Upload
ermelvindias
View
226
Download
0
Embed Size (px)
DESCRIPTION
88
Citation preview
2nd RA BILL
Detailed Measurement Sheet No. - 24
PREMEASUREMENT
Date of Recording :
Item of work No. L in M B in M D in M Qty unit
26
FOR CD WORK 1000 MM Dia.1) CH. 0.050 Km.Head wall L/S 1 6.30 1.40 1.65 14.55 Cum R/S 1 6.30 1.40 1.65 14.55
Pipe portion 1 4.85 1.35 0.60 3.93
Head wall L/S 2 1.80 0.90 1.65 5.35 R/S 2 2.60 1.40 1.65 12.01
2) CH. 0.45 Km.Head wall 2 6.30 1.40 1.65 29.11 Pipe portion 1 4.85 1.35 0.60 3.93
3) CH. 1.150 Km.Head wall 2 6.30 1.40 1.65 29.11 Pipe portion 1 4.85 1.35 0.60 3.93
4) CH. 1.33 Km.Head wall 2 6.30 1.40 1.65 29.11 Pipe portion 1 4.85 1.35 0.60 3.93
5) CH. 1.87 Km.Head wall 2 6.30 1.40 1.65 29.11 Pipe portion 1 4.85 1.35 0.60 3.93
6) CH. 2.595 Km.Head wall 2 6.30 1.40 1.65 29.11 Pipe portion 1 4.85 1.35 0.60 3.93
NAME OF WORK :METALLING AND ASPHALTING OF ROAD FROM KELADI TO T-09 ROAD IN SAGARA TLAUK, SHIMOGA DISTRICT. FROM 0.00 TO 7.450 KM (PACKAGE NO. 24-29)
Tender Sl. No.
Earth work in excavation for structure as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal dressing of sides and bottom and backfilling in trenches with excavated suitable material. In all soil with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
2nd RA BILL
Detailed Pre-Measurement Sheet No. - 25
Item of work No. L in M B in M D in M Qty unit
7) CH. 5.63 Km.Head wall L/S 1 6.30 1.40 1.65 14.55 R/S 2 1.80 0.90 1.65 5.35 R/S 1 1.10 0.90 1.65 1.63 R/S 2 1.80 1.40 1.65 8.32
Pipe portion 1 4.85 1.35 0.60 3.93
8) CH. 6.30 Km.Head wall 2 6.30 1.40 1.65 29.11
Pipe portion 1 4.85 1.35 0.60 3.93282.38 Cum
27
FOR CD WORK 1000 MM Dia.
For Pipe jointing portion 2 10 0.60 0.60 0.15 1.08 Cum
28
FOR CD WORK 1000 MM Dia.1) CH. 0.050 Km.Head wall L/S 1 6.30 1.40 0.15 1.32 Cum R/S 1 6.30 1.40 0.15 1.32
R/S 2 1.80 0.90 0.15 0.49 R/S 2 2.60 1.40 0.15 1.09
2) CH. 0.45 Km.Head wall L/S 2 6.30 1.40 0.15 2.65
3) CH. 1.150 Km.Head wall L/S 1 6.30 1.40 0.15 1.32 R/S 1 6.30 1.40 0.15 1.32
4) CH. 1.33 Km.Head wall 2 6.30 1.40 0.15 2.65
Tender Sl. No.
Providing and laying concrete cradle bedding with (Type-A) M 15 Grade Cement concrete as per clause 1105 with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete
Providing and laying concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 and 1203 PCC grade M 10, Nominal mix 1:3:6 with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
2nd RA BILL
Detailed Pre-Measurement Sheet No. - 26
Item of work No. L in M B in M D in M Qty unit
5) CH. 1.87 Km.Head wall 2 6.30 1.40 0.15 2.65
6) CH. 2.595 Km.Head wall 2 6.30 1.40 0.15 2.65
7) CH. 5.63 Km.Head wall L/S 1 6.30 1.40 0.15 1.32 R/S 2 1.80 0.90 0.15 0.49 R/S 1 1.10 0.90 0.15 0.15 R/S 2 1.80 1.40 0.15 0.76
8) CH. 6.30 Km.Head wall 2 6.30 1.40 0.15 2.65
22.81 Cum
10
Jelly Hip measurementsCh. 5.50 to 6.00 Km 6 9.50 (1.00+0.50)/2 0.49 20.95
7 10.00 (1.05+0.50)/2 0.50 27.136 9.80 (1.10+0.55)/2 0.48 23.285 8.50 (1.00+0.48)/2 0.52 16.356 8.00 (1.00+0.40)/2 0.50 16.807 9.30 (1.00+0.52)/2 0.51 25.237 9.20 (1.20+0.51)/2 0.48 26.436 9.00 (1.15+0.48)/2 0.45 19.806 10.00 (1.15+0.48)/2 0.48 23.475 9.80 (1.20+0.51)/2 0.48 20.116 9.50 (1.00+0.40)/2 0.50 19.957 9.30 (1.00+0.45)/2 0.52 24.54
Ch. 6.00 to 7.00 Km 7 9.30 (1.00+0.50)/2 0.50 24.416 10.20 (1.05+0.50)/2 0.49 23.247 9.70 (1.10+0.55)/2 0.48 26.896 9.60 (1.00+0.48)/2 0.55 23.446 9.20 (1.00+0.40)/2 0.60 23.187 9.30 (1.00+0.52)/2 0.52 25.736 9.20 (1.20+0.51)/2 0.53 25.016 9.80 (1.15+0.48)/2 0.43 20.616 10.10 (1.15+0.48)/2 0.47 23.215 9.75 (1.20+0.51)/2 0.48 20.015 9.40 (1.00+0.40)/2 0.50 16.456 9.30 (1.00+0.45)/2 0.52 21.04
Tender Sl. No.
Providing, laying, Spreading and compacting stone aggregates of specific sizes to Water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel roller 80-100 KN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill up the intersectices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification Clause 405 by all means with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
2nd RA BILL
C/F 537.26Detailed Pre-Measurement Sheet No. - 27
Item of work No. L in M B in M D in M Qty unit
B/F 537.26Ch. 7.00 to 7.45 Km 6 9.20 (1.00+0.50)/2 0.52 21.53
7 8.80 (1.05+0.50)/2 0.53 25.305 10.00 (1.10+0.55)/2 0.51 21.046 10.10 (1.00+0.48)/2 0.52 23.327 9.80 (1.00+0.40)/2 0.48 23.056 9.50 (1.00+0.52)/2 0.49 21.237 9.60 (1.20+0.51)/2 0.47 27.005 9.75 (1.15+0.48)/2 0.55 21.856 8.80 (1.15+0.48)/2 0.49 21.096 10.20 (1.20+0.51)/2 0.49 25.64
768.31
Section Officer. Assistant Executive EngineerProject sub division,
Shimoga.
Tender Sl. No.
Detailed Measurement Sheet No. - 9
R.A BILL - FIRST AND PART BILL
27937.50
" PRADHANA MANTRI GRAMA SADAK YOJANA" PHASE VII 2006-07
Date of Recording :
Item of work Nos. L in M D in M Qty Unit Amount
1
Pre measurement qty. vide this M.B.No.01 at page No.1 to 3 of Item No. 3.35003.3500 Hectare 18974.00 63563.00
3
0.00 to 0.20 KMLeft side 5 30.00 150.00 Rmtr
1 8.00 8.00Right side 6 30.00 180.00
0.20 to 0.40 KmLeft side 3 30.00 90.00
1 20.00 20.00Right side 4 30.00 120.00
1 5.00 5.00
0.40 to 0.60 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.000.80 to 1.00 KmLeft side 1 10.00 10.00
NAME OF WORK : METALLING AND ASPHALTING OF ROAD FROM KELADI TO T-09 ROAD IN SAGARA TLAUK, SHIMOGA DISTRICT. FROM 0.00 TO 7.450 KM (PACKAGE NO. 24-29)
Name of Contractor : Mr. Sharath J ShetEstimate Cost : Rs. 205.69 LakhsTechnical approval No. : TCH/06231/DIV/PH - VII B' /07-08Head of Account : 3054-06-337-Rural roads - 01
Agreement No. : Starting Period : 12-12-2008Stipulated Period : 11-09-2009
Sl. No. B in M Tender
rate
Cutting and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable materials to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201 by manual means in area of non-throny jungle etc., complete as directed by the Engineer in charge of the work.
Surface drains in soil construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines, grades levels and dimensions. Excavated material to be used in embankment with all lead and lifts, loading and unloading charges cost and conveyance of all materials, labour, equipment and other incidental charges etc., complete as per Technical specification Clause 307. Mechanical means as directed by the Engineer in charge of the work.
Right side 1 20.00 20.00Detailed Measurement Sheet No. - 10
Item of work Nos. L in M D in M Qty Unit Amount
1.00 to 1.20 KmLeft side 5 30.00 150.00
1 27.00 27.00Right side 6 30.00 180.00
1 20.00 20.00
1.20 to 1.40 KmLeft side 2 30.00 60.00
1 23.00 23.00Right side 4 30.00 120.00
1 5.00 5.00
1.40 to 1.60 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
1.60 to 1.80 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
1.80 to 2.00 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
2.00 to 2.20 KmLeft side 2 30.00 60.00
1 5.00 5.00Right side 4 30.00 120.00
1 25.00 25.00
2.20 to 2.40 KmLeft side 2 20.00 40.00Right side 1 30.00 30.00
1 7.00 7.00
2.40 to 2.60 KmLeft side 5 30.00 150.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
2.60 to 2.80 KmLeft side 6 30.00 180.00
Sl. No. B in M Tender
rate
1 20.00 20.00Right side 6 30.00 180.00
1 10.00 10.00Detailed Measurement Sheet No. - 11
Item of work Nos. L in M D in M Qty Unit Amount
2.80 to 3.00 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
3.00 to 3.20 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
3.20 to 3.40 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
3.40 to 3.60 KmLeft side 3 30.00 90.00
1 28.00 28.00Right side 3 30.00 90.00
1 25.00 25.00
3.60 to 3.80 KmLeft side 3 30.00 90.00Right side 5 30.00 150.00
3.80 to 4.00 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
4.00 to 4.20 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
4.20 to 4.40 KmLeft side 1 30.00 30.00
1 20.00 20.00Right side 1 30.00 30.00
1 20.00 20.00
Sl. No. B in M Tender
rate
4.40 to 4.60 KmLeft side 5 30.00 150.00
1 15.00 15.00Right side 5 30.00 150.00
1 25.00 25.00Detailed Measurement Sheet No. - 12
Item of work Nos. L in M D in M Qty Unit Amount
4.60 to 4.80 KmLeft side 4 30.00 120.00
1 15.00 15.00Right side 4 30.00 120.00
1 10.00 10.00
4.80 to 5.00 KmLeft side 5 30.00 150.00
1 5.00 5.00Right side 3 30.00 90.00
1 15.00 15.00
5.00 to 5.20 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 15.00 15.00
5.20 to 5.40 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 20.00 20.00
5.40 to 5.60 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 15.00 15.00
5.60 to 5.80 KmLeft side 6 30.00 180.00
1 15.00 15.00Right side 6 30.00 180.00
1 15.00 15.00
5.80 to 6.00 KmLeft side 5 30.00 150.00Right side 5 30.00 150.00
1 15.00 15.00
6.00 to 6.20 KmLeft side 1 15.00 15.00Right side 1 30.00 30.00
Sl. No. B in M Tender
rate
6.20 to 6.40 KmLeft side 4 30.00 120.00
1 20.00 20.00Right side 6 30.00 180.00
1 15.00 15.00Detailed Measurement Sheet No. - 13
Item of work Nos. L in M D in M Qty Unit Amount
6.40 to 6.60 KmLeft side 6 30.00 180.00
1 20.00 20.00Right side 6 30.00 180.00
1 15.00 15.00
6.60 to 6.80 KmLeft side 4 30.00 120.00
1 15.00 15.00Right side 4 30.00 120.00
1 15.00 15.00
6.80 to 7.00 KmLeft side 5 30.00 150.00
1 5.00 5.00Right side 5 30.00 150.00
1 5.00 5.00
7.00 to 7.20 KmLeft side 6 30.00 180.00
1 15.00 15.00Right side 6 30.00 180.00
1 15.00 15.00
7.20 to 7.45 KmLeft side 3 30.00 90.00Right side 3 30.00 90.00
Total Qty . = 11093.00 Rmtr 40.00 443720.00
4
#REF!Total Qty . = #REF! Sqm 10.00 #REF!
Sl. No. B in M Tender
rate
Scarifying existing granular surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m and leads upto 1000 m as per Technical Specification Clause 301.4 with all lead and lifts, loading and unloading charges cost and conveyance of all materials, labour, equipment and other incidental charges etc., complete as per Technical specification Clause 307. Mechanical means as directed by the Engineer in charge of the work.
Pre measurement qty. vide this M.B.No.01 at page No.4 to 6 of Item No. 4
Detailed Measurement Sheet No. - 14
Item of work Nos. L in M D in M Qty Unit Amount
5
0.00 to 0.20 KmShoulders 2 6 30.00 1.875 0.15 101.25 Cum
2 1 20.00 1.875 0.15 11.25
0.20 to 0.40 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
0.40 to 0.60 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
0.80 to 1.00 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
1.00 to 1.20 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
1.20 to 1.40 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
1.40 to 1.60 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
1.60 to 1.80 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
1.80 to 2.00 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
2.00 to 2.20 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
2.20 to 2.40 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
2.40 to 2.60 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
Sl. No. B in M Tender
rate
Compacting Original ground supporting embankment loosening, levelling and compacting original ground supporting embankment to fecilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling as to achieve minium dry density as given in Table 300.1 and 300.2 for embankment construction as per Technical specification clause 301.4.1 as directed by the Engineer in charge of the work.
2.60 to 2.80 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
2.80 to 3.00 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
3.00 to 3.20 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
Detailed Measurement Sheet No. - 15
Item of work Nos. L in M D in M Qty Unit Amount
3.20 to 3.40 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
3.40 to 3.60 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
3.60 to 3.80 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
3.80 to 4.00 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
4.00 to 4.20 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
4.20 to 4.40 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
4.40 to 4.60 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
4.60 to 4.66 Km 2 2 30.00 1.875 0.15 33.75
4.675 to 4.80 Km 2 4 30.00 1.875 0.15 67.502 1 5.00 1.875 0.15 2.81
4.80 to 5.00 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
5.00 to 5.20 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
5.20 to 5.40 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
5.40 to 5.60 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
5.60 to 5.80 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
5.80 to 6.00 Km 2 6 30.00 1.875 0.15 101.25
Sl. No. B in M Tender
rate
2 1 20.00 1.875 0.15 11.25
6.00 to 6.20 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
6.20 to 6.40 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
Detailed Measurement Sheet No. - 16
Item of work Nos. L in M D in M Qty Unit Amount
6.40 to 6.60 Km 2 6 30.00 1.625 0.15 87.752 1 20.00 1.625 0.15 9.75
6.60 to 6.80 Km 2 6 30.00 1.625 0.15 87.752 1 20.00 1.625 0.15 9.75
6.80 to 7.00 Km 2 6 30.00 1.625 0.15 87.752 1 20.00 1.625 0.15 9.75
7.00 to 7.20 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
7.20 to 7.40 Km 2 6 30.00 1.875 0.15 101.252 1 20.00 1.875 0.15 11.25
7.40 to 7.45 Km 2 1 5.00 1.875 0.15 2.81Total Qty . = 3999.37 Cum 10.00 39994.00
7.a
1.00 to 1.20 KmLeft side 3 30.00 90.00
1 15.00 15.00Right side 3 30.00 90.00
1 15.00 15.00
1.20 to 1.40 KmLeft side 3 30.00 90.00
1 15.00 15.00Right side 3 30.00 90.00
1 15.00 15.00
1.40 to 1.60 KmLeft side 2 30.00 60.00
Sl. No. B in M Tender
rate
construction of embankment with approved material deposited at site from road way cutting and excavation from drain and foundation other structures graded and compacted to need the requirement of tables 300.1 & 300.2 as per technical specification Clause 301.5 with all lead and lift loading and unloading charges including cost of labour Hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of the work including transporting etc., complete. as per the detailed standard specification and as directed by the Engineer in charge of the work etc. complete
1 10.00 10.00Right side 4 30.00 120.00
1 20.00 20.00
1.60 to 1.80 KmLeft side 3 30.00 90.00Right side 3 30.00 90.00
1 20.00 20.00
Detailed Measurement Sheet No. - 17
Item of work Nos. L in M D in M Qty Unit Amount
1.80 to 2.00 KmLeft side 3 30.00 90.00
2 20.00 40.00Right side 2 30.00 60.00
2.00 to 2.20 KmLeft side 2 30.00 60.00
2 20.00 40.00Right side 3 30.00 90.00
1 10.00 10.00
2.20 to 2.40 KmLeft side 3 30.00 90.00Right side 3 30.00 90.00
2 7.00 14.00
2.40 to 2.60 KmLeft side 3 30.00 90.00
1 20.00 20.00Right side 2 30.00 60.00
1 20.00 20.00
2.60 to 2.80 KmLeft side 3 30.00 90.00
1 20.00 20.00Right side 3 30.00 90.002.80 to 3.00 KmLeft side 3 30.00 90.00
2 20.00 40.00Right side 2 30.00 60.00
1 20.00 20.00
3.00 to 3.20 KmLeft side 3 30.00 90.00
2 20.00 40.00Right side 3 30.00 90.00
3.20 to 3.40 KmLeft side 3 30.00 90.00
Sl. No. B in M Tender
rate
1 20.00 20.00Right side 3 30.00 90.00
3.40 to 3.60 KmLeft side 3 30.00 90.00
1 28.00 28.00Right side 3 30.00 90.00
3.60 to 3.80 KmLeft side 3 30.00 90.00Right side 4 30.00 120.00
Detailed Measurement Sheet No. - 18
Item of work Nos. L in M D in M Qty Unit Amount
3.80 to 4.00 KmLeft side 3 30.00 90.00
2 20.00 40.00Right side 2 30.00 60.00
2 10.00 20.00
5.00 to 5.20 KmLeft side 4 30.00 120.00
1 20.00 20.00Right side 2 30.00 60.00
5.20 to 5.40 KmLeft side 4 30.00 120.00Right side 1 30.00 30.00
3 20.00 60.00
5.40 to 5.60 KmLeft side 3 30.00 90.00Right side 3 30.00 90.00
2 15.00 30.00
5.60 to 5.80 KmLeft side 3 30.00 90.00
1 15.00 15.00Right side 2 30.00 60.00
3 15.00 45.00
5.80 to 6.00 KmLeft side 3 30.00 90.00Right side 5 30.00 150.00
6.00 to 6.20 KmLeft side 1 15.00 15.00Right side 1 30.00 30.00
6.20 to 6.40 Km
Sl. No. B in M Tender
rate
Left side 3 30.00 90.001 20.00 20.00
Right side 3 30.00 90.00
6.40 to 6.60 KmLeft side 3 30.00 90.00
1 20.00 20.00Right side 3 30.00 90.00
1 15.00 15.00
6.60 to 6.80 KmLeft side 2 30.00 60.00
1 15.00 15.00Right side 2 30.00 60.00
Detailed Measurement Sheet No. - 19
Item of work Nos. L in M D in M Qty Unit Amount
6.80 to 7.00 KmLeft side 3 30.00 90.00
1 5.00 5.00Right side 3 30.00 90.00
1 5.00 5.00
7.00 to 7.20 KmLeft side 3 30.00 90.00Right side 3 30.00 90.00
1 15.00 15.00
7.20 to 7.45 KmLeft side 2 30.00 60.00Right side 1 30.00 30.00
4182.00 RmtrVolume of drain qty. = (4182.00 x 0.40 Cum / Rmtr) 1672.80 Cum 40.00 66912.00
8
0.00 to 0.20 Km
1 6 30.00 7.500 292.50 Cum
1 1 20.00 7.500 31.50
0.20 to 0.40 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.50
Sl. No. B in M Tender
rate
Construction of Subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to requried slope and compacted to meet requirement of table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1 with all lead and lifts, loading and unloading charges cost and conveyance of all materials, labour, equipment and other incidental charges etc., complete as per Technical specification Clause 307. Mechanical means as directed by the Engineer in charge of the work.
(0.20+0.25+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.25+0.20) 3
0.40 to 0.60 Km 1 6 30.00 7.500 279.00
1 1 20.00 7.500 31.50
0.80 to 1.00 Km 1 6 30.00 7.500 292.50
1 1 20.00 7.500 31.50
1.00 to 1.20 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
Detailed Measurement Sheet No. - 20
Item of work Nos. L in M D in M Qty Unit Amount
1.20 to 1.40 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
1.40 to 1.60 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.50
1.60 to 1.80 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.50
1.80 to 2.00 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.50
2.00 to 2.20 Km 1 6 30.00 7.500 279.00
1 1 20.00 7.500 32.50
2.20 to 2.40 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 31.50
2.40 to 2.60 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 31.50
(0.20+0.22+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.25+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
Sl. No. B in M Tender
rate
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.25+0.20) 3
(0.20+0.22+0.20) 3
(0.20+0.25+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.23+0.20) 3
2.60 to 2.80 Km 1 6 30.00 7.500 279.00
1 1 20.00 7.500 32.50
2.80 to 3.00 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 31.50
3.00 to 3.20 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 31.50
Detailed Measurement Sheet No. - 21
Item of work Nos. L in M D in M Qty Unit Amount
3.20 to 3.40 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 32.00
3.40 to 3.60 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
3.60 to 3.80 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
3.80 to 4.00 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
4.00 to 4.20 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
4.20 to 4.40 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.50
(0.20+0.22+0.20) 3
(0.20+0.25+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.23+0.20) 3
Sl. No. B in M Tender
rate
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
4.40 to 4.60 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.50
4.60 to 4.66 Km 1 2 30.00 7.500 94.50
4.675 to 4.80 Km 1 4 30.00 7.500 192.00
1 1 5.00 7.500 8.00
4.80 to 5.00 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.50
5.00 to 5.20 Km 1 6 30.00 7.500 283.50
Detailed Measurement Sheet No. - 22
Item of work Nos. L in M D in M Qty Unit Amount
1 1 20.00 7.500 31.50
5.20 to 5.40 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
5.40 to 5.60 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
5.60 to 5.80 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
5.80 to 6.00 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.50
6.00 to 6.20 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.50
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
Sl. No. B in M Tender
rate
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
6.20 to 6.40 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.50
6.40 to 6.60 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
6.60 to 6.80 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
6.80 to 7.00 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
7.00 to 7.20 Km 1 6 30.00 7.500 288.00
1 1 20.00 7.500 32.00
Detailed Measurement Sheet No. - 23
Item of work Nos. L in M D in M Qty Unit Amount
7.20 to 7.40 Km 1 6 30.00 7.500 283.50
1 1 20.00 7.500 31.00
7.40 to 7.45 Km 1 1 5.00 7.500 8.00
Total Qty . = 11428.00 Cum 156.00 1782768.00
9
Pre measurement qty. vide this M.B.No.01 at page No. 7 to 8 of Item No #REF!Part rate #REF! Cum 1000.00 #REF!
Full Rate Rs. 1500.00
(0.20+0.23+0.20) 3
(0.20+0.23+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
(0.20+0.24+0.20) 3
Sl. No. B in M Tender
rate
(0.20+0.23+0.20) 3
(0.20+0.22+0.20) 3
(0.20+0.24+0.20) 3
Water bound macadam sub base / base WBM Grading 2 Providing, laying spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel roller 80-100 KN static roller in stages to proper grade and camber, applying and brooming, stone screening / binding materials to fill up the intersectices of coarse aggregate, watering and compacting to the required density grading 2 with all lead and lifts, loading and unloading charges, cost and conveyance of all materials, labour equipment and other incidental charges etc., complete as per Technical specification Clauses 405 as directed by the Engineer in charge of the work.
Part Rate paid Rs. 1000.00
10
15 7.50 112.50 Rmtr 4000.00 450000.00
Full Rate Rs. 4590.00Part Rate paid Rs. 4000.00
Toatl Bill amount = Rs. #REF!
Providing and laying Reinforced cement concrete pipe NP3 as per design in Single row. Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets with all lead and lifts, loading and unloading charges, cost and conveyance of all materials, labour, equipment and other incidental charges etc., complete. Clause 1106 as directed by the Engineer in charge of the work. 1000 mm dia single vent.
Unit Item of work
1
3.47 18974.00
2
Cum 4476.00
3
Rmtr 14900.00 40.00
Tend
er
S
l No
. Tender Qty
Tender Rate
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable materials to be used or auctioned, including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201 by mechanical means (In Non Thorny Jungle) with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Hectare
Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance as directed, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections with all leads and lifts, loading and unloading charges, cost and conveyance of all materials, labour, equipments and all other incidental charges for the successful completion of work etc., complete as per directions of the Engineer in charge of the work.
Construction of unlined Surface drains of average cross sectional area 0.40 sqm in all soil to specified lines, grades levels and dimensions, excavated material to be used in embankment as per Technical specification Clause 307 by manual means with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Previous measurement Present measurement Total Upto dateQty Amount Qty Rate Amount Qty Amount
3.35 63563.00 18974.00 3.35 63563.00
4470.20 45.00 201159.00 4470.20 201159.00
11093.00 443720.00 11093.00 443720.00
Unit Item of work
Tend
er
S
l No
. Tender Qty
Tender Rate
4
Sqm ### 10.00
5
Cum 4190.63 10.00
6
Cum 4384.00 40.00
8
Scarifying existing granular surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m and leads upto 1000 m as per Technical Specification Clause 301.4 with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Compacting Original ground supporting embankment loosening, levelling and compacting original ground supporting embankment to fecilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed with water at OMC and then compacted by rolling as to achieve minium dry density as given in Table 300.1 and 300.2 for embankment construction as per Technical specification clause 301.4.1 as directed by the Engineer in charge of the work.
Construction of embankment with approved material deposited at site from road way cutting and excavation from drain and foundation other structures graded and compacted to meet requirement of tables 300.1 & 300.2 as per technical specification Clause 301.5 with all lead and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Construction of Subgrade and earthen shoulders with approved material obtained from borrow pits shall not be less than CBR 8%. If the existing surface CBR is more than 8%, the CBR of the material brought from the borrow pit should not be less than the existing surface (CBR of such soil should be checked by contractor or by his site engineer considering the materials brought at site which shall be certified for it's accuracy by Assistant Engineer/Junior Engineer and shall be checked by Assistant Engineer and final clearance should be given by Executive Engineer) with all lead and lifts and leads, transporting to site, spreading, shall not be carried out unless and until Executive Engineer gives clearance grading to required slope and compacting to meet requirement of Tables 300.2 as per Technical Specification Clause 303.1 with all lead, lifts, loading and unloading charges, cost and conveyance of all materials, labour, equipments etc., complete as per the directions of the Engineer incharge of the work.
Previous measurement Present measurement Total Upto dateQty Amount Qty Rate Amount Qty Amount
27131.25 271313.00 750.00 10.00 7500.00 27881.25 278813.00
3999.37 39994.00 10.00 3999.37 39994.00
1672.80 66912.00 2712.00 40.00 108480.00 4384.80 175392.00
Unit Item of work
Tend
er
S
l No
. Tender Qty
Tender Rate
Cum ### 156.00
9
Cum 5587.50 445.00
10
Cum 2204.91 1500.00
CD WORKS
26
Granular sub-base / base/ surface course with local material (table 400.13) using gravel mix soil (mix designed) by mix in place method normal construction of granula sub base by providing local material Spreading in uniform layers with mortar grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller 408 with all leads and lifts, loading and unloading charges cost and conveyance of all materials, labour, equipments etc., as per the directions of the Engineer in charge of the works (proposed portion 70:30 Gravel and Sand).
Providing, laying, Spreading and compacting stone aggregates of specific sizes to Water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel roller 80-100 KN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill up the intersectices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification Clause 405 by all means with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Tender rate paid = Rs. 1500.00 Part rate paid = Rs. 1000.00
Earth work in excavation for structure as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal dressing of sides and bottom and backfilling in trenches with excavated suitable material. In all soil with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Previous measurement Present measurement Total Upto dateQty Amount Qty Rate Amount Qty Amount
11428.00 1782768.00 5334.50 156.00 832182.00 16762.50 2614950.00
5586.95 445.00 2486193.00 5586.95 2486193.00
1436.72 1436720.00 768.31 1000.00 768310.00 2205.03 2205030.00
Unit Item of work
Tend
er
S
l No
. Tender Qty
Tender Rate
Cum
27
Cum
28
Cum
29
Cum
31
Providing and laying concrete cradle bedding with (Type-A) M 15 Grade Cement concrete as per clause 1105 with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete
Providing and laying concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 and 1203 PCC grade M 10, Nominal mix 1:3:6 with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Providing and constructing Stone masonry work in cement mortar in foundation complete as per drawing and technical specification Clauses 702, 704, 1202 and 1203 Coursed rubble masonry (2nd) loading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Providing and constructing Stone masonry in cement mortar 1:4 for parapet complete as per drawing and technical specification Clauses 700 and 1208.4 Coursed rubble masonry (1st sort) with all lead and lifts, loading and unloading charges, cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Previous measurement Present measurement Total Upto dateQty Amount Qty Rate Amount Qty Amount
282.38 150.00 42357.00 282.38 42357.00
1.08 4000.00 4320.00 1.08 4320.00
22.81 3700.00 84397.00 22.81 84397.00
157.10 2300.00 361330.00 157.10 361330.00
Unit Item of work
Tend
er
S
l No
. Tender Qty
Tender Rate
Cum
34
Rmtr 112.50 4590.00
38
Rmtr
Total Amount =
1 Royalty a) Granite Metal = 208.18 Cum
b) Gravel = 3352.17 Cum
c) Sand = 89.28 Cum
Contractor Section Officer
Providing and laying Reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106-1000 mm dia. with all lead and lifts, loading and unloading charges, cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Tender rate paid = Rs. 4590-00 Part rate paid = Rs. 4000-00
Providing and laying PCC M-20 architectural coping on the top of wing wall return wall etc., complete as per ndrawing and technical specification Clauses 615,710,1204 3.11 with all lead and lift, loading and unloading charges, including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Previous measurement Present measurement Total Upto dateQty Amount Qty Rate Amount Qty Amount
19.42 3500.00 67970.00 19.42 67970.00
112.50 450000.00 112.50 450000.00
95.90 225.00 21578.00 95.90 21578.00
4554990.00 4985776.00 ###
Assistant Executive Engineer
Project sub division,
Shimoga.
ROYALTY STATEMENT
SpecificationMetal Sand Gravel
Constant Quantity Constant Quantity Constant Quantity27 CC M15 Grade 1.08 0.81 0.87 0.459 0.5028 PCC M10 1:3:6 22.81 0.92 20.99 0.410 9.35
29 157.10 1.05 164.96 0.45 70.70
31 19.42 1.10 21.36 0.45 8.74
9 G.S.B. 5586.95 0.00 0.40 2234.78 0.60 3352.17
208.18 89.28 3352.17
Section Officer. Assistant Executive EngineerProject Sub Division,
Shimoga
NAME OF WORK: METALLING AND ASPHALTING OF ROAD FROM KELADI TO T-09 ROAD IN SAGARA TLAUK, SHIMOGA DISTRICT. FROM 0.00 TO 7.450 KMTender Item
No.
Qty. in Cum
Rubble stone masonryStone masonry in CM 1:4
2nd RA BILL
Detailed Measurement Sheet No. -28
R.A BILL - SECOND AND PART BILL
" PRADHANA MANTRI GRAMA SADAK YOJANA" PHASE VII 2006-07
Date of Recording :
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9
2
As per Earth work calculation sheet 4470.20 Cum 45.00 201159.00
4
Qty. vide MB No. 24-29, Pre measurement Page No. 4 to 6 750.00 Cum 10.00 7500.00
6
As per Earth work calculation sheet 4384.80
Less Previously paid Vide MB 24-29, Page No.16 to 19 1672.802712.00 2712.00 Cum 40.00 108480.00
NAME OF WORK : METALLING AND ASPHALTING OF ROAD FROM KELADI TO T-09 ROAD IN SAGARA TALUK, SHIMOGA DISTRICT. FROM 0.00 TO 7.450 KM (PACKAGE NO. 24-29)
Name of Contractor : Mr. Sharath J ShetEstimate Cost : Rs. 205.69 LakhsTechnical approval No. : TCH/06231/DIV/PH - VII B' /07-08Head of Account : 3054-06-337-Rural roads - 01
Agreement No. : Starting Period : 12-12-2008Stipulated Period : 11-09-2009
Ten I.No. B in M Tender
rate
Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance as directed, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections with all leads and lifts, loading and unloading charges, cost and conveyance of all materials, labour, equipments and all other incidental charges for the successful completion of work etc., complete as per directions of the Engineer in charge of the work.
Scarifying existing granular surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m and leads upto 1000 m as per Technical Specification Clause 301.4 with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Construction of embankment with approved material deposited at site from road way cutting and excavation from drain and foundation other structures graded and compacted to meet requirement of tables 300.1 & 300.2 as per technical specification Clause 301.5 with all lead and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
2nd RA BILL
Detailed Measurement Sheet No. -29
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9
8
As per calculation sheet 16762.50
Less Previously paid Vide MB 24-29, Page No.19-23 11428.005334.50 5334.50 Cum 156.00 832182.00
9
0.00 to 0.20 Km
6 30.00 7.50 157.50 Cum
1 20.00 7.50 17.50
0.20 to 0.40 Km 6 30.00 7.50 157.50
1 20.00 7.50 17.50
0.40 to 0.60 Km 6 30.00 7.00 138.60
1 20.00 7.00 14.93
0.60 to 0.80 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
C/F 653.53
Sl. No. B in M Tender
rate
Construction of Subgrade and earthen shoulders with approved material obtained from borrow pits shall not be less than CBR 8%. If the existing surface CBR is more than 8%, the CBR of the material brought from the borrow pit should not be less than the existing surface (CBR of such soil should be checked by contractor or by his site engineer considering the materials brought at site which shall be certified for it's accuracy by Assistant Engineer/Junior Engineer and shall be checked by Assistant Engineer and final clearance should be given by Executive Engineer) with all lead and lifts and leads, transporting to site, spreading, shall not be carried out unless and until Executive Engineer gives clearance grading to required slope and compacting to meet requirement of Tables 300.2 as per Technical Specification Clause 303.1 with all lead, lifts, loading and unloading charges, cost and conveyance of all materials, labour, equipments etc., complete as per the directions of the Engineer incharge of the work.
Granular sub-base/base/surface course with local material, (table 400.13) using gravel mix soil (mix designed) by mix in place method normal construction of granular sub base by providing local material Spreading in uniform leyers with mortar grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 408 with all lead and lifts, loading & unloading charges, cost and conveyance of all materials, labour, equipments etc., complete as per the directions of the Engineer in charge of the work (proposed proportion 70:30 Gravel and sand).
(0.10+0.15+0.10) 3
(0.10+0.15+0.10) 3
(0.10+0.15+0.10) 3
(0.10+0.15+0.10) 3
(0.10+0.13+0.10) 3
(0.10+0.12+0.10) 3
2nd RA BILL
Detailed Measurement Sheet No. - 30
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9B/f 653.53
0.80 to 1.00 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
1.00 to 1.20 Km 6 30.00 7.00 134.40
1 20.00 7.00 14.93
1.20 to 1.40 Km 6 30.00 7.00 134.40
1 20.00 7.00 14.93
1.40 to 1.60 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
1.60 to 1.80 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
1.80 to 2.00 Km 6 30.00 7.00 134.40
1 20.00 7.00 14.93
2.00 to 2.20 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
2.20 to 2.40 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
2.40 to 2.60 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
2.60 to 2.80 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
2.80 to 3.00 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
3.00 to 3.20 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
C/F 2451.53
Sl. No. B in M Tender
rate
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
2nd RA BILL
Detailed Measurement Sheet No. - 31
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9B/f 2451.53
3.20 to 3.40 Km
6 30.00 7.00 134.40
1 20.00 7.00 14.93
3.40 to 3.60 Km6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
3.60 to 3.80 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
3.80 to 4.00 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
4.00 to 4.20 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
4.20 to 4.40 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
4.40 to 4.60 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
4.60 to 4.66 Km 2 30.00 7.50 0.10 45.00
4.675 to 4.800 Km 4 30.00 7.50 0.10 90.001 5.00 7.50 0.10 3.75
5.00 to 5.20 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
5.20 to 5.40 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
5.40 to 5.60 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
5.60 to 5.80 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
5.80 to 6.00 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
6.00 to 6.20 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
C/F 4539.62
Sl. No. B in M Tender
rate
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
2nd RA BILL
Detailed Measurement Sheet No. - 32
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9B/f 4539.62
6.20 to 6.40 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
6.40 to 6.60 Km 6 30.00 7.00 134.40
1 20.00 7.00 14.93
6.60 to 6.80 Km 6 30.00 7.00 134.40
1 20.00 7.00 14.93
6.80 to 7.00 Km 6 30.00 7.00 134.40
1 20.00 7.00 14.93
7.00 to 7.20 Km 6 30.00 7.00 134.40
1 20.00 7.00 14.93
7.20 to 7.40 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
7.40 to 7.450 Km 6 30.00 7.50 0.10 135.001 20.00 7.50 0.10 15.00
5586.95 Cum 445.00 2486193.00
10
Vide Pre-measurement vide this MB Package-24-29, Page No.26,27 768.31 Cum 1000.00 768310.00
Sl. No. B in M Tender
rate
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
(0.10+0.12+0.10) 3
Providing, laying, Spreading and compacting stone aggregates of specific sizes to Water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel roller 80-100 KN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill up the intersectices of coarse aggregate, watering and compacting to the required density Grading II as per Technical Specification Clause 405 by all means with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
(Full Rate= 1500.00 Part Rate= 1000.00)
2nd RA BILL
Detailed Measurement Sheet No. - 33
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9CD WORKS
26
Pre measurement vide this MB 24-29, Page No.24, 25 282.38 Cum 150.00 42357.00
27
Pre measurement vide this MB 24-29, Page No. 25 1.08 Cum 4000.00 4320.00
28
Pre measurement vide this MB 24-29, Page No. 25, 26 22.81 Cum 3700.00 84397.00
29
1) Ch. 0.050 KMHead wall L/S 1 6.30 1.40 0.45 3.97 Cum " 1 6.30 1.20 0.40 3.02 " 1 6.30 1.00 0.22 1.39 " 1 6.30 0.80 0.22 1.11 " 1 6.30 0.60 0.40 1.51
Sl. No. B in M Tender
rate
Earth work in excavation for structure as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal dressing of sides and bottom and backfilling in trenches with excavated suitable material. In all soil with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Providing and laying concrete cradle bedding with (Type-A) M 15 Grade Cement concrete as per clause 1105 with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete
Providing and laying concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 and 1203 PCC grade M 10, Nominal mix 1:3:6 with all leads and lifts, loading and unloading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
Providing and constructing Stone masonry work in cement mortar in foundation complete as per drawing and technical specification Clauses 702, 704, 1202 and 1203 Coursed rubble masonry (2nd) loading charges including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
2nd RA BILL
2nd RA BILL
Detailed Measurement Sheet No. - 34
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9
R/S 1 6.00 1.40 0.45 3.78 " 1 6.00 1.20 0.45 3.24 " 1 6.00 1.00 0.45 2.70 " 2 1.80 0.80 0.45 1.30 " 2 1.80 0.60 0.45 0.97 " 2 2.60 1.40 0.45 3.28 " 2 2.60 1.20 0.45 2.81 " 2 2.60 1.00 0.45 2.34 " 1 6.00 0.60 0.45 1.62
33.03
Deduct pipe portion 2 3.14 1.2x1.2 0.85 (-) 1.92
4 31.11
2) Ch. 0.450 KMHead wall L/S 1 6.00 1.40 0.45 3.78 " 1 6.00 1.20 0.23 1.66 " 1 6.00 1.00 0.23 1.38 " 1 6.00 0.80 0.25 1.20 " 1 6.00 0.60 0.25 0.90
R/S 1 6.00 1.40 0.45 3.78 " 1 6.00 1.20 0.45 3.24 " 1 6.00 1.00 0.20 1.20 " 1 6.00 0.80 0.20 0.96 " 1 6.00 0.60 0.45 1.62
19.72
Deduct pipe portion 2 3.14 1.2x1.2 0.85 (-) 1.92
4 17.80
3) Ch. 1.150 KMHead wall L/S 1 6.00 1.40 0.45 3.78 " 1 6.00 1.20 0.23 1.66 " 1 6.00 1.00 0.23 1.38 " 1 6.00 0.80 0.23 1.10 " 1 6.00 0.60 0.23 0.83
R/S 1 5.90 1.40 0.40 3.30 " 1 5.90 1.20 0.23 1.63 " 1 5.90 1.00 0.23 1.36 " 1 5.90 0.80 0.45 2.12 " 1 5.90 0.60 0.40 1.42
18.58
Deduct pipe portion 2 3.14 1.2x1.2 0.85 (-) 1.92
Sl. No. B in M Tender
rate
2nd RA BILL
4 16.66
2nd RA BILL
Detailed Measurement Sheet No. - 35
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9
4) Ch. 1.330 KMHead wall L/S 1 5.95 1.40 0.40 3.33 " 1 5.95 1.20 0.40 2.86 " 1 5.95 1.00 0.20 1.19 " 1 5.95 0.80 0.20 0.95 " 1 5.95 0.60 0.20 0.71
R/S 1 6.00 1.40 0.40 3.36 " 1 6.00 1.20 0.40 2.88 " 1 6.00 1.00 0.20 1.20 " 1 6.00 0.80 0.40 1.92 " 1 6.00 0.60 0.20 0.72
19.12
Deduct pipe portion 2 3.14 1.2x1.2 0.85 (-) 1.92
4 17.20
5) Ch. 1.870 KMHead wall L/S 1 6.00 1.40 0.40 3.36 " 1 6.00 1.20 0.40 2.88 " 1 6.00 1.00 0.20 1.20 " 1 6.00 0.80 0.40 1.92 " 1 6.00 0.60 0.40 1.44
R/S 1 5.95 1.40 0.60 5.00 " 1 5.95 1.20 0.45 3.21 " 1 5.95 1.00 0.20 1.19 " 1 5.95 0.80 0.20 0.95 " 1 5.95 0.60 0.45 1.61
22.76Deduct pipe portion 2 3.14 1.2x1.2 0.85 (-) 1.92
4 20.846) Ch. 2.595 KM
Head wall L/S 1 6.00 1.20 0.45 3.24 " 1 6.00 1.00 0.45 2.70 " 1 6.00 0.80 0.45 2.16 " 1 6.00 0.75 0.20 0.90 " 1 6.00 0.60 0.25 0.90
R/S 1 6.00 1.20 0.45 3.24 " 1 6.00 1.00 0.45 2.70 " 1 6.00 0.80 0.20 0.96 " 1 6.00 0.75 0.23 1.04 " 1 6.00 0.60 0.23 0.83
18.66Deduct pipe portion 2 3.14 1.2x1.2 0.85 (-) 1.92
4 16.74
Sl. No. B in M Tender
rate
2nd RA BILL
Detailed Measurement Sheet No. - 36
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9
7) Ch. 5.630 KMHead wall L/S 1 6.00 1.20 0.45 3.24 " 1 6.00 1.00 0.45 2.70 " 1 6.00 0.80 0.45 2.16 " 1 6.00 0.60 0.45 1.62
R/S 2 1.80 1.20 0.40 1.73 " 2 1.80 1.00 0.40 1.44 " 2 1.80 0.60 0.60 1.30 " 1 1.10 1.00 0.40 0.44 " 1 1.10 0.80 0.40 0.35 " 1 1.10 0.60 0.60 0.40 " 2 1.80 1.40 0.60 3.02 " 2 1.80 1.20 0.40 1.73 " 2 1.80 1.00 0.40 1.44 " 2 1.80 0.60 0.23 0.50 " 1 6.00 0.60 0.23 0.83
22.89Deduct pipe portion 2 3.14 1.2x1.2 0.85 (-) 1.92
4 20.978) Ch. 6.300 KM
Head wall L/S 1 5.90 1.20 0.40 2.83 " 1 5.90 1.00 0.20 1.18 " 1 5.90 0.80 0.20 0.94 " 1 5.90 0.75 0.40 1.77 " 1 5.90 0.60 0.40 1.42
R/S 1 5.90 1.20 0.45 3.19 " 1 5.90 1.00 0.45 2.66 " 1 5.90 0.80 0.45 2.12 " 1 5.90 0.60 0.45 1.59
17.70
Deduct pipe portion 2 3.14 1.2x1.2 0.85 (-) 1.92
4 15.78TOTAL QTY. 157.10 Cum 2300.00 361331.00
31
Sl. No. B in M Tender
rate
Providing and constructing Stone masonry in cement mortar 1:4 for parapet complete as per drawing and technical specification Clauses 700 and 1208.4 Coursed rubble masonry (1st sort) with all lead and lifts, loading and unloading charges, cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
2nd RA BILL
Detailed Measurement Sheet No. - 37
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9
1) Ch. 0.050 KM Parapet L/S 1 6.30 0.45 0.45 1.28 R/S 1 6.00 0.45 0.45 1.22
2) Ch. 0.450 KM Parapet 2 6.00 0.45 0.45 2.43
3) Ch. 1.150 KM Parapet L/S 1 6.00 0.45 0.45 1.22 R/S 1 5.90 0.45 0.45 1.19
4) Ch. 1.330 KM Parapet L/S 1 5.95 0.45 0.45 1.20 R/S 1 6.00 0.45 0.45 1.22
5) Ch. 1.870 KM Parapet L/S 1 6.00 0.45 0.45 1.22 R/S 1 5.95 0.45 0.45 1.20
6) Ch. 2.595 KM Parapet 2 6.00 0.45 0.45 2.43
7) Ch. 5.630 KM Parapet 2 6.00 0.45 0.45 2.43
8) Ch. 6.300 KM Parapet 2 5.90 0.45 0.45 2.39
19.42 Cum 3500.00 67969.00
38
1) Ch. 0.050 KM Parapet L/S 1 6.30 6.30 R/S 1 6.00 6.00
2) Ch. 0.450 KM Parapet 2 6.00 12.00
3) Ch. 1.150 KM Parapet L/S 1 6.00 6.00
Sl. No. B in M Tender
rate
Providing and laying PCC M-20 architectural coping on the top of wing wall return wall etc., complete as per ndrawing and technical specification Clauses 615,710,1204 3.11 with all lead and lift, loading and unloading charges, including cost of labour, hire charges of machinery and equipments and all other incidental charges necessary for the successful completion of works including transportation etc., complete as per detailed standard specification and as directed by the Engineer in charge of the works etc., complete.
2nd RA BILL
R/S 1 5.90 5.90
Detailed Measurement Sheet No. - 38
Item of work Nos. L in M D in M Qty Unit Amount
1 2 3 4 5 6 7 8 9
4) Ch. 1.330 KM Parapet L/S 1 5.95 5.95 R/S 1 6.00 6.005) Ch. 1.870 KM Parapet L/S 1 6.00 6.00 R/S 1 5.95 5.956) Ch. 2.595 KM Parapet 2 6.00 12.00
7) Ch. 5.630 KM Parapet 2 6.00 12.00
8) Ch. 6.300 KM Parapet 2 5.90 11.80
95.90 Rmtr 225.00 21578.00
TOTAL BILL AMOUNT 4985776.00
Section Officer. Assistant Executive EngineerProject sub division,
Shimoga.
Sl. No. B in M Tender
rate