Upload
montana
View
33
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Kriegers Flak and its way to become best practice area EOW 2009 Achim Berge wpd offshore. ”How to find a common approach in three different countries towards three neighbouring projects, which find themselves in the focus of EU-policies”. Installation of FINO II. wpd at a glance. - PowerPoint PPT Presentation
Citation preview
Kriegers Flak and its way to become best practice area
EOW 2009Achim Berge wpd offshore Installation of FINO II
”How to find a common approach in
three different countries towards three
neighbouring projects, which find
themselves in the focus of EU-policies”
wpd at a glance
Baltic I, GER (76 MW)
Kriegers Flak I, GER (329 MW)
HochseeWP Nord-see, GER (400 MW)
He Dreiht, GER (595 MW)
Kriegers Flak III, DAN (455 MW)
Korsnäs, FIN(600-800 MW)
Suurhiekka, FIN(400-600 MW)
Klocktärnan, SE(660 MW)
Storgrundet, SE(230-265 MW)
Finngrunden, SE (1,300-1,400 MW)
Kriegers Flak II, SE (640 MW)
Aiolos, GER (1,050 MW)
5 projects with a total capacity of ~ 2,040 MW permitted and sold
7 projects with a total capacity of ~ 4,500 MW (net) in advanced permission process
10 projects with a total capacity of ~ 5,000 MW (net) in early permission stage
Several projects under site evaluation
Calvados, F(250 MW)
Several projects in siteevaluation
Kaikas, GER (440 MW)
Notos, GER (250 MW)
Fecamps, F(260 MW)
Projects X+Y+Z, F (450+250+750MW)
Vendée, F(600MW)
Several projects in site evaluation/ early development stage
Gargano N, IT(680 MW)
Gargano S, IT(855 MW)
Participation in Round3 with JV partner
wpd offshore References
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Kriegers Flak Area
Baltic1 + Kriegers Flak I+II+III =21+80+128+91 = 320 WTG(up to 1600 MW)
together Europes largest advanced project area in terms of area, turbines and capacity
developed by wpd since 2001
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Kriegers Flak development
Kriegers Flak I (Germany)
Kriegers Flak II (Sweden)
Kriegers Flak III (Danmark)
2001 wpd starts development in all three areas
2002 wpd files application for 80 turbines
2004 wpd files application for 128 turbines
2005 Permission granted wpd sells Kriegers Flak II to Vattenfall AB and stays as consultant
wpd files application for 91 turbines
2006 Permission granted
2007 Erection of met mast FINO II (partly financed and managed by wpd)
Soil investigations
2008 • wpd sells Kriegers Flak I to EnBW and stays as project manager
• soil investigations at all 80 locations
Studies on potential foundation types
Working group by the Energy Board on Kriegers Flak III
2009 • EnBW/wpd establish project management team
• procurement aims for start of construction 2011
Motives & Challenges for Kriegers Flak development
Motives• One of the biggest potential areas in the Baltic Sea• Few environmental issues• High wind speed above 9,5 m/s• Strategic interesting location along big transmission needs
Challenges• Sea bed conditions• Far offshore – potentially high connection costs
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Investigations at Kriegers Flak
Kriegers Flak Interconnector
• Basic idea: replacing three independent grid connections by one common solution including HVDC technology
• 2003: wpd and NVE starts studies on interconnector between Germany and Sweden
• 2005: wpd integrates interconnector as possible grid connection in the application of Kriegers Flak II
• 2006: Vattenfall AB starts working group on the Interconnector (”Baltic Wind Link”)
• 2007: Vattenfall Europe Transmission GmbH includes the Interconnector as potential solution for Kriegers Flak I
• 2009: TSO ”Joint Pre-feasibility Study”, TSO application for 150 M€ EU grant
map wpd study 2003
map TSO study 2009
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Motives for Kriegers Flak Interconnector
Motives• Socio-economic benefit up to 100€ Mio/year
• HVDC technology means less energy losses and higher capacity• Multiple connections lower the project operator’s risk of business interruption
Graph from the TSO Joint Pre-feasibilty Study, presentation at EWEC March 2009
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Challenges for Kriegers Flak Interconnector
• Three different national laws on
transmission networks
• The three different wind farm owners
might have different interests
• Involvement of EU could add more
complexity than support
• National consumer interests could
become a hurdle
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Grid North West Europe,Svenska Kraftnät 2008
Governmental initiatives regardingKriegers Flak
• EOW December 2007: Joint declaration of ministers from Denmark, Germany and Sweden on cooperation regarding Kriegers Flak (ending up in the Nordwind project)
• September 2008: EU-coordinator Adamowitsch identifies Kriegers Flak as ”best practise case” and ask for an ”European vision not accepting cheap national solutions”
• January 2009: EU Recovery Plan includes proposal of 150 € Mio grant for grid connection Kriegers Flak
• June 2009: EU Strategy for the Baltic Sea Region – Action Plan highlights Kriegers Flak as ”demonstration of coordinated offshore wind farm connection solutions”
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Motives for governmental initiatives
• Baltic Sea riparian countries already agreed on
close cooperation in the Helsinki Convention
(featuring HELCOM).
• Kriegers Flak as lighthouse project for the benefit of the citizens and the
environment
• National interests might be taken care of in the best way by mutual
cooperation
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Preconditions for successful joint cooperation between stakeholders at Kriegers Flak
• Focus on the needs of the project owners and operators because:
– The wind projects are the key of the area’s development
– Grid connection is the key for the wind projects’ realisation
– Project owners are in charge of the projects’ timetable
– Project owners are in possesion of all site related data
– Project owners have ressources to be allocated with short notice
• Project owners and operators need to participate in the economic benefit of joint cooperation because:
– Project owners have taken the development risk
– Most of the projects are still not profitable
– Certain conditions (e.g. sea bed) require more ressources
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
How to structure further development of the interconnector and other joint efforts?
• For the time being, at least five parallel working groups are discussing Kriegers Flak
• Instead ONE working group with 10 members should head further development:
– 3 project owners/developers
– 3 TSOs
– 3 governments
– 1 EU representive
• Sub-groups are necessary, but should be supervised by the overall working group
• Initiative for restructering the work should come from the EU level
• Kriegers Flak needs to have high priority at all involved organisations and levels
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
How to deal with three legal regimes?
• Under the existing three legal regimes an interconnector is not realistic
• The existing rules are the result of energy politics with clear national
interests in mind
• Examples for legal hurdles:
– Ownership rules for transmission cables under Swedish law
– Rules on grid connection of electricity under Danish law
– Special rules for grid connection and sale of wind power under
German law
• Harmonisation is needed – but is harmonisation also wanted?
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
Kriegers Flak is the European Union’s idea in a nutshell
• Cooperation and trade with
neighboring countries gives benefits to
the customers seen from a European
perspective
• Harmonisation of legal rules is
necessary
• Public and private sector have to work
together
• Climate change and new jobs are the
major drivers
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm
European ParliamentColleagues from Deutsche
Windtechnik at Thornton Banks (B), July 2008
Contact
Achim BergeManaging Director
wpd offshore GmbH
Kurfürstenallee 23a
DE 28211 Bremen
+49 421 168 66 10
wpd offshore GmbH EOW 2009, 14-16 September, Stockholm