Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
HIGH VOLTAGE TRANSMISSION LINES (220 KV) FROM KRAFLA AND
ÞEISTAREYKIR TO BAKKI BY HÚSAVÍK. UNDERGROUND CABLE (132
KV) FROM BJARNARFLAG TO KRAFLA; NORÐURÞING,
SKÚTUSTAÐAHREPPUR MUNICIPALITY AND ÞINGEYJARSVEIT
MUNICIPALITY
THE CONCLUSIONS OF THE ICELANDIC NATIONAL PLANNING AGENCY ON THE
ENVIRONMENTAL IMPACT ASSESSMENT (EIA) (24TH NOVEMBER 2010)
This is an English translation. The original Icelandic text, is the authoritative text. Should
there be discrepancy between this translation and the authoritative text, the latter prevails.
Unofficial translation
2
Contents
1 INTRODUCTION ............................................................................................................................... 3
1.1 COMMENTS FROM THE ICELANDIC NATIONAL PLANNING AGENCY ...................................... 3
2 IMPLEMENTATION AND OBJECTIVES .............................................................................................. 6
2.1 CONNECTED CONSTRUCTION ................................................................................................ 10
2.2 OTHER OPTIONS .................................................................................................................... 12
3 RESULTS OF THE ENVIRONMENTAL IMPACT ASSESSMENT (EIA) .................................................. 14
3.1 CHARACTERISTICS AND EXTENT OF ENVIRONMENTAL EFFECTS .......................................... 14
3.2 VISUAL IMPACT AND EFFECTS ON LANDSCAPE, PROTECTION, OUTDOOR RECREATION AND
TOURISM ........................................................................................................................................... 15
3.3 EFFECTS ON GEOLOGICAL FORMATIONS .............................................................................. 24
3.4 EFFECTS ON CULTURAL RELICS .............................................................................................. 28
3.5 EFFECTS ON VEGETATION ..................................................................................................... 29
3.6 EFFECTS ON BIRDLIFE ............................................................................................................ 32
3.7 EFFECTS ON HYDROLOGICAL CONDITIONS ........................................................................... 33
3.8 EFFECTS OF ATMOSPHERIC NOISE AND ELECTRIC AND MAGNETIC FIELDS .......................... 35
3.9 STATUS OF PLANNING AND LICENCES ................................................................................... 36
4 THE ICELANDIC NATIONAL PLANNING AGENCY’S CONCLUSIONS ................................................. 38
Unofficial translation
3
1 INTRODUCTION
1.1 COMMENTS FROM THE ICELANDIC NATIONAL PLANNING AGENCY
Landsnet submitted an IEIS on high voltage transmission lines (220 kV) from Krafla and Þeistareykir
(pronounced Theistareykir) to Bakki by Húsavík and an underground cable (132 kV) from Bjarnarflag
to Krafla, Norðurþing (pronounced Nordurthing), Skútustaðahreppur Municipality and Þingeyjarsveit
(pronounced Thingeyarsveit), to be assessed by the Icelandic National Planning Agency, under the
Environmental Impact Assessment Act no. 106 / 2000 „with subsequent amendments”.
The construction project and ‘Initial Environmental Impact Statement (IEIS)’ were publically advertised
in Lögbirtingablaðið (the Official Gazette) and the Fréttablaðið and Morgunblaðið newspapers on the
30th of April, 2010 as well as Mýflugan and Hlaupastelpan on the 28th of April, 2010 and in Skarpi on
the 29th of April, 2010. The IEIS was available from the 30th of April until the 14th of June, 2010 at
the local office of the Skútustaðahreppur Municipality and Þingeyjarsveit Municipality, in the
administrative building for Norðurþing in Húsavík and at the library in Húsavík. The report was also
available at the National University Library of Iceland and at the Icelandic National Planning Agency.
The IEIS was also accessible on the internet: www.mannvit.is, www.landsnet.is and www.the Icelandic
National Planning Agency.is. The Icelandic National Planning Agency requested the opinions of
Norðurþing, Skútustaðahreppur Municipality, Þingeyjarsveit Municipality, Iceland Fire Authority, the
Icelandic Tourist Board, the Archaeological Heritage Agency of Iceland, the Public Health Authority for
Northeast Iceland, the Soil Conservation Service, the National Energy Authority, the Environment
Agency of Iceland, the Icelandic Met Office and the Icelandic Road Association. The Icelandic National
Planning Agency received seven comments/opinions during the review period and sent these to the
Developer.
Landsnet sent the assessment report on high voltage transmission lines (220 kV) from Þeistareykir to
Bakki by Húsavík and an underground cable (132 kV) from Bjarnarflag to Krafla, Norðurþing
Skútustaðahreppur Municipality and Þingeyjarsveit Municipality to the Icelandic National Planning
Agency and requested the Agency's opinion on the EIA on construction. The construction of high
voltage transmission lines is connected with proposed energy generation in the Krafla and Þeistareykir
area and the construction of the aluminium plant at Bakki. The Minister for the Environment and
Natural Resources ruled that the environmental effects of all these projects should be assessed during
the same period, in a joint assessment. The scope of the project meant that the Icelandic National
Unofficial translation
4
Planning Agency needed more than the usual four week time limit to issue an opinion (until the 25th
of November, 2010). The process included a visit to the proposed project site.
1.2 DOCUMENTS SUBMITTED FOR THE OPINION OF THE ICELANDIC NATIONAL PLANNING AGENCY
Initial Environmental Impact Statement: High voltage transmission lines (220 kV) from Krafla and
Þeistareykir to Bakki by Húsavík. Underground cable (132 kV) from Bjarnarflag to Krafla.
Skútustaðahreppur Municipality, Þingeyjarsveit Municipality and Norðurþing. April, 2010.
Other documents: The following expert reports were submitted as supporting documents:
Appendix 1: Visual impact
Ásýnd/Landslag- Aðferðafræði- Ragnar Heiðar Þrastarson, Mannvit, 2009.
Appendix 2: Energy generation
Orkuflutnings mannvirki frá Kröflu og Þeistareykjum til Húsavíkur -Jarðfræði, efnistökusvæði og
verndargildi jarðmyndana. Eiríkur Freyr Einarsson. Mannvit, 2008.
Appendix 3: Vegetation in geothermal areas
Gróðurfar á háhitasvæðum og fyrirhugðum línu- og vegstæðum á Norðausturlandi. Guðmundur
Guðjónsson, Kristbjörn Egilsson og Rannveig Thoroddsen. Unnið fyrir Landsvirkjun, Landsnet hf. og
Þeistareyki ehf. sumarið 2007.Náttúrufræðistofnun Íslands, okt. 2008 (NÍ-08009).
Appendix 4: Birdlife in the construction area
Fuglalíf á framkvæmdasvæðum fyrirhugaðra háhitavirkjana í Þingeyjarsýslum. Þorkell Lindberg
Þórarinsson og Aðalsteinn Örn Snæþórsson. Unnið fyrir Landsvirkjun, Landsnet hf. og Þeistareyki ehf.
sumarið 2007. Náttúrustofa Norðausturlands, desember 2007.
Appendix 5: Effects on tourism and outdoor recreation
Áhrif fyrirhugaðrar virkjunar á Þeistareykjum og háspennulína frá Kröflu að Bakka við Húsavík á
ferðaþjónustu og útivist. Dr. Edward H. Huijbens. Unnið fyrir Landsvirkjun, Landsnet hf. og Þeistareyki
ehf. 2007-2008. Ferðamálasetur Íslands, janúar 2008.
Appendix 6: Detailed survey
Deiliskráning vegna fyrirhugaðra framkvæmda við línustæði og orkuvinnslustöðva, Krafla-Gjástykki-
Þeystareikir-Bakki. Uggi Ævarsson. Unnið fyrir Landsvirkjun, Landsnet hf. og Þeistareyki ehf. sumarið
2007. Fornleifastofnun Íslands SES, 2007 (FS-366-07211).
Appendix 7: Þeistareykir Road/ Kísilvegur Road
Þeistareykjavegur. Þeistareykir – Kísilvegur. Vegagerð ríkisins, desember 2008.
Unofficial translation
5
The following opinions were received:
• Norðurþing, with a letter dated the 4th of June 2010.
• Skútustaðahreppur Municipality, with a letter dated the 12th of July 2010.
• Þingeyjarsveit Municipality, with a letter dated the 24th of June 2010.
• Iceland Fire Authority, with a letter dated the 12th of May 2010.
• The Archaeological Heritage Agency of Iceland, with a letter dated the 4th of June 2010.
• The Public Health Authority in Northeast Iceland, with a letter dated the 1st of June 2010.
• The Soil Conservation Agency, with a letter dated the 10th of June 2010.
• The National Energy Authority, with a letter dated the 9th of June 2010.
• Tjörneshreppur, with a letter dated the 12th of June 2010.
• The Environment Agency of Iceland, with a letter dated the 29th of June 2010.
• Icelandic Meteorological Office, with a letter dated the 28th of June 2010.
• The Icelandic Road Association, with a letter dated the 4th of June 2010.
The Icelandic Tourist Board did not respond.
Following comments were received:
• Birkir Fanndal Haraldsson, with a letter dated the 12th of June 2010.
• Dagur Jóhannesson and Arnþrúður Dagsdóttir, with a letter dated the 13th of June 2010.
• Indriði Úlfsson, in an email dated the 14th of June 2010.
• Jón Illugason, in an email dated the 14th of June 2010.
• Jónas Jónasson and Rósa Kjartansdóttir, in an email dated the 13th of June 2010.
• The Icelandic Environment Association, in an email dated the 14th of June 2010.
• Iceland Nature Conservation Association, with a letter dated the 14th of June 2010.
• Ragnar Þór Árnason, on behalf of the residents and owners of land in Einarsstaðir, Skarð and
Skarðaborg in Reykjahverfi, with a letter dated the 11th of June 2010.
The comments from the Iceland Nature Conservation Association were responded to in a joint
assessment for the aluminium plant at Bakki, Þeistareykir Geothermal Power Station, Krafla
Geothermal Power Station II and the high voltage transmission line from Krafla and Þeistareykir to
Bakki.
Assessment report: High voltage transmission lines (220 kV) from Krafla and Þeistareykir to Bakki by
Húsavík. Underground cable (132 kV) from Bjarnarflag to Krafla. Skútustaðahreppur, Þingeyjarsveit
and Norðurþing Municipalities. October, 2010.
Unofficial translation
6
Other documents: The assessment report was accompanied by the same expert reports referred to in
the IEIS as well as appendix 8: Comments and opinions during the review period of the IEIS.
2 IMPLEMENTATION AND OBJECTIVES The assessment report states that Landsnet plans to construct two 220 kV high voltage transmission
lines, approximately 120 km in length, with the aim of transmitting electricity from power stations in
high temperature areas in Krafla and Þeistareykir to Bakki by Húsavík. A 10km underground cable
(132 kV) will also be laid from the power station in Bjarnarflag to the Krafla Geothermal Power Station.
The high voltage transmission lines will be constructed in five phases: Krafla Lines 4 and 5,
Hólasandur Lines 1 and 2 and Þeistareykir Line 1. All phases will be able to transmit 500 MVA and
Hólasandur Line 1 and Þeistareykir Line 1 will be able to transmit approx. 950 MVA. Galvanised
steel frame transmission towers with a concrete base (M-type, 14-30 m in height but mostly 22-23 m)
will be used as supporting transmission towers for the high voltage transmission lines. Corner
transmission towers will mostly be steel frame columns. Guy wires from transmission towers will be
connected to the ground using anchors (anchoring plates or anchoring bolts).
Krafla Line 1 will run alongside Krafla Lines 4 and 5, from the substation at the Krafla Geothermal Power
Station in (across the southern part of the Leirhnjúkshraun Lava Field), westward to Hrafnabjörg and
the substation in Hólasandur. Hólasandur Lines 1 and 2 take over at this point and run in separate
directions. Hólasandur Line 1 will run to the west of the Lambafjöll Mountains and northward, past
Geldingadal and Höskuldsvatn Lake, whereas Hólasandur Line 2 will run northward from the
substation, up to the Kvíhólafjöll Mountains and past the Bæjarfjall Mountain up to the substation by
Þeistareykir. Þeistareykir Line 1 will run from the substation at Þeistareykir and across
Jónsnípuskarð Pass up to Höskuldsvatn Lake. Þeistareykir Line 1 will meet Hólasandur Line 1 to the
west of Höskuldsvatn Lake and the lines will run alongside each other northward between the
Krubbsfjall Mountain and Gyðuhnjúkur and up to the substation at the proposed industrial site at
Bakki by Húsavík.
Table 1: Key indices of individual lines (table 2.2 page 16 in the assessment report).
KR4 KR5 HS1 HS2 TR1 Total
Length, km 14 14 44 19 29 120
Estimated
number of
transmission
towers
48 48 134 57 88 375
Average
spanlength,
m
294 292 331 332 331 320
Average
height
transmission
towers
22 22 23 23 23 23
Unofficial translation
7
The underground cable will be laid from Bjarnarflag Geothermal Power Station and up to þjóðvegur 1
(National Road 1) and alongside the road across Námaskarð. The cable will run alongside a water
pipeline from Námaskarð and up to the access road to Krafla Geothermal Power Station. The cable will
then follow the road up to the Krafla Geothermal Power Station substation. The cable will be laid in a
canal which will be 1 m in depth and 1.5 m in width. The cable is expected to transmit at least 110
MVA. The substation for high voltage transmission lines will be in Bjarnarflag, by Krafla and in
Hólasandur, Þeistareykir and Bakki. The trails alongside the lines will be 4 m in width and 10-50 cm in
height. The trails will mostly be new and will cover a distance of 95 km. Older trails in need of
reinforcement will also be used but new rails will be created from the old trails and up to the
transmission tower bases. The final location of trails will be decided during the construction period.
The estimated total quantity of filling materials for trails, construction pads, foundations and anchors
will be 250,000 m3, of which 20,000 m3 will be used for construction pads. Materials will be extracted
from 27 material extraction areas, controlled by the Icelandic Road Association, Landsnet, Landsvirkjun
and Þeistareykir ehf. New extraction sites (mines) will also be needed.
The purpose of the high voltage transmission line project is to ensure the supply of electricity to
industrial sites at Bakki by Húsavík from high temperature areas in Þingeyjarsýsla District, as well
as facilitating increased general electricity usage within the area. The purpose of underground cables
between Krafla Lines 4 and 5 (KR4 and 5), Hólasandur Line 1 and 2 (HS1 and 2), Þeistareykir Line 1 (TR1)
Bjarnarflag Geothermal Power Station and Krafla Geothermal Power Station is to connect
Bjarnarflag Geothermal Power Station with Landsnet‘s transmission network.
The IEIS shows that Dagur Jóhannesson and Arnþrúður Dagsdóttir repeatedly objected to plans to raise
high voltage transmission lines across the Jónsnípuskarð Pass. They voiced this opinion both in
connection with the Regional Plan for high temperature areas in Þingeyjarsýsla District and in
connection with the advertised draft of the assessment plans for the high voltage transmission line
from Krafla across Þeistareykir and up to Bakki. They recommended that the high voltage transmission
line from Þeistareykir should be laid alongside the proposed road for Þeistareykir Geothermal Power
Station and between Höfuðreiðarmúla and Sæluhúsmúla (Option A1c in the EIA for the Regional
Plan) instead of across Jónsnípuskarð Pass (Option A1d). The line across Jónsnípuskarð Pass would
cause significant disturbance to land and would have a significant visual impact. Jónsnípuskarð Pass is
also located in an area known for volatile weather conditions and icing, whereas the line to the north
of Höfuðreiðarmúla would be better sheltered. The cooperative committee for the Regional Plan has
pointed out that the assessment on the visual impact of the proposed options was in fact part of the
EIA of the plan and the line across Jónsnípuskarð Pass would be 1.3 km shorter than a line to the north
of Höfuðreiðarmúla.
Unofficial translation
8
The opinion given by Dagur Jóhannesson and Arnþrúður Dagsdóttir on the draft for assessment plans
also pointed out that the criteria developed for the EIA of the Regional Plan was unsatisfactory and the
high voltage transmission line between Höfuðreiðarmúla and Sæluhúsmúla should not have been
rejected. The EIA on construction could be utilised to discuss and assess the positive aspects of each
option i.e. a high voltage transmission line across Jónsnípuskarð Pass and between Höfuðreiðarmúla
and Sæluhúsmúla. Landsnet responded that the Regional Plan had discussed different transmission
line routes the visual impact was assessed and discussed in the IEIS. Finally, Dagur and Arnþrúður
point out the fact that the IEIS only assessed the visual impact of the line across Jónsnípuskarð Pass
and that a comparison of the proposed options had not been completed. High voltage transmission
lines across Jónsnípuskarð Pass would affect a 7 km stretch of untouched land and the roads and
transmission towers would be obvious to the naked high in mountain ridge areas. This type of
disturbance would not be justified by the fact that the proposed high voltage transmission lines would
be 1.3 km shorter. The construction of the line alongside the proposed power station road could
however decrease the negative environmental effects of the project.
Landsnet´s response reaffirms the results of the EIA of the Regional Plan for high temperature areas
which states that both transmission routes: Route A1d across Jónsnípuskarð Pass and A1c to the north
of Höfuðreiðarmúla, will both traverse the Þeistareykir Lava Field. The route across Jónsnípuskarð
Pass runs along the Þeistareykir Lava Field to the west from Guðfinnugjá and traverses less disturbed
land than the route across Höfuðreiðarmúla. The transmission route for Höfuðreiðarmúla conforms
to the policy outlined in the plan which states that roads and lines should run alongside each other
wherever possible but there is another line already located in the area (Kópasker Line) and there would
be negative, combined effects if another line were to be added to the area. The route across
Jónsnípuskarð Pass better reflects the policy set out by Norðurþing that high voltage transmission lines
should run to the west of Höskuldsvatn Lake and to Bakki by Húsavík. Option A1d was chosen as a
result of this. This would enforce Norðurþing‘s policy and the environmental criteria set out in the
Regional Plan: The lines would partly run alongside the proposed road from Húsavík to Þeistareykir
and then across the lava in a smaller area than the route outlined in the Höfuðreiðarmúla option (A1c).
Landsnet‘s response points out that the cooperative committee for the Regional Plan did not agree
with the rationale presented by Dagur and Arnþrúður and there had been no indication that the
transmission route could change as a result of visual impact. The relative parties within the
municipalities will therefore include the Jónsnípuskarð Pass route in their general/master plan. The
IEIS only included the options that had already been approved in the Regional Plan and their visual
impact assessed. The report did not compare all possible options at the Regional Plan stage. Landsnet
supplied photographs and computer-generated images which show that the proposed transmission
Unofficial translation
9
towers and trails across Jónsnípuskarð Pass would merge neatly with the landscape and would not be
obvious from busy areas. Landsnet concludes that high voltage transmission lines across
Jónsnípuskarð Pass would not have a significant visual impact. Landsnet also points out the fact that
the proposed high voltage transmission lines across Jónsnípuskarð Pass will cross the Kópasker Line
(by Árnahvammur) which would mean that specialised transmission towers would not be required.
However, these transmission towers would be required if the line were to pass through rather narrow
land by Höfuðreiðarmúla. The lines from Þeistareykir would cross the Kópasker Line and turn sharply
westward, running alongside the Kópasker Line (the lines would vary in height). This would create a
strange mix of mismatched tower types which could potentially have a significant visual impact. There
would also be a significant combined negative effect of the line and the proposed road to Þeistareykir.
These issues were considered when the municipalities approved the Regional Plan for high
temperature areas, with a transmission line across the Jónsnípuskarð Pass. The route across
Jónsnípuskarð Pass is also 1.3 km shorter and would cause fewer disturbances to the lava than the
Höfuðreiðarmúla route. Landsnet believes that there is no significant difference between the
Jónsnípuskarð Pass and Höfuðreiðarmúla option with regard to the security of supply, when icing
issues are considered.
The Icelandic National Planning Agency points out that the Minister for the Environment and Natural
Resources approved the Regional plan for high temperature areas in Þingeyjarsýslu 2007 - 2025
in January of 2008. The procedure for the Regional Plan was in accordance with the Planning and
Building Act No. 73/1997 and the Environmental Assessment of Plans and Programmes Act No.
105/2006. The Regional Plan outlines a clear policy on the utilisation of high temperature areas in
Krafla, Bjarnarflag, Þeistareykir and in Gjástykki as well as the policy on the construction of high voltage
transmission line, power station roads and the demarcation of protected areas by energy generation
areas. The scope of the EIA reflected its accuracy and the role of the Regional Plan. Specific research
was not undertaken as baseline data on environmental aspects that could be potentially affected was
utilised. The construction project policies outlined in the Regional Plan would eventually be subject
to Act No. 106/2000 on environmental effects and the process, which would be based on more exact
data, could lead to a result that would require changes to the policy outlined in the Regional Plan. This
type of change would require the approval of the municipalities involved in the development of the
Regional Plan but there is generally nothing to prevent more extensive data leading to changes in the
policies outlined for regional planning.
Security of supply must be ensured as far as possible in the proposed construction of high voltage
transmission lines from Krafla across Þeistareykir and up to Bakki. Potential environmental effects
must also be minimised and the Icelandic National Planning Agency believes that in cases where both
Unofficial translation
10
options fulfil security concerns, then the regulations on the environmental impact of construction
should be considered and the option with the least environmental impact should be chosen. The
Icelandic National Planning Agency has concluded that the Environmental Impact Assessment (EIA)
shows that the route chosen for the high voltage transmission line across Jónsnípuskarð Pass will have
a significant and irreversible negative impact on the Þeistareykir Lava Field (see chapters 3.2 and 3.3).
Landsnet proposed two options for Þeistareykir Line 1 as a result of the Regional Plan (across
Jónsnípuskarð Pass or to the north of Höfuðreiðarmúla). Both options involved lines passing through
the Þeistareykir Lava Field. The Icelandic National Planning Agency believes that both options would
have a similar effect on the lava and that there are no well-known mitigation measures to reduce the
impact. The Höfuðreiðarmúla option is considered to be the most feasible with regard to security of
supply and the Icelandic National Planning Agency believes that Landsnet should assess the possibility
of developing another option for the route for Þeistareykir Line 1 (where the line would pass
Höfuðreiðarmúla).
2.1 CONNECTED CONSTRUCTION
The assessment outlines plans for the construction of a 16 km road from Bæjarfjall Mountain and up
to the Kísilvegur Road in Hólasandur, which is a continuance of the proposed Þeistareykir Road,
between Húsavík and Þeistareykir. The road will be 7 m in width and raised to a height of 50-70 cm
with a load bearing road base and an estimated speed limit of 80-90 km/hr. The distance between
Hólasandur Line 2 and the road will be at least 100 m and trails will connect the road and the line. The
road will follow the current road trail over an 8 km stretch, alongside Bæjarfjall Mountain and south
of Kvíhólafjall Mountain but the road will then follow a new road path in Neðra- Bóndhólshraun and
up to the Kísilvegur Road. Two routes can be considered at this point; each one covering approx. 5 km
(routes A and B). The estimated material needs are 340,000 m3 (route B) to 360,000 m3 (route A). The
materials will mostly be sourced from mines within the area and material from road cut will be approx.
81,000 m3 (route A) to 135,000 m3 (route B).
The proposed road will be within the proposed construction area for transmission line trails and the
high voltage transmission lines. The road will therefore not have a significant impact on the landscape
beyond those caused by the proposed construction work in connection with the high voltage
transmission lines. The road will not disturb rare vegetation communities but will have a considerable,
localised negative impact on vegetation. The assessment shows that the proposed road could have a
negative impact on nesting areas and that construction work and traffic could disturb birdlife. The road
will generally have a negligible effect on birdlife but access to Ptarmigan hunting areas could increase
as a result of the road which could have an indirect but somewhat negative impact on the survival of
the falcon. Furthermore, two cairns and one road will also be affected by the construction of the road.
Unofficial translation
11
Supervisory bodies will be given the task of enforcing any regulations with regard to work carried out
in the vicinity of these remains. If the protection of archaeological remains should fail, then the
Archaeological Heritage Agency of Iceland will be consulted on the removal of the remains. The
Developer believes that the potential environmental effects of the road from Bæjarfjall Mountain and
up to the Kísilvegur Road are acceptable.
The Environment Agency of Iceland believes that the road construction from Bæjarfjall Mountain and
up to the Kísilvegur Road is part of the construction project for the high voltage transmission line, as
the IEIS did not outline any plans for the location of access roads and transmission line bases for
Hólasandur Line 2 and Þeistareykir Line 1 and a trail that would be consistent with these plans. The
Environment Agency of Iceland also points out that additional materials will be required for the
construction of a road and construction pads from Bæjarfjall Mountain and up to the Kísilvegur Road
and that the estimated quantity required could be anything up to 610,000 m3 for both construction
projects, of which approx. 80,000 m3 will come from road cut. (route A).
Landsnet reiterates that proposed construction work on Hólasandur Line 2 means that the
construction of a road would be unnecessary. Road construction is not a part of the construction
project on the high voltage transmission line and material extraction plans would therefore not be
required. The route of the proposed road is used to demarcate trails to minimise any later disturbance
as a result of road construction that may or may not be carried out at a later stage.
The Soil Conservation Service of Iceland points out that the IEIS shows that vegetation will disappear
underneath the proposed road and will be disturbed as a result of soil disturbance during road
construction. Plans for re-vegetation (or equivalent measures) as a result of land lost during
construction must be outlined.
Landsnet‘s response outlines the fact that the land is poorly vegetated and that the high voltage
transmission lines and the proposed road will run alongside each other within the area. Sowing
measures will not be implemented in unvegetated areas. Other finishing work will be completed in
accordance with the description in Chapter 3.5.
The Archaeological Heritage Agency of Iceland comments on the IEIS include the suggestion that any
archaeological remains within the road construction site would need to be identified. The results of
this assessment would then be presented to the Agency and would be subject to conditions set out by
the Archaeological Heritage Agency of Iceland, on mitigation measures.
Unofficial translation
12
Landsnet assumes that an assessment of archaeological remains will be conducted in the area not
included in the archaeological survey in connection with high voltage transmission lines before
construction work on the road begins.
The Icelandic National Planning Agency believes that the proposed road across Hólasandur to
Þeistareykir is connected with the construction project on high voltage transmission lines with a view
to any cumulative effects on the environment. The Icelandic National Planning Agency points out
that the current road across Hólasandur and up to Þeistareykir will only be partly utilised during the
construction phase of the transmission line project and to provide access points for maintenance work
in the future i.e. the section to the south of Þeistareykir and up to the point where the road meets the
turn-off point which is located to the east of the Gæsafjöll Mountains (coordinate 40.000 in Figure 3.3
in the assessment report). The current road is located far away from the proposed line route from
this point and up to the proposed substation for the high voltage transmission line in Hólasandur and
Landsnet plans to create new trails in this section of the road which will disturb untouched land. The
Icelandic National Planning Agency believes that these trails should follow the proposed road site for
the constructed road. This layout would prevent any additional environmental effects to those already
expected in this area as a result of road construction. The Icelandic National Planning Agency
reiterated the importance of this in the early stages of the process and Landsnet has subsequently
decided to utilise the proposed route of the constructed road to create the necessary trails. The actual
construction of the road at a later date would require and environmental assessment on the basis of
Item 10ii in appendix 1 of the law on Environmental Impact Assessments where relics must be
identified and reclaimed vegetated areas must replace areas disturbed by road construction.
2.2 OTHER OPTIONS
Landsnet identified a number of transmission routes for electricity within the area during the
preparation period for the development of the Regional Plan for high temperature areas in
Þingeyjarsýsla District. These were assessed alongside other structures connected to energy
generation within the area with a view to the overall effects of land usage on the environment.
Option 1: The results of the Regional Plan for transmission routes shows that the option put forward
by Landsnet was the option chosen (Option 1), i.e. alongside lines from Krafla and up to the proposed
substation in Hólasandur, from Höskuldsvatn Lake and up to Bakki and a simple line along two routes
from Hólasanduri: One across Þeistareykir and up to Höskuldsvatn Lake and the other west of
Lambafjöll Mountains and up to Höskuldsvatn Lake up to Bakki. The EIA for Option 1 are included in
the assessment report.
Unofficial translation
13
Option 2: In Option 2, high voltage transmission lines would run alongside each other from Krafla,
across Þeistareykir and up to Bakki. The area to the west of Bæjarfjall, by Þeistareykir, the Þeistareykir
Lava Field and Jónssnípuskarð could however create more technical problems and negative
environmental effects than a simple line running either side of Lambafjall (Option 1). The land in the
Bæjarfjall Mountain area and up to Þeistareykir is covered in fissures and there is therefore only a small
area of viable land for the construction of high voltage transmission lines. The vegetation in the area
is sensitive and the geological formations are unique. There are a number of archaeological remains
and protected land areas, according to the Regional Plan for high temperature areas in Þingeyjarsveit.
Two lines across Þeistareykir would therefore increase the visual impact, would have more of a
negative impact on the experience of tourists and would increase the negative effects on the unique
landscape, geological formations and vegetation within the area. Two lines from the proposed
substation at Hólasandur and across Þeistareykir, Jónsnípuskarð Pass and up to Höskuldsvatn Lake
would increase the likelihood of bird impact whereas a simple high voltage transmission line could
have a permanent and somewhat negative effect on birdlife. The trails that would accompany Option
2 would be 34 km shorter than in Option 1 and would therefore require less material.
Landsnet´s main option (Option 1) would better fulfil the objectives of the Regional Plan for high
temperature areas in Þingeyjarsýsla District, the policies of the relevant municipalities and security of
supply than Option 2.
Zero option: The zero option is not an option (the option not to construct a high voltage transmission
line to Bakki by Húsavík). A policy has been developed on the utilisation of geothermal energy for
energy generation in Þingeyjarsýsla District and high voltage transmission lines are an essential part of
transmitting electricity from the proposed geothermal power stations.
The Environment Agency of Iceland points out that Option 2 would constrict the Þeistareykir area
more than Option 1 and supports Landsnet‘s opinion that Option 2 would be likely to have a greater
negative environmental effect than Option 1.
The Icelandic National Planning Agency agrees with the Environment Agency of Iceland and Landsnet
and believes that the doubling of the number of lines across the Þeistareykir area (Option 2) would
have a greater negative environmental effect than Landsnet‘s Option 1.
Unofficial translation
14
3 RESULTS OF THE ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
3.1 CHARACTERISTICS AND EXTENT OF ENVIRONMENTAL EFFECTS
The Environment Agency of Iceland points out that the Developer‘s definitions with regard to terms
and explanations as to the extent of effects do not conform with the instructions given by the Icelandic
National Planning Agency in December 2005 on the characteristics and extent of environmental
effects.
The Developer responded by pointing out that the report‘s author had used the term ‘somewhat’ in
the Environmental Impact Assessment on the construction project. The justification for this decision
was the author‘s opinion that the difference between the term negligible and significant was too great
and the term ‘somewhat’ was therefore added to the scale. The decision was made in cooperation
with the Icelandic National Planning Agency at that time as a result of the IEIS from Alcoa Fjarðaál. The
methodology outlined by the Agency in their instructions can therefore be deviated from, in
cooperation with the Icelandic National Planning Agency.
The Icelandic National Planning Agency points out that the Developer‘s assessment report included an
assessment of the effect of construction on specific environmental aspects. The extent of these effects
is described by using ‘extent grades’, where the most negative grade is significantly negative, followed
by considerably negative, somewhat negative and negligible/no effects. The scale also includes
positive effects graded as somewhat positive, considerably positive and finally significantly positive.
The instructions from the Icelandic National Planning Agency (since 2005) on the categorisation of
environmental aspects, the criteria for characteristics and the extent of environmental effects include
proposals for terms on the extent of the effects which support the Environmental Impact Assessment
(EIA). The Icelandic National Planning Agency is currently reviewing these instructions and the Agency
believes that many cases require a description of the extent of the effects using a grade which the
Agency calls ‘somewhat negative’, which represents the stage between considerably negative and
negligible effects and is similar to the Developer‘s definitions in the assessment report. However, this
would mostly be used to describe localised effects which would not cover large areas. The area would
not be protected and would not be in any way sensitive to change but the effects could be permanent
and irreversible. The Icelandic National Planning Agency therefore chooses to use the same terms as
those used by the Developer in the assessment report to describe the combined environmental effects
of the four construction projects.
Unofficial translation
15
3.2 VISUAL IMPACT AND EFFECTS ON LANDSCAPE, PROTECTION, OUTDOOR RECREATION AND
TOURISM
Landscape and visual impact: The assessment report shows that the landscape within the
construction area was assessed and categorised into landscape units on the basis of geology,
vegetation, hydrological conditions, land usage and land form. The value of the land was assessed
according to its status: Untouched wilderness, outdoor recreation, protected as a result of the direct
potential effect on the characteristics and appearance of the land and geothermal activity at the
surface. Altimetry data has been utilised to assess where and when high voltage transmission lines
and their connecting trails will become conspicuous in the landscape. The basis for this is the idea
that transmission towers are generally not visible at a distance of more than 5 km. The assessment
report also shows that the proposed high voltage transmission lines will run across diverse landscapes.
The landscape by Þeistareykir is considered special as a result of the diverse geothermal formations,
solfataras, fumaroles and geothermal plant life. The Þeistareykir area is on the Nature Conservation
Register and is partly protected by the Regional plan for high temperature areas in Þingeyjarsýsla
District 2007-2025. Craters present within the landscape units of Þeistareykjabungu are on the Nature
Conservation Register and the area is part of an untouched wilderness. The value of Þeistareykir and
Þeistareykjabunga is therefore high and is followed by landscape units (from south to north) in
Nónbugur, Leirhnjúkshraun, Hlíðarfjall, Bóndhólshraun, Gæsafjall Mountains, Draugagrundir,
Lambafjall Mountains, Botnsvatn and Grísatungufjöll. Landscape units between Bæjarfjall and
Lambafjall have a rather low value (the second lowest value category) and this includes Hólasandur,
Kvíhóla, Bæjarfjall, Austurhlíð Lambafjöll, Þeistareykir Lava Field and Skildinga and Stóravítishraun
Lava Field. The landscape units to the west and north of the Lambafjöll Mountains generally have a
low value; from Kasthvamsheiði in the south to the Bakki River in the north, with the exception of the
Höskuldsvatn Lake, Höskuldsvatnshnúkur, Botnsvatn and Bakki, which are all in the second lowest
value category.
The assessment report shows that the high voltage transmission line will have a somewhat negative
overall effect on the landscape. The proposed construction of a high voltage transmission line across
Þeistareykir will alter the physical appearance of the area and will have a significant negative effect
on the physical landscape. High voltage transmission lines will be located in the middle of the
Þeistareykir Lava Field and will have a considerable negative effect on the lava, which is unique as a
result of its texture and appearance which is an obvious characteristic of the landscape. The area also
has special geological formations (lava channels and craters). The lines will also have a considerable
negative effect on the landscape in the Bóndhólshraun Lava Field, the eastern slope of Lambafjall
Unofficial translation
16
Mountain and by the Höskuldsvatn Lake and Höskuldshnjúka. Construction will also mean that the
aforementioned landscape units will no longer be considered an untouched wilderness. High voltage
transmission lines across the Leirhnjúkshraun Lava Field will affect the view from rambling paths in the
lava field and will have a considerably negative impact on the landscape. The proposed high voltage
transmission lines will run across five landscape units to the west of Lambafjall and will have a
somewhat negative impact on Bæjarfjall, where the high voltage transmission line across Hólasandur,
Þeistareykir, Þeistareykir Lava Field and Jónsnípuskarð Pass will be visible. The transmission towers
will also be visible in Krubbsfjall towards the direction of the coastline where the lines run across the
landscape unit in the Bakki River and Bakki. The proposed lines will also be conspicuous in
Hólasandur and the surrounding area and the impact on the landscape will be somewhat negative.
High voltage transmission lines are already located in landscape units in Grísatunga and Þríhyrninga
and the effects of the proposed construction work will therefore be less than expected i.e. somewhat
negative. The assessment report shows that mitigation measures have not been planned in connection
with the effects on the physical landscape.
The Environment Agency of Iceland believes that the aspects used to assess the value of landscape
units (untouched wilderness, outdoor recreation, geothermal activity at the surface and special
protection) do not give an accurate picture of the value of the units. Geological formations could for
instance have a conservation value, despite the fact that they are not considered candidates for special
protection, according to the law. The Agency points out that the landscape unit in Hlíðarfjall is
considered to be an untouched wilderness and the Agency believes that its value is greater than the
IEIS indicated. The Agency believes that the landscape units in Leirhnjúkshraun and Hlíðarfjall will be
significantly and negatively affected by the proposed construction.
Landsnet points out that the use of plans and regulations is based on the policies outlined by the state
and by the relevant municipalities with regard to protection. The visual impact of high voltage
transmission lines will be significantly negative in areas within 1 km of the transmission lines but
Landsnet does not agree with the opinion that the overall visual impact within the landscape units in
Hlíðarfjall and Leirhnjúkshraun will be significant. However, tourists will probably venture away from
the rambling paths across Leirhnjúkshraun and in the area surrounding Hlíðarfjall and head towards
higher land in the mountain area. Landsnet can therefore agree with the Environment Agency of
Iceland on the value of Hlíðarfjall and the assessment report has increased the value of the area (which
now has a rather high value) and the effects of the high voltage transmission line on this landscape
unit is now categorised as somewhat negative.
Unofficial translation
17
The assessment report shows that the high voltage transmission line will naturally have a considerable,
negative visual impact at a distance of anything up to 1-2 km and would still be considered somewhat
negative at a distance of 2-5 km from the transmission towers. The proposed structure will be
conspicuous by Þeistareykir and the visual impact will therefore be significantly negative. High voltage
transmission lines will be conspicuous by Bakki, from the Húsavíkurfjall Mountain, southeast of
Botnsvatn, west of Höskuldsvatn Lake, by Þeistareykir, at viewing locations in Leirhnjúkshraun and
from the Krafla area (Krafla already has a number of high voltage transmission lines and other
structures). The high voltage transmission lines will be obvious on the national road from Kísilvegur
Road by Hólasandur, by Þeistareykir and by Bakki. The high voltage transmission lines will generally
not be easily seen from residential areas and will not be seen in Húsavík or on the national road up to
the farm (to the south) or from outdoor recreation areas by Botnsvatn, the residential area by
Reykjahlíð or the national road surrounding it. High voltage lines will blend into the landscape and
will therefore be less visible from Húsavíkurfjall and the Krubbsfjall Mountains, to the west of
Höskuldsvatn Lake, from Hlíðarfjall Mountain and Reykjahlíðarheiði therefore lessening the visual
impact. Four material extraction areas will be easily seen from busy areas and material extraction in
these areas will have a somewhat negative visual impact. The assessment report shows that mitigation
measures have not been planned in connection with the visual impact of high voltage transmission
lines.
Residents and owners of the Skarðaborg, Skarð and Einarsstaðir í Reykjahverfi Farms commented
on plans to construct a high voltage transmission line across Jónsnípu and down to Árnahvammur.
They recommended that the line should be constructed to the north of Höfuðreiðarmúla and then
westward towards the south banks of Höskuldsvatn Lake and alongside the proposed road route
outlined in the general/master plan for the town of Húsavík. This would reduce the visual impact and
would not spoil the physical appearance of land from Árnahvammur and up to Höskuldsvatn Lake.
Landsnet agrees that the physical appearance of the area by Árnahvammur would be altered as a result
of the transmission line (Þeistareykir Line 1) and the line would be more visible in this area than in the
area north of Höfuðreiðarmúla. The visual impact in Árnahvammur will however be less than the
combined visual impact of lines and roads by Höfuðreiðarmúla (see Landsnet‘s response to
comments made by Dagur and Arnþrúður above).
Residents and owners of the Skarðaborg, Skarð and Einarsstaðir í Reykjahverfi Farms commented
that high voltage transmission lines to the west of Lambafjall (Hólasandur Line 1) will be located to
the west of the Kópasker Line and would penetrate sensitive vegetated areas, cultivated over a long
period of time. The line will also be visible from farms close by. Recommendations include the proposal
Unofficial translation
18
that the lines could run alongside each other where the Hólasandur Line meets the Kópasker Line and
up to the north end of Höfuðreiðarmúla. The Hólasandur Line would then run westward, past the south
banks of Höskuldsvatn and alongside the proposed road route outlined in the general/master plan for
the town of Húsavík.
Landsnet‘s response explained that efforts to minimise any operational disturbances include the
avoidance of areas that are susceptible to icing. Landsnet points out that the Kópasker Line passes
through the highland area in Höfuðreiðar and is susceptible to winds from the northwest and
experience of the line shows that icing can be expected in this area. Landsnet therefore believes that
this option would not ensure the satisfactory security of supply. The route is also 3 km longer than the
proposed line route. The route chosen by Landsnet will lead to more disturbances in vegetated areas.
Landsnet will attempt to minimise this disturbance by creating side trails to the transmission towers
which are able to carry heavy machinery and land reclamation measures will be implemented in
cooperation with the Soil Conservation Service. Landsnet also points out that the distance from the
farms to the lines would be 3.5-4 km. The lines would be more obvious if they were further away and
higher up.
The district council of Tjörneshreppur has voiced its concerns with regard to the negative visual impact
of high voltage lines on tourism and outdoor recreation in the area next to Bakki. The residents of
Héðinshöfða 2 have spoken against the location of the substation by Bakki and believe that it will be
too conspicuous and easily seen from the farm; that the high voltage transmission lines will be
conspicuous and will depreciate the value of the farm. Residents in Héðinshöfða 1 have pointed out
the fact that their initial concerns regarding the visual impact of high voltage transmission lines and
their demands for an underground cable have not been addressed.
Landsnet‘s response outlines the fact that the visual impact of the high voltage transmission line will
be significant up to a distance of 2 km from the lines but will decrease as the distance increases. The
effects will be considerably negative in the area where the lines meet the aluminium plant at Bakki.
High voltage transmission lines will have considerable negative impact on tourists who enjoy the
natural surroundings by Bakki, but will not hinder access to the Bakki area. The lines will be a part of
a number of structures in the area next to Bakki and these structures will be visible. The lines will
blend in with the landscape in Héðinshöfða which will reduce the impact. Landsnet also points out the
fact that overhead lines obviously have a greater visual impact but underground cables cause more
environmental effects and overhead lines are easier to dismantle and remove.
Conservation value: The assessment report shows that the largest part of the proposed high voltage
transmission line will be located within the water catchment area in Mývatn and Laxá which are both
Unofficial translation
19
protected under regulation No. 97/2004. The high voltage transmission lines will end close to
Bakkifjöru and Bakkihöfða and the affected area of the lines will penetrate Þeistareykir. All these areas
are included in the Nature Conservation Register. The lines will also run through an area which is
locally protected according to the Regional plan for high temperature areas in Þingeyjarsýsla District
2007-2025, by Þeistareykir and in the Þeistareykir Lava Field. Krafla Lines 4 and 5 will run across a
locally protected area by Þríhyrning to the west of the Krafla geothermal Power Station and across
Leirhnjúkshraun Lava Field. The assessment report shows that the Environment Agency of Iceland had
proposed a protection order for Leirhnjúkshraun and construction will not be approved in the area
until the results of the proposal have been released.
Landsnet believes that protected areas will be disturbed as a result of the construction of high voltage
transmission lines and the project will have a somewhat negative and to some degree permanent
effect on protected areas in Þeistareykir, in the Þeistareykir Lava Field and by Þríhyrning to the
west of the Krafla Geothermal Power Station. The effects will be negligible with regard to hydrological
conditions in Mývatn and Laxá and in the Bakkihöfða area.
The National Energy Authority points out that high voltage transmission lines will traverse protected
areas and electricity lines and underground cables disturb geological formations in these areas. The
irreversible environmental effects of these projects must be considered.
Landsnet‘s response confirms the fact that the proposed high voltage transmission lines will inevitably
have a somewhat negative and to some degree permanent effect on protected areas. The local
protection measures outlined in the regional plan for high temperature areas in Þingeyjarsýsla allow
for a belt of manmade structures that traverse the Þeistareykir Lava Field (area HÞ2) and in areas
where fissures and faults are located (area HÞ4).
Outdoor recreation and tourism: The proposed high voltage transmission lines are close to the main
rambling paths: Between Reykjahlíð and Leirhnjúkar, from North Hólasandur to Þeistareykir, from
Þeistareykir to Höfuðreiðarmúla, up to Húsavíkurfjall and alongside the coastline from Húsavík to
Bakki. Popular riding trails can also be found to the south of Gæsafjöll, across Hólasandur and
Þeistareykir and across the gorge between Höfuðreiðarmúla and Sæluhúsmúla. Telemark skiers
mostly travel across Reykjaheiði and Hólasandur and there are plans to develop a skiing area for
residents in Húsavík in the southern part of the Húsavíkurfjall Mountain. Rescue teams and jeep and
snowmobile enthusiasts mostly travel across Hólasandur and up to Jónsnípuskarð Pass and the areas
surrounding Þeistareykjabungu and Gæsafjöll. There is also an important Ptarmigan hunting area to
the east of Höfuðreiðarmúla, by Sæluhúsmúla and by Rauðhól, in the Lambafjöll Mountains, by
Þeistareykir and Bæjarfjall and also Gæsafjöll. Outdoor enthusiast cabins by Sæluhúsmúla and in
Unofficial translation
20
Þeistareykir. The results of research conducted by the Icelandic Tourism Research Center showed an
increase in tourists interested in the Þeistareykir area. There are popular outdoor recreation areas in
the vicinity of Bakki by Húsavík (Tjörnes, by Gónhól and in the Húsavíkurfjall Mountain).
The high voltage transmission lines will traverse rambling areas to the west of the Krafla Geothermal
Power Station and from Reykjahlíð to Gæsafjöll. The lines will run alongside routes used by outdoor
enthusiasts southward under the Kvíhólafjöll Mountains and northward alongside Bæjarfjall Mountain
and up to Þeistareykir. The lines in this area will be closer to the Ptarmigan hunting area by Bæjarfjall
and Þeistareykir. The high voltage transmission line from Þeistareykir and across Jónsnípuskarð
Pass will run alongside a riding trail across the Þeistareykir Lava Field and a rambling path from
Þeistareykir to Höfuðreiðarmúla and will also be in close proximity to the Ptarmigan hunting area to
the south of Jónsnípuskarð Pass. Plans have been put forward for a Telemark skier’s area by
Höskuldsvatn. High voltage transmission lines will be located in the area and will be easily seen from
the rambling path in Húsavíkurfjall. The lines will also traverse rambling and riding trails by Bakki.
The construction period for high voltage transmission lines will be accompanied by heavy vehicle traffic
on transmission line roads and line sites and noise. This will have a considerably negative impact on
tourism and outdoor recreation in the area. The effects during the operational period of the high
voltage transmission line will be considerably negative and permanent on outdoor enthusiasts seeking
out an untouched natural environment. The area will probably become less popular as a result.
Improved transport from Krafla and across Þeistareykir and up to Bakki (in connection with
construction work) will make the area more accessible and it could therefore be said that the high
voltage transmission line will have a considerably positive and permanent effect on outdoor
enthusiasts, who travel by vehicle. The effects of the high voltage transmission line on the experience
of skiers in the area to the west of Höskuldsvatn will be considerably negative, although the lines are
unlikely to have a negative effect on the development of the skiing area.
The Environment Agency of Iceland agrees that the proposed high voltage transmission lines will have
a considerably negative effect on nature tourism. The Agency points out that increased access to
outdoor recreation areas comes as a result of the grounds for construction and the development of
the area and not for outdoor enthusiasts or tourists. The Environment Agency of Iceland believes that
the effects of construction will be considerably negative as most of the visitors to the area are nature
tourists.
Landsnet‘s response agrees that the effect on tourists seeking out an untouched natural environment
will be considerably negative but will be negligible or somewhat positive for other tourists (e.g. those
Unofficial translation
21
travelling in vehicles). Landsnet believes that the value of nature tourism is no higher than that of any
other branch of tourism.
The Environment Agency of Iceland points out that the IEIS shows that tourism agents believe that
cooperation between the tourism industry, outdoor recreation enthusiasts and the Developer is
important to ongoing business within the area. Landsnet should put forward proposals on how
construction can be carried out in such a manner that it would decrease the impact on tourism and
outdoor recreation in the area and how the cooperation between the parties would be organised.
Landsnet points out that the proposed construction project was introduced to tourism agents in
connection with the release of the draft on proposals for assessment. Representatives from the
tourism industry have been involved in the development of the Regional plan for high temperature
areas in Þingeyjarsýsla District 2007-2025. Expectations of a positive impact from construction have
been identified according to this cooperation but there are also concerns about the negative impact
on tourism, as described in the IEIS. Mitigation measures have not been developed to reduce the
effects of construction on tourism and any future cooperation between Landsnet and tourism agencies
is expected to be successful.
The Icelandic National Planning Agency believes that the proposed construction will mainly have a
negative visual impact and a negative impact on the landscape. The Icelandic National Planning Agency
agrees with Landsnet that the proposed construction will have a significant negative effect on the
Þeistareykir area as the high voltage transmission lines and rails will traverse an area with a unique
natural environment and well vegetated land (when compared with neighbouring lava areas). The
Icelandic National Planning Agency believes that the effects will be irreversible in this area. The
Icelandic National Planning Agency also agrees with Landsnet that the high voltage transmission lines
will have a considerably negative effect on the eastern slopes of Lambafjall where the lines will traverse
outdoor recreation areas. There will also be a considerably negative impact from high voltage
transmission lines where they run across the Leirhnjúkshraun Lava Field, in an area already disturbed
by drilling. There will also be a considerably negative impact on Höskuldsvatn and Höskuldsvatnhnúka,
as the experience of the area as an untouched wilderness will be affected. The impact on the
untouched wilderness to the south of Hólasandur and to the west of Lambafjall, where the value of
the landscape is low (according to the report) will also be somewhat negative. The Icelandic National
Planning Agency agrees that overhead lines have more of a visual impact than underground cables.
However, the Icelandic National Planning Agency also believes that the laying of underground cables
can, under certain circumstances, have more of a negative impact on the landscape than overhead
Unofficial translation
22
lines and the extent of irreversible damage would also be more e.g. if high voltage transmission lines
are laid underground across lava areas.
The Icelandic National Planning Agency does not agree with Landsnet that the effects of the proposed
construction on the Þeistareykir Lava Field will be considerably negative. The assessment report shows
that Landsnet conducted an assessment of the landscape units, categorising and describing the
characteristics of the units, within the proposed construction area and also analysed the effects of the
proposed high voltage transmission line on the landscape and the potential visual impact. The value of
each landscape unit was assessed according to its status: Untouched wilderness, outdoor recreation,
protected and geothermal activity at the surface. The Icelandic National Planning Agency points out
that Landsnet‘s definition of protected areas is limited as it is based on the Nature Conservation
Register or on areas that enjoy local protection or cultural relic protection, according to the Regional
Plan for high temperature areas in Þingeyjarsýsla District 2007-2025. The definition does not consider
protection as a result of craters, pseudocraters or lava, in accordance with the regulations on nature
conservation (Article 37a), which reflects the government policy on protection. The landscape units
characterised by modern day lava (Þeistareykir Lava Field) are therefore categorised as having a rather
low value in Landsnet‘s assessment report. The Þeistareykir Lava Field is the youngest lava field within
the area, with unique craters, pseudocraters and lava channels and otherwise fulfils the stipulations of
the law on the protection of these types of geological formations. The Icelandic National Planning
Agency therefore does not agree with Landsnet‘s assessment of the value of the Þeistareykir Lava
Fields and believes that the area should be categorised with other landscape units in the area with a
rather high or high value. The Icelandic National Planning Agency also points out that the proposed
construction of a high voltage transmission line and trails across Jónsnípuskarð Pass will result in the
disturbance of the area in the northernmost part of Bunga. The Þeistareykir Lava Field will be divided
into two somewhat equally large areas and the overall view of the lava will be permanently altered.
The Icelandic National Planning Agency also believes that the lava is unique at the national level despite
its relatively small size. The area is also sensitive to changes and traces from trails and construction
pads will be permanent. The disturbance of the lava does not conform to government policy which is
reflected by the laws on nature conservation and the protection of geological formations is a priority
(policy on sustainable development in Icelandic society). The Icelandic National Planning Agency is
therefore unable to accept Landsnet‘s conclusion that construction on high voltage transmission lines
will have only a considerably negative effect on the landscape unit within the Þeistareykir Lava Fields
and believes that the effects on the lava will be significantly negative and irreversible.
The Icelandic National Planning Agency agrees with Landsnet‘s assessment that the experience of
outdoor enthusiasts by Höskuldsvatn will be considerably negative as a result of the high voltage
Unofficial translation
23
transmission line to the west of the lake, where outdoor enthusiasts will no longer be able to see an
untouched wilderness from areas like Höskuldsvatnshnjúkar. The Icelandic National Planning Agency
does not agree with Landsnet‘s assessment that the effects of proposed construction work on the
travels of outdoor enthusiasts and tourists who hope to enjoy a largely undisturbed environment will
be considerably negative. The Icelandic National Planning Agency points out that high voltage
transmission lines across Hólasandur and alongside the Kvíhólafjöll Mountains and Bæjarfjall Mountain
and up to Þeistareykir will run alongside rambling and riding trails in the area. Most organised trips to
the lowland area between Lambafjall (westward) and Gæsafjöll to Bæjarfjall (eastward) are planned
on the premise that participants will be able to enjoy the untouched wilderness. The Icelandic
National Planning Agency believes that the presence of the high voltage transmission lines in a large
part of the area and the location of the line across the Þeistareykir Lava Field will obviously significantly
affect the experience of ramblers and riders. The aforementioned research indicates that the
enthusiasm of outdoor enthusiasts and tourists for the Þeistareykir area will be lost. The presence of
high voltage transmission line will mean that the area can no longer be promoted based on the promise
of an untouched wilderness. However, other opportunities for tourism, based on easy access to the
area should develop as a result of the construction of the road from Krafla across Þeistareykir and up
to Bakki. The Icelandic National Planning Agency believes that visits to the area by ‘untouched natural
wilderness enthusiasts’ will decrease and that there is a danger that planned trips to the area will be
discontinued. There are no recent, accurate figures on the number of tourists of this type visiting the
area but research carried out by the Icelandic Tourism Research Center indicates that the area is mostly
visited by outdoor recreation enthusiasts and tourists. The Icelandic National Planning Agency
therefore believes that outdoor enthusiasts and tourists who wish to enjoy untouched wilderness
areas will be significantly, negatively affected by the proposed high voltage transmission lines. Tourism
agencies planning this type of trip will also be affected.
The Icelandic National Planning Agency agrees with the conclusions of the assessment report with
regard to the considerable visual impact of the high voltage transmission lines on the area surrounding
the lines (within 5 km of the lines). The Icelandic National Planning Agency points out that the
construction project is extensive: Each line will be 60 km in length, 375 transmission towers will be
raised and trails will be built up within the area. The Agency also points out that laying high voltage
transmission lines either side of the Lambafjall Mountains will affect more landscape units than if the
lines were to run alongside each other between Krafla and Bakki. Nine landscape units out of ten
which have been categorised as part of an untouched wilderness will be affected by construction work
and high voltage transmission lines will run through unique landscape areas, protected areas and
through lava areas that are protected according to the laws on nature conservation. The Icelandic
Unofficial translation
24
National Planning Agency also points out that the lines from Þeistareykir and across Jónsnípuskarð Pass
will have a negative impact on the experience of outdoor recreation enthusiasts and tourists in the
mostly untouched area from Hólasandur to Höfuðreiðarmúla and between Lambafjall (west) and
Gæsafjall (east). The Icelandic National Planning Agency believes that construction will disturb a large
area which is sensitive to change and that the effects on landscape and the physical appearance of the
area will be extensive. The Icelandic National Planning Agency believes that the aforementioned
combined effects of the proposed high voltage transmission line on the landscape, protection matters,
outdoor recreation and tourism will be significantly negative and will also have a visual impact.
3.3 EFFECTS ON GEOLOGICAL FORMATIONS
The assessment report shows that high voltage transmission lines will penetrate areas in the
northernmost part of Bungu in the Þeistareykir Lava Field which is unlike other areas in the country.
The line will also be in close proximity to an explosion crater in the Laufrandarhraun Lava Field in
Jónsnípuskarð Pass and will pass through areas covered in rock thrown from the crater. The lines will
also traverse an area 3 km to the south of the Guðfinnugjá Fault. The high voltage transmission lines
will be located in the periphery of the geothermal area in Þeistareykir which is on the Nature
Conservation Register due to the diverse geological formations in the area. The lines located further
south in Reykjahlíðarheiði will be 750 m from hot springs by Krókóttuvatn, approx. 3 km from the
crater by Hvannstóðshöfða and 1.5 km from Leirhnjúkar. The high voltage transmission lines will also
traverse the Leirhnjúkshraun Lava Field.
Material extraction plans expect all the materials for the construction of the high voltage transmission
line to be sourced from loose earth layers from the present day and from the end of the Ice Age ísaldar
(sandbanks in narrow gorges and glacial moraine or glacial sediment). The report states that 17 of the
27 proposed material extraction areas have a low or very low conservation value according to the
categorisation system of the Icelandic Road Association and proposed material extraction in these
areas will have a negligible effect on geological formations. The same categorisation system indicated
that several material extraction areas in Norðurþing have a high conservation value as a result of water
protection and not as a result of geological formations. Many of the areas have a medium conservation
value as they can be easily seen from busy areas. The effects of material extraction in these areas are
somewhat negative.
The assessment report also shows that disturbances to lava as a result of the construction of the high
voltage transmission lines will be unavoidable, including the Leirhnjúkshraun, Þeistareykir and
Bóndhólshraun Lava Fields (a total area of 5 hectares). However, Landsnet believes that the effect on
lava will be negligible, with the exception of the western part of Leirhnjúkshraun. There is a trail in
Unofficial translation
25
Leirhnjúkshraun where Krafla Lines 4 and 5 will be located and the lava to the west of the trail will be
disturbed by the construction of high voltage transmission lines. The lava area is undisturbed and the
impact of construction could therefore be considerable but localised in Leirhnjúkshraun.
The Environment Agency of Iceland believes that the assessment should include an analysis of the
effects of construction on individual geological formations rather than a general analysis of the extent
of the disturbance within the entire lava field area. The exact location of disturbances to lava is
important as well as an assessment on whether construction will divide the lava area into units. The
Agency also points out that the construction of a high voltage transmission line across Þeistareykir Lava
Field, the trails running alongside the lines and the construction of the power station road across the
lava field will divide the Þeistareykir Lava Field into units. Geological phenomena could create a
‘whole’ which would need to be protected e.g. crater rows, lava, lava channels, faults and fissures.
Relatively little disturbance to the area could therefore damage the conservation value of these types
of geological formations. Lava disturbed by construction generally has a lower conservation value than
undisturbed lava and construction work in lava areas should not be justified by the fact that the area
has already been disturbed. The Agency points out that the disturbance of geological phenomena as a
result of construction leads to a reduction in this type of lava environment and similar undisturbed
geological formations elsewhere therefore attain a higher conservation value. The Environment
Agency of Iceland points out that any disturbance to pahoehoe lava during construction is usually less
obvious than similar construction carried out in apal lava. However, smooth lava does not have a
lower conservation value than apal lava (according to the guidelines). The Environment Agency of
Iceland points out that the area where high voltage transmission lines will be constructed across
Leirhnjúkshraun, from Hvíthólaklif, is an area covered by coarse lava and the Agency believes that this
lava has a high conservation value. The construction of the high voltage transmission line will have a
considerably negative and irreversible effect on Leirhnjúkshraun and geological formations protected
according to Article 37 of the law on nature conservation have not been considered. The Environment
Agency of Iceland points out that there is no guarantee that contractors working on the construction
of high voltage transmission lines across Leirhnjúkshraun will use smaller machinery than the
machinery used for drilling. There is therefore no guarantee that the trails in the lava will be less than
those used for drilling purposes. It should therefore be assumed that construction will affect the area
to the same extent as the current trail in Leirhnjúkshraun and that construction will have a considerably
negative and irreversible effect on Leirhnjúkshraun.
Landsnet‘s response shows that the IEIS had taken the Environment Agency of Iceland‘s opinions into
account and had described any localised negative impact on the lava although the overall effects were
still the main focus (considering the size of the lava field). The construction of the proposed high
Unofficial translation
26
voltage transmission line will inevitably disturb the lava but the design of the structures was completed
with a view to minimising any disturbance to the lava. Landsnet points out that the current trail
across Leirhnjúkshraun was designed to carry heavy machinery used for drilling. Lighter machinery
will be used for the construction of the high voltage transmission line and this type of trail will therefore
not be needed in Leirhnjúkshraun. This should ensure fewer disturbances to the area than that caused
by the current trail. Landsnet will appoint supervisory bodies to ensure that this is the case. Landsnet
believes that the construction of the high voltage transmission line across Leirhnjúkshraun will have a
localised and considerable negative effect on the area affected by new trails (the western section of
the line across the lava) although the overall effects on the lava will be negligible.
The Environment Agency of Iceland points out that the hot spring area by Hitur has a high
conservation value, according to the assessment of the Icelandic Institute of Natural History. The
Environment Agency of Iceland believes that transmission towers should not be raised within the area
and the prevention of traffic disturbing the area must be ensured.
Landsnet‘s response outlines the fact that the assessment report states that raising transmission
towers in hot solfatara areas is not a feasible option. Measures will be taken to ensure that Hitur is
not disturbed and experts will be consulted as to the location and size of structures (later on in the
construction process) within areas that should be protected.
Birkir Fanndal states that laying an underground cable within the geothermal area by Næamaskarð
would be difficult and operating the cable would also be problematic. He raises concerns with regard
to the proposed route of underground cables alongside the Krafla Road in Hlíðardalur, which would
disturb a unique lava area in the valley even more than previous road construction. Jón Illugason
agrees with these conclusions and recommends that the underground cable be laid further east in the
valley from Dalleiri across Halaskóga and northward to the west of Halaskógafjall Mountain
Landsnet‘s response states that the Company will assess the possibility of laying the underground cable
elsewhere to protect the lava. Landsnet put forward a draft for the new location of the underground
cable during the development of the assessment report, in an area further east and outside the lava
area. The assessment report states that the changes will be announced to the Icelandic National
Planning Agency in accordance with the Environmental Impact Assessment Act no. 106/2000 “with
subsequent amendments“.
The Environment Agency of Iceland points out that the IEIS only refers to 12 material extraction areas
out of the 27 identified in the report and there is no clear indication that material extraction areas will
be limited to these areas. A detailed description of material extraction plans would be difficult at this
Unofficial translation
27
point but the IEIS should include information on which material extraction areas will be opened, which
will be closed as well as details on finishing work. The Environment Agency of Iceland also points out
that mines are expected to be distributed at a regular distance along the line route (3-6 km) and all
mines from proposed line route will be less than 1,5 km. The Environment Agency of Iceland believes
that the choice of material extraction areas should not be solely based on their distance from the
proposed construction area but also based on the visual impact of extracting materials from these
areas.
Landsnet‘s response notes that the appendix of the IEIS discussed 27 potential material extraction
areas, intended for use during the construction period and only gave 12 examples of material
extraction areas in the relevant municipalities. The material extraction areas are expected to fulfil the
material needs for construction so that new extraction areas will not need to be identified during the
construction period. Landsnet agrees with the Environment Agency of Iceland that material
extraction plans should be submitted for each area once construction work is imminent. The report
states that finishing work on the material extraction areas will be carried out in accordance with the
laws on nature conservation. The conservation value of material extraction areas was the deciding
factor in choosing material extraction areas. Shorter distances between material extraction areas lead
to less pollution and minimise any disturbance during the construction period.
The Icelandic National Planning Agency agrees with the Environment Agency of Iceland that the
overall effects of construction on lava with regard to geological formations is more important than the
overall percentage of disturbed land mass within the area (as assessed by Landsnet ). The Icelandic
National Planning Agency points out that construction may only affect a small part of the lava field but
the transmission line runs through an area with unique geological formations (Bungur) and will in fact
divide the lava field into two equally large units which will change the overall appearance of the lava.
Landsnet put forward two options during the preparation of the Regional Plan for high temperature
areas with regard to the route for Þeistareykir Line 1 (across Jónsnípuskarð Pass or north of
Höfuðreiðarmúla). Both options traversed the Þeistareykir Lava Field. The Icelandic National Planning
Agency believes that both options are in fact weak when the effects of construction on the lava field
are considered; both options divide the area, disturb unique geological formations in the lava and
transmission towers, trails and construction pads will have a significantly negative and permanent
effect on Þeistareykir Lava Field. The Icelandic National Planning Agency believes that there are no
satisfactory mitigation measures to reduce these effects. The Icelandic National Planning Agency
therefore believes that Landsnet should consider another option with regard to the transmission route
for Þeistareykir Line 1, which would run pass Höfuðreiðarmúla (see Chapter 2). The Icelandic National
Unofficial translation
28
Planning Agency agrees with the Environment Agency of Iceland and Landsnet that construction will
have a considerably negative and permanent effect on Leirhnjúkshraun.
The Icelandic National Planning Agency also agrees that underground cables alongside the Krafla
Road in Hlíðardalur Valley would disturb the lava in the valley even more. The Agency believes that
Landsnet should stand by its plans to assess the possibility of laying an underground cable to the east
of the lava in order to protect it. Any changes must be announced to the Icelandic National Planning
Agency in accordance with Article 6 of regulation No. 106/2000 “with subsequent amendments” and
Item 13a in Appendix 2.
3.4 EFFECTS ON CULTURAL RELICS
The assessment report shows that there are 60 relics within the affected area of the proposed
construction area for the high voltage transmission line, including 42 cairns. All the relics will be at
risk as a result of ground disturbance, human traffic and machinery: 44 will be at high risk, including
32 cairns, five mines/peat mines, two ruins, two walls and two sheep herding areas. The relics in
Þeistareykir are to the east of the area affected by the high voltage transmission lines and they are not
believed to be at risk.
The report states that contractors have been made aware of the location of archaeological remains
and arrangements have been made to protect these areas during the construction period. If the
protection of archaeological remains should fail, then the Archaeological Heritage Agency of Iceland
will be consulted. They will also be consulted if any new remains are discovered. Landsnet believes
that the effects of the proposed construction project on archaeological remains will be negligible.
The Archaeological Heritage Agency of Iceland points out that the IEIS does not cover two
archaeological remains in the Þeistareykir area which are described in the specialist report. The
Agency believes that all cairns should be marked within the proposed construction area to prevent any
unintentional damage to them. The following archaeological remains must be especially considered:
Þeistareykir land area: sheep gathering area (SÞ-250x: 046), Klif (SÞ-250x: 051, not referred to in the
IEIS), Þeistareykjaaðhald (SÞ-250x:056, not referred to in the IEIS), road/route (SÞ-250x:088)
and a ruin (SÞ-250x:096).
Bakki land area : wall (SÞ-312:033), peat mines (SÞ-312:054, SÞ-312:055, SÞ- 312:056, SÞ-312:057,
SÞ-312:058), ruin (SÞ-312:059) wall/irrigation (SÞ-312:061).
Landsnet‘s response outlines the reason that the archaeological remains in Klif and
Þeistareykjaaðhald were not included in the IEIS. The remains were not included because the proposed
Unofficial translation
29
line route was altered after a specialist report was submitted. The altered route meant that the
assessment of archaeological remains would need to be revie