Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
YOUR PARTNER IN
GROUND ENGINEERING
L&M Foundation Specialist Pte Ltd(A member of CSC Holdings Limited)
CONTRACT T306 – TANJONG KATONG STATION
Construction of Tanjong Katong Station and Tunnels for Thomson East Coast Line
Developer Land Transport Authority, Singapore
Consultant Mott Macdonald Singapore Pte Ltd
Main Contractor Woh Hup Pte Ltd
Contract Sum Approximately (SGD) $ 17.0 Million
Construction Period Dec 2016 to Aug 2019
Scope of Works Diaphragm Wall, Cross Wall and
Installation of King Post
Location Tanjong Katong South Road
YOUR PARTNER IN
GROUND ENGINEERING
Scope of Works
• Construction of 74 panels 1200mm thick Diaphragm Wall up to 49m deep.
• Construction of 35 panels 800mm thick Diaphragm Wall up to 75m deep
• Installation of King Post (356x406x990kg/m) up to 24m long into 1200mm diaphragm wall
• Construction of Cross Wall 1000mm thick up to 36m deep
• Total 15,000m3 of treatment volume for Deep Cement Mixing (DCM) and Jet Grouting Pile (JGP) works
(drilling depth up to 42m with 24m grouting thick)
The challenges of this project include;
• Deep Excavation
Construction of diaphragm wall as deep as 75m from ground level with presence of OA(A) soil up to 35m
thick required high skill operator, intensive koden check and a close supervision in order to achieve good
trench verticality.
CONTRACT T306 –
TANJONG KATONG STATION
YOUR PARTNER IN
GROUND ENGINEERING
The challenges of this project include;
• Site Constraint
Constructing cross wall at the center of the site and diaphragm wall at the same time required a great planning
and sequencing of work in order to ensure both work can be carried out smoothly.
• Kingpost Installation
Installing of huge king posts into the narrow space of d-wall cage required detail technical study as well as
close supervision to ensure smooth king post installation.
• Road and Utility Diversion
Great communication and coordination with Main Contractor were required in order to ensure all the
diaphragm wall can be constructed within the given space and time.
CONTRACT T306 –
TANJONG KATONG STATION