L-band test stations in End Station B

Richard Swent

Page 2: L-band test stations in End Station B Richard Swent

Modulator and Klystron Testing

• We need to test two modulators and two klystrons for the ILC project

• We are testing 2 modulators designs for reliability and cost-effectiveness

• 2 Klystron designs are being evaluated for reliability and efficiency

• The RF produced will not be used for anything, just measured and dissipated

Page 3: L-band test stations in End Station B Richard Swent

2 ILC-class modulators

• One, “Marx”, made at SLAC

• One, “direct switch”, coming from Diversified Technologies (DTI) in Mass.

• Both must meet ILC specs:

• 120 kV at 140 Amps

• 1.7 msec pulses at 5 Hz

• 29 kjoules per pulse

Page 4: L-band test stations in End Station B Richard Swent

Station Equipment

• Each test stand has– Modulator w/ Power Supply– Oil Tank with:

• Water Load• Filament Xfmr• Klystron (Vertical now, horizontal later)

– Instrumentation and Controls

• Each test stand will run independently, 24/7, with summary data archived for trends, detailed data for every fault

Page 5: L-band test stations in End Station B Richard Swent

End Station B West End

This is the part of End Station B where we will put 2 new test stands.

Page 6: L-band test stations in End Station B Richard Swent

Shielding Wall

Removal of the shielding wall is required before any new installation can proceed.

This is what the area looked like at the beginning of 2007.

Page 7: L-band test stations in End Station B Richard Swent

Shielding Wall Removal

Page 8: L-band test stations in End Station B Richard Swent

Shielding Wall Removal

Page 9: L-band test stations in End Station B Richard Swent

Shielding Wall Removal

Page 10: L-band test stations in End Station B Richard Swent

Marx Modulator

• Preliminary testing in B015

• Delivery to ESB later this year

Page 11: L-band test stations in End Station B Richard Swent

DTI Modulator

• Status unknown—DTI ran out of money before the modulator was completed, and they did not get the follow-on SBIR grant they wanted.

Page 12: L-band test stations in End Station B Richard Swent

Klystrons: 2x 5 MW outputs

Toshiba klystronBeing built, will arrive in

October

SLAC Sheet BeamBeing designed, should

arrive in Spring 2008

Page 13: L-band test stations in End Station B Richard Swent

Loads and tanks

• Each tank can hold a vertical klystron, a water load, and a filament transformer

• Water loads will be able to take the full output of a modulator in the absence of a klystron

Most tank parts have been received. Some small modifications are needed.

Page 14: L-band test stations in End Station B Richard Swent

Water Loads

Old New

Page 15: L-band test stations in End Station B Richard Swent

Electrical Power – Phase I

SN

Page 16: L-band test stations in End Station B Richard Swent

LCW Phase I

We need 400 gpm of water for two test stands.

Regulator and controls will be outside, with pipes emerging behind the clean room.

Tie-in will occur in early September.

Page 17: L-band test stations in End Station B Richard Swent

Floor Plan

Page 18: L-band test stations in End Station B Richard Swent

Controls and LLRF

• Commercial instruments have been ordered:– Frequency source– Function generators– Booster amplifiers– Peak power meter (not ordered yet, but soon)

• Custom LLRF hardware is being built, based on existing designs:– IQ modulator– Pulse width controller– RMS detectors

Page 19: L-band test stations in End Station B Richard Swent

Schedule

• Wall removal August 2007• Water Cut-In September 2007• Marx Modulator Oct 2007• DTI Modulator ??• Tanks and Water Loads July 2007• Toshiba Klystron Oct 2007• Sheet Beam Klystron Spring 2008