21

Laura Hemming – Project Manager Jan Dodd – Project Engineer Ty Gremaux – Report Editor/CAD Tech. Cory Howell – Project Engineer

  • View
    220

  • Download
    2

Embed Size (px)

Citation preview

Laura Hemming – Project Manager

Jan Dodd – Project Engineer

Ty Gremaux – Report Editor/CAD Tech.

Cory Howell – Project Engineer

Project Location13th and Hulman Streets

Terre Haute, IN

History of Property

• Opened in 1916 as Indiana Coke and Gas Company

• Closed in 1988• Known contaminants

include: benzene, toluene, ethylbenzene, xylene, and polyaromatic hydrocarbons

January 1940

Design Requirements

• Brownfield considerations

• Environmental remediation

• Commercial and industrial use

• Hulman and 13th Street improvements

• Railroad access to site

• Location of detention pond

Site Map

13th Street

Hulman Street

Canadian Pacific Railroad

North Plat

Middle Plat

South Plat

Hulman M ini Speedway

Time Warner Cable Relay Sation L ease

ProposedDetention

Pond

N

Project Approach

Site Assessment Phase II Review &GIS Mapping

Remediation Plans

Development Scenarios

Progress to Date

• Development Envelope

• Topographic Survey

• Low Impact Development (LID)

• Codes and Regulations

• Subsurface Conditions

• Begin Phase II Review

Int. of 13th Street and Lockport Road

September 2004

Development Envelope

• Availability and location of utilities

• Floodplains, wetlands and underground mines

• Right-of-way

• Zoning restrictions

• Soil contamination

Holey Moley 800-382-5544

Topographic Survey

• Rough topographic survey completed

• Obtained complete survey performed by American Consulting Inc.

• Compared two surveys to ensure accuracy

Topographic Survey

Low Impact Development

• Bioretention considerations

• Vegetated swales

• Pervious pavements

• Cisterns

• Cost analysis

Codes & Regulations

• Risk Integrated System of Closure (RISC) document

• Federal contamination guidelines for ground water

• Design Standards and Specifications Terre Haute and Indiana Department of Transportation

Subsurface Conditions

• Preliminary geological investigation

• Compared with soil borings from Trinity Environmental Group and ATC investigations

• Limitations for development

Intersection of 13th and Hulman Streets

September 2004

Future Direction

• Finish Phase II review & GIS mapping

• IDEM response letter & proposed additional testing

• Remediation plans

• Potential development scenarios

Phase II Review & GIS Mapping

• Soil borings and analytical testing

• Location of contaminants

• Contamination density mapping (GIS)

• Brownfield research

• Federal, state, and local development requirements

• Grant availability

IDEM Response Letter & Proposed Additional Testing

• Inadequacies of initial testing• What tests need to be conducted again?

• What tests have never completed that are needed?

• How much extra will this cost?

Remediation Plans

• Specific areas or entire site

• Closure levels

• Worst-case scenario

• Plan based on current contaminant knowledge

• Cost analysis of two options

13th Street

Hulman Street

Canadian Pacific Railroad

North Plat

Middle Plat

South Plat

Hulman M ini Speedway

Time Warner Cable Relay Sation L ease

ProposedDetention

Pond

N

Potential Development Scenarios

• Site layout

• Phasing of project

• Roadway design

Phase I

Phase II

Phase III

Phase IV

Timeline

TASKSEPTEMBE

ROCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL

Site Assessment        

                                                       

Phase II Review & GIS Mapping

       

                                                       

Remediation Plans        

                                                       

Potential Development

Scenarios       

                                                       

Cost Estimation        

                                                       

Questions?