38
Resource Piling Large Load Tests using a Reaction System

Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Embed Size (px)

Citation preview

Page 1: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Resource Piling

Large Load Tests using a

Reaction System

Page 2: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

RESOURCE PILING’S

BACKGROUND

Page 3: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

3

RESOURCE PILING

Bored Piles

Secant Piles

Kentledge Load Test

Ancillary Services

Contiguous Bored Pile

Wall

Reaction System

Load Test

Core businesses

Page 4: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Achievements

• Over 30 years of Piling (since 1981)

• >489 piling projects completed

• Grade L6 (unlimited piling contracts value)

• Largest & deepest piles: Ø2.5m & 92m

• Largest Kentledge in Singapore: 5,700 ton

• Largest Reaction test in Singapore: 7,652 ton

Recent major projects: Sengkang Hospital, Marina Coastal Expressway,

Garden by the Bay, Marina Barrage, Singapore Deep Tunnel Sewerage

System, Business and Financial Centre, Tuas-A Power Station,

Page 5: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

THE PROBLEM

Page 6: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Singapore is land scarce (~700 km2). However it has an ever growing population

(latest figures are above 5.3 million people). This dense population results in a

change in infrastructure design. Hence a need for taller buildings and

underground infrastructure.

Page 7: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

The Sail @ Marina Bay BFC @ Marina South

Taller Buildings = Larger and deeper piles

Page 8: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

MCE – C483 @ Marina Coastal Expressway

Deep Tunnel, soft soil = Larger & deeper piles

Page 9: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

5700 ton Kentledge Test, Jun 10. Biggest in

Singapore

Therefore larger & taller load tests

These taller buildings and

deep underground

infrastructures (tunnels,

basements, etc.) require larger

and deeper piles. To ensure

that these piles have sufficient

capacity they are tested using

load tests.

A kentledge using concrete

blocks is one of the most

common method of doing a

load test in Singapore.

Page 10: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

If it is not properly carried out, the outcome can be catastrophic. Such an

example is seen at the Gilstead road incident on 16 Jan 2011. A Kentledge

load test failed and blocks landed onto a public road causing:

• Road closure & traffic congestion

• Gas pipe disrupted / leakage

• Church evacuated & Kindergarten temporary stop

• Negative public perception

• Deploy SCDF, SP Power Grid, Police, etc.

However... If not done properly…

Page 11: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Reaction from authorities

• WSH Council’s alert

• GEOSS committee

– Guidelines on good

practices

– Resource Piling (Mr. Foo

Hee Kang) invited

Page 12: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

THE TEAM

Page 13: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

The team Project Team Name - Designation

Chairman Foo Hee Kang – MD

Technical

Advisor

Tan Hock Seng - GM

Leader Benjamin Lee - PM

Facilitators Calvin Ng –

Coordinator

Mitram Gopal –

HSE Executive (Keller)

Members Donald Choo – Plant Mngr

Kumaresan – Site Mngr

Prabakar – Site Engineer

A team of management

staff, operational staff,

and safety personnel

was gathered to work on

a better solution to the

Kentledge using

concrete blocks for high

capacity load test.

Page 14: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

SCHEDULE

Page 15: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Oasis Hotel

•Schedule was

developed to plan and

monitor progress of the

progress

•Corrective actions

were taken when

deadlines were not met

•Overall progress was

in line with plan

Schedule of project

Implementation

Review

Root cause

analysis

Team

formation

Design solution

Gilstead rd collapse

Project planning

Page 16: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

ROOT CAUSE ANALYSIS

Page 17: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Root cause analysis

The Ishikawa model along with the 5 Why model were

used to postulate the cause of the accident at Gilstead

road.

The main conclusions were:

– Height of Kentledge leading to large toppling zone

– Inadequacy of design

Page 18: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

ALTERNATIVE SOLUTIONS

Page 19: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Alternative solutions Description Test time Safety improvment

Statnamic 10 days No dead weight but explosive

O-cell 8 days All inside the pile. Good safety

improvement.

Kentledge (steel plates) 35 days Reduced

1. height,

2. toppling zone

Reaction system 15 days Reduced:

1. height,

2. lift,

3. Toppling zone,

4. Vehicular movement

4 alternative solutions to the Kentledge using concrete blocks were considered:

Statnamic test, O-cell, Kentledge using steel plates, and Reaction system (using

reaction from piles). The table above shows the test times and safety

imrovements. Further analysis of the solutions are on next slide.

Page 20: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Statnamic O-cell Steel plates Reaction

system

$7.8 million $0.78 million

Statnamic is an

explosive test. There

are inherent risks

with the handling

explosive material

especially with

increase of test

loads.

2 main difficulties with O-

cells are in terms of the

design (accurate

placement of the O-cell in

the pile) and quality of

construction (especially

with the concrete just

below the O-cell).

Estimated cost of steel

plates for a 7,068 ton

Kentledge test is S$7.8

million. This is a huge

investment.

Estimated cost for a

7,068 ton Reaction

load test is S$0.78.

Hence this is the

preferred option

Explosive

Alternative solutions

Page 21: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Current Capacity Limitations

However, reactions systems capacities have so far been in the range of 1,500

tons to 2,000 tons. Hence the Reaction System load test would need to be re-

designed to allow test of more than 4,000 tons.

Addition factors considered during the re-designing process were

- Ease of transport,

- Assembly technique,

- New safety risks (if any),

- Time of fabrication,

- Detailed cost calculations

- etc.

Page 22: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

SELECTED SOLUTION

Page 23: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Reaction system

Reaction

Piles

Test Pile

Page 24: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

BENEFITS

Page 25: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Height reduction -

21,1

45m

m

3750

5250

7500

2176

838

912

338

381

1400

5400 3350 3350 5400

1300

2000 PileHead

835

760

15000

16

,50

0

21.2m

6.4m

A 7,068 ton Kentledge using

concrete blocks (left) would

require employees to work at a

maximum height of 21.2 m

whereas a Reaction load test of

the same capacity would

require employees to work at a

much reduced 6.4 m.

Page 26: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Toppling zone

21,1

45m

m

3750

5250

7500

2176

838

912

338

381

1400

5400 3350 3350 5400

1300

2000 PileHead

835

760

15000

16

,50

0

Area = 900m²

78.6m

Area = 5,300 m²

78.6

m

Height:

21.2m Height:

6.4m

A 7,068 ton Kentledge using concrete

blocks (left) has a toppling area of

5,300 m2 whereas a Reaction load test

of the same capacity has a toppling

area of 900 m2

Page 27: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Height Toppling

Zone Lifts Traffic Cost

Reaction

System

15 m

(70%)

Reduced

4,400 m2

(83%)

Reduced

3,900

(97%)

Reduced

425

(94%)

Reduced

S$ 182,000

(15%)

annual

savings

• Figures are based on 7,068 ton tests

• Figures compares a Reaction System load test to a Kentledge load test using concrete blocks

• Savings calculations are based on annualized costs and includes estimates of life cycles of materials such

as concrete, steel, jacks, etc.

Benefits at a glance

Page 28: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

DESIGN & STANDARDIZATION

Page 29: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Design & Standardization

The solution is standardized through the

following methods:

– Engineering design

– Method Statement

– Risk Assessments

– Safe Work Procedures

Page 30: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

IMPLEMENTATION

Page 31: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Communication

To ensure successful implementation of the solution, the work procedures, risks and

hazards need to be communicated to the supervisors, and workers. The following are

the main methods used to communicate the solution:

• Discuss with execution team

• Brief RA & SWP

• Brief lifting plan

• Pre-start talks

Page 32: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Execution

Having communicated the solution, the work is executed on site. Execution is monitored

at several points to ensure that work being carried out complies to safe work

procedures, risk assessments, permit-to-work (PTW), etc.

Page 33: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Execution

An example of the completed setup (a 7,652 ton) load test using the Reaction System at

Ophir road, Singapore.

Page 34: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

EXPANDABILITY

Page 35: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Projects completed Project Test Load Done on

Oasis Hotel @ Peck

Seah St.

5380t 2012 Aug.

M+S Project @ Ophir

Road

7652t 2012 Nov.

7652t 2012 Nov.

6240t 2013 Feb.

5046t 2013 Apr.

6240t 2013 Mar.

7532t 2013 May

TRX(Tun Razak

Exchange @

Malaysia)

7500t 2013 Oct

7500t 2013 Oct

Tampines Town Hub

@ Tampines Ave.4

7068t 2013 Nov

Page 36: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

RESULTS

Page 37: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors

Results

Tangible results

o Height of load test = Reduced

o Work-at-Height exposure height & hours = Reduced

o Number of lifts using cranes = Reduced

o Toppling zone = Reduced

o Vehicular movement on the road = Reduced

o Productivity = Increased

Intangible results

o Workers morale = Improved

o Safety awareness = Improved

o Public perception = Improved

Page 38: Large Load Tests using a Reaction System - WSH c · PDF fileHence the Reaction System load test would need to be re-designed to allow test of more than 4,000 tons. Addition factors