LAX Landside Access Modernization ProgramTransportation Conformity Working GroupFebruary 23, 2016

Page 2: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 2

Los Angeles International Airport (LAX)

• LAX is the largest commercial service airport in southern California 

• 3rd busiest airport in the United States with approximately 74.9 million passengers in 2015

• LAX is the world’s busiest origin and destination airport

• Over 6,000 vehicles an hour enter LAX during peak periods

Page 3: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 3

Problem Today

All airport users must rely on an inefficient roadway system to get to or from their flight, regardless of mode choice

Page 4: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 4

Problem in the Future

If no changes are made in the future, LAWA expects an almost 20% increase in the volume of vehicles in the CTA in the peak hr.

Page 5: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016)

Landside Access Modernization Program

CTACTA

ITF WESTITF WESTITF EASTITF EAST

CONRACCONRAC

CENTER STATIONCENTER STATION

WEST STATIONWEST STATION

EAST STATIONEAST STATION

ITF WEST STATIONITF WEST STATION

METRO/ITF EAST STATION

METRO/ITF EAST STATION

APM – Automated People MoverCONRAC – Consolidated Rental Car FacilityITF – Intermodal Transportation Center

APM GUIDEWAYAPM GUIDEWAY

ConRAC STATIONConRAC STATION

5

Page 6: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 6

Element Description

Guideway • 2‐1/4 miles long• 50 to 70 feet above ground• Width Varies: 35 feet wide (typ. section) & 70 

feet wide at stations• Columns every 100 feet (typ.)

APM System Overview APM System

AVIATION BLV

D

Element Description

Trains • 4‐car trains, up to 175 feet long

Cars • Approximately 50 passengers per car, with bags

System Operation

• Up to 9 trains in simultaneous operation• 2 minute wait time

WEST ITFWEST ITF

EAST ITFEAST ITF

ConRACConRAC

CTA StationsCTA Stations

Metro 96th St. Station & Transit 

Center

Metro 96th St. Station & Transit 

Center

CENTURY BLVD

W ARBOR VITAE ST 

Page 7: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 7

Rental Car Companies at LAXConRAC

• Most rental car companies own their own land

• Approximately 30 agencies spread throughout the area

• Over 1 million one‐way trips made annually by rental car shuttles to/from the LAX Central Terminal Area

ConRAC

Page 8: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 8

Consolidated Rental Car FacilityConsensus CONRAC Concept• Customer Service Building• Ready‐Return Area• Idle Storage• Quick‐Turn‐Around (QTA) and Light 

Maintenance

CONRAC

CENTURY BLVD

W ARBOR VITAE ST 

CONRAC Station  CSB

R/R  Storage

QTA

Idle Storage Garage  

Page 9: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016)

ITFs

9

Intermodal Transportation Facility Locations

• Provide new choices for passengers to access LAX via the APM system.

• Allows LAWA to manage congestion and traffic in the CTA and the airport area.

• Each ITF designed to serve particular markets.

• Various transit options available at each ITF

ITF WESTITF WEST

ITF EASTITF EAST

Page 10: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 10

Metro – Overview & Connection

• Metro has agreed to build a 96th Street Station, to provide a rail and bus link to the airport.

• LAWA has agreed to build an APM station above the planned 96th Street Metro Station to allow for quick and convenient transfers to LAX.

Transit

Page 11: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 11

Roadway Improvements

I 405

Roads

RoadsNew roads (2 miles)Improved roads (4.5 miles)

Page 12: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016)

Conformity

Page 13: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 16

Regional Transportation Plan (RTP)• 2012‐2035 Regional 

Transportation Plan/Sustainable Community Strategies (RTP/SCS) adopted in April 2012

• Contained APM, CONRAC, and ITF for Los Angeles International Airport

• FHWA/FTA found the plan to conform to the SIP

Page 14: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 17

Regional Transportation Plan (RTP)• Draft 2016‐2040 RTP/SCS Plan released in December 2015• Draft Environmental Impact Report (EIR) released for public review• SCAG plans to adopt this Spring

Page 15: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 18

2016-2040 Regional Transportation Plan (RTP)

Page 16: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 19

2016-2040 Regional Transportation Plan (RTP)

Page 17: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 20

2016-2040 Regional Transportation Plan (RTP)

Page 18: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 21

2016-2040 Regional Transportation Plan (RTP)

Page 19: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 22

2016-2040 Regional Transportation Plan (RTP)

Page 20: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 23

2016-2040 Regional Transportation Plan (RTP)

Page 21: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 29

Conformity Approach

Approach Program Elements BasisTransportation conformity in partnership with FTA and FHWA (with SCAG, Metro, CalTranssupport)

Elements in 2016 RTP for which TransportationConformity is being secured:  APM, ConRAC, ITF, improvements to regionallysignificant roads, improvements needed to implement above elements

Title 40, Part51, §93.153(a)

General conformity for non‐transportation conformity elements

Improvements with no link to multi‐modal non‐aviation transportation.

Title 40, Part51, §93.153(b)

Page 22: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 30

Conformity Approach

Project Element in RTPTransportation Conformity

Project Element affects regionally significant 

project/facility

Transportation Conformity

Project Element directly caused by project in RTP

Transportation Conformity

All other Project Elements General Conformity

Page 23: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 31

Conformity ApproachTransportation Conformity 

(LAWA, SCAG, FTA, FHWA (and FAA if interested)) General Conformity (FAA) NEPA (FAA, FHWA, FTA, LAWA)

Determine TransportationConformity/General Conformity applicability with all agencies

Determine TransportationConformity/General Conformity applicability with all agencies

Develop air quality protocol for EA (coordinate with Transportation Conformity and General Conformity protocols)

Complete 2016 RTP and FTIP Develop protocol for General Conformityanalysis

Implement protocol with emissions and dispersion

Prepare traffic and air quality protocol for Transportation Conformity Working Group

Implement protocol Incorporate in EA

Implement Transportation Conformityprotocol – Transportation Control Measures and hotspots

Document conformity findings or determination

Transportation Conformity Working Group process

SCAG issues letter confirming Transportation Conformity

Page 24: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 34

Program Timeline

APM and ConRACoperational in 2023

ENVIRONMENTAL REVIEW

Assuming all clearances are received by 2nd

Quarter 2017

Page 25: LAX Landside Access Modernization Program · 2019-06-28 · LAX Landside Access Modernization Program Transportation Conformity Working Group February 23, 2016. ... W ARBOR VITAE

Program Briefing (2016) 37

Thank You!