Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
Key information for builders and developers: Fibre ready pit and pipe for nbnTM New Developments Horizontal Multi Dwelling Units (HMDU)
Dwelling preparation requirements are to assist with the installation of the nbn™ access network technology being installed to the dwelling.
• 1 x internal P20 nominal rigid white telecommunications conduitinstalled from the nbn™ utility box, electrical enclosure location toa suitable location within the dwelling (see Figures 9 and 10).
• Dwellings constructed on new lots, HMDUs or that are streetfacing will require a lead-in. For an example of a lead-in seeFigure 9.
• Street frontage dwellings would require the lead-in fromthe dwellings proposed nbn™ utility box, electrical enclosurelocation, to the property’s front boundary closest to an nbn™pit.
• Where the dwelling/s are located within an HMDU the lead-inwould be installed from an internal pit (see Figures 13, 14and 16) to the dwellings proposed nbn™ utility box, electricalenclosure location. Do not exceed the pits conduit or lead-incapacity (see Figure 4).
• The lead-in conduit at the building entry point can beinstalled within the dwelling footings and exit the wall cavityat the proposed nbn™ utility box location, electrical enclosurelocation or the lead-in can be surface mounted over thedwelling footings and up the external wall to the proposednbn™ utility box, electrical enclosure location. See Figures 1and 2.
• Pit types available for selection: type 2, type 5, type 6, type 8. Allpits to contain pit lid gaskets. All pit lids to be branded NBN asper NBN-TE-CTO-194.
• Conduit entry into pits is important; good examples are shown inFigures 5, 6 and 7. Do not install conduits into the longest side ofa pit Figure 8.
• No more than two 300mm radius 90° underground bends fromthe pit to the nbn™ utility box location and one aboveground100mm radius 90° bend can be used between draw points. Amaximum of three bends in total. See Figure 1, 2, 9 and 10.
• All conduit fittings and joins must be glued using solventcement.
• Lead-in conduits installed into the dwelling footings rising upinto the wall cavity must not terminate in the wall cavity; theconduit must exit the wall cavity using a 100mm radius 90° bendunbroken as per Figure 3. Any lead-in conduit terminating withinthe wall cavity should be discarded. Lead-in conduits terminatingwithin a wall cavity could allow the ingress of water, moisture orinsects into the wall cavity.
• In this case the lead-in must be intercepted before thefootings and redirected as surface conduit to the nbn™ utilitybox, electrical enclosure location. For an example of a surfacemounted lead-in see Figure 4.
• Flexible conduit must not be used underground, or in wall orceiling cavities.
• It is the developer / builder’s responsibility to ensure where thebuilding entry point is lower than the street conduit a drainagepit may be required near the dwelling.
26.7
23.3
1.7
60.3
53.0
3.65
113.9
Nominal dimensions
(in mm.)
Nominal dimensions
(in mm.)
Nominal dimensions
(in mm.)
104.9
4.5
26.7
23.3
1.7
60.3
53.0
3.65
113.9
Nominal dimensions
(in mm.)
Nominal dimensions
(in mm.)
Nominal dimensions
(in mm.)
104.9
4.5
26.7
23.3
1.7
60.3
53.0
3.65
113.9
Nominal dimensions
(in mm.)
Nominal dimensions
(in mm.)
Nominal dimensions
(in mm.)
104.9
4.5
Lead-in Conduit via the footing and cavity wall
Temporary Cap
100mm – 140mmHorizontal separation
300mm min to
500mm max below
FGL
Ensure all conduit ends are joined. Where the lead-in is
not immediately connected to the Service Drop Conduit, cap
the end of the conduit
Single 300 mm radius bend from the horizontal to the
vertical alignment
Single 100 mm radius bend from vertical to horizontal alignment
Lead-in ConduitService Drop Conduit
FGL
All conduit and bends joints must be glued with solvent cement
Service Drop /
Access Pit
Bedding sand or
excavated material
All conduit and bends joints must be glued with solvent cement
Future Interio
r Wall
Min 4
10 m
m fro
m FG
L
Pro
perty B
ound
ary
Developers ServiceDrop Conduit Builders Lead-in Conduit
Surface mounted lead-in conduit and internal conduit
Developers ServiceDrop Conduit Builders Lead-in Conduit
Temporary Cap
100mm – 140mmHorizontal separation
300mm min to
500mm max below
FGL
Ensure all conduit ends are joined. Where the lead-in is
not immediately connected to the Service Drop Conduit, cap
the end of the conduit
Single 300 mm radius bend from the horizontal to the
vertical alignment
Single 100 mm radius bend from vertical to horizontal alignment
FGL
All conduit and bends joints must be glued with solvent cement
Service Drop /
Access Pit
Bedding sand or
excavated material
All conduit and bends joints must be glued with solvent cement
Future Interio
r Wall
Min 4
10 m
m fro
m FG
L
Pro
perty B
ound
ary
Service Drop Conduit Lead-in Conduit
Figure 1
Figure 3
Figure 2
Conduit dimensions white telecommunications
Conduit dimensions white telecommunications
Nominal Size (Inside Diameter)
20 mm PN 12
AS/NZS 1477:2006
table 4.2(A)
50 mm PN 12
ASPN 12 A S/NZS
1477:2006 table 4.2(A)
100 mm PN 9 AS/
NZS 1477:2006
table 4.2(A)
Nominal Size (Inside Diameter)
Nominal Size (Inside Diameter)
Conduit dimensions white telecommunications
1© 2018 nbn co ltd. ‘nbn’, ‘bring it on’, ‘Sky Muster’, ‘gen nbn’ and the Aurora device are trade marks of nbn co ltd | ABN 86 136 533 741.
Boundary Of The Premises
3
2
1
5
4
6 7
8
9
111213
1014Admin
BEP at each building
2
>50mm
>50mm
>25mm
Boundary Of The Premises
3
2
1
5
4
6 7
8
9
111213
1014Admin
BEP at each building
Boundary Of The Premises
3
2
1
5
4
6 7
8
9
111213
1014Admin
BEP at each building
Boundary Of The Premises
3
2
1
5
4
6 7
8
9
111213
1014Admin
BEP at each building
Min. 100mm radius bends Nominal P20
1 x Nominal P20 Conduit (builder to Supply)
nbn™ utility box
Min. 100mm Radius bend
1 x Nominal P20 Conduit(builder to supply)
General Power Outlet (Builder
to Supply)
Min. 300mm
*Alternate Lead-in conduit Nominal P20 installed in the internal wall cavity
100mm – 140mm Horizontal separation
Min. 410 mm height from Finished Ground Level (FGL)
Min. 300mm Radius bend
Saddle
Saddle
All conduit fittings must be glued
orange or corrugated conduit must not be used
Internal Conduit
Min. 300mm set backfrom building corner
FGL
Lead-in ConduitWall Cavity
Property Boundary
Property Boundary
P20 Lead-in Conduit
P20 Lead-in Conduit
Property Entry Point
ElectricityEnclosure
InternalP20Conduit
InternalP20Conduit
nbn™ utility box
Pit (typical)
ElectricityEnclosure
nbn™ utility box
Property Entry Point
Pit (typical)
Figure 9
Figure 5
Figure 8
Figure 4
Figure 7
Figure: 6
Figure 10
Refer to the Internal P20 and Lead-in Conduit configurations diagram
Figure A
Electricity enclosure on the same side of the building to the property entry point
Figure B
Electricity enclosure on the opposite side of the building to the property entry point
Conduit entry into a pit - 50mm above the pit floor and vertical corners. 25mm separation between conduits entering the pit
Boundary Of The Premises
3
2
1
5
4
6 7
8
9
111213
1014Admin
BEP at each building
Boundary Of The Premises
3
2
1
5
4
6 7
8
9
111213
1014Admin
BEP at each building
Key information for builders and developers:Fibre ready pit and pipe for nbnTM New Developments Horizontal Multi Dwelling Unit (HMDU)This document should be read in conjunction with the following documents for new developments pit and pipe requirements:
• NBN-TE-CTO-194: New developments deployment of thenbn™ pit and conduit access network.
• NBN-DES-STD-0011: Preparation and Installation Guide -SDUs and MDUs.
• G645 Communications Alliance Ltd: Fibre-ready Pit and PipeSpecifications for Real Estate Development Projects.
Important items to remember:
All new lots or subdivided existing lots require fibre ready facilities (pit and pipe). All P100 and P50 conduit must be roped. P20 conduit must be strung and tagged. All conduit entering pits must be fitted with the appropriate sized bush. All conduits shall be plugged as per NBN-TE-CTO-194. This could be in the form of internal reticulated pit and pipe with service drop conduits; generally in Horizontal Multi Dwelling Unit sites (HMDU) are 4 units / townhouses or more.
• HMDU internal reticulated conduit between pits for 3 to 24units / townhouses shall be P50. See Figure 3 for all conduitdimensions.
• HMDU internal reticulated conduit between pits for 25 ormore units / townhouses shall be P100.
• The developer is responsible for installing any new pitand pipe externally in the road reserve where the newlot/s are street facing, this pit and pipe must interconnectto the internal pit and pipe servicing the internal units /townhouses. See Figures 11, 13 and 17.
• Where existing suitable carrier network pit and pipe exists,any pits and service drop conduits requiring installation overthe existing network to service the development and or anystreet fronting units / townhouses will be funded by thedeveloper. See Figures 12, 14, 15, 16 and 18.
Note: Not all HMDU unit / townhouse pit and pipe configurations are represented; Figures 11 through 18 are examples only.
Pit Pit
Pit
Pit
Pit
Existing Lot Existing Lot New Lot New Lot
Existing Carrier Pit and PipeDevelopment BoundaryPitNew Pit and Pipe provided by the developer
New Lot
New Lot
Existing Lot
Truncation
No existing network that meets fibre ready requirements
Existing Public Road Reserve
Note: - Street Conduit shall be installed along/across the full frontage of all Building Lots Including Pits to service the Lots, where the existing Carrier network (if any) is not a Fibre-Ready Facility.If acceptable to the Carrier, the Developer must obtain all necessary council and other approvals to perform work on public roadway(s) and associated verge(s).
Pit Pit
Pit
Pit
Pit
Existing Lot Existing Lot New Lot New Lot
Existing Carrier Pit and PipeDevelopment BoundaryPitNew Pit and Service Drop Conduit providedby the Carrier funded by the developer.
New Lot
New Lot
Existing Lot
Truncation
New Pits Added To Existing Facilities
Existing Public Road Reserve
Note: - The figure includes Carrier installed Pits and Conduits. The Industry convention is for the Developer to fund the installation of all telecommunications Infrastructure.
Pit Pit
Pit
Pit
Pit
Existing Lot Existing Lot New Lot New Lot
Existing Carrier Pit and PipeDevelopment BoundaryPitNew Pit and Pipe provided by the developer
New Lot
New Lot
Existing Lot
Truncation
No existing network that meets fibre ready requirements
Existing Public Road Reserve
Note: - Street Conduit shall be installed along/across the full frontage of all Building Lots Including Pits to service the Lots, where the existing Carrier network (if any) is not a Fibre-Ready Facility.If acceptable to the Carrier, the Developer must obtain all necessary council and other approvals to perform work on public roadway(s) and associated verge(s).
Pit Pit
Pit
Pit
Pit
Existing Lot Existing Lot New Lot New Lot
Existing Carrier Pit and PipeDevelopment BoundaryPitNew Pit and Service Drop Conduit providedby the Carrier funded by the developer.
New Lot
New Lot
Existing Lot
Truncation
New Pits Added To Existing Facilities
Existing Public Road Reserve
Note: - The figure includes Carrier installed Pits and Conduits. The Industry convention is for the Developer to fund the installation of all telecommunications Infrastructure.
Figure 11: No existing network that meets fibre ready requirement
Figure 12: New pit/s and service drop conduit (provided by the carrier, funded by the developer)
3© 2018 nbn co ltd. ‘nbn’, ‘bring it on’, ‘Sky Muster’, ‘gen nbn’ and the Aurora device are trade marks of nbn co ltd | ABN 86 136 533 741.
Develo
per P
rovided
Pit and
Pip
e
Develo
per P
rovided
Pit and
Pip
e
Existing Carrier PipeExisting Carrier Pipe
Existing Carrier PipeExisting Carrier Pipe
Pit
Pit PitPit Pit
New pit installed by Carrier at the Developers Cost
New Fibre Ready Network at Developers CostNew pit installed by Carrier at the Developers Cost
U3
U2
U1
U3U2U1U3U2U1
U3
U2
U1
New pit installed by Carrier at the Developers Cost
Pit
Pit
Develo
per P
rovided
Pit and
Pip
e
Develo
per P
rovided
Pit and
Pip
e
Existing Carrier PipeExisting Carrier Pipe
Existing Carrier PipeExisting Carrier Pipe
Pit
Pit PitPit Pit
New pit installed by Carrier at the Developers Cost
New Fibre Ready Network at Developers CostNew pit installed by Carrier at the Developers Cost
U3
U2
U1
U3U2U1U3U2U1
U3
U2
U1
New pit installed by Carrier at the Developers Cost
Pit
Pit
Develo
per P
rovided
Pit and
Pip
e
Develo
per P
rovided
Pit and
Pip
e
Existing Carrier PipeExisting Carrier Pipe
Existing Carrier PipeExisting Carrier Pipe
Pit
Pit PitPit Pit
New pit installed by Carrier at the Developers Cost
New Fibre Ready Network at Developers CostNew pit installed by Carrier at the Developers Cost
U3
U2
U1
U3U2U1U3U2U1
U3
U2
U1
New pit installed by Carrier at the Developers Cost
Pit
Pit
Develo
per P
rovided
Pit and
Pip
e
Develo
per P
rovided
Pit and
Pip
e
Existing Carrier PipeExisting Carrier Pipe
Existing Carrier PipeExisting Carrier Pipe
Pit
Pit PitPit Pit
New pit installed by Carrier at the Developers Cost
New Fibre Ready Network at Developers CostNew pit installed by Carrier at the Developers Cost
U3
U2
U1
U3U2U1U3U2U1
U3
U2
U1
New pit installed by Carrier at the Developers Cost
Pit
Pit
New
pit installed
by C
arrier at the Develo
pers C
ost
New Fibre Ready Network at the Developers Cost
New
Fib
re Read
y Netw
ork at the D
evelop
ers Co
st
New pit installed by Carrier at the Developers Cost
PitPitPit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Developer Provided Pit and PipeDeveloper Provided Pit and Pipe
Developer Provided Pit and PipeExisting Carrier Pipe
Existing
Carrier P
ipe
U1 U11
U2 U10
U3 U9
U4
U5
U6
U8
U7 U15 U16
U14
U13
U12
U17 U18
U19
U20
U21
U22U1 U11
U2 U10
U3 U9
U4
U5
U6
U8
U7 U15 U16
U14
U13
U12
U17 U18
U19
U20
U21
U22
New
pit installed
by C
arrier at the Develo
pers C
ost
New Fibre Ready Network at the Developers Cost
New
Fib
re Read
y Netw
ork at the D
evelop
ers Co
st
New pit installed by Carrier at the Developers Cost
PitPitPit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Pit
Developer Provided Pit and PipeDeveloper Provided Pit and Pipe
Developer Provided Pit and PipeExisting Carrier Pipe
Existing
Carrier P
ipe
U1 U11
U2 U10
U3 U9
U4
U5
U6
U8
U7 U15 U16
U14
U13
U12
U17 U18
U19
U20
U21
U22U1 U11
U2 U10
U3 U9
U4
U5
U6
U8
U7 U15 U16
U14
U13
U12
U17 U18
U19
U20
U21
U22
Figure 13
Figure 14
Figure 15
Figure 16
Figure 17 Figure 18
4