Progress since September 9th Sector 56: ELQA at cold finished Powering tests phase 2 will start this week. 2 wks. of delay w.r.t September 9 th Is this coming from the DFBA consolidation ??? Sector 67 Boil-off in progress- 2 wks. of delay w.r.t September 9 th (Logistic) Sector 78 ELQA at cold finished nQPS tests at 2kA in progress Powering tests phase 2 in progress 2 wks. of delay w.r.t September 9 th Is this coming from the DFBA consolidation ??? Sector 81 ELQA at cold in progress, some delays due to DFBA consolidation 1 wk. of delay w.r.t September 9 th Wednesday, Oct. 7th 2009K. Foraz - LMC
Citation preview
Latest on the Schedule
K. ForazLMC October 7th , 2009
Wednesday, Oct. 7th 2009 K. Foraz - LMC
Progress since September 9th• Sector 12:
• QPS IST finishing. The first sector took longer than expected, and its experiment shows that 3 steps are needed for the full
commissioning of the nQPS system. But the results are there.
• Powering tests phase 2 in progress
• Sector 23• ELQA at cold finished• nPST racks installed, the tests for 2kA will follow the 6kA tests in sector 78 Powering phase 2 of the mains will start in wk. 43 (2 wks. of delay w.r.t September 9th )
• Sector 34• DSLC filling this week-end, boil-off will be done next week, • 2 wks. of delay w.r.t September 9th (Logistic)
• Sector 45• ELQA at cold finishing, some delays due to DFBA consolidation (valves and filter)• Powering test, pahse 1 just starting• 1.5 wks. of delay w.r.t September 9th
Wednesday, Oct. 7th 2009 K. Foraz - LMC
Progress since September 9th• Sector 56:
• ELQA at cold finished• Powering tests phase 2 will start this week. • 2 wks. of delay w.r.t September 9th Is this coming from the DFBA consolidation ???
• Sector 67• Boil-off in progress- 2 wks. of delay w.r.t September 9th (Logistic)
• Sector 78• ELQA at cold finished• nQPS tests at 2kA in progress• Powering tests phase 2 in progress• 2 wks. of delay w.r.t September 9th Is this coming from the DFBA consolidation ???
• Sector 81• ELQA at cold in progress, some delays due to DFBA consolidation• 1 wk. of delay w.r.t September 9th
Wednesday, Oct. 7th 2009 K. Foraz - LMC
Schedule outcomes
• Powering phase 2 – durations (number of shifts): the experiment of
sector 12 shows that the number of shifts was overestimated,
– but the experiment of sector 12 shows that about two weeks are needed to commission the system at 2kA & 6kA (part of the powering tests).
Wednesday, Oct. 7th 2009 K. Foraz - LMC
Powering F2
Updated Schedule
Wednesday, Oct. 7th 2009 K. Foraz - LMC
Cool-down
ELQA
nQPS installation & IST
nQPS tests @2kA &6kA
Powering F1
Beam
Com
miss
ioni
ng
1.5 wks of delay w.r.t September 9th
Remaining activities
• Doors: PM18 and SPS• Floor painting• Smoothing and beam vacuum chamber alignment in sector 34• Test of UPS batteries
All the machine areas have been cleaned again, all the “alone” materials have been removed. So please keep the areas clean.
Wednesday, Oct. 7th 2009 K. Foraz - LMC
Conclusion
• Machine cold in wk.41• Powering tests phase 2– Experiment of the first sector was very good– Durations (in term of shifts) were overestimated– New tests to be included for the nQPS– End of powering tests phase 2 = wk.47 (+1.5wks)