Larry O. Daniel Prototype Integration Facility A Government Owned and Government Operated Organization Established in July 2002. Larry O. Daniel Prototype Integration Facility . In 2008 the name PIF was adopted throughout RDECOM. . Prototype Integration Facility. - PowerPoint PPT Presentation
Citation preview
1
Larry O. Daniel Prototype Integration Facility Larry O. Daniel Prototype Integration Facility A Government Owned and Government
Operated Organization Established in July 2002
In 2008 the name PIF was adopted throughout RDECOM.
2
Prototype Integration FacilityPremier Provider of Rapid Response and Integrated Hardware Solutions
A Government Owned and Government Operated (GOGO) contractor supported Enterprise established to meet the most compelling and urgent needs of the U.S. Government and our allies
PIF Products rapidly fielded directly to the warfighter• PIF products save lives• Unique Streamlined Processes developed from
Lessons Learned and Best Government and Industry Practices
• Collocation of all People in the Value Stream
PIF products cover a very broad range of requirements• Unforecasted warfighter requirements daily• Very rapid response required• Innovation with a sense of urgency
•Proven 10 Year History of Success• Unique teams for each project• 300+ Subcontractors• 2000 material vendors
“This is a technology hub for our Army, and I have been impressed with Redstone Arsenal, especially in an area called the PIF.” GEN George W Casey Jr.
US Army Chief of Staff
ISO9001:2008 Registered
3
WIDE RANGE of INNOVATION with a sense of URGENCY
Blue Force Tracker4000 fielded, 150 ConfigurationsLess than 5 yrs2004 Top Ten Greatest Inventions
WARFIGHTER FOCUSED RAPID RESPONSE APPROACH
Naval Autonomous Underwater VehicleFabricating piece parts within 2 weeks
ASPIDesign to Fielding Less than 1 year
Aviation M4 Gun Mounts 2322 sets fielded, 6 configurations
Jet Ranger5 Aircraft for Iraqi Air Force, 10 months
GMD Rocket RestraintEnabled Largest Rocket test in DOD history, 6 months
SLAMRAAM onHIMARS DEMOConcept to Test – 8 Months
RECCE VehicleFully integrated system in 120 days2007 Top Ten Greatest Inventions
FIDO/PackBot Remote Explosive Detector Initiation to field in 90 days2006 RDA Award Winner2006 Top Ten Greatest Inventions
UAV CRS - Communication Relay SystemDeveloped & fielded in 1 year2007 RDA Award Winner2007 Top Ten Greatest Inventions
Crew Extraction Brackets800 fielded in 2 weeks2006 Top Ten Greatest Inventions
Tandem HUSKYProvided improved capabilities for route clearance teams2010 Top Ten Greatest Inventions
Broad Mission
4
Engineering Design and Analysis Circuit Card Design/Layout Simulation, Analysis and Modeling Visualization Based Design Test and Documentation Obsolescence Management
Fabrication Machining and Sheet Metal Cable/Wiring Harness Assembly Circuit Assembly and test Circuit Board Fabrication and Plating Electrical and Mechanical Assembly
Integration Ground Platforms Aviation Platforms
• GGFR Assigned for Ground Operations• GFR Assigned for Flight Operations
Program Management Govt to Govt Interface Acquisition Corp Members Experienced TS/SCI PM Team On-Site Budget Office On-Site Contracting Officers
Test On-Site Airworthiness Coordination ATEC Test Coordination
Documentation Technical Data Packages Technical Manuals Maintenance Work Orders Acquisition Packages for Future
Acquisitions
Operations Support Quality Assurance Production Planning and Control Inventory Control Purchasing
One-Stop-Shop Capabilities
RAPIDLY INTEGRATE Core Competencies with other Government andIndustry Expertise to get the RIGHT TEAM for EACH PROJECT
5
GOGO Project Execution
PIF Gov PM TeamDefines Requirements
with Customer
GOGO Project Execution
PIF Gov PM TeamCreates SOW for
Contract
Prime DevelopsSOW(s) for Subs
Prime Requests Proposals from Subs
Sub(s) Draft Proposal(s)
Internal
Internal
Government Action
Prime Contractor Action
Sub-Contractor(s) Action
LEGEND
ProcureMaterials
Best Value Selection of Subs and Material Vendors
TeamingRequiredw/Subs
Dedicate internal staffor develop teaming
arrangements
PIF Gov Team DefinesExecution Strategy
Dedicate internal staffor develop teaming
arrangements
PrimeContractor Determines
Execution Strategy
ProcureMaterials
Right team rapidly responding to the WarfighterDifferent teams assembled for each taskAutomated tool for contracted activity
Project is Executed through TEAMING
6
GovernmentPrime Contractor - RDSSubcontractors
PM Design Materials Facilities Fabrication Integration
AH-64 ASPI
PM Design Materials Facilities Fabrication Integration
RECCE (JIEDDO)
PM Design Materials Facilities Fabrication Integration
FidoPackbot
PM Design Materials Facilities Fabrication Integration
PM Design Materials Facilities Fabrication Integration
A2C2S
COMM Relay
PIF projects require flexible and rapid teaming
Teaming Flexibility
7
Industry Days
December 4-6, 2013, Redstone Defense Systems will be hosting an Industry Days for the PIF at 631 Discovery Dr., Huntsville, AL
• Industry is invited to brief their capabilities &/or resources for consideration on future tasks
POCs: Jeanette Watson, (256) 313-5155, [email protected] Julio C. Driggs, (256) 876-2275, [email protected]
Teamwork
8
Summary
PIF provides rapid development and fielding of hardware directly to the warfighter
• PIF products save lives, delays cost lives PIF products cover a very broad range of
requirements• No two projects are alike• Unforecasted customer requirements• Wide range of customers and needs
PIF effectiveness and rapid response enabled by:• Flexible contract vehicle allowing rapid
contract action and subcontracting w/o limitation of companies used
• Core PIF team augmented by government network and subcontracted SMEs as required
Engineering Computer Aided Design Manufacturing Integration & Fielding