Key Civil & Structural Issues

  • Upload
    brock

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 8/17/2019 Key Civil & Structural Issues

    1/27

    CIVIL AND STRUCTURES KEY ISSUES AND ACTIONS

    FOR SUCCESSFUL PROJECT EXECUTION

    OF LARGE THERMAL POWER PLANTS

    POWER LINE MEET 22ND AND 23RD MAY 2012

    S K KODANDARAMAIAH

    Director(BD) & CEO

    Sunil Hi Tech Engrs Ltd

  • 8/17/2019 Key Civil & Structural Issues

    2/27

    INDUSTRY PERSPECTIVE AND EXPECTATIONS

    • Capacity to add 15000mw/ year

    • Managing costs with Civil and structures being about 20% of EPC cost &

    45-50% of BOP Costs

    • Cycle t ime Pressures

    - 250/300mw 24-26 months

    - 500/600mw 32-34 months

    - 660mw 44 months• Needs about 50% of Labour needs of a Power plant

    • Better Lay Out management with reduced Land availabili ty

    • Project delays related to Labour non availabili ty

    • Civil and Structures key input for Electro Mech packages

    • Cut down of delays of BTG/Mech packages of 6 to 12 months

    due to Civil works• Concreting requirement 4M M3 and Structural reqt of 5 lac MT/year 

    • Focus on improving Engg inputs and Optimization of BOQ

    • Increased mechanization to reduce manpower 

    • Better interface management & Engg Co ord to reduce delays

    • Sound planning and sequencing of work

  • 8/17/2019 Key Civil & Structural Issues

    3/27

    CONTRACT STRUCTURE AND RESPONSIBILITIES

    Owner/EPC

    Contractor 

    Owners

    Engr 

    Structural

    Civil & StrBTG & BOP

    Detailer 

    Fabrication

    Erection

    Raw Mats

    From

    Steel Plants• Res for Civil & Str • Infrastructure

    • Raw Mat Supply• Providing Civil fronts

    • Plant Engg• Engg Drgs

    • Fab. Drawings

    • Cranes

    • Welding eqpt

    • Skilled/Unskilled

    • Painting

    • Bought out items

    OR

    Civil

    Excavation

     Architectural& Buildings

    concreting

    • Batching plant

    • Other equipment

    • Sand & Metal

    • BOIs,Cement & Steel

    • Bar bending• Labour 

  • 8/17/2019 Key Civil & Structural Issues

    4/27

    Un certainty in the Soil conditions and below ground work

    Infrastructure of Land development, Temporary roads, drains

     Availabili ty of Metal and Sand

    Key engg inputs from BTG Vendor & BOP Elect/Mech packages

    Key layout issues and land availability constraints

    Storage yard and Fabrication yard space availability

    Inadequate investment in Infrastructure Roads, drains, power & water 

    Engg co ordination issues between Civil and other areas

    Interfacing issues between Civil and Structures

    Interfacing issues between Civil and Electro- Mech

    Non availabili ty of labour carpenters, barbenders, welders, fitters

    Seasonal labour strength depletion and turn around

    Delivery of Critical steel sections in Rolled and Plate sections Volatility of steel prices

    Major Delays in Civil & Structural works

    - Between Boiler & ESP

    - Bunkers on the LHS – General delay of 4 to 6 months

    CIVIL & STRUCTURAL WORKS KEY ISSUES

  • 8/17/2019 Key Civil & Structural Issues

    5/27

    Concreting in Different Areas

    % age of

    concreting

    0

    10

    20

    30

    40

    50

    60

    NDCT /

    Chimney

    Buildings Flooring

    work

    Foundation

    Super Str.

    • TG & Bunker Floors Critical• Str completion key

    • Buildings Delay due to

    - Engg

    - BOI items

    - Const material

    - Labour 

    • Major augmentation at the

    time of LU and Coal firing

    • Serious manpower shortages

  • 8/17/2019 Key Civil & Structural Issues

    6/27

    VARIOUS INTERFACING ISSUES TO BE TACKLED

    Completing the Furnace bottom AH works beneath O meter along with

    Boiler Foundations

    Simultaneous commencement of work in

    - Boiler area

    - ESP Area

    - TG Area( A, B & C rows)- Commencement of Fabrication of TG Structures

    Engg drgs of TG Building str from grid 0 to 7 at the time of commencement

    CEP pit and CWP drgs release early to Facili tate A and B row foundation

    continuity

    Mill side foundations on the RHS along with Boiler work up to O level

     Aux col interfacing with CW Pit and its eng drg release

    Completion of Aux col foundations prior to TG Deck casting

    CEP sump along with the liners to be finished prior to TG Deck work

     Also priorit ize the foundations for duct ing between ESP to Chimney

    planning Foundations work of Transfer Points & Boi ler to ESP

     AB Bay f loor at the operating level on A row and B row side

  • 8/17/2019 Key Civil & Structural Issues

    7/27

     Areas Needing Attention

    From Project Events Points of View

    Sl No Description(Boiler)

    Event Remarks

    1 Ducting work not

    complete

    LU & CF • Boiler inside duct

    • BOF to ESP

    • Duct Foundation inputs issues

    • Manpower & Welders problems

    • Shortfall of 30 to 40%

    2 Coal Piping & Mills

    completion

    Problems

    Syn & CF • Foundations

    • Mat feeding issues

    • Prob of erecting coal pipes

    • CHP & AHP Civil work problems

    3 Left side Milling

    system

    Full Load • Affects 3000 to 5000mt of Boiler work

    • Late foundation readiness

    • Integration of TPs, Gallaries, FeederFloor,Bunkers,Mills & Coal piping

    4 LU & CF shortfalls

    from the beginning

    LU & CF • At HT/LU about 20% shortfall

    • At CF 10 to 15% shortfall

    • Water & Elect systems civil delays

    Major Shift in Atti tude: Do Initial LU with Coal Firing

  • 8/17/2019 Key Civil & Structural Issues

    8/27

    Sl

    No

    Description

    Others)

    Event Remarks

    5 Mismatch between

    TG Deck and TG

    building Readiness

    TG

    Erection

    Start

    • CEP/CW Piping in terface delays

    • Aux Col Readiness &Deck support

    removal

    6 Left side Bunker

    Structure

    Full

    Load

    • Late start/Foundations availability

    • Inadequate Cranes & manpower 

    • Mat feeding problems

    7 BOF to ESP

    Foundations & Str 

    • For Ducts

    • For FD/PA Fans

    • Fan Handling str 

    • TPs of CHP

    • PAPH Str 

    LU/CF/F

    ull Load

    • Prioritizing FD & PA fan foundations

    • How to accommodate Duct &TP

    foundations

    • working on TPs, Ducting & Fans

    simultaneously

    8 Pipe rack

    • Foundations

    • Structures

    LU/CF • Early s tart can help events

    • Interfacing and approach issues to be

    worked out

  • 8/17/2019 Key Civil & Structural Issues

    9/27

    Critical out look on Thermal Power Cycle

    times(500-600mw units)

    Boiler Island:• Civil Engg and Initial Civil works very critical

    • BLU and Coal firing to be most cri tical

    • Other events can only be inputs for the above

    • Typically @ HT, the physical shortfall of LU work is 15-20%

    • For full load operation the physical shortfall can continue to be 10-15%

    • Major input delays from Civil Side

    Problem Areas:

    • Not identifying the Commissioning sequence at the time of Civil

    works for 

    Milling system(RHS OR LHS), Duct ing system between Boiler andESP

    • Too many civil works at a time between Boiler & ESP

    - Duct foundations & Duct work

    - Fan Foundations & Fans erection

    - CHP Transfer point foundations & Transfer Point Erection

  • 8/17/2019 Key Civil & Structural Issues

    10/27

    TG Island Side

    • Interfacing of CEP Pit, CW Piping along the A and B row of TGBuilding

    • Aux column foundation work and structural work around theTG Deck & Operating Floor completion with TG Building work

    Key Cycle times with Proper interface management

    • Foundation start to LU :25-27 months

    • LU to CF: 3 - 5 months

    • TG Side Foundation start to EOT Crane+TG Deck-12-14M• TG Start to Barring Gear 12 months

  • 8/17/2019 Key Civil & Structural Issues

    11/27

    TG Deck and Structure up to 660 MW

    Sl.no

    Project Unit TG Deckcasting

    comp. in

    TG Bldgwith TG

    floor

    readiness

    EOT Cranereadiness

    TG Bldg. Structurewith floors

    readiness

    (In months) (In months) MT (In months) MT

    1 DB

    Power 

    (600 MW)

    # 1 13 months 15 Months 11 Months 2900 MT 18 months 6500 MT

    # 2 18 months(Anticipate

    d)

    21 Months(Anticipated)

    17 months(Anticipate

    d)

    2900 MT 23 months(Anticipate

    d)

    6000 MT

    2 Koradi

    (660

    MW)

    # 8 14 months 18 months 12 Months 3000 MT 21 months

    (Anticipate

    d)

    5200 MT

    # 9 21 months

    (Anticipate

    d)

    23 months

    (Anticipated)

    18 Months 2500 MT 27 months

    (Anticipate

    d)

    5200 MT

    # 10 26 months

     Ant ic ipated

    28 months

     Ant ic ipated

    24months

     Ant ic ipated

    2500 mt 32months

     Ant ic ipated

    5200mt

    3 Vallur  

    (500MW)

    # 1 14 Months 750 MT 27 Months 6500 MT

    # 2 19 Months 2000 MT 40 Months 6500 MT

    NEED TO MATCH THE DECK AND FLOOR SCHDULES

  • 8/17/2019 Key Civil & Structural Issues

    12/27

    KEY PROBLEM AREAS OF BTG CIVIL WORKS

  • 8/17/2019 Key Civil & Structural Issues

    13/27

    TEMPORARY FRAMING ARRANGMENT FOR INSERTS WORK OF TG DECK

    FOR 660MW L&T MHI DESIGN

  • 8/17/2019 Key Civil & Structural Issues

    14/27

    SUPPORT FROM DEVLOPERSSUPPORT FROM DEVLOPERS

    • Liberal investment in Infrastructure

    • Infrastructure of Roads, Drains, Sewerage system,Lighting

    - to with stand Indian Monsoon(2 seasons)- Fit for movement of heavy cranes(200-400mt) & HeavyDumpers

    • Establishing reliable Construction & Water supply

    • Drinking water facility

    • Adequate Lighting arrangements

  • 8/17/2019 Key Civil & Structural Issues

    15/27

    CIVIL WORKS-Improving Schedules

    o Simultaneous excavation on Boiler, RHS of Mill, ESP & Duct Supportso Explore possibi lity of Civil works between Boiler & ESP before

    commencement of Boiler Erection

    o Start the TG area foundation along with Boi ler 

    o For AB,BC bay along w ith Aux columns for Floor work

    o Prioritise Floor castings & use Deck sheeting's

    o Use cranes for Erection of Cribs erection for TG Deck/or cuplockso Provide Hard crusted surface for Fabrication Area

    o Provide clear approach roads & Drains

    o Commence Fabrication of Structures along with Excavation

    o Complete the TP foundations before Boiler Hydraulic test

    o Erection of Bunkers wi th Cranes or Jacking System

    o Prioritise the completion of main control and ESP control room

    o Kick start of Water system side of Civil workso Focus on the Cable and Pipe racks as a parallel activity

    GOOD START IN CIVIL WORKS ENABLES MEETING SCHEDULES

  • 8/17/2019 Key Civil & Structural Issues

    16/27

    QUANTUM OF STEEL STRUCTUES FOR LARGE

    POWER PLANTS

    Sl No Area 250mw 500/600mw 660mw Remarks

    1 Power House Str 5000 6500 7500

    2 Bunker Str 3500 5000 6000

    3 Pipe Racks 600 1500 2500 Common

    4 Service Building 750 1800 2000 Common

    5 ESP Cont Room 250 400 500

    6 Comp House 100 150 200 Common

    7 Air washer Room 150 200 250 Common

    8 Work shop Building 200 350 400 Common

    9 CWP House 500 1000 1200 Common

    11050 16900 20350

    FOR MULTIPLE

    UNITS 2 2 5Capacity in MW 500 1000/1200 3300

    Total Structures 19900 28500 76350

    Coal Handling Str 5000 9000 15000

    24900 37500 91350

    Per MW Steel use in

    MT 50 31 28

  • 8/17/2019 Key Civil & Structural Issues

    17/27

     APPLICATION IN MEGA AND ULTRA MEGA PROJECTS

    1000/1200mw and >3200mw

    Total Quantum of work 37500mt / 1,00,000mt

    Completion schedule 36 / 45 months per unit

    Packaging can be part of main Civil works or in BTG civil work for BTG Area

    TG Building has two or three bays( Typ for 2 x 600 MW :- 42mx240m)

    Bunker on the left and Right side of Boiler or between TG building & Boiler 

    70% Plates and 30% Rolled Sections

    Material Handling is a major input

    Fabrication Area Reqt is about 30000m2 to 50000m2

    Can be 7 to 10% of Project Costs

    Transfer points betn Boiler & ESP can be part of main Str Package

  • 8/17/2019 Key Civil & Structural Issues

    18/27

    TYPICAL BUNKER SHELL SECTIONAL VIEW FOR ONE UNIT

    Bunker Shell RCC

    SS Hopper

    ABCDE

    FEEDER

    FLOOR

    TRIPPERFLOOR

    BUNKER

    SHELL

    BUNKERHOPPER

    22.4m

    56.6m

    Deck Sheet

    Cladding for Bunker Sealing

    N

    M

  • 8/17/2019 Key Civil & Structural Issues

    19/27

    A

    • COLUMN HT. OF BUNKER SUPPORTSTRUCTURE IS :- 68.0 m

    • SAME HAS BEEN FABRICATED &

    ERECTRED IN 3 PARTS

    • 1st PART is OF 27.0 m IN LENGTH

    WEIGHING 60.0 MT

    • 2nd Part is OF 17.0 m IN LENGTH

    WEIGHINH 22.00 MT.

    • 3rd Part is OF 22.0 m IN LENGTH

    WEIGHINH 14.00 MT. 22.0 mtr

    feeder

    floor

    Bunker

    supporting

    str

    Tripper floor

    Roof floor

    METHODOLOGY OF BUNKER STRUCTURE AND BUNKER SHELL ERECTION

    150 MT Capacity crane

  • 8/17/2019 Key Civil & Structural Issues

    20/27

    A

    •BUNKER SHELL ARE SUPPORTED ON

    TWO ROWS OF COLUMNS MRK M & N.

    • BUNKER SHELL HT. IS 12.5 m

    • SAME IS BEEN FABRICATED & ERECTED

    IN 3 PARTS

    •1st PART IS 5.0 MITER HEIGHT AND

    WEIGHT IS AROUND 15.00 MT

    •2nd PART ALSO 5.0 MITER HEIGHT

    WEIGHT AROUND 15.00 MT

    •3rd PART IS 2.50 MITER WEIGH AROUND

    7.50 MT . 22.0 mtr

    feeder

    floor

    Bunker

    supporting

    str

    Tripper floor

    Roof floor

    METHODOLOGY OF BUNKER STRUCTURE AND BUNKER SHELL ERECTION

    150 MT Capacity crane

    N

    M

  • 8/17/2019 Key Civil & Structural Issues

    21/27

    A

    •THE BUNKER SHELL 1ST PART WITH 4NOS STUB COLUMN RESTED ON DIRECT

    BUNKER SUPPORTING STRUCTURE

    TOWARDS M-ROW WERE ERECTED.

    • AFTER PROPER ARRESTING THE SAME

    2ND PART AND 3RD PART WERE

    ERECTED.

    • AFTER THAT TRIPPER FLOOR BEAM

    AND ROOF BEAM WERE ERECTED.

    • SS HOPPER ALONG WITH THE RING

    BEAM HAD BEEN ERECTED.

    •FINALLY N- ROW BRACINGS & BEAMS

    HAD BEEN ERECTED.

    22.0 mtr

    feeder

    floor

    Bunker

    supporting

    str

    Tripper floor

    Roof floor

    METHODOLOGY OF BUNKER STRUCTURE AND BUNKER SHELL ERECTION

    150 MT Capacity crane

    N

  • 8/17/2019 Key Civil & Structural Issues

    22/27

    BOLTED STRUCTURES ADVANTAGES & DISADVANTAGES

    Structures present status

    • General practice of Fab & Ern @ site

    • Make shift arrangement for fabrication

    • Design by Customer & Detailing by Contractor 

    • Material supply by mostly customer 

    • Site erection of welded joints

    • Erection tolerances can be flexible

    • Welding by MIG/MAW welding

    • Schedules 30-40 months for 500/600mw units

    Bolted Design Requirements

    • All the structures including cols, main &sec beams

    of bolted design

    • Needs factory manufacture with NC/3 axis m/cs

    • Very close tolerances for manufacturing & Ern

    • Transportation logistics to be worked out

    • Local MM logistics for storage @ site

    • Design and Detailed Engg to be with Owner 

    • Raw material supply with the Vendor 

    • Manufacturing to gear up to handle 60 to 80mt wts

    • Large infra and area to be created for offsite work

     Advantages

    • Factory made work, better quality

    • Erection can be faster 

    • No need for large infrastructure at site

    • No burden of raw material procurement

    • Welding work can be eliminated

    • Saving in cycle time if properly managed

    • work can be done with less work force

    • CENVAT benefits can be taken

    Disadvantages

    • Fab + Ern cost go up by 20 to 25%

    • ED on factory dispatch's on site work

    • Transportation cost extra on large components

    • No flexibility on managing matching items

    • Non sequential supplies can delay the site work

    • can nullify the advantages if shipments are non sequenti

    • Addl cost for site storage and MM

    • High levels of accuracy for manufacturing & tolerances

    • High levels of erection accuracy reqd

    • Detailing to be done by Customer 

    • Total cost per MT can go up by 10-12%

  • 8/17/2019 Key Civil & Structural Issues

    23/27

    MAJOR PROBLEMS AND CHALLENGES FOR STRUCTURAL

    WORKS IN POWER PLANTS

    Structural and Civil works are to be integrated for better execution

    Very poor infrastructure at site for Fabrication yard and Movement of material

    Major mat. availability problems with Plates of 32mm,36mm,40mm &

    Rolled sections ISMB 300,400,500 & 600

    General Delay of 3 to 5 months in Critical Steel Sections

    Volatili ty in Steel Prices

    Manufactur ing capacity of higher sections limited and mismatch between

    Site reqt and Steel Plant Roll ing plans Engg input issues between Mechanical inputs for Civil Const Drgs

    Transportation bott lenecks for Heavy items at site- Poor Roads

     Availability of skil led welders and f itters & Material Handling Equipment

    Mismatch with the events of Mechanical fronts w ith Civil and Str fronts

    like

    - EOT Crane Readiness in TG hall

    - TG Building readiness for Mechanical Erection

    - Bunker Structure for Coal Firing system of Boiler 

    - Bunker readiness for Coal firing

    - CHP Transfer point Erection Problems( Very tall structures)

  • 8/17/2019 Key Civil & Structural Issues

    24/27

    CAPABILITIES & LEARNINGS

    Critical steel sections in manufacturing to be augmented for timely supply

    Better to discuss with the steel supplier at the beginning with tentative sections

    Need for Deployment of Higher Capacity cranes of 150mt to 250mt

    Present capacity to be increased by about 30-50% for 12th Plan Objectives

    There is a general shortage of experienced good Civil and Structural Engrs.

    Shop manufacturing as a substitute to site fabrication can be an alternative

    Bolted structure can be an alternative to Welded structure for site joints

    Investment in site infrastructure for proper Fab Yards, Roads and Approaches

    Development of skilled welders and Fitters for site work

    Development of more agencies for Fabrication detailing drawings

    Safety standards for tall structures erection to improve

    Suitable Price Escalation for Steel Price volatility cover up

  • 8/17/2019 Key Civil & Structural Issues

    25/27

    FOCUS AREAS KEY ACTIONS

    Boiler Foundations • To excavate the Mill side foundations on RHS• To do Bottom ash hopper foundations to GL

     A, B Structure column erection • CEP and CWP engg clearance for RCC work• Engg drgs for Cols, bracings, Floors ,trusses

    • Heavy lift crane

    Floors in AB and BC Bay • Readiness of Aux cols• Deck sheeting arrangement

    TG Deck work/TG operating floorreadiness

    • Cup lock/staging arrangement• Inserts incorporation with proper material handling

    • Bar bending and placement arrangement for

    reinforcement

    • UPV testing arrangement & Deck support

    dismantling

    Foundations between Boiler & ESP

    & TPs

    • Priority for Duct and Fan Foundations for LU

    • Priority for TP foundations for CF

    • Sequencing of foundations, duct work and CHP

    work & clearances

    • Erection of TPs the most difficult structure

    BOP Bui ldings( DM plant, CWP

    House, FOPH,Aerator,Service

    building, APH, Silos

    • Labour arrangement

    • Shuttering & staging material

    • Drgs

    • Clearances

  • 8/17/2019 Key Civil & Structural Issues

    26/27

    SAFETY RECORDSAFETY RECORD – –

    Civil & structure packageCivil & structure package

  • 8/17/2019 Key Civil & Structural Issues

    27/27

    LOOKING AHEAD……

    Engg inputs to be ahead for 3 to 5 months progress of site work Adequate and t imely investment in Roads, Drains, Const Power & Infra

    Improve mechanization and reduce dependence on labour 

    - More Use of Boom placers, concrete pumps

    - Use of Deck sheeting for floor work

    - Use of RMC wherever it is feasible

    - Use of higher capacity cranes and more in nos

    - Use of Tower cranes for Building works

    Pre pone CHP Civil works between Boi ler and ESP by 6 months

    Better integration of Civil and Structural works of TG Building

    Invest in Monsoon preparation on temporary works

    Switch over to Bolted structure for major structural work

    HR init iatives for Strengthening Civil and Structural Supervision

    Improving Construction safety records Provide differential rates for concreting of Buildings & Floor works

    Proper escalation clauses for Cement and Steel price volatility

    Prioritize Bunker work on RHS and LHS

    Plan for LU with Coal firing instead of Coal firing for Full load operation