Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida, USA Challenges of Dredging and Material Disposal at a LNG Facility in Savannah Harbor, Georgia, USA

Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Embed Size (px)

Citation preview

Page 1: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA

Kenneth W. Cargill, P.E. – KW Cargill, P.A..Punta Gorda, Florida, USA

Challenges of Dredging and Material Disposal at a LNG

Facility in Savannah Harbor, Georgia, USA

Page 2: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Presentation Outline• Project Location and Background• The Business – LNG Operations• Contract and Permit Requirements• Dredging Challenges• Evaluation of Dredging Options• Disposal Challenges• Prediction of DMCA Life• Evaluation of Disposal Options• Summary

2

2

Page 3: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Project Location and Background• Located 5 miles

East Northeast of Savannah

• Bounded by the Savannah River, South Channel, and Intracoastal waterways

• River Mile 7.5• Lower Savannah

Harbor• Most seaward

port facility 3

Page 4: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

The Business – LNG Operations

• Storage capacity 11.5 Bcfe• Delivery rate capacity:

– Firm delivery rate 1,518 MMcf/d– Maximum delivery rate 1,755 MMcf/d

D-1D-4

D-5

D-6(future)

D-2D-3

4

Page 5: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Relevant Infrastructure• Turning Basin – Approx. 33 acres conforming with U.S.

Coast Guard minimum (FERC Recommendation)

• Ship Slip – Approx. 44 acres, berths for 2 ships simultaneously

• DMCA 1 – Approx. 130 acres, dike last raised 2011, current dike elevation 50 ft MLW, being used for disposal

• DMCA 2 – Approx. 120 acres, dike last raised 2009, being intensively managed for drying and material harvesting, current dike elevation 44 ft MLW

5

Page 6: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Dual Ship Off-loading

6

Page 7: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

2008 Elba IslandAerial Photograph

7

Page 8: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Dredged Material Containment AreasDMCA 1~ 130

ac

DMCA 2~ 120 ac

Sedimentation Pond

Weir Outlet

Elba Island Aerial Photograph(August 2011)

8

DMCA 1~ 130

ac

DMCA 2~ 120 acSedimentatio

n Pond

Elba Island Aerial Photograph(August 2011)

Page 9: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Contract and Permit Requirements

• Typical 1-month notification of LNG Tanker ship coming

• Huge Financial Penalty if ship cannot come or dock

• Maintain required dredge depths year round– Ship Slip: -42 ft MLW min. (-46 ft max.)– Turning Basin: -38 ft MLW min. (-42 ft max.)– Dredging ship slip every 2 to 3 months– Annual total volume ≈ 1 million cubic yards 9

Page 10: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Dredging Challenges• Rapid Sediment Accumulation

– Loading Conditions of Savannah River– Ship Slip and Turning Basin acting as Bath Tubs (Sinks)

• Permit Renewal Challenges– 20-month (in lieu of 5-yr) permit issued in July 2011– New renewal application tied with upper harbor users– Water quality and EFH conditions - NMFS, USFWS,

GAEPD, SCDHEC• Procurement and Mobilization of Dredging

Contractor– One hydraulic cutterhead dredger in Savannah River– Use by USACE and other harbor users– Scheduling of next dredging event

• Disposal Issues 10

Page 11: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Dredging Challenges

11

Page 12: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Evaluation of Dredging Options• Long-term contract with hydraulic cutterhead dredging

contractor – Lump sum contract ($5/cy to $10/cy in lieu of typical $3/cy to

$4.50/cy) – Continual negotiations with USACE to release dredge

• Purchase and operate its own dredge • Contract dredging operations to a non-dredging contractor

• Pursue alternative dredging solutions

– Use of I-beam bed leveling – agitation dredging• Nationwide Permit (NW) 5 issued by USACE as research study • Four trial tests completed to date – results being analyzed

– Use of clamshell bucket dredging and ocean disposal• Permitting Challenges• Tier III testing and analyses 12

Page 13: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Disposal Challenges• Long-Term Dredged Material Management Plan

(DMMP)– Prediction of DMCAs Life using Corps’ PSDDF

software program• Impact of Increased Frequency of Dredging

– Rapid Filling of DMCAs– Less Time for consolidation and desiccation – Changes to Dike Raising schedules

• Dike Raising Constraints– Maximum dike height of 62 to 68 ft MLW– Stability Constraints– Availability of fill material 13

Page 14: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Prediction of DMCA LifeUsing Corps Model PSDDF

Cases CommentsDredging

Event

Thickness Deposited

(ft)

Estimated Life Expectancy

DMCA 1 DMCA 2

DMCA 1

DMCA 2

62 ft 68 ft 62 ft 68 ft

Case 1 

2 dredging events per year: SS and TB

1 April 3.94 4.22 Apr-25Apr-29

Oct-24

Oct-28

2 October 3.94 4.22        

Case 2 

3 dredging events per year: SS and TB

1 March 2.63 2.82 Jul-25Mar-29

Nov-24

Nov-28

2 July 2.63 2.82

3Novembe

r2.63 2.82        

Case 3 

3 dredging events per year: SS

1 March 1.07 1.15 Mar-49 - Jul-50 -

2 July 1.07 1.15

3Novembe

r1.07 1.15        

Case 4 

3 dredging events per year: SS

2 dredging events per year: TB

1 March 3.4 3.65 Mar-25Mar-29

Mar-27

Nov-28

2 July 3.4 3.65

3Novembe

r1.07 1.15        

Notes: SS = Ship Slip; TB = Turning Basin

14

Page 15: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

15

Page 16: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Evaluation of Disposal Options• Bed leveling in ship slip

o Nationwide Permit (NW) 5 issued – results of trial tests being analyzed

o Allow more drying time in DMCA by increasing time between dredging

• Intensive management of DMCA drainage and dredged material harvesting o Concepts developed during last DMCA 1 dike raisingo Concepts currently being implemented in DMCA 2o Final objective is system steady state where volume

capacity of DMCA is perpetually restored between dredging

• Negotiations with USACE – Use of SC DMCAs for dredged material disposal– Ship Slip and Turning Basin are for a single user

• Ocean Disposal

16

Page 17: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Development of Interior Borrow Pits

17

Page 18: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Concept of Intensive DMCA Management

• Rapid removal of decanted water immediately after end of dredging and constant removal of drainage

• Use of specialty equipment to create and enhance drainage pathways

• Early and continual removal of dredged material slurry at perimeter to promote interior desiccated crust

• Early and continual removal of desiccated crust on perimeter of DMCA

• Development of interior borrow pits for material mining as possible

• Removal of desiccated and consolidated material and hauling to stockpile areas 18

Page 19: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

19

Concept of Intensive DMCA Management

Page 20: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

20

Concept of Intensive DMCA Management

Page 21: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Concept of Intensive DMCA Management

Page 22: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

22

Concept of Intensive DMCA Management

Page 23: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Tracking Consolidationand Settlement

23

Page 24: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

24

On-going Settlement in DMCA 2

Page 25: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Preliminary Construction Costs

• 3-yr contract for $5.9 million signed in 8/2011• Average cost of $120,000 per month to date• 29% of contract expended thru 9/2012• $500,000 per ft of settlement gained thru 9/2012• Key equipment used to date:

– 1 Swamp buggy– 2 Long-reach excavators– 1 dozer– 1 harrow/tractor

Page 26: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Summary• Dredging Permits for Ship Slip and Turning

Basin– Dredge anytime of year– No DO Limit and no fish windows

• Ability to dredge when needed– Continual negotiations with USACE and dredge

contractor– Permit and implement bed leveling concept

• Have disposal capacity in DMCAs thru 2050– Intensive DMCA management– Ocean disposal

26

Page 27: Kwasi Badu-Tweneboah, Ph.D., P.E. – Geosyntec Consultants Jacksonville, Florida, USA Kenneth W. Cargill, P.E. – KW Cargill, P.A.. Punta Gorda, Florida,

Thank You