
e
(M)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-1 (
12
"-
X7
0-
6.4
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-2 (
12
"-
X7
0 -
6.4
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-3 (
12
"-
X7
0 -
7.1
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-4 (
12
"-
X7
0 -
8.4
th
k.)
Len
gth
of
Cro
ssin
gs
(CL
-
2)
(12
"-X
70
- 6
.4 t
hk
.)
Len
gth
of
Cro
ssin
gs
(CL
-
3)
(12
"-X
70
- 7
.1 t
hk
.)
Len
gth
of
Cro
ssin
gs
(CL
-
4)
(12
"-X
70
- 8
.4 t
hk
.)
Ty
pe
of
Cro
ssin
g
Min
imu
m C
ov
er T
op
of
Pip
e (m
)
Len
gth
of
HD
D (
m)
Len
gth
of
Co
ncr
ate
Co
ati
ng
(m
)
Len
gth
of
Co
ncr
ate
Sla
b (
m)
Len
gth
of
Un
case
d (
m)
Len
gth
of
Ca
ssin
g p
ipe
(m)
Len
gth
of
Ca
ssin
g p
ipe
(m)
for
Ra
ilw
ay
Rem
ark
s
LEGEND:- B=BORING, C=CASSING, CC=COCRETE COATING, CS=CS CONDUIT CASING, OC=OPEN CUT, UC=UNCASED, COS=CONCRETE SLAB, HDD=HORIZONTAL DIRECTIONAL DRILLING, TB=THRUST BORING
CS-20Asphalted Road ( From HoraHanamudai - To Bhimavaram
EnH.Co )HAIL-BUPL-CS-022 AR 3 16489.16 16479.62 16523.93 - - 44.31 - - - - OC+COS 1.5 - - 45.00 - - -
CS-21 Tallikodu Channel HAIL-BUPL-CS-023 LC 3 16509.76 16479.62 16523.93 - - 44.31 - - - - B+C 1.5 - - - - 46.00 -
CS-22South Central Railwa ( From Bhimavaram RS - To Pennadapalem
RS(N )HAIL-BUPL-CS-024 RY 4 16921.24 16901.02 16944.51 - - - 43.49 - - - B+C 1.5 - - - - - 45.00
Total Length - - 88.62 43.49 - - - - - 45.00 - 46.00 45.00
CS-23 Unlined Channel HAIL-BUPL-CS-025 ULC 3 17559.95 17551.75 17577.68 - - 25.93 - - - - OC 1.5 - - - 28.00 - -
CS-24 Metalled Road ( From Pennadapalem - ) HAIL-BUPL-CS-026 MR 3 17800.04 17796.09 17802.66 - - 6.57 - - - - OC+COS 1.5 - - 7.00 - - -
CS-25 National HiHhway-65 ( From Bhimavaram - To Viravasaram ) HAIL-BUPL-CS-027 NH 3 18085.64 18080.6 18091.76 - - 11.16 - - - - HDD 160.00 - - - - - HDD
Total Length - - 43.66 - - - - 160.00 - 7.00 28.00 - -
CS-26 Unlined Channel HAIL-BUPL-CS-028 ULC 1 19707.32 19702.49 19715.03 12.54 - - - 24.00 - - OC 1.5 - - - 15.00 - -
CS-27 Metalled Road ( From Vendra - To Pennada )R HAIL-BUPL-CS-029 MR 1 19711.36 19702.49 19715.03 12.54 - - - 24.00 - - OC+COS 1.5 - - 13.00 - - -
CS-28 Metalled Road ( From FishPond - To Pennada ) HAIL-BUPL-CS-030 MR 1 20198.53 20195.05 20226.87 31.82 - - - 36.00 - - OC+COS 1.5 - - 32.00 - - -
CS-29 Adarikodu Channel HAIL-BUPL-CS-031 LC 1 20212.57 20195.05 20226.87 31.82 - - - 36.00 - - B+C 1.5 - - - - 34.00 -
CS-30 Viravasaram West Channel HAIL-BUPL-CS-033 LC 1 20539.37 20526.53 20550.76 24.23 - - - 36.00 - - B+C 1.5 - - - - 26.00 -
Total Length 112.95 - - - 156.00 - - - - 45.00 15.00 60.00 -
- - - - - - - - - - - - -
- - - - - - - - - - - - -
Total Length - - - - - - - - - - - - -
- - - - - - - - - - - - -
- - - - - - - - - - - - -
Total Length - - - - - - - - - - - - -
CS-27 Field Chanal FC 1 15725.56 15721.5 15726.8 5.30 - - - 12.00 - - OC 1.5 - - - 7.00 - -
CS-26 Asphalted Road AR 1 15718.75 15715.4 15721.5 6.10 - - - 12.00 - - OC+COS 1.5 - - 7.00 - - -
CS-25 Asphalted WBM Road AR 1 14490.12 14487.04 14496.34 9.30 - - - 12.00 - - OC+COS 1.5 - - 10.00 - - -
Total Length 20.70 - - - 36.00 - - - - 17.00 7.00 - -
CS-24 Field Chanal FC 1 13862.96 13852.6 13865.67 13.07 - - - 24.00 - - OC 1.5 - - - 15.00 - -
CS-23 Field Chanal FC 1 13348 13340 13351.73 11.73 - - - 12.00 - - OC 1.5 - - - 14.00 - - HDD
CS-22 Canal ULC 1 11946.36 11940.82 11950.6 9.78 - - - 12.00 - - OC 1.5 - - - 12.00 - -
Total Length 34.58 - - - 48.00 - - - - - 41.00 - -
CS-21 Unined Canal ULC 1 11932.24 11917.06 11940.82 23.76 - - - 24.00 - - OC 1.5 - - - 26.00 - -
CS-20 Asphalted Road AR 1 11676.66 11666.29 11687.66 21.37 - - - 24.00 - - OC+COS 1.5 - - 22.00 - - -
CS-19 Basavarajukodu Drain DR 1 10588.26 10563.45 10633.44 69.99 - - - 72.00 - - HDD 1.5 410.00 - - - - -
CS-18 Gonteru Drain DR 1 9793.9 9757.74 9824 66.26 - - - 72.00 - - HDD 1.5 200.00 - - - - -
Total Length 181.38 - - - 192.00 - - 610.00 - 22.00 26.00 - -
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/07 OF 110
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/09 OF 110
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/08 OF 110
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/10 OF 110
GAIL-BUPL-ALN-013 0
GAIL-BUPL-ALN-010 0
GAIL-BUPL-ALN-011 0
GAIL-BUPL-ALN-012 0
Page 2 of 3
Ref
era
nce
Dra
win
g N
o.
Rev
. N
o
Cro
ss S
ecti
on
No
.
Det
ail
s o
f C
ross
ing
Ref
Cro
ssin
g D
raw
ing
No
.
Ty
pe
of
Cro
ssin
g
Cla
ss
Cen
ter
lin
e C
ha
ina
ge
In (
M)
Sta
rt C
ross
ing
Ch
ain
ag
e (M
)
En
d C
ross
ing
Ch
ain
ag
e
(M)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-1 (
12
"-
X7
0-
6.4
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-2 (
12
"-
X7
0 -
6.4
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-3 (
12
"-
X7
0 -
7.1
th
k.)
Wid
th o
f C
ross
ing
In
(M)
in C
lass
-4 (
12
"-
X7
0 -
8.4
th
k.)
Len
gth
of
Cro
ssin
gs
(CL
-
2)
(12
"-X
70
- 6
.4 t
hk
.)
Len
gth
of
Cro
ssin
gs
(CL
-
3)
(12
"-X
70
- 7
.1 t
hk
.)
Len
gth
of
Cro
ssin
gs
(CL
-
4)
(12
"-X
70
- 8
.4 t
hk
.)
Ty
pe
of
Cro
ssin
g
Min
imu
m C
ov
er T
op
of
Pip
e (m
)
Len
gth
of
HD
D (
m)
Len
gth
of
Co
ncr
ate
Co
ati
ng
(m
)
Len
gth
of
Co
ncr
ate
Sla
b (
m)
Len
gth
of
Un
case
d (
m)
Len
gth
of
Ca
ssin
g p
ipe
(m)
Len
gth
of
Ca
ssin
g p
ipe
(m)
for
Ra
ilw
ay
Rem
ark
s
LEGEND:- B=BORING, C=CASSING, CC=COCRETE COATING, CS=CS CONDUIT CASING, OC=OPEN CUT, UC=UNCASED, COS=CONCRETE SLAB, HDD=HORIZONTAL DIRECTIONAL DRILLING, TB=THRUST BORING
CS-17 Asphalted Road AR 2 9257.68 9248.33 9261.07 - 12.74 - - - 24.00 - OC+COS 1.5 - - 13.00 - - -
CS-16 Asphalted Road AR 2 8519.96 8508.54 8530.33 - 21.79 - - - 24.00 - OC+COS 1.5 - - 22.00 - - -
CS-15 Asphalted Road AR 3 7904.56 7893.14 7914.93 - - 21.79 - - - - OC+COS 1.5 - - 22.00 - - -
CS-14 Drain-Rapaka Channel-drain ULC 3 7842.37 7830.95 7852.74 - - 21.79 - - - - OC 1.5 - - - 24.00 - -
Total Length - 34.53 43.58 - - 48.00 - - - 57.00 24.00 - -
CS-13 Asphalted Road AR 3 7209.99 7198.57 7220.36 - - 21.79 - - - - OC+COS 1.5 - - 22.00 - - -
CS-12 RCC Road RCC 3 6146.21 6131.74 6155.8 - - 24.06 - - - - OC+COS 1.5 - - 25.00 - - - HDD
Total Length - - 45.85 - - - - - - 47.00 - - -
CS-11 Asphalted Road AR 3 5829.34 5824.78 5835.24 - - 10.46 - - - - OC+COS 1.5 - - 11.00 - - -
CS-10 RCC Road RCC 3 5720.61 5711.65 5724.05 - - 12.40 - - - - OC+COS 1.5 - - 13.00 - - -
CS-09 Koderu No.1 Branch Canal ULC 3 5475.26 5467.56 5481.81 - - 14.25 - - - - OC 1.5 - - - 16.00 - -
CS-08 Asphalted Road AR 3 5170.9 5164.6 5179.91 - - 15.31 - - - - OC+COS 1.5 - - 16.00 - - -
Total Length - - 52.42 - - - - - - 40.00 16.00 - -
CS-07 BhaHHeswae Drain DR 2 4158.91 4141.3 4176.39 - 35.09 - - - 36.00 - HDD 1.5 180.00 - - - - - HDD
CS-06 Asphalted Road AR 2 3627.06 3618.85 3631.01 - 12.16 - - - 24.00 - OC+COS 1.5 - - 13.00 - - -
Total Length - 47.25 - - - 60.00 - 180.00 - 13.00 - - -
CS-05 Jnnuru Unlined Channel ULC 3 2792.01 2780.59 2802.38 - - 21.79 - - - - OC 1.5 - - - 24.00 - -
CS-04 Asphalted Road AR 3 2272.6 2263.48 2280.75 - - 17.27 - - - - OC+COS 1.5 - - 18.00 - - -
CS-03 MOHALLURU DRAIN DR 3 1987.41 1971.68 2005.75 - - 34.07 - - - - OC 1.5 - - - 36.00 - -
Total Length - - 73.13 - - - - - - 18.00 60.00 - -
CS-02 Narsapur Unlined Canal ULC 3 689.73 0 0 - - - - - - - HDD 1.5 200.00 - - - - - HDD
CS-01 SH-41 SH 3 669.75 658.47 717.16 - - 58.69 - - - - HDD 1.5 - - - - - -
Total Length - - 58.69 - - - - 200.00 - - - - -
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/01 OF 110
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/04 OF 110
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/03 OF 110
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/02 OF 110
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/06 OF 110
A645/GAIL/PRP2/T/ULMP-
DMPL/PL/ALMT/05 OF 110
Page 3 of 3
RECOMMENDED VENDER LIST
LAYING AND ASSOCIATED WORKS FOR ONGC
BANTUMILLI TO ULLAMPARU PIPELINE IN KG BASIN
TRACTEBEL ENGINEERING PVT. LTD.
VENDOR LIST
0 01.05.2018 Issued for Procurement SKG SK SKH
Rev. Date Subject of revision Prepared By Checked By Approved By
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
MECHANICAL
STATION PIPE
1 Maharashtra Seamless Ltd.
2 Indian Seamless Metal Tubes
3 BHEL
4 DylanBelgie bvba, Belgium
5 F.B.F. Belgium
6 Ferrostaal (MAN Group), Germany
7 INTERFORGE
8 KURVERS Piping, Germany
9 MEREK Engineering
10 Groupe Genoyer (PHOCEENNE)
11 VAN LEEUWEN TUBES
BALL VALVES
1 CAMERON INTERNATIONAL CORPORATION
2 MSA
3 Petrol Valves S.r.L.
4 RMA Maschinen- und Armaturenbau Faulhaber & Truttenbach
5 SCHUCK ARMATUREN (ex BORSIG)
6 Tormene Gas Technology S.p.A.
7 Breda Energia Spa
8 TRP (Perar), srl, Italy
10 Microfinish Valves Pvt. Ltd.
11 Virgo Valves & Control Pvt. Ltd. ( Emerson Group)
12 L&T Valves Ltd.
13 Oswal Industries Ltd.
14 Petro Valves Pvt. Ltd.
15 Flowchem Industries
GAS OVER OIL ACTUATORS
1 BIFFI Italia s.r.l, Italy
2 Rotork fluid Sytem s.r.l
3 Shafer Actuators
4 Bettis Corporation (Emerson Group)
GLOBE VALVES
1 NSSL Limited
2 Oswal Industries Ltd
3 L&T Valves Ltd.
5 LEADER VALVES LTD.
6 Galperti Engineering & Flow control spa
7 Douglas Chero SPA
8 Niton Valves Pvt. Ltd.
9 Petro Valves Pvt. Ltd.
10 Flowchem Industries
CHECK VALVES
1 Econo Valves Pvt. Ltd.
2 L&T Valves Ltd.
4 Oswal Industries Ltd
Page 1 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
5 Weir BDK Valves
6 Flowchem Industries
7 NSSL Limited
8 Leader Valves Ltd.
9 Niton Valves Ind. Pvt. Ltd.
PRESSURE RELIEF VALVE (PRV)
1 FMC Sanmar Ltd.
2 PROTEGO India Pvt. Ltd.
3 L&T Valves Ltd.
4 Mekaster (Formerly SEBIM) Valves India Pvt. Ltd.
5 RMG Regal + Messtech GmbH, Germany
6 Tyco Valves
PIPE FITTINGS ( SEAMLESS / WELDED)
1 Groupe Genoyer (PHOCEENNE)
2 TECHNOGORGE- Italy (International Piping Group)
3 FBF Global Services Co.
4 Allied International SRL Italy
5 Bassi Luigi Fittings, Italy
6 GAM Raccordi Spa Italy
7 Groupe Genoyer (PHOCEENNE)
8 Teekay Tube
9 Pipefit Engineers Pvt. Ltd.
10 Sawan Engineers Pvt. Ltd.
11 Dee Piping System (EARLIER DEE DEVELOPMENT ENGINEERS LTD.)
12 Siddharth & Gautam
13 M.S. Fittings Manufacturing Company Pvt. Ltd.
14 Gujarat Infra Pipes Pvt. Ltd.
PIPE FITTINGS (FORGED)
1 Siddharth & Gautam
2 Commercial Supply Agency
3 Eby Industries
4 Dee Piping System (EARLIER DEE DEVELOPMENT ENGINEERS LTD.)
FLOW TEES
1 TECHNOGORGE- Italy (International Piping Group)
2 Pipefit Engineers Pvt. Ltd.
3 Multitex Filtrations
4 Sawan Engineers Pvt. Ltd.
BARRED TEES
1 TECHNOGORGE- Italy (International Piping Group)
2 Pipefit Engineers Pvt. Ltd.
3 Multitex Filtrations
4 Sawan Engineers Pvt. Ltd.
SPLIT TEES FOR HOT TAPPING
1 TD Williamson
2 Advantica
3 Furmanite International Ltd - UK
Page 2 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
FLANGES
1 Echjay Industries Pvt. Ltd.
2 CD Industries
3 CHW Forge (Choudhary Hammer Works)
4 Metal Forgins (P) Ltd.
5 Punjab Steel Works
6 JAV Forgings Pvt. Ltd.
7 C D Engineering Co.
8 J K Forgings
9 Sanghvi Forging & Engineering Ltd.
10 Pipefit Engineers Pvt. Ltd.
11 Sawan Engineers Pvt. Ltd.
Fire Fighting Equipment
a Fire Extinguisher
1 Safex Fire Services
2 Brijbasi Hi-tech Udyog
3 Nitin Fire Protection Industries Ltd.
4 Supermex Equipments
5 Kooverji Devshi & Co.
b Hire Hydrant, Monitors, Deluge Valves & Nozzles
1 Minimax\
2 Vijay Fire
3 Newage
4 Zenith
5 Nitin Fire Protection Industries Ltd.
c Hoses & Hoses accessories
1 Gayatri Industrial Corporation
2 Royal India Corporation
3 Brijbasi Hi-tech Udyog
4 Nitin Fire Protection Industries Ltd.
5 Zaverchand Marketing Pvt. Ltd.
6 Newage
7 Simplex Rubber Products
Welding Electrode
1 For Mainline- Lincoln / Bohler make
2For Terminal- For Root Pass- Lincon Make
For Other passes- Lincoln, D & H or equivalent make
NDT Agencies
1 NDT Services, Ahmedabad
2 RTD, Mumbai
3 Sievert , Mumbai
4 X-Tech- Vizag
5 Geecy Industrial Service Pvt. Ltd., Mumbai.
Page 3 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
FLAME ARRESTOR
1 Fluidyne Instruments Pvt. Ltd.
2 PROTEGO India Pvt. Ltd.
3 NIRMAL INDUSTRIAL CONTROLS PVT. LTD.
4 Super Safety Services
5 A plus Projects & Technology (P) Ltd.
FASTENERS
1 Multi Thread Fasteners ,Baroda
2 Precision Engineering Industries
3 Nireka Engg. Co. Pvt. Ltd.
4 Deepak Fasteners Ltd.
5 Fix Fit Fasteners
GASKETS
1 Goodrich Gaskets Pvt. Ltd.
2 IGP Engineers Pvt. Ltd.
3 Madras Industrial Products
4 Banco Products (P) Ltd.
5 Starflex Sealing India Pvt. Ltd.
HEAT SHRINKABLE SLEEVES
1 BERRY Plastics Corporation, Belgium- Covalence Brand
2 Denso GmbH
3 CANUSA-CPS a division of SHAWCOR INC.
COLD APPLIED TAPES
1 BERRY Plastics Corporation, Belgium- Covalence Brand
2 Denso GmbH
3 CANUSA-CPS a division of SHAWCOR INC.
PUR (TAR-FREE) COATING
1 Denso GmbH
2 BERRY Plastics Corporation, Oman/ Houston- Powercrete Brand
HOT INDUCTION BENDS
1 Fabricom
2 Jindal Saw Ltd.
3 PSL Ltd
4 Welspun Gujarat Stahl Rohren Ltd
5 Sawan Engineers Pvt. Ltd.
CASING END CLOSURE
1 RACI SPACERS INDIA PVT. LTD.
2 Raychem RPG Limited
ROCKSHIELD
1 Raychem RPG Limited
2 Denso GmbH
SPACER / INSULATOR
1 RACI SPACERS INDIA PVT. LTD.
2 Malon Technical Products
3 Advance Product s & System Inc.
4 Raychem RPG Limited
WARNING MESH / WARNING TAPES/ WARNING NET
1 Sparco Multiplast Pvt. Ltd.
2 Shri Ambica Plastic Industries
QUICK OPENING END CLOSURE
Page 4 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
1 Forain Srl, Italy
2 G.D.Engineering
3 Perry Equipment Corporation
4 Pipeline Engineering
5 Siirtec Nigi S.p.A
6 Groupe Genoyer (PHOCEENNE)
7 Rosen Group
8 TD Williamson
PIG SIGNALLER / PIG ALERTS
1 G.D.Engineering
2 Forain S.R.L
3 TD Williamson
4 Groupe Genoyer (PHOCEENNE)
CONTRACTORS FOR HDD WORK
1 Punj Lloyd Limited (India)
2 Cherington Asia (India) Pvt. Ltd.
3 Essar Construction Ltd.
4 Mersing Construction and Engineering Sdn Bhd., Selangor (Malaysia)
5 Herrenknecht (Asia) Ltd. (Thailand)
6 Mid East Pipeline
7 N.R. Patel & Co.,
8 Trenchless
CONTRACTORS FOR EGP/ INTELLIGENT PIGGING
1 Rosen Group
2 Pipeline Engineering
3 Spetsneftegaz NPO JSC (NGKS), Russia
4 TD Williamson
CONTRACTORS FOR VACCUM DRYING
1 Corrtech International Pvt. Ltd.
2 Totaline, Australia
PAINTS FOR INTERNAL COATING
1 Dupont, India
2 Performance Coating Gmbh
3 COPAN
PAINTS FOR OUTER SURFACE
1 Asian Paints Ltd.
2 Sigma Paints S.A. Ltd.
3 Berger Paints India Ltd.
4 Kansai Nerolac Paints Ltd.
CIVIL
VITREOUS CHINA SANITARYWARE
1 Parryware
2 Hindustan
3 Cera
Page 5 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
STAINLESS STEEL SINKS
1 AMC
2 Neelkanth
C.P FITTINGS
1 Parco
2 GEM
C.P ACCESSORIES, WASTE FITTINGS
1 ESS
2 Lotus
3 Orient
PVC PIPES
1 Supreme
2 Prince
GI PIPES/MS PIPES
1 TATA
COMPOSITE PIPES & FITTINGS
1 KITEC
GUN METAL VALVES AND LOCKS
1 Leader
2 Zolote
CI DOUBLE FLANGED SLUICE VALVES, NON RETURN VALVES
1 Kirloskar
STONE WARE PIPE AND GULLY TRAPS
1 Perfect
HDPE PIPES AND FITTINGS
1 Hasti
2 Oriplast
WATER TANKS
1 Sintex
ALUMINIUM HARDWARE
1 Earibihari
GLASS
1 Modiguard
2 Atul
ALUMINIUM DOOR/WINDOW SECTION
1 Hindalco
CEMENT
1 Ultratech Cements
2 Ambuja
3 ACC
4 Birla
PAINTS
1 Asian
2 Berger
3 Nerolac
4 Shalimar
5 Bombay
Page 6 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
CERAMIC/VITRIFILED/VITREOUS TILES
1 Kajaria
2 Johnson
3 Somany
STRUCTURAL STEEL
1 SAIL
REINFORCEMENT STEEL
1 TISCO
2 SAIL
ELECTRICAL
AMF DG SET
1 Sudhir Engg. Co.
2 Powerica Limited
3 Bhaskar Power Project Ltd.
4 Jakson Engineers Ltd.
SILENT D.G. SET SUPPLIER
1 Sudhir Engg. Co.
2 Powerica Limited
3 Jakson Engineers Ltd.
MAIN / SECONDARY, MEDB, DCDB & UPS DISTRIBUTION BOARD
1 Contronics Switchgear (I) Pvt. Ltd.
2 Elpro Engineering
3 RYB Switchgears Pvt. Ltd.
4 Trident Switchgears
5 Birla Ericsson Optical Ltd.
6 MileStones Switchgear Pvt. Ltd.
7 Vidhyut Control (I) Pvt. Ltd.
8 Electronic Insatrumentation & Control
9 Crompton Greaves Ltd.
10 Larsen & Toubro Ltd.
11 Control & Switchgear Co. Ltd.
POWER CABLES
1 Universal Cables Ltd., M.P.
2 Fort Gloster Industries Ltd.
3 Associated Flexibles & Wires Pvt. Ltd., Mumbai
4 NICCO Corporation Ltd., Baroda
5 Cable Corporation of India Ltd.
6 KEI Industrie Ltd.
7 Grandlay
8 Ravin Cables Ltd.
9 Thermopads Pvt. Ltd.
10 R.P.G. Cable Ltd.
11 Finolex Cable
12 Delton Cables Ltd.
13 Polycab Wire Pvt. Ltd.
14 CORDS Cable Industries
15 Finolex Cable
16 GESCAB Industries Ltd.
17 INCAB
Page 7 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
FLAMEPROOF LIGHTING FIXTURES, FLP, J.BOX/FLP SWITCH SOCKET
1 Balinga Lighting Equipments Pvt. Ltd.
2 Sudhir Switch Gears Pvt. Ltd.
3 Flame Proof Control Gears Pvt. Ltd.
4 Flame Proof Equipment Pvt. Ltd.
5 Flex Pro Electricals Pvt. Ltd., Navsari
6 CEAG
SWITCH SOCKET AND PLUGS
1 B.C.H.
2 Baliga Lighting Equipments Pvt. Ltd.
3 CGL
4 MDS
LIGHTING FIXTURES
1 Crompton Greaves Ltd.
2 Philips
3 Bajaj Electrical Ltd.
4 KESELEC Schreder
U.P.S
1 Fuji Electric Company Limited
2 Hitachi Hi-REL Controls Ltd.
3 Emmerson Network Power Management (Formerly known as Tata Libert)
4 Gutor Electronics Ltd. (L&T Representative)
5 Kerala State Electronics Development Corporation Ltd.
AIR CIRCUIT BREAKER
1 L&T / Siemens / CGL / GE / CSC / Schneider Electric
MOULDED CASE CIRCUIT BREAKER
1 L&T / Siemens / CGL / GE / SCS / Schneider Electric
SWITCH
1 L&T / Siemens / CGL / GE / CSC / Schneider Electric
FUSE
1 L&T / EE / CGL / GE / Schneider Electric / CSC
CONTACTOR
1 L&T / Siemens / CGL / GE / Schneider Electric / CSC
INSTRUMENT / METER
1 IMP / Rishab / AE
CT / PT
1 Indcoil / Gm / Koppa / Silkana / Siemens / AE / Pragati Electricals
PUSH BUTTON
1 L&T / Siemens / BCH / Kaycee
SELECTOR SWITCH
1 Kaycee
INDICATION LAMP
1 Concord / L&T / Vashinu
CABLE GLANDS
1 Control Switch Gear / Electromac / Comment / Baliga / Flameproof Control Gear
CABLE LUGS
1 Commet / Dowells / Ismail
TERMINAL BLOCKS
1 Eleme / DAV / Essem / BCH / Connect well / Tosha
2 Phonix Contact (India) Pvt. Ltd.
Page 8 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
NICKEL CADMIUM BATTERY
1 AMCO
2 HBL NIFE Power System Ltd.
LIGHTING MCB DB
1 MDS
2 Indo-Asian
3 Clipsal
4 Datar
5 Havels
6 Standard
7 Shrenik and Co., Ahmedabad
AIR CONDITIONER
1 Voltas
2 Carrier
3 LG
4 Blue Star
5 Hitachi
BATTERY CHARGER
1 Chhabi Electricals Pvt. Ltd.
2 Universal Instruments
3 HBL NIFE Power System Ltd.
PANEL
1 ICA
2 Swati Switchgears(I) Pvt. Ltd., Ahmedabad
3 Elemech Switchgears & Instrumentations, Ahmedabad
4 Rittal
5 Pyrotech Controls
6 Enclotek
I.S. BARRIER / REPEATER
1 MTL
2 P&F
TRANSFORMER
1 Patson Transformers Pvt. Ltd., Ahmedabad
2 Voltamp Transformers Pvt. Ltd., Ahmedabad
CATHODIC PROTECTION SUB-CONTRACTOR
1 Mitcorr Cathodic Protection Pvt. Ltd., Baroda
2 Corrosion Control Servcies(B) Pvt. Ltd., Mumbai
3 Raychem RPG Ltd.
4 Corrtech International Pvt. Ltd., Ahmedabad
SOLAR LIGHT
1 Saroj Urja Services Co
2 Solartech System
3 Khodiyar Enterprise
4 Hitech Industrial Corp.
INSTRUMENTATION
PRESSURE, LEVEL, DIFFERENTIAL, TEMPERATURE TRANSMITTER
1 Emerson Process Management
2 Invensys
3 Tata Honeywell
4 Fuji
5 Yokogawa Blue star
6 ABB
7 Endress & Hauser
Page 9 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
RTD WITH THERMOWELL
1 Pyroelectric Instruments
2 General Instruments
3 A.N. Instrument
PRESSURE GAUGE
1 H. Guru
2 General Instruments
3 A.N. Instrument
4 Fiebig
5 Wika
6 Baumer
PRESSURE/DIFFERENTIAL SWITCH
1 SWITZER
2 DELTA
3 UNITED ELECTRIC
4 SOR
5 GAUGE BOURDON
6 DRESSER
TEMPERATURE GAUGE WITH THERMOWELL
1 General Instruments
2 Pyroelectric Instruments
3 A.N. Instrument
FIRE & GAS DETECTION SYSTEM
1 DET-TRONIC
2 HONEYWELL
3 JOSEPH LESLIE DRAGGER
4 DETECTION INSTRUMENTS
5 OLDHAM
RELAYS
1 Omron
2 OEN
3 Jyoti
PLC
1 Allen Bradley
2 GE Fanuc
3 Bristol Babcock Inc.
4 Honeywell
5 Schnieder
6 ABB
7 Siemens
8 Emerson
MCT
1 NEIMEX
2 Signet International
3 ROTEX
OFC
1 Finolex Cable
2 Birla Ericsson Optical Ltd., Rewa (M.P.)
3 RPG Cables Limited
4 Tamilnadu Telecommunications Limited
5 U M Cables
6 Himachal Futuristic Communications Ltd.
7 Sterlite Industries (I) Ltd.
Page 10 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
HDPE DUCT FOR OFC
1 Jain Irrigation System Ltd., Jalgaon
5 Parixit Industries Ltd., Ahmedabad
6 Pennwalt Agru Plastic Ltd., Baroda
I.S BARRIER/REPEATER/SIGNAL MULTIPLIER
1 MTL
2 P&F
INSTRUMENT PANEL
1 RITTAL
2 ICA
3 Pyrotech Controls
INSTRUMENT CABLES
1 CORDS Cable Industries
2 Associated Cables
3 KEI Industries Ltd.
4 Universal Cables Ltd., M.P.
JUNCTION BOX / CABLE GLANDS / PLUGS
1 Flex Pro Electrical Pvt. Ltd., Navsari
2 Baliga
3 Exprotecta
INSTRUMENT FITTINGS, VALVES AND MANIFOLDS
1 Swagelock
2 Parker
TELECOM
1 NOKIA SIEMENS NETWORKS hiT 7025/ CORIANT
RTU
1 SYNERGY
CCTV
1 PELCO
TELEPHONE
1 Alcatel-Lucent
CORROSIVE MONITORING SYSTEM (CMS)
1 Caproco, UK
2 Corrpro, Sharjah
3 Metal Samples, USA
4 Cormon, UK
5 Atel, Italy
6 Korosi Specindo
ELECTRONIC MARKER AND LOCATOR
1 3M
2 Moeller
FIBER TERMINAL CLOSER (FTC)
1 Raychem
2 3M
3 Siemens
4 F&G
6 Keptel
7 Alcoa Fujikura Limited
THIRD PARTY INSPECTION AGENCY
1 Lloyd Register of Industrial Services
2 Technische Ulierwachungs Verein (TUV)
Page 11 of 12
RECOMMENDED VENDOR LIST FOR LAYING AND
ASSOCIATED WORKS FOR ONGC BANTUMILLI TO
ULLAMPARU PIPELINE
Sr. No. NAME OF VENDOR
3 DNV-GL
4 AIB-Vincotte
5 Bureau Veritas
6 SGS
7 American Bureau Services (ABS)
8 Velosi Certification Services
Note :
1) The details of Vendors indicated in this list are based on the information available with TE, Contractor shall verify capabilities of each vendor for producing
the required quantity with. Consultant does not Guarantee any responsibility on the performance of the Vendor, it is the contractor's responsibility to verify the
correct status of vendor and quality control of each parties and also to expedite the material in time. Contractors to also ensure that supplier / bidder selected
for Award should not be in the Holiday list of GAIL/ EIL/ MECON
2. Above vendor list is indicative only and any other vendor(s) apart from as mentioned above may be accepted subject to approval by Owner/Owners
representative based on past track record.
3. For the vendors of items not covered in above vendor list, but required for completion of project successfully, supplier shall take approval form
Owner/Owners representative for the same during project execution. Bidder shall submit the required certifications, documents, PTR and Performance letters
from clients for the same
Page 12 of 12
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
LAYING AND ASSOCIATED WORKS FOR ONGC BANTUMILLI TO ULLAMPARU PIPELINE IN KG BASIN
TRACTEBEL ENGINEERING PVT. LTD.
QUALITY ASURANCE / QUALITY CONTROL
(QA/QC) DURING CONSTRUCTION
BY CONTRACTOR
DOC. NO. P.011947 D 11037 101
0 01.05.2018 Issued for Implementation GG NC SKH
Rev Date Description Prepared By Checked By Approved By
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 1 of 1
Table of
Table of Table of
Table of Contents
1.0 ABBREVIATION .......................................................................................................... 1
2.0 PURPOSE ................................................................................................................... 1
3.0 SCOPE ........................................................................................................................ 1
4.0 RESPONSIBILITY ....................................................................................................... 1
5.0 METHODOLOGY ......................................................................................................... 1
6.0 WAIVER & DEVIATION .............................................................................................. 4
ATTACHMENT –I: WAIVER / DEVIATION PERMIT ............................................................... 5
ATTACHMENT –II: FORMAT OBSERVATION ON QUALITY ASPECTS .................................... 7
ATTACHMENT-III: REQUIREMENT FOR CONTROL OF MONITORING AND MEASURING DEVICES. .............................................................................................................................. 8
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 1 of 10
1.0 ABBREVIATION
H : Hold
IC : Inspection Certificate
IR : Inspection Report
ITP : Inspection and Test Plan
IRN : Inspection Release Note
PMC : Project Management Consultant
PO : Purchase Order
PR : Purchase Requisition
PS : Purchase Specification
QA/QC : Quality Assurance / Quality Control
QAP : Quality Assurance Plan
QTY : Quantity
R : Review
RCM : Resident Construction Manager
P : Perform
W : Witness
RW : Random Witness
2.0 PURPOSE
The purpose of this document is for uniform understanding and implementation of quality
management and quality control by contractor during construction to produce the product by
combination of various activities and role of Owner/ Consultant in verification. The management of
quality shall also cover co-ordination, review, approval audit and proper documentation of the works
performed.
3.0 SCOPE
This document shall be applicable to all construction works to be executed by CONTRACTOR.
4.0 RESPONSIBILITY
It is CONTRACTOR’s prime responsibility to arrange/produce the product conforming to contract
specifications and inspect all equipment, materials and works at various stages of execution as per the
approved QA Plans. In addition, they have to coordinate directly with the OWNER/ Consultant and
other involved agencies to give adequate confidence that the activities are performed as per approved
ITPs and necessary documentation are available. Verification by Owner/ Consultant or his
representative at any stage shall not relieve CONTRACTOR of his responsibility towards quality of
the product.
The CONTRACTOR shall comply with all statutory rules & regulations in force during execution of
work and interface with such authorities as required.
5.0 METHODOLOGY
The management of construction quality control is divided into the following categories:-
(1) Procurement of materials required for the construction work.
(2) Execution of work
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 2 of 10
5.1 Procurement Of Materials Required For The Construction Work
The CONTRACTOR shall develop list(s) defining the items to be procured along with proposed
Vendors for approval of the Owner/ Consultant. The list shall comprise of all items except vessels,
equipments, pumps, electrical/ instrumentation panels etc. which may be available directly ready for
installation or require small fabrication as per requirement. The vendor list shall be in line with the
contract document. In case, no vendor list exists in the contract for a particular item, the
CONTRACTOR shall propose a list of Vendors to Owner/ Consultant. CONTRACTOR has to satisfy
himself with the capability of the vendor to deliver the product in time with quality before proposing
him as a prospective vendor. CONTRACTOR shall submit the Quality Assurance Plans for all major
items and carry out their procurement in line with the approved plans. The CONTRACTOR can either
provide his own adequate qualified staff for inspection or employ a separate third party inspection
agency with prior approval to carry out these functions. Involvement of OWNER/ Consultant in the
quality control plan, if required, shall be defined during approval of the same.
5.2 Execution Of Work
5.2.1 The QA plans for execution shall be developed by the CONTRACTOR. OWNER/ Consultant’s
approval for the same shall be taken prior to start of the work. The final Inspection & Test Plans (ITPs
shall be developed by the CONTRACTOR as per contract specifications within fifteen (15) days after
award of work for approval by OWNER/ Consultant. For the activities which are identified as Witness
or Hold Point, specific inspection call shall be raised by the CONTRACTOR with OWNER/
Consultant in the requisite format well in advance.
CONTRACTOR shall be completely responsible for management of approved quality plans and
OWNER/ Consultant involvement will be only of Surveillance in nature to randomly check the works
at selective/critical junctures. Their role shall be to monitor that the CONTRACTOR is executing the
quality plans as per the approved drawings, employing adequately qualified staff and other resources
for various items of works. Any deviation to the specifications shall be brought to the notice of
OWNER/ Consultant in prescribed formats by CONTRACTOR for approval.
5.2.2 It is likely that the CONTRACTOR may engage sub-contractor(s)/vendors for performance of the
work. CONTRACTOR shall be responsible for ensuring the implementation of approved QA plan,
contract specifications and contract conditions through their sub-contractors to achieve the quality
during all stages of construction. It shall be the responsibility of the CONTRACTOR to ensure proper
coordination between his sub- contractor(s) and other agencies working at site.
The sub-contractor(s)/vendors selection shall be done after evaluation by the CONTRACTOR in line
with contract requirements and shall get approval of Owner/ Consultant before engaging them for the
works.
5.2.3 Storage
All the materials procured shall be stored/stacked as per the standard norms and as recommended in
various clauses of relevant codes and contract document. The storage of material shall be such as to
avoid damage to life/properties (physical and chemical) of the materials. The storage shall not cause
deterioration, rusting, mix-up etc. and hamper the other related works in any way. CONTRACTOR
shall submit his detailed warehouse plan for OWNER/ Consultant approval to manage the above in
open/covered areas.
The materials susceptible to fire shall be kept away in a separate protected place.
In general, the materials shall be kept systematically in order of their class, batch number and
identification number, so that they are accessible for the inspection by OWNER/ Consultant whenever
required and to avoid the mix up in those materials.
5.2.4 Use
The materials shall be stacked in such a way that the lot, which is procured first, will be consumed
first. For materials which are having specific expiry date/ shelf life shall not be used beyond that date
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 3 of 10
and shall be removed from site. Wherever there is any doubt about the change in properties of the
materials, such materials shall be sent to reputed approved laboratory for testing and acceptance.
5.2.5 Inspection
The CONTRACTOR shall be responsible for carrying out inspection of the materials brought at site
and conducting tests/ checks (at site or in approved laboratories) at predefined frequencies as per
contract. It is the responsibility of the CONTRACTOR to ensure that the materials used at site shall
conform to relevant codes/ standards and Manufacturer Test Certificates are available for correlation
as and when required. The CONTRACTOR shall maintain the records of all materials brought at site
and tests conducted on them.
5.2.6 In process and final Inspection
CONTRACTOR shall be responsible to arrange verification of products during in- process and final
inspection. Relevant checks and tests shall be arranged for the works performed and records
maintained. Tolerances achieved with respect to contract specification and execution drawings for
various activities/processes shall be ascertained and submitted to OWNER/ Consultant for approval.
Efforts shall be made to keep checks and controls in such a way that a non-conforming product is
avoided. However, if in an isolated case, the tolerances are beyond the acceptable values given in the
contract/execution drawings/codes, non-conformance resolution/Deviation permit need to be raised by
the CONTRACTOR and got approved/resolved from OWNER/Consultant.
5.2.7 Any Observation on quality aspects, Owner/ Consultant shall raise OQA format (attached as
Attachment-II) which has to be acknowledged & compliance to be done by the contractor within
the agreed time period.
5.2.8 The contractor shall follow the requirements given for control of monitoring and measuring
devices as per Attachment-III.
5.3 Documentation
All the necessary documentation & records shall be maintained by CONTRACTOR till completion of
project and handed over to OWNER/ Consultant in requisite copies as a part of completion
documents. Wherever OWNER/ Consultant personnel were directly involved particularly in witness
and hold point, the copies of the records shall also be provided to personnel on completing inspection
of those activities. The documentation & records shall include the following as a minimum but not
limited to:
• Approved Quality Assurance Plan
• Approved Inspection and Test Plans
• Inspection and test documents covering :
a) Manufacturer Test Certificate
b) Material Receipt Report including Inspection Release Note, if applicable and Site
Inspection and acceptance Report on quality and quantity of material
c) Site test/laboratory test Report reviewed by CONTRACTOR for acceptance vis-à-vis
to contract/code requirements for materials/including PMI report at warehouse
d) In process Verification reports of CONTRACTOR representative and OWNER/
Consultant as applicable
e) Final verification report including any test checks done for compliance
f) As-built vis-à-vis to contract/drawings including tolerances
g) As-built for erection
h) Non-conformance resolution raised by Contractor/Owner/ Consultant
i) Concession/Deviation approval by OWNER/ Consultant
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 4 of 10
j) Change order approval by OWNER/ Consultant in case there is variation from
contract
k) QA/QC Audit Reports and compliance Reports thereof
l) Mechanical Completion formats
6.0 WAIVER & DEVIATION
Contractor shall strictly comply with specifications and no deviation shall be permitted. However, if
the need for deviation arises under exceptional circumstances, such deviation shall be subject to the
approval of Owner/Owner's representative and shall be submitted through Owner / Owner's
representative in the prescribed "WAIVER /DEVIATION /EXCEPTION REQUEST" format. The
WAIVER /DEVIATION / EXCEPTION REQUEST shall also indicate the cost benefit to the Owner.
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 5 of 10
ATTACHMENT –I: WAIVER / DEVIATION PERMIT
Report No.: _____________
Date:_____________
Waiver/Deviation Permit
(TO BE RAISED BY CONTRACTOR / VENDOR)
Project :
Client :
Consultant :
Third Party Insp. :
Order/Contract No. :
Originator :
Originator Ref. :
S. No Requirement as per
Specification / Drawing
Description of Waiver /
Deviation Sought Remarks
1.
2.
3.
Why the Waiver / Deviation is required?
Contractual Implications if Waiver / Deviation is granted.
Time taken shall be More / Less / No Change
Cost of item shall be More / Less / No Change
(Detailed Break up of cost implication to be attached in a separate sheet)
Performance requirement shall be Satisfied / Not Satisfied
Under present constraints, requested waiver / deviation is most optimum for the project and does not involve any safety
and security hazard.
Date: Signature of the Originator:
Name & Seal
Recommended by Consultant (Site):
Date: Signature:
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 6 of 10
Name & Seal
Justification by Consultant (HO) (When required):
Date: Signature:
Name & Seal
Recommended by Owner (Site):
Date: Signature:
Name & Seal
Recommended by TPIA (when required):
Date: Signature:
Name: & Seal
Final Approval by PM Owner:
Date: Signature:
Name & Seal
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 7 of 10
ATTACHMENT –II: FORMAT OBSERVATION ON QUALITY ASPECTS
OBSERVATION ON QUALITY ASPECTS
Job No: No:
Name of Work: Date of Issue:
FOI/LOA No:
Issued To : M/s
Location Of Work:
Item Of Work:
Details Of Observation( Deficiency) Recommended Course Of Action
Time Allowed For Correction
Issued By:
Name:
Designation:
Signature:
Received by:
Name:
Signature:
Date and Time:
Corrective Action Report By Contractor/Vendor:
Name:
Date: Signature:
Distribution Before Resolution:
RCM/QA Mgr (EPC):
Verification Of Resolution By Issuer/OWNER(Site)/PMC(Site):
Name:
Date: Signature:
Distribution After Resolution:
RCM/QA Mgr (EPC):
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 8 of 10
ATTACHMENT-III: REQUIREMENT FOR CONTROL OF MONITORING AND MEASURING
DEVICES.
Sl.
No. Description Calibration requirements Frequency Remarks
Civil-Survey
1. Theodolite
To check for permanent
adjustments by traversing and
observing the closing error
once in a year or
project duration
whichever is earlier
Record to be
maintained
(See note below)
2. Levels
To check by Backsight/
Foresight readings, the
temporary adjustments of level
Every use
Record to
be maintained
(See note below)
3. Steel measurement
tapes
a. "Freemans" make
or BIS approved
make shall be used
b. Mutilated, or
broken tapes shall
not be used
c. Legible markings
---- ---
4. Cross staff Same as 3b&3c above --- ---
5. Distomat Actual Physical
Verification at Site
Before using
first time at site
Records to be
maintained
6. Total Station
To check for permanent
adjustments by traversing and
observing the closing error etc.
once in a year or
project duration
whichever is earlier
Record to be
maintained
(See note below)
Civil Laboratory
1. All balances-
Mechanical Check for zero error Whenever used ---
2.
Weigh
Batcher/Batching
Plant
Calibration of scales Once in three
months
Records to be
maintained
3. Cube testing
machine
Calibration certificate from
manufacturers or from reputed
Calibrating agency.
As per manufacturer
specification or once
in a year whichever
is earlier
Records to be
maintained
4. Moisture Meter Calibration of scales 6 months Records to be
maintained
Mechanical/ Electrical/ Welding
1. Pressure Gauges
Calibration certificate from
reputed laboratories or
calibrate by dead weight
testers with standard weights
or with master Gauge
Once in 6 months Records to be
maintained
2. Dial gauges Check for Zero Error Whenever used ---
3. Dead Weight
Tester
Calibration from
manufacturer or reputed
calibrating agency and
calibration certificate shall not
be older than one month from
the date of mobilization.
As per
manufacturer's
recommendation or
once in a six month
whichever is earlier.
Records
(Calibration
certificate) to
be maintained
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 9 of 10
4. Vernier caliper/ screw
gauge Check for Zero error Whenever used ---
5. Holiday tester
Calibration from
manufacturer or reputed
calibrating agency or by
calibrating by zeep meter.
Once in 6 months Records to
be maintained
6. Elcometer Check with standard test films
supplied by the manufactures Before use
Records to
be maintained
7. Universal Testing
Machine
Calibration Certificate
from any reputed third party
inspection agency. viz, CEIL,
LRS, BV, ABS, DNV or IRS.
As per manufacturer's
recommendation or
once a year whichever
is earlier
Records to
be maintained
8.
Charpy V-notch
Impact testing
machine
Calibration Certificate
from any reputed third party
inspection
agency. viz, CEIL, LRS, BV,
ABS, DNV or IRS.
As per manufacturer's
recommendation or
once in a year
whichever is earlier
Records to be
maintained
9. Hardness Testing
Machine
Check with the standard test
block supplied with the
machine as per manufacturer's
Recommendation
Before use Records to be
maintained
10.
Chemical
Analysis ,ex :PMI
etc.
Check with the
standard samples Before use
Records to be
maintained
11.
Various Digital
and Analog
meters
Calibration Certificate from
reputed laboratories or the
manufacturer
Once in Six
Months or as per
manufacturer's
recommendation
whichever is earlier.
Records to be
maintained
12.
Variable current,
voltage and
resistance generators
Calibration Certificate from
reputed
laboratories
Once in Six
months
Records to be
maintained
13. Temperature/
Pressure Recorders
Calibration from
manufacturer or any
reputed calibrating
agency
Once in Six
months
Records to be
maintained
14. Temperature gauges
Calibration Certificate
from reputed
laboratories
Once in Six months
To be discarded
in case of damage
or malfunctioning
15. Thermocouples Manufacturer's Certificate or
Chemical Check --- ---
16. Vibration probes Calibration from
reputed laboratory Once in a year
To be discarded
in case of
damage or
malfunctioning
17. Decibel-meter Calibration from
reputed laboratory Once in a Year - do-
QA/QC DURING
CONSTRUCTION BY
CONTRACTOR
P.011947
D 11037
101
Rev. 0 ONGC - Bantumalli To Ullamparu Pipeline Project Page 10 of 10
Note: If Error is found, it has to be sent to manufacturers or their agents for rectification and certification &
reputed laboratory shall be NABL accredited for relevant testing.
##----##
At the helm of the Energy Transition, Tractebel provides a full range of engineering and consulting servicesthroughout the life cycle of its clients’ projects, including design and project management. As one of the world’slargest engineering consultancy companies and with more than 150 years of experience, it's our mission to activelyshape the world of tomorrow. With about 4,400 experts and offices in 33 countries, we are able to offer ourcustomers multidisciplinary solutions in energy, water and infrastructure.
TRACTEBEL ENGINEERING PVT. LTD.Intec House 37Institutional Area, Sector 44122 002 - Gurgaon - INDIAtractebel-engie.com
Sunil KUMARtel. + 91 124 4712200fax + 91 124 [email protected]