4
Key information for builders and developers: Fibre ready pit and pipe for nbn TM New Developments Horizontal Multi Dwelling Units (HMDU) Dwelling preparation requirements are to assist with the installation of the nbn™ access network technology being installed to the dwelling. 1 x internal P20 nominal rigid white telecommunications conduit installed from the nbn™ utility box, electrical enclosure location to a suitable location within the dwelling (see Figures 9 and 10). Dwellings constructed on new lots, HMDUs or that are street facing will require a lead-in. For an example of a lead-in see Figure 9. Street frontage dwellings would require the lead-in from the dwellings proposed nbn™ utility box, electrical enclosure location, to the property’s front boundary closest to an nbnpit. Where the dwelling/s are located within an HMDU the lead-in would be installed from an internal pit (see Figures 13, 14 and 16) to the dwellings proposed nbn™ utility box, electrical enclosure location. Do not exceed the pits conduit or lead-in capacity (see Figure 4). The lead-in conduit at the building entry point can be installed within the dwelling footings and exit the wall cavity at the proposed nbn™ utility box location, electrical enclosure location or the lead-in can be surface mounted over the dwelling footings and up the external wall to the proposed nbn™ utility box, electrical enclosure location. See Figures 1 and 2. Pit types available for selection: type 2, type 5, type 6, type 8. All pits to contain pit lid gaskets. All pit lids to be branded NBN as per NBN-TE-CTO-194. Conduit entry into pits is important; good examples are shown in Figures 5, 6 and 7. Do not install conduits into the longest side of a pit Figure 8. No more than two 300mm radius 90° underground bends from the pit to the nbn™ utility box location and one aboveground 100mm radius 90° bend can be used between draw points. A maximum of three bends in total. See Figure 1, 2, 9 and 10. All conduit fittings and joins must be glued using solvent cement. Lead-in conduits installed into the dwelling footings rising up into the wall cavity must not terminate in the wall cavity; the conduit must exit the wall cavity using a 100mm radius 90° bend unbroken as per Figure 3. Any lead-in conduit terminating within the wall cavity should be discarded. Lead-in conduits terminating within a wall cavity could allow the ingress of water, moisture or insects into the wall cavity. In this case the lead-in must be intercepted before the footings and redirected as surface conduit to the nbn™ utility box, electrical enclosure location. For an example of a surface mounted lead-in see Figure 4. Flexible conduit must not be used underground, or in wall or ceiling cavities. It is the developer / builder’s responsibility to ensure where the building entry point is lower than the street conduit a drainage pit may be required near the dwelling. 26.7 23.3 1.7 Nominal dimensions (in mm.) 60.3 53.0 3.65 Nominal dimensions (in mm.) 113.9 Nominal dimensions (in mm.) 104.9 4.5 Lead-in Conduit via the footing and cavity wall Temporary Cap 100mm – 140mm Horizontal separation 300mm min to 500mm max below FGL Ensure all conduit ends are joined. Where the lead-in is not immediately connected to the Service Drop Conduit, cap the end of the conduit Single 300 mm radius bend from the horizontal to the vertical alignment Single 100 mm radius bend from vertical to horizontal alignment Lead-in Conduit Service Drop Conduit FGL All conduit and bends joints must be glued with solvent cement Service Drop / Access Pit Bedding sand or excavated material All conduit and bends joints must be glued with solvent cement Future Interior Wall Min 410 mm from FGL Property Boundary Developers Service Drop Conduit Builders Lead-in Conduit Surface mounted lead-in conduit and internal conduit Developers Service Drop Conduit Builders Lead-in Conduit Temporary Cap 100mm – 140mm Horizontal separation 300mm min to 500mm max below FGL Ensure all conduit ends are joined. Where the lead-in is not immediately connected to the Service Drop Conduit, cap the end of the conduit Single 300 mm radius bend from the horizontal to the vertical alignment Single 100 mm radius bend from vertical to horizontal alignment FGL All conduit and bends joints must be glued with solvent cement Service Drop / Access Pit Bedding sand or excavated material All conduit and bends joints must be glued with solvent cement Future Interior Wall Min 410 mm from FGL Property Boundary Service Drop Conduit Lead-in Conduit Figure 1 Figure 3 Figure 2 Conduit dimensions white telecommunications Conduit dimensions white telecommunications Nominal Size (Inside Diameter) 20 mm PN 12 AS/NZS 1477:2006 table 4.2(A) 50 mm PN 12 ASPN 12 A S/NZS 1477:2006 table 4.2(A) 100 mm PN 9 AS/ NZS 1477:2006 table 4.2(A) Nominal Size (Inside Diameter) Nominal Size (Inside Diameter) Conduit dimensions white telecommunications 1 © 2018 nbn co ltd. ‘nbn’, ‘bring it on’, ‘Sky Muster’, ‘gen nbn’ and the Aurora device are trade marks of nbn co ltd | ABN 86 136 533 741.

Key information for builders and developers: Fibre ready ... · Developers Service Drop Conduit Builders Lead-in Conduit. Surface mounted lead-in conduit and internal conduit Drop

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Key information for builders and developers: Fibre ready ... · Developers Service Drop Conduit Builders Lead-in Conduit. Surface mounted lead-in conduit and internal conduit Drop

Key information for builders and developers: Fibre ready pit and pipe for nbnTM New Developments Horizontal Multi Dwelling Units (HMDU)

Dwelling preparation requirements are to assist with the installation of the nbn™ access network technology being installed to the dwelling.

• 1 x internal P20 nominal rigid white telecommunications conduitinstalled from the nbn™ utility box, electrical enclosure location toa suitable location within the dwelling (see Figures 9 and 10).

• Dwellings constructed on new lots, HMDUs or that are streetfacing will require a lead-in. For an example of a lead-in seeFigure 9.

• Street frontage dwellings would require the lead-in fromthe dwellings proposed nbn™ utility box, electrical enclosurelocation, to the property’s front boundary closest to an nbn™pit.

• Where the dwelling/s are located within an HMDU the lead-inwould be installed from an internal pit (see Figures 13, 14and 16) to the dwellings proposed nbn™ utility box, electricalenclosure location. Do not exceed the pits conduit or lead-incapacity (see Figure 4).

• The lead-in conduit at the building entry point can beinstalled within the dwelling footings and exit the wall cavityat the proposed nbn™ utility box location, electrical enclosurelocation or the lead-in can be surface mounted over thedwelling footings and up the external wall to the proposednbn™ utility box, electrical enclosure location. See Figures 1and 2.

• Pit types available for selection: type 2, type 5, type 6, type 8. Allpits to contain pit lid gaskets. All pit lids to be branded NBN asper NBN-TE-CTO-194.

• Conduit entry into pits is important; good examples are shown inFigures 5, 6 and 7. Do not install conduits into the longest side ofa pit Figure 8.

• No more than two 300mm radius 90° underground bends fromthe pit to the nbn™ utility box location and one aboveground100mm radius 90° bend can be used between draw points. Amaximum of three bends in total. See Figure 1, 2, 9 and 10.

• All conduit fittings and joins must be glued using solventcement.

• Lead-in conduits installed into the dwelling footings rising upinto the wall cavity must not terminate in the wall cavity; theconduit must exit the wall cavity using a 100mm radius 90° bendunbroken as per Figure 3. Any lead-in conduit terminating withinthe wall cavity should be discarded. Lead-in conduits terminatingwithin a wall cavity could allow the ingress of water, moisture orinsects into the wall cavity.

• In this case the lead-in must be intercepted before thefootings and redirected as surface conduit to the nbn™ utilitybox, electrical enclosure location. For an example of a surfacemounted lead-in see Figure 4.

• Flexible conduit must not be used underground, or in wall orceiling cavities.

• It is the developer / builder’s responsibility to ensure where thebuilding entry point is lower than the street conduit a drainagepit may be required near the dwelling.

26.7

23.3

1.7

60.3

53.0

3.65

113.9

Nominal dimensions

(in mm.)

Nominal dimensions

(in mm.)

Nominal dimensions

(in mm.)

104.9

4.5

26.7

23.3

1.7

60.3

53.0

3.65

113.9

Nominal dimensions

(in mm.)

Nominal dimensions

(in mm.)

Nominal dimensions

(in mm.)

104.9

4.5

26.7

23.3

1.7

60.3

53.0

3.65

113.9

Nominal dimensions

(in mm.)

Nominal dimensions

(in mm.)

Nominal dimensions

(in mm.)

104.9

4.5

Lead-in Conduit via the footing and cavity wall

Temporary Cap

100mm – 140mmHorizontal separation

300mm min to

500mm max below

FGL

Ensure all conduit ends are joined. Where the lead-in is

not immediately connected to the Service Drop Conduit, cap

the end of the conduit

Single 300 mm radius bend from the horizontal to the

vertical alignment

Single 100 mm radius bend from vertical to horizontal alignment

Lead-in ConduitService Drop Conduit

FGL

All conduit and bends joints must be glued with solvent cement

Service Drop /

Access Pit

Bedding sand or

excavated material

All conduit and bends joints must be glued with solvent cement

Future Interio

r Wall

Min 4

10 m

m fro

m FG

L

Pro

perty B

ound

ary

Developers ServiceDrop Conduit Builders Lead-in Conduit

Surface mounted lead-in conduit and internal conduit

Developers ServiceDrop Conduit Builders Lead-in Conduit

Temporary Cap

100mm – 140mmHorizontal separation

300mm min to

500mm max below

FGL

Ensure all conduit ends are joined. Where the lead-in is

not immediately connected to the Service Drop Conduit, cap

the end of the conduit

Single 300 mm radius bend from the horizontal to the

vertical alignment

Single 100 mm radius bend from vertical to horizontal alignment

FGL

All conduit and bends joints must be glued with solvent cement

Service Drop /

Access Pit

Bedding sand or

excavated material

All conduit and bends joints must be glued with solvent cement

Future Interio

r Wall

Min 4

10 m

m fro

m FG

L

Pro

perty B

ound

ary

Service Drop Conduit Lead-in Conduit

Figure 1

Figure 3

Figure 2

Conduit dimensions white telecommunications

Conduit dimensions white telecommunications

Nominal Size (Inside Diameter)

20 mm PN 12

AS/NZS 1477:2006

table 4.2(A)

50 mm PN 12

ASPN 12 A S/NZS

1477:2006 table 4.2(A)

100 mm PN 9 AS/

NZS 1477:2006

table 4.2(A)

Nominal Size (Inside Diameter)

Nominal Size (Inside Diameter)

Conduit dimensions white telecommunications

1© 2018 nbn co ltd. ‘nbn’, ‘bring it on’, ‘Sky Muster’, ‘gen nbn’ and the Aurora device are trade marks of nbn co ltd | ABN 86 136 533 741.

Page 2: Key information for builders and developers: Fibre ready ... · Developers Service Drop Conduit Builders Lead-in Conduit. Surface mounted lead-in conduit and internal conduit Drop

Boundary Of The Premises

3

2

1

5

4

6 7

8

9

111213

1014Admin

BEP at each building

2

>50mm

>50mm

>25mm

Boundary Of The Premises

3

2

1

5

4

6 7

8

9

111213

1014Admin

BEP at each building

Boundary Of The Premises

3

2

1

5

4

6 7

8

9

111213

1014Admin

BEP at each building

Boundary Of The Premises

3

2

1

5

4

6 7

8

9

111213

1014Admin

BEP at each building

Min. 100mm radius bends Nominal P20

1 x Nominal P20 Conduit (builder to Supply)

nbn™ utility box

Min. 100mm Radius bend

1 x Nominal P20 Conduit(builder to supply)

General Power Outlet (Builder

to Supply)

Min. 300mm

*Alternate Lead-in conduit Nominal P20 installed in the internal wall cavity

100mm – 140mm Horizontal separation

Min. 410 mm height from Finished Ground Level (FGL)

Min. 300mm Radius bend

Saddle

Saddle

All conduit fittings must be glued

orange or corrugated conduit must not be used

Internal Conduit

Min. 300mm set backfrom building corner

FGL

Lead-in ConduitWall Cavity

Property Boundary

Property Boundary

P20 Lead-in Conduit

P20 Lead-in Conduit

Property Entry Point

ElectricityEnclosure

InternalP20Conduit

InternalP20Conduit

nbn™ utility box

Pit (typical)

ElectricityEnclosure

nbn™ utility box

Property Entry Point

Pit (typical)

Figure 9

Figure 5

Figure 8

Figure 4

Figure 7

Figure: 6

Figure 10

Refer to the Internal P20 and Lead-in Conduit configurations diagram

Figure A

Electricity enclosure on the same side of the building to the property entry point

Figure B

Electricity enclosure on the opposite side of the building to the property entry point

Conduit entry into a pit - 50mm above the pit floor and vertical corners. 25mm separation between conduits entering the pit

Boundary Of The Premises

3

2

1

5

4

6 7

8

9

111213

1014Admin

BEP at each building

Boundary Of The Premises

3

2

1

5

4

6 7

8

9

111213

1014Admin

BEP at each building

Page 3: Key information for builders and developers: Fibre ready ... · Developers Service Drop Conduit Builders Lead-in Conduit. Surface mounted lead-in conduit and internal conduit Drop

Key information for builders and developers:Fibre ready pit and pipe for nbnTM New Developments Horizontal Multi Dwelling Unit (HMDU)This document should be read in conjunction with the following documents for new developments pit and pipe requirements:

• NBN-TE-CTO-194: New developments deployment of thenbn™ pit and conduit access network.

• NBN-DES-STD-0011: Preparation and Installation Guide -SDUs and MDUs.

• G645 Communications Alliance Ltd: Fibre-ready Pit and PipeSpecifications for Real Estate Development Projects.

Important items to remember:

All new lots or subdivided existing lots require fibre ready facilities (pit and pipe). All P100 and P50 conduit must be roped. P20 conduit must be strung and tagged. All conduit entering pits must be fitted with the appropriate sized bush. All conduits shall be plugged as per NBN-TE-CTO-194. This could be in the form of internal reticulated pit and pipe with service drop conduits; generally in Horizontal Multi Dwelling Unit sites (HMDU) are 4 units / townhouses or more.

• HMDU internal reticulated conduit between pits for 3 to 24units / townhouses shall be P50. See Figure 3 for all conduitdimensions.

• HMDU internal reticulated conduit between pits for 25 ormore units / townhouses shall be P100.

• The developer is responsible for installing any new pitand pipe externally in the road reserve where the newlot/s are street facing, this pit and pipe must interconnectto the internal pit and pipe servicing the internal units /townhouses. See Figures 11, 13 and 17.

• Where existing suitable carrier network pit and pipe exists,any pits and service drop conduits requiring installation overthe existing network to service the development and or anystreet fronting units / townhouses will be funded by thedeveloper. See Figures 12, 14, 15, 16 and 18.

Note: Not all HMDU unit / townhouse pit and pipe configurations are represented; Figures 11 through 18 are examples only.

Pit Pit

Pit

Pit

Pit

Existing Lot Existing Lot New Lot New Lot

Existing Carrier Pit and PipeDevelopment BoundaryPitNew Pit and Pipe provided by the developer

New Lot

New Lot

Existing Lot

Truncation

No existing network that meets fibre ready requirements

Existing Public Road Reserve

Note: - Street Conduit shall be installed along/across the full frontage of all Building Lots Including Pits to service the Lots, where the existing Carrier network (if any) is not a Fibre-Ready Facility.If acceptable to the Carrier, the Developer must obtain all necessary council and other approvals to perform work on public roadway(s) and associated verge(s).

Pit Pit

Pit

Pit

Pit

Existing Lot Existing Lot New Lot New Lot

Existing Carrier Pit and PipeDevelopment BoundaryPitNew Pit and Service Drop Conduit providedby the Carrier funded by the developer.

New Lot

New Lot

Existing Lot

Truncation

New Pits Added To Existing Facilities

Existing Public Road Reserve

Note: - The figure includes Carrier installed Pits and Conduits. The Industry convention is for the Developer to fund the installation of all telecommunications Infrastructure.

Pit Pit

Pit

Pit

Pit

Existing Lot Existing Lot New Lot New Lot

Existing Carrier Pit and PipeDevelopment BoundaryPitNew Pit and Pipe provided by the developer

New Lot

New Lot

Existing Lot

Truncation

No existing network that meets fibre ready requirements

Existing Public Road Reserve

Note: - Street Conduit shall be installed along/across the full frontage of all Building Lots Including Pits to service the Lots, where the existing Carrier network (if any) is not a Fibre-Ready Facility.If acceptable to the Carrier, the Developer must obtain all necessary council and other approvals to perform work on public roadway(s) and associated verge(s).

Pit Pit

Pit

Pit

Pit

Existing Lot Existing Lot New Lot New Lot

Existing Carrier Pit and PipeDevelopment BoundaryPitNew Pit and Service Drop Conduit providedby the Carrier funded by the developer.

New Lot

New Lot

Existing Lot

Truncation

New Pits Added To Existing Facilities

Existing Public Road Reserve

Note: - The figure includes Carrier installed Pits and Conduits. The Industry convention is for the Developer to fund the installation of all telecommunications Infrastructure.

Figure 11: No existing network that meets fibre ready requirement

Figure 12: New pit/s and service drop conduit (provided by the carrier, funded by the developer)

3© 2018 nbn co ltd. ‘nbn’, ‘bring it on’, ‘Sky Muster’, ‘gen nbn’ and the Aurora device are trade marks of nbn co ltd | ABN 86 136 533 741.

Page 4: Key information for builders and developers: Fibre ready ... · Developers Service Drop Conduit Builders Lead-in Conduit. Surface mounted lead-in conduit and internal conduit Drop

Develo

per P

rovided

Pit and

Pip

e

Develo

per P

rovided

Pit and

Pip

e

Existing Carrier PipeExisting Carrier Pipe

Existing Carrier PipeExisting Carrier Pipe

Pit

Pit PitPit Pit

New pit installed by Carrier at the Developers Cost

New Fibre Ready Network at Developers CostNew pit installed by Carrier at the Developers Cost

U3

U2

U1

U3U2U1U3U2U1

U3

U2

U1

New pit installed by Carrier at the Developers Cost

Pit

Pit

Develo

per P

rovided

Pit and

Pip

e

Develo

per P

rovided

Pit and

Pip

e

Existing Carrier PipeExisting Carrier Pipe

Existing Carrier PipeExisting Carrier Pipe

Pit

Pit PitPit Pit

New pit installed by Carrier at the Developers Cost

New Fibre Ready Network at Developers CostNew pit installed by Carrier at the Developers Cost

U3

U2

U1

U3U2U1U3U2U1

U3

U2

U1

New pit installed by Carrier at the Developers Cost

Pit

Pit

Develo

per P

rovided

Pit and

Pip

e

Develo

per P

rovided

Pit and

Pip

e

Existing Carrier PipeExisting Carrier Pipe

Existing Carrier PipeExisting Carrier Pipe

Pit

Pit PitPit Pit

New pit installed by Carrier at the Developers Cost

New Fibre Ready Network at Developers CostNew pit installed by Carrier at the Developers Cost

U3

U2

U1

U3U2U1U3U2U1

U3

U2

U1

New pit installed by Carrier at the Developers Cost

Pit

Pit

Develo

per P

rovided

Pit and

Pip

e

Develo

per P

rovided

Pit and

Pip

e

Existing Carrier PipeExisting Carrier Pipe

Existing Carrier PipeExisting Carrier Pipe

Pit

Pit PitPit Pit

New pit installed by Carrier at the Developers Cost

New Fibre Ready Network at Developers CostNew pit installed by Carrier at the Developers Cost

U3

U2

U1

U3U2U1U3U2U1

U3

U2

U1

New pit installed by Carrier at the Developers Cost

Pit

Pit

New

pit installed

by C

arrier at the Develo

pers C

ost

New Fibre Ready Network at the Developers Cost

New

Fib

re Read

y Netw

ork at the D

evelop

ers Co

st

New pit installed by Carrier at the Developers Cost

PitPitPit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Developer Provided Pit and PipeDeveloper Provided Pit and Pipe

Developer Provided Pit and PipeExisting Carrier Pipe

Existing

Carrier P

ipe

U1 U11

U2 U10

U3 U9

U4

U5

U6

U8

U7 U15 U16

U14

U13

U12

U17 U18

U19

U20

U21

U22U1 U11

U2 U10

U3 U9

U4

U5

U6

U8

U7 U15 U16

U14

U13

U12

U17 U18

U19

U20

U21

U22

New

pit installed

by C

arrier at the Develo

pers C

ost

New Fibre Ready Network at the Developers Cost

New

Fib

re Read

y Netw

ork at the D

evelop

ers Co

st

New pit installed by Carrier at the Developers Cost

PitPitPit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Pit

Developer Provided Pit and PipeDeveloper Provided Pit and Pipe

Developer Provided Pit and PipeExisting Carrier Pipe

Existing

Carrier P

ipe

U1 U11

U2 U10

U3 U9

U4

U5

U6

U8

U7 U15 U16

U14

U13

U12

U17 U18

U19

U20

U21

U22U1 U11

U2 U10

U3 U9

U4

U5

U6

U8

U7 U15 U16

U14

U13

U12

U17 U18

U19

U20

U21

U22

Figure 13

Figure 14

Figure 15

Figure 16

Figure 17 Figure 18

4