K.Wyllie Electronics meeting 29/05/061
RICH Power Supplies & Grounding
Thanks to Johan MorantPaolo Baesso
Xavier Le Gouard
K.Wyllie Electronics meeting 29/05/062
Example: RICH2 module
Each module is mechanically and electrically independent.
Cooling plate (not shown) grounded.Plastic pipes for insulation
K.Wyllie Electronics meeting 29/05/063
Power connections & grounding
MaratonLV (5V) channel 1 – floating. Tested
MaratonLV (5V) channel 2 – floating. Tested
CAEN SY1527LC- A1511BSi bias (80V) – floating. Tested
ISEG (20kV) – varistor protection.
Under test
K.Wyllie Electronics meeting 29/05/064
Module Power and Grounding
Within module – one common ground, connected to safety earth
Local ST-4913 regulators few cm from load (L0 + HPD)Regulators enabled/disabled by SPECS slave
Allows possibility to enable/disable L0s/HPDs => a ‘gentle’ power-up sequence
We power-up with a well-defined sequence for each module:
Turn on LV suppliesTurn on Si bias
Enable regulators for L0/HPDs (SPECS)Enable GOLs on L0 (SPECS)Loop for all L0s in module
Filtering of LV, Si bias (and HV) done locally
SPECS – shield of cable connected to module ground AND SPECS master ground. No problems seen yet……….
K.Wyllie Electronics meeting 29/05/065
Tests with Maraton
Tested in lab with programmable load
Then used in system tests & Frascati testbeams since January
K.Wyllie Electronics meeting 29/05/066
Hardware
12-channel 6U prototype now in constant use in labs
Not yet operated with all channels used (maximum so far is 6 out of 12 = 3 modules)
Sense…… looks OK, more tests to be done
Tested with proposed grounding scheme – no problems
All ‘analog’ settings with potentiometers
Needs water cooling – particular connectors for pipes
Documentation VERY bad
K.Wyllie Electronics meeting 29/05/067
Software
Tests done with simple user-panel, via USB
OPC server from Wiener seems to work (although installation is not obvious…..)Maraton is now networked (same as CAEN system)Now included in PVSS framework
Panels/ FSM under development
K.Wyllie Electronics meeting 29/05/068
Conclusions
Power and grounding scheme follows LHCb recommendations
Tested successfully with prototype and production modules:
System tests in lab since summer 2005
Two testbeams in Frascati
Tests on-going, adding final HV system
Good experience with Wiener Maraton in system-tests/testbeams