19
Key SEA framing issues Power demand and power trade development in the LMB and GMS SEA Team

Key SEA framing issues

  • Upload
    papina

  • View
    39

  • Download
    0

Embed Size (px)

DESCRIPTION

Key SEA framing issues . Power demand and power trade development in the LMB and GMS SEA Team. Purpose. This presentation aims to illustrate the changing character of the demand for power within the LMB and where the mainstream dams fit within the mix of electricity generation . - PowerPoint PPT Presentation

Citation preview

Page 1: Key SEA framing issues

Key SEA framing issues

Power demand and power trade development in the LMB and GMS

SEA Team

Page 2: Key SEA framing issues

Purpose

• This presentation aims to illustrate the changing character of the demand for power within the LMB and where the mainstream dams fit within the mix of electricity generation

Page 3: Key SEA framing issues

LMB Selected indicators 2004Cambodia Lao PDR Thailand Viet Nam

Population (million) (2004)

13.8 5.8 64.2 82.1

GDP (current USD billion)

4.9 2.2 150.1 41.2

GDP per capita (current USD)

361 420 2,519 551

FDI (USD million) 131 17 1,064 1,610

FDI/capita (USD) 9.5 2.9 16.6 19.6

Electricity use per capita (kWh)

45 160 1,752 (2003) 433 (2003)

Energy use per capita (kgoe)

180.0 355.0 1,405.7 (2003) 544.3 (2003)

Fuelwood share in total primary energy

88% 67% 16% 49%

Source: Economics of energy integration , ADB, 2008

Page 4: Key SEA framing issues

Regional GMS energy issues •Dependence on traditional sources of energy (e.g. fuelwood)•20 % of GMs population (74 mil.) no access to electricity•Energy consumption in GMS is only 2/3 of the world average for developing countries

Energy poverty

widespread

•1993-2005 8% annual growth in energy consumption•21% of total energy consumed in the region imported•Volatile energy prices and limited alternative energy sources mean the region is vulnerable

Energy vulnerability

high and rising

•Energy supplies low and unpredictable – overall quality low•Lack of competitive pressure on energy suppliers•Policy regimes inadequate to address emerging challenges

Energy productivity and policy

Source: Building a sustainable energy future the GMS, ADB 2008

Page 5: Key SEA framing issues

High economic growth in the LMB 1985-2005

Source: Building a sustainable energy future the GMS, ADB 2008

Page 6: Key SEA framing issues

Significant differences in electricity consumption

Country Per capita household consumption (Kwh)

Share of residential sector in total electricity consumption (%)

Cambodia 29 52.0

Lao PDR 95 53.0

Thailand 409 21.0

Vietnam 242 42.0

Source: Building a sustainable energy future the GMS, ADB 2008

Page 7: Key SEA framing issues

Growing demand for power

• Not consistent between countries• All projects in Cambodia and Laos, so will be

generating more than they can consume• Mainstream project – high proportion of

power generated will be exported• If projects are planned on basis of export, they

must have secure markets, • Anticipated markets are at moment are

Thailand, Vietnam, China

Page 8: Key SEA framing issues

Uncertainty of markets in short-term

• Thailand in economic crisis and may be some years before want to import more power

• Already some projects giving anticipated unit cost prices to break even which are well above market prices e.g. Sambor and Vietnam

• Vietnam in process of multi-year power market reform over many years, e.g. competitive generation by 2005 - 2014 and competitive retail power markets by 2022

• China moving towards greater self-provision of energySO there are uncertainties in use of this capacity from

mainstream dams and when they are going to come

Page 9: Key SEA framing issues

Significant differences in hydropower potential (MWyr/yr)

Cambodia Lao PDR Thailand Viet Nam Regional total (GMS)

Low –cost 1,670 4,640 2,784 3,248 54,102

Medium-cost 1,114 3,944 1,856 3,712 43,802

High-cost 742 2,320 928 1,392 23,571

Small 650 1,015 406 812 5,928

Total 4,176 11,919 5,974 9,164 127,403

Source: Economics of energy integration , ADB, 2008

Page 10: Key SEA framing issues

Limited power trade flows between LMB countries in 2005 (GWh)

Exports

Imports

Cambodia Lao PDR Thailand Viet Nam RoW Total

Cambodia - 74 74

Lao PDR - 2,628

Thailand 2,033 - 3,234 5,267

Viet Nam 521 - 521

RoW -

Total 2,628 3,234 -

Source: Economics of energy integration , ADB, 2008

Page 11: Key SEA framing issues

Regional power demand• Lao –700 MW generated now with 60 MW imported

from Thailand• 7,000 MW by 2020 • 90% of 2020 will come from Hydropower• 1500 MW of 2020 would come from mainstream

dams• Domestic demand is 450 MW by 2020, so only about

7% of installed capacity• But one major energy consuming project mine might

have requirement for 60 MW

Page 12: Key SEA framing issues

Cambodia power demand• 13 MW generated now • 90% of power generated from imported fuels • Target to reduce dependence on fuel wood from 80%

of population to 52% by 2015• Target to increase domestic provision of electricity

from to 20% of population to 70% • Potential 10,000 MW from large hydropower

projects, plus 3,000 from mini-hydro• 3,580 MW of 2020 would come from mainstream

dams (Sambor and Stung Treng)• But most of this is destined for export

Page 13: Key SEA framing issues

Projected growth in power demand in LMB 2005-2025

Source: Economics of energy integration , ADB, 2008 (base case projection)

Page 14: Key SEA framing issues

LMB Regional Energy Story

time

Energy Demand

Demand delayed through demand management & efficiency measures

Future • Coal/thermal?• tributaries?• nuclear?• gas?• mainstream hydropower?• Oil?• biomass• renewable?• RoW

Existing Capacity • coal/

thermal• gas• Tributaries• Oil• biomass• RoW

Projected energy demand Projected energy demand with demand management Supply

*RoW = Rest of World

Page 15: Key SEA framing issues

Hydropower in GMS power demand to 2025

Source: Economics of energy integration , ADB, 2008 (base case projection)

Page 16: Key SEA framing issues

Projected power trade with integrated power markets 2025 (GWh)

Exports

Imports

Cambodia Lao PDR Thailand Viet Nam RoW Total

Cambodia - 40 15 55

Lao PDR 22 - 50 57 129

Thailand 9,482 42,458 - 147,269* 199,209

Viet Nam 3,612 25,988 - 5,918 35,518

RoW 644 584 - 1,228

Total 13,116 69,130 649 153,244 -

Source: Economics of energy integration , ADB, 2008 (based on IRM modeling)*Thailand is projected to import 139,385 GWh from Myanmar by 2025

Page 17: Key SEA framing issues

What about the crisis?

Source: World Bank 2009e – expectedf - forecast

Page 18: Key SEA framing issues

Changing economic environment?What does this mean for investment in the energy sector? And more specifically investment in hydropower?

Page 19: Key SEA framing issues

Mainstream dams

• Provide 11.5% of installed capacity by 2020• 9.3% of power produced in the LMB by 2020• 60 GW hrs annually of the 644 GWhrs per

annum in LMB by 2020• Conditions of BOT, 25 – 30 year handover in

which government would have the capacity to manage, but there would be major maintenance and replacements costs