Upload
droby
View
370
Download
1
Embed Size (px)
Citation preview
Landowner-Driven Wind Development
Sponsored by
In Cooperation with
Great Falls, Montana ~ October 17,2009
1. Proven, Developable, and Competitive Wind Resource
2. Organization with Committed Leadership, Support, and a Plan
3. Seed Money and Initial Development Capital
4. Control of Wind Resource Footprint
5. Committed Client(s)
6. Generation Interconnection/Transmission Solution
7. Generation Outlet
8. Strategic Partner(s)
9. Permits and Licenses
10.Dedicated Project Manager
Critical Components
1. Proven, Developable, and Competitive Wind Resource
• Met Towers (commissioned, height, and location)
• History and Corroboration of Data
• Modeling and Analysis
• Net Capacity Factor with Different Turbines
• Developability Factors
• Current Market Expectations
2. Organization with Dedicated Leadership, Support, and a Plan
• Constituency and Leaders (controlling your own destiny)
• Legal Counsel
• The Landscape
• The Organization
• Engaging a “Developer”
• Potential Business Models
• Feasibility Study of Alternatives (risks/rewards)
3. Seed Money and Initial Development Capital
• Planning and Startup Funding
• Offering Memorandum
• Staging and Raising Investment Capital
4. Control of Wind Resource Footprint
• Optimum Area for Development (footprint)
• Landowner Participation in Ownership
• Landowner Information Meetings
• Web Site and/or Point of Information Dissemination
• The “Land Man” and Landowner Relations
• Wind Right Options and Project “Buy-In”
U.S. Wind Energy Projects - Montana (existing)(As of 03/31/2009)
Source – American Wind Energy Association
Power Capacity - Existing projects (MW): 271.53
Power Capacity - Projects under construction (MW): 0
Rank In US (by Existing Capacity): 19
Rank In US (by Potential Capacity): 5
Potential Capacity (in MW): 116000
Annual Energy (in billion kWh): 1020
5. Committed Client(s)
• Opportunity Evaluation (business model)
• Unsolicited Proposals
• Requests for Proposals
• Letter of Intent
6. Generation Interconnection & Transmission Solution
• The Experienced “Grid Engineer”
• Optimum Interconnection Point and System Impacts/Costs
• Potential Partners in Interconnection/Transmission Solution
• Application for Interconnection
7. Generation Outlet
• Parameters for Generation Outlet Transmission Line
• Landowner Considerations
• Local Utility Considerations
8. Strategic Partners(s)
• The “tax incentive” Factor
• Partner(s) with Investment Capital and Turbine Access
• Partner(s) with Commitment to “Community Ownership”
• Partner(s) with Credibility
9. Permits and Licenses
• State Jurisdiction over Facility Siting
• Federal Compliance and Environmental Issues
• Local Conditional Use and Building Permits
10. Dedicated Project Manager
• Many Complex Issues
• Many Parties
• Many Meetings
• Many Negotiations
• Many Decisions
• Dedicated Professional Support
‘Landowner Driven’ Wind Energy Development Process Flow Chart
Landowner
Interest
Potential Wind Resource
Potential Market
Transmission Options
Site Identification
Site Control
On-Site Wind
Assessment
Indicative Data Review
Abandon Site
Market Evaluation
Interconnect and
Transmission
Permitting Assessment and Initiation
Preliminary Engineering and Design
Easement Acquisition
Capital & Operating
Cost Estimate
Select Strategic Finance Partner
Project Still Feasible?
Abandon Site
Begin
Construction
Commercial Operation
No Yes
<NO-GO>
<GO>