175
1 Good quality reliable drinking water supply and sanitation are essential basic needs of every citizen. It has been the endeavour of successive Governments of Karnataka to satisfy this need for all its citizens. It is on on-going effort which aims at meeting the growing demand both in the urban and rural areas. The policy framework for rural drinking water provision is already in place. In view of the different institutional structure and different sets of issues involved in the delivery of the services of urban areas, it is necessary to have a separate policy statement for this sector. A detailed sector strategy paper to action plan will be issued later to carry forward the objectives outlined in this statement. Increasing urbanization has resulted in greater pressure on the existing urban water supply and sanitation systems leading to increasing demand on the one hand to augment the source and improve distribution and on the other to increase the coverage of underground drainage (UGD). At the same time, as stated in the State Water Policy brought out by the Department of the Water Resources, there is an urgent need to conserve the limited water resources of the State to ensure sufficient availability of water for various needs as well as for the future. The Government‘s efforts, therefore, have to focus on raising the levels of efficiency in the management of drinking water systems in urban areas so as to give satisfactory service to the citizens while at the same time discouraging over exploitation of resources and preventing wastage. Objective The Government of Karnataka in partnership with urban local bodies in the State, the Karnataka Urban Water Supply & Drainage Board (KUWS&DB) and the Bangalore Water Supply and Sewerage Board (BWSSB) will continue and strengthen its efforts to provide all residents of urban areas of the State, piped water supply and sanitation services at or near their dwellings. The efforts of the Government of Karnataka and its partner agencies will be to Ensure universal coverage of water and sanitation services that people want and are willing to pay for and To do so in a manner that preserves the sustainability of the precious water resources of the State, project and enhances the commercial and economical sustainability of the operations at the same time. Ensure a minimum level of service to all citizens. Karnataka Urban Drinking Water and Sanitation Policy, 2003

Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

1

Good quality reliable drinking water supply and sanitation are essential basic needs of

every citizen. It has been the endeavour of successive Governments of Karnataka to

satisfy this need for all its citizens. It is on on-going effort which aims at meeting the

growing demand both in the urban and rural areas. The policy framework for rural

drinking water provision is already in place. In view of the different institutional structure

and different sets of issues involved in the delivery of the services of urban areas, it is

necessary to have a separate policy statement for this sector. A detailed sector strategy

paper to action plan will be issued later to carry forward the objectives outlined in this

statement.

Increasing urbanization has resulted in greater pressure on the existing urban water

supply and sanitation systems leading to increasing demand on the one hand to

augment the source and improve distribution and on the other to increase the coverage

of underground drainage (UGD). At the same time, as stated in the State Water Policy

brought out by the Department of the Water Resources, there is an urgent need to

conserve the limited water resources of the State to ensure sufficient availability of water

for various needs as well as for the future. The Government‘s efforts, therefore, have to

focus on raising the levels of efficiency in the management of drinking water systems in

urban areas so as to give satisfactory service to the citizens while at the same time

discouraging over exploitation of resources and preventing wastage.

Objective

The Government of Karnataka in partnership with urban local bodies in the State, the

Karnataka Urban Water Supply & Drainage Board (KUWS&DB) and the Bangalore

Water Supply and Sewerage Board (BWSSB) will continue and strengthen its efforts to

provide all residents of urban areas of the State, piped water supply and sanitation

services at or near their dwellings. The efforts of the Government of Karnataka and its

partner agencies will be to

Ensure universal coverage of water and sanitation services that people want and are

willing to pay for and

To do so in a manner that preserves the sustainability of the precious water

resources of the State, project and enhances the commercial and economical

sustainability of the operations at the same time.

Ensure a minimum level of service to all citizens.

Karnataka Urban Drinking Water and Sanitation

Policy, 2003

Page 2: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

2

Institutional Arrangements

Government of Karnataka: The Government of Karnataka will continue to be responsible

for:

Policy Formulation

Ensuring provision of the bulk of the resources required for capacity creation

Regulation, monitoring and evaluation of the efficiency of operations, including

prescribing reporting requirements, procurement procedures, etc.

Setting minimal service standard

Encouraging the use of public private partnerships as well as private sector

participation to achieve the sector goals

Promotion of the economic and commercial viability of water supply systems and the

exploitation of economies of scale and scope by appropriate aggregation options

Institution of necessary incentives for urban local bodies and other service providers

to implement sector reforms

Ensuring co-ordination and collaboration among the various agencies both at the

policy and operational level through the establishment of appropriate committees

and agencies.

Urban Local Bodies (ULBs)

In accordance with the principle enshrined in Article 243 (W) of the Constitution of India

read with the Twelfth Schedule. ULBs will be responsible for water supply and sewerage

services from water catchments to waste water treatment. The Government of

Karnataka, however, will have the responsibility to monitor that ULBs provide quality

services in accordance with the standards prescribed at the State level. ULBswill have

the choice of providing the services directly through public bodies or through such

appropriate Private Sector Participation (PSP) arrangements. Given however, the

paramount need for financial and commercial viability of the operations, the State will

monitor strictly policies relating to minimal tariff operations autonomy of the municipal

water operations, etc.

KUWS&DB and BWSSB

The Karnataka Urban Water Supply and Drainage Board will continue to be responsible

for capacity creations and augmentation in all ULBs and O & M in selected ULBs for the

present. Over the medium term, the KUWS&DB will be restructured and its role

redefined. In the longer term the KUWS&DB could become a publicly owned

independent provider of technical assistance and management support to ULBs who do

not have adequate capacity. Similarly, the appropriate role of BWSSB will be defined in

the action for the Bangalore City and surrounding areas.

Page 3: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

3

Tariff

Given that piped water supply inexpensive, it is necessary both for natural resource

sustainability and commercial viability of operations to recover from the users of water,

the full cost of providing service. The longer-term objective is to establish an appropriate

cost recovery mechanism through adequate tariff to ensure that revenues cover

operations and maintenance costs, debt service plus a reasonable return on capital. In

the medium term, however, subsidies will continue to be needed and will be focused in

areas such as pockets and communities of extreme poverty and investments with large-

scale externalities like wastewater treatment.

Tariff will be structured in a manner such as to disincentives excessive consumption and

wastage of water, whilst ensuring at least a minimum ―life line‖ supply to the poor. In a

realistic time frame of about five years, efforts will be made and ULBs encouragedto

achieve 100 percent metering and volumetric pricing based on long run marginal costs.

Capital investments

Though considerable amount of capital expenditure has been undertaken for creation of

water supply capacity, this has not been the result entirely of a coherent plan. The

consequences have been

Mismatched capacities

No objection criterion based prioritization

Incremental and hence expensive capital decisions leading to duplication and

avoidable expenditures

To deal with all urban water supply investment issues appropriate state level

mechanisms will be established. A revised demand driven urban water action plan

based on the principles outlined in this statement will be prepared and the GoK will

adopt this after discussing it with all the relevant agencies. Future capital investments in

the sector will be in accordance with this plan. Investments will be guided by the

principle of optimal utilization of water and water system infrastructure and financial

resources and the financial as well as the social returns on investment.

Private Sector Participation (PSP)

To improve efficiency in service provision, continuously update technology and

ultimately bring in private investment into sector, the GoK will actively encourage private

sector participation. Given the current state of the sector, PSP will necessarily have to

Page 4: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

4

be gradual. Preparatory work for PSP in the sector like fostering a culture of

commercialization, encouraging outsourcing, building local capacity and most

importantly identifying and expediting the necessary legislative institutional and regularly

changes that are necessary of PSP will be undertaken in the meanwhile. Given the very

different sizes of urban areas in the State, the GoK will allow a range of different PSP

methods of service provision and service providers.

Page 5: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

5

Background

Lakes are important features of the earth‘s landscape. They are not only a significant

source of precious fresh water, but often provide valuable habitats to plants and

animals, moderate the hydrological extreme events(drought and floods),influence

microclimate, enhance the aesthetic beauty of the landscape and extend many

recreational opportunities.

The lakes provide a wide diversity of values and uses ranging from ecological goods

and services to direct production values. These can be categorized as direct use values

with consumptive and non-consumptive use such as drinking, irrigation, fishing, eco-

tourism etc. Indirect use values such as water recharge / in flouting microclimate with

beneficiaries located away from the lake, and also potential future use and non-use

social benefit of availability of a healthy water resource for future generation.

The different problems encountered in the lake, include excessive influx of sediments

from the lake catchment, discharge of untreated or partially treated sewage and

industrial waste waters/ solid waste disposal, entry of diffused source nutrients from

agriculture and forestry, improper management of storm water/ combined with over

adsorption, over-exploitation of lake for activities like recreation, fishing, encroachments,

land reclamation resulting in lake shrinkage, shoreline erosion and impact on lake

hydrology, deterioration in water quality and impact on bio diversity, climate change etc.

As part of the urban context, the role and use of the lakes assumes greater significance

as they serve as passive recreational open space, urban bio diversity spots, ground

water recharge. The operation and maintenance of urban lakes is a serious challenge

faced by the owners of the lake. Though the location of the lake determines the

ownership/jurisdiction, the components associated and their stakeholders for the urban

lake management are many. The roles and responsibilities of the stakeholders of the

lake operation & maintenance are very diverse and unclear. The actions that need to be

taken up for the sustainable operation is also not clear as it crosses the defined

boundaries of legalities / engineering / urban bio diversity / water management / land

use management etc.

Urban Lake Management

Page 6: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

6

The Government of Karnataka and the various urban local bodies have rightly

recognized the significance of lake restoration and have invested substantially in the

past decade. The experiences are varied addressing the ground realities, nature of

community participation and use of resources.

Sustainability in lake operation and maintenance require many actions to be carried out

in a concerned manner, some of them to be considered in the planning and

development of the lake itself. The emphasis of the workshop will be on the formulation

of practices to strengthen the ecological structure of the urban lakes. There is now a

growing recognition that engineering practices need to imbibe the ecological processes

for arriving at the long term solutions. For instance, the notion of permanent water

quantity residing in the lake, deep excavation/ de-silting, provision of revetments based

on irrigation standards may need adaptation. The need for accommodating the birding

habitats, wetlands and passive treatment of water need special attention. Many of these

aspects require a comprehensive urban water shed and catchment intervention,

involving land use planning and urban design.

The other aspect that is crucial for the operations and maintenance involve devising a

suitable business model that can support the recurring expenses and up keep of the

water body. While dedicating the water bodies for ecological resources, many urban

lakes offer potential for development of passive recreation as well as tourist attractions.

A uniform approach to the lake management needs a re-look. A logical framework

based on the ecological and the financial principles can be developed.

The flora of the Urban Water bodies

The flora (Macro flora) of the Urban Water bodies, which is in no way different form that

of rural lakes, is vital from several points of view. It, not only offers food, shelter and

secure nesting sites for the aquatic fauna of the lakes but also serves as a source of

materials for different human needs and uses. It is also an important bio-indicator of the

status of the water body.

Sadly, the importance of these hydrophytes is not properly realized or under estimated.

These plants are grossly neglected at times of maintenance or restoration of lakes.

The flora of the urban water bodies does not basically differ from that of rural lakes.

However in recent years because of drastic changes in the urban areas mainly due to

several ―developmental‖ reasons:

Page 7: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

7

(i) Drying up of lakes due to neglect

(ii) Pollution – letting municipal sewage, domestic and industrial effluents into the

water bodies

(iii) Conversion of catchment area into residential extensions or industrial sites

(iv) Growth of invasive exotic plant species, much of the floristic composition of these

bodies has undergone a vast change. Many of the plants that were so common

about 50 years ago have entirely disappeared from urban lakes.

The flora of these lakes, which is an integral part of the same, is composed of plants

better known as hydrophytes or aquatic plants. Of course the term Flora, in the larger

sense, denotes both microscopic phyto-planktons and algae and macroscopic ferns and

flowering plants.

The higher plants i.e. ferns and flowering plants show several modifications in their

external and internal morphology, in their physiology and in their reproductive behavior.

These changes are excellent adaptation for an aquatic mode of life.

Whatever their modifications are, these plants constitute an important component of

water bodies as they provide food for the aquatic fauna such as insects, fishes, reptiles,

birds and mammals. At the same time they act as secure places for shelter, nesting etc.,

they also help in the healthy maintenance of the lakes. They are valuable sources of

oxygen, various nutrients for different microbes, fishes and so on.

Thus, the floristic components render invaluable service to the ecology of water bodies.

They are also indicators of the ecological health of lakes – e.g. Water lily water hyacinth.

They constitute a vital link in the intricate balance of life in a lake. Not only the

hydrophytes, but the other plants that grow around a lake or in the foreshore are an

excellent niche for non-aquatic creatures such as butterflies.

The aquatic plants are also important from human point of view. The leaves, tubers,

petioles, fruits and seeds of many of them are edible and to a certain extent are used by

local people. For example, the leaves of Ipomea aquatica (Ballesoppu), Alternanthera

paronychioides (Neeruhonnagonesoppu) are used as vegetables. Some of them are

highly prizes as green manure which provides valuable nitrogen to crops such as rice,

Azolla sp. which harbours the nitrogen fixing blue, green alga Anabaena azollae, is one

such plant. Duckweeds (Lemna sp.) are eagerly consumed by ducks. Several

hydrophytes are of medicinal importance and are used by herbal doctors as well as

Page 8: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

8

ayurvedic practitioners to alleviate certain ailments (Marsilea, Hygrophila schulli). In this

context it is suggested that some of them can be explored and studied scientifically to

extract drugs from them (for instance, a nutraceutical drug has been extracted from

Ipomeaaquatica).

Many of the aquatic plants have been traditionally used by rural folk to make floor mats,

thatching materials, baskets, doragu (an indigenous rain – cover), etc. The pith of

Aeschynomene, was widely used a shock – absorber in pith huts (Sola pith).

Lastly, the aesthetic value of the lake flora cannot be ignored and if manicured properly

and used with discrimination, lakes can be developed as open-air class rooms as well

as places of recreation.

But unfortunately, the importance of water bodies is not properly realizes. They are

neglected and are used as dumping area for urban garbage or as area for building

construction or as stadia/ playgrounds or encroached by farmers for cultivating

commercial crops.

Fauna of Urban Lakes

Lakes and ponds are one of the landscape features that significantly contribute to

increase the quality of life in urban centers and mitigate urban climate. By 2030, more

than 60% of global population and the resources it consumes will be concentrated in

metropolitan setting (United Nations, 1996). Urban lakes are very often manmade

ecosystems and generally have a surface area of a few hectares. A typical lake has

distinct zones of biological communities linked o the physical structure of lake. Fauna of

urban lakes generally vary and depend on the status of lake itself. Fauna of lake are

classified as bacteria and fungi, plants, benthos, plankton, macro-zooplankton, fish,

amphibians, snakes and turtles.

Phycology of Urban Lakes

Phycology is the study of algae, while the study of freshwater lakes is known as

Limnology. Algae play a significant role in the eutrophication of urban lakes. In some

areas they multiply enormously after rain showers and tend to decrease the quality of

lake water. However there are many which have high economic value. Five major

groups are found as plankton in fresh waters. They include Chlorophyceae

(Chlorococcales), Bacillariophyceae, Desmidaceae, Euglenaceae and Cyanophyceae

and many of these serve as indicators of pollution. Microcystisaeruginosa, blue green

algae forms a bloom and emits a bad odour to the lake water. Euglenaceae are

Page 9: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

9

indicators of organic pollution while the abundance of Desmids indicates pristine habitat.

Diatoms are excellent indicators of anthropogenic disturbances mainly of animal origin.

Algae not only a component of food to aquatic organisms but can be an excellent

source as ecological indicators and can be used in monitoring of water quality and

conservation of urban freshwater lakes.

Lake as an ecosystem: Ecosystem based approach to lake conservation

Inland wetlands and lakes are biologically most productive eco systems on earth. A

stream draining a catchment gathers all the nutrients and pollutants, transports it and re

deposit in lakes and associated wetlands. While the lake bed acts as a recipient or sink

for this bounty, the wetlands act as a microbial biotechnology industry to transform the

inputs into simpler, stable forms to flow back in to the ecosystem. This forms the base

for the food chain and also the consequent abundance in Biodiversity.

Apart from soil and moisture conservation and water storage, the greatest ecosystem

function of lake is its capacity to trap and transform the organic and chemical inputs

through its wetlands and release cleaner water downstream. This has high ecosystem

value as it synergizes benefits like water purification, storage, and support biodiversity.

This is achieved through a delicate, symbiotic relationship between the microbes in the

aerobic and anaerobic zones, the micro and macro flora and fauna that inhibit the

wetlands and active participation of myriad life forms. This is a delicate balance,

vulnerable to drastic changes .This diversity is an indicator of the ecosystem health and

that of the society.

The tradition of lake construction over centuries gave increasing water security to the

subsistence communities. Emergence of industrial communities which could access

water from far through electrification and bore well technology saw rapid urbanization

.With the changing context the lakes have become the repositories of wastes from the

urban sprawl and last islands biodiversity in distress. Experience has shown detrimental

effect of draining the lakes in urban areas with recurring floods and ground water

scarcity, and has moved the judiciary to uphold their right to exist for the wellbeing of the

society through far reaching judgments .The restoration of the lakes remains a civil

engineering affair to maximize storage and develop the lake for recreational purposes.

The general ignorance and aversion to wetlands makes their existence unwelcome and

they disappear. The result is a huge water storage tank with few ecological niches to

nurture biodiversity. If the understanding of the dynamics of wetland ecosystem is

applied in lake restoration plans, they will be able to render better ecosystem services

Page 10: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

10

like increased biodiversity, water quality and livelihoods as outcomes. The issues of

environment and climate change make such an outcome an imperative rather than a

choice.

Role of Wetlands in Rapidly Urbanizing Landscapes

Bangalore is experiencing unprecedented urbanization and sprawl in recent times due

to concentrated developmental activities with impetus on industrialization for the

economic development of the region. This concentrated growth has resulted in the

increase in population and consequent pressure on infrastructure, natural resources and

ultimately giving rise to a plethora of serious challenges such as climate change,

enhanced greenhouse gases emissions, lack of appropriate infrastructure, traffic

congestion, and lack of basic amenities (electricity, water, and sanitation) in many

localities, etc. This study shows that there has been a growth of 632% in urban areas of

Greater Bangalore across 38 years (1973 to 2010). Urban heat island phenomenon is

evident from large number of localities with higher local temperatures. The study

unravels the pattern of growth in Greater Bangalore and its implication on local climate

(an increase of ~2 to 2.5 ºC during the last decade) and also on the natural resources

(76% decline in vegetation cover and 79% decline in water bodies), necessitating

appropriate strategies for the sustainable management. The study reveals that frequent

flooding (since 2000, even during normal rainfall) in Bangalore is a consequence of the

increase in impervious area with the high density urban development in the catchment

and loss of wetlands and vegetation. This is coupled with lack of drainage upgrade

works with the changes in enhanced run-offs, the encroachment and filling in the

floodplain on the waterways, obstruction by the sewer pipes and manholes and relevant

structures, deposits of building materials and solid wastes with subsequent blockage of

the system and also flow restrictions from under capacity road crossings (bridge and

culverts). The lack of planning and enforcement has resulted in significant narrowing of

the waterways and filling in of the floodplain by illegal developments.

Floods in an urbanized landscape refer to the partial or complete inundation from the

rapid accumulation or run-off resulting in the damage to property and loss of biotic

elements (including humans). Urban flooding is a consequence of increased

impermeable catchments resulting in higher catchment yield in a shorter duration and

flood peaks sometimes reach up to three times. Thus, flooding occurs quickly due to

faster flow times (in a matter of minutes). Causal factors include combinations of loss of

pervious area in urbanizing landscapes, inadequate drainage systems, blockade due to

indiscriminate disposal of solid waste and building debris, encroachment of storm water

Page 11: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

11

drains, housing in floodplains and natural drainage and loss of natural flood-storages

sites. Flood mitigation in urban landscape entails integrated ecological approaches

combining the watershed land-use planning with the regional development planning.

This includes engineering measures and flood preparedness with the understanding of

ecological and hydrological functions of the landscape.

Integrating urban water bodies within Urban Development

Cities in the Deccan plateau are gifted with a unique landscape comprising of terrains,

landforms with valleys and ridges, rivers, water bodies, etc. The landscapes over the

years have been moulded in various ways to support life, including the making of water

bodies and formation of tanks (kere) within the settlements for drinking, irrigation, etc.

With increased urbanization and urban activities, significant disturbances to the surface

water systems have occurred mainly through land reclamation, land use changes,

structural alterations and pollution from different sources.

The linkage between land and water resource management in the urban area needs

prompt attention. Currently, urban planning and water management practices are both

undergoing deep changes through innovative approaches, investments, operations and

institutional working. A common spatial policy for land and surface water systems has

not been developed, today references to planning come from the zoning to control

construction and land use in and around the surface water bodies. Practices in different

parts of the world showcase the opportunities for design of urban space around the

surface water systems. The water resources management in form of the dual piping

systems, water storage reservoirs, recirculation of the grey water, etc requires

contextual adaptation to the surface water systems as well as the land use

configurations/development.

Case Study: Lakes of Mysore

Introduction

In the undulating terrain of south Karnataka the practice of tank construction has been a

tradition of antiquity. The eight district of south have 60% of tanks in Karnataka. The

Mysore region under patronage of benevolent rulers witnessed the development of well-

engineered tanks. Water for domestic use, irrigation, for cattle, animals and birds, for

fodder was provided perennially through the tanks. Water in open wells influenced by

the tanks lead to development of permanent settlements around the tanks.

Mysore city located in the southern plateau of Karnataka is at an elevation of 2460 ft.

above sea level. This is a rain shadow region beyond the Western Ghats and the

Introduction to Water Management: Issues and ConcernsKarnataka Urban Drinking Water and Sanitation Policy, 2003

Page 12: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

12

vegetation varies from grassland to dry scrub with dry deciduous vegetation in the

valleys. Annual precipitation is 790 mm, which falls in 60 rainy days. This was harvested

through tanks securing water for rest of the year.

The river Cauvery flows 16 kms to the north of Mysore and river Kabini flows 22 kms to

the south. The Watershed of which 30% drains to the north and 70 drains to the south.

Valleys in this plateau had seen the development of chain of tanks. The present spread

of Mysore had 5 major and 25 small and minor tanks. About 10 of the small and minor

tanks would be around the foot of Chamundi hill.

Lakes of Mysore – once up on a time.

Water flowing from the north and western sides of the Chamundi hill has farmed a

natural valley called the Chamundi valley. The tank series consist of Karanji, Doddakere

and Dalvoy tanks in this valley. The village of Mysore depended on the Doddakere for

its water requirement. Earlier it was called ‗Cholakere‘, later ‗Devarajakere‘ and later

developed as Doddakere. The town of Mysore evolved around the tank and on the

western side of the Chamundi valley. Dalvoy Lake located further downstream provided

water for irrigation.

Lingambudi Lake located in the south of Mysore was constructed by the

KrishnarajaWodeyar III on behest of his wife Lingarajammanni of Krishna Vilas in the

year 1828 to provide irrigation to the dry lands.

In the 19th century, DiwanPoornaiah proposed to provide water to the growing Mysore

town from Kaveri or Lakkshmanathirtha rivers. But what materialized was his plan of

constructing Kukkarahalli tank. Water was gathered from the higher level tanks through

a 23 km long ‗Poornaiha Canal‘ and led to Kukkarahalli tank during 1864. This was

constructed by Sri ChamarajaWodeyar to provide water to the Mysore heading towards

industrialization. A cast iron pipeline laid from this tank to the sandal oil factory located

farther south exists even today. Around the same time Karanji tank was constructed in

the Chamundi valley which reduced the inflow to Doddakere. As the valley had

numerous springs the lake was named ‗KaranjiKere‘ meaning springs / fountains.

Twentieth century saw development of electrification, of allowing sewage to flow into the

lake resulted in increased nutrient and biodiversity. It also rendered the seasonal lakes

perennial. But increased sewage flows have rendered the lakes eutrophic stifling this

very biodiversity. People in the neighborhood suffered from the emanating stench and

mosquitoes.

Page 13: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

13

Since 1980, the growing environmental awareness has globally manifested in Mysore as

a concerted effort to save these lakes.

Lakes of Mysore – Now

Looking like shining jewels from the sky, the lakes of Mysore have wielded a strong

influence on the green cover, salubrious weather and water security. These have been

repositories of biodiversity within the urban boundaries. The four remaining large lakes

of Mysore are KukkarahalliKere, Karanjikere, Dalvoykere and Lingambudhikere.

a) KukkarahalliKere:

A beautiful lake located in the heart of Mysore is the first of a series of lakes. Water

passes through Kukkarahallikere, Malalvadikere, RayanaKere and Yenneholekere

before joining Kabini River.

Spread over 58 Ha, this lake has a merge catchment of 414 Ha only. What used to keep

this lake alive and vibrant was the 23 km long Poornaiah canal. Starting from

Bommanahalli lake overflow the canal gathered surplus water from several small tanks

and meander like a snake along the contours for 23 kms to reach Kukkarahalli. The

canal width varied from 30 to 60 ft.

In 1916 the University of Mysore was born on the banks of Kukkarahallikere. Since then

the lake has inspired many Writers, Poets and Artists apart from Naturalists. Kuvempu,

R.K. Narayan, C.D. Narasimhaiah, T.S Satyan, are few who fell for the charm of

Kukkarahallikere. Being in the heart of Mysore, the lake is a veritable treasure trove of

biodiversity and has played an important role in evoking environmental consciousness,

love toward nature and ecosystem knowledge among the students and citizen of

Mysore. It is popular among walkers, joggers and health conscious people. It attracts

artists and photographers like a magnet. For students of biology it is like an open text

book. Years of effort has resulted in the establishment of a wooded area in the

foreshore. It is a popular lake to watch sunrise and sunset.

The lake has been formed by the construction of a kilometer long bund in the East-west

direction in Kukkarahalli valley. On the west is the University of Mysore and on the

eastern side is the Crawford hall, the administrative office of the UOM. To the north

formation of Hunsur road has truncated the lake to present boundary. In the year 1960

the lake came under the custodianship of the University of Mysore. In the 1970

construction of a road across the lake was undertaken and later abandoned resulting in

Page 14: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

14

a beautiful wooded island, 1980‘s saw the destruction of the canal while forming

Vijayanagara layout. Valiant effort by activists resulted in protesting the last 6 km stretch

of the feeder channel. But only last 2 kms is active. The lake was overgrown with reeds

and floating vegetation which were cleared with great effort. The water level remained

low during the 80s prompting the UOM to construct the academic staff training college

on its banks. During the 90s, the water level rose inundating the building. This repeated

frequently on subsequent years. Steady flow of sewage resulted in algal blooms and

fish death due to oxygen depletion.

Emanating foul odour from the dead alga attracted the wrath of public. In the year 2000

due to concerted action from citizens, the UOM along with M.C.C. prepared a plan to

divert the sewage and to improve the precinct. This resulted in effective fencing, gates,

wide walking path, gardens, widened bund, boating jetty, toilets and drinking water

facilities. Fishery was resumed.

In 2012, sewage continues to flow into the lake loading it severely with nutrients. A

project for beatification is a foot but the project for sewage diversion is still languishing

attracting the ire of Lokadalat.

b) Karanjikere:

Located at a vantage point in the city it catches the beautiful reflection of Chamundi hill

in it. This is the first big tank in the Chamundi valley series. Water flows through

Tavanekatte, Karanjikere, Doddakere and Dalvoykere to Kabini River. The lake has an

area of 35 Ha and a catchment of 745 Ha. The valley had natural springs which inspired

the name Karanjikere or spring tank. This can the observed in the upstream tank even

now.

The Mysore Zoo is located in the command area of this lake the lake was handed over

to the Zoo in 1976 by the PWD for development and maintenance. The lake located in

the north-east of Mysore is basically a percolation tank. During 80s the lake used to dry

up. The Zoo fenced and secured the lake. De-silted the lake and created islands. In

2000 determined effort from the Zoo and district administration could clear the

obstruction and encroachments on the feeder channel, de-silt the lake, provide basic

amenities and recreational space. The garden, open aviary, boating facility, aeration

fountain and butterfly garden attract large number of visitors.

The uniqueness of this lake is that the islands in the lake attract endangered species of

birds to breed in them. Spot billed pelicans, Painted storks, Cormorants, Snake bird,

White ibis and night herons breed in significant numbers. Despite increasing number of

Page 15: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

15

visitors the lake has been able to retain its natural charm thanks to the alert and

responsive administration and nature levers of Mysore.

Increased flow and sewage has been hurting this lake with algal boom, profusion of

weeds and fish death though constructed wetlands, floating bio-deck, bio-culture and

aeration is managing the situation. The lake generates more than enough revenue to be

self-sufficient. The lake is managed with the advice of a technical committee and the

management follows scientific principles. The lake‘s fortune will depend on the effective

diversion of sewage which is still pending.

c) Lingambudikere

Located in the southwest of Mysore, Lingambudikere was an important irrigation tank.

The series starts with Hinkalkere, HinkalRayanakere, BogadiMariyappanakere and

passing through Lingambudi, Rayanakerehalla and Yenneholekere reaches Kabini

River.

This lake was constructed in 1828 by KrishnarajaWodeyar III to provide water for

irrigation and livestock. 1980 saw brisk growth of Mysore resulting in rapid siltation and

pollution of the lake in 1990 through public pressure the lake was handed over to forest

department for protecting and development. Since then a forest has emerged in its

precinct in 2010 the lake precinct was declared as a protected forest.

The lake has an area of 96 Ha and a catchment of about 2200 Ha. The precinct has

wide diversity of niches from wetland, grassland to woodland. It has emerged as an

important nature park. Presently it is being managed by the Forest Department and

Ligambudhi forest committee. Lack of sufficient water has been rendering the lakes dry.

This lake has the potential of being an excellent bird sanctuary.

d) Other lakes

Hebbalkere, Bommanahallikere, BogadhiMariappanakere and Hinkalkere ranging from

40 acres to 10 acres have been rejuvenated in a recent scheme. The

HinkalRayanakere, Basavanakatte, Parasayyanakere, Dhobighatkere, Devamurkere

and Kyatamaranahallikere are awaiting their revival from their death bed. There are

several other nameless small water bodies which are potential victims of urbanization.

Lakes that have disappeared

The growing city Mysore due to poor water management drained many of its lakes to

avoid mosquito breeding. Lakes that have disappeared but have retained the names are

Doddakere, Jeevannarayanakatte, Subrayanakere. Many have disappeared without

Page 16: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

16

names; they are Kyatamaranahallikere, Malalavadikere, Dhobhighatkere, Beetle leaf

garden lakes etc.

Lakes are relevant even today

Lakes were built by our ancestors as an insurance against drought. Lessons learnt over

centuries are forgotten in a few decades. Though the original purpose of the tank was

irrigation, in the changing urban context their roles have changed. Today they help in

regulating urban floods, facilitates ground water recharge, maintain microclimate. These

lakes are also very important and biological productive ecosystems. They harbour

diverse life forms, provide habitat, food and shelter and are indicators of health of our

own ecosystems. Keeping them in good shape and passing them on to the next

generation is more important than ever.

Page 17: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

17

1. INTRODUCTION

The large investments made to construct utilities intended to provide facilities for water

supply are becoming unproductive in the sense that the objective for which they have

been installed is not achieved mainly on account of poor maintenance. Often the

investments become unproductive, and a larger amount of money is required to replace

and rebuild the system components. Interruptions in service occur owing to the

breakdown of equipment as a result of poor maintenance. The utility control

organizations are not able to ensure that the maintenance staff follow valid practices to

achieve proper maintenance. The management of water supply systems in the water

authorities is receiving relatively lower priority. Lack of funds coupled with lack of

enthusiasm among the operation and maintenance staff to keep schemes in working

condition; lack of training, lack of motivation among the staff may be reasons for the

present status of water supply systems.

DEFINITION OF OPERATION AND MAINTENANCE

In an engineering sense, operation refers to hourly and daily operations of the

components of a system such as plant, machinery and equipment (valves etc.) which is

done by an operator or his assistant. This is a routine work. The term maintenance is

defined as the art of keeping the plant, equipment, structures and other related facilities

in optimum working order. Maintenance includes preventive maintenance or corrective

maintenance, mechanical adjustments, repairs and corrective action and planned

maintenance. Often repairs, replacements and corrections of defects (of material or

workmanship) are considered as actions excluded from preventive maintenance. In

some organizations the normal actions taken by operation staff are considered as

maintenance activities whereas a separate unit or cell does repairs and replacements.

Often both corrective and preventive maintenance are included in the job functions of

operators and limits to which operators are expected to do normal maintenance are set

forth for various equipment. Budgetary provisions of operation and maintenance

organizations also incorporate heads of expenditure under maintenance for cost of

spare parts and cost of labour or contract amount for repairs and replacements.

Operation and Maintenance of Water Supply System

Page 18: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

18

2. SOURCES OF WATER

NATURAL SOURCES

Rain, snow, hail and sleet are precipitated upon the surface of the earth as

meteorological water and may be considered as the original source of all the water

supplied. Water, as source of drinking water, occurs as surface water and ground water.

Three aspects should be considered in appraising water resources e.g., the quantity,

the quality, and the reliability of available water.

SURFACE WATER

Surface water accumulates mainly as a result of direct runoff from precipitation (rain or

snow). Precipitation that does not enter the ground through infiltration or is not returned

to the atmosphere by evaporation, flows over the ground surface and is classified as

direct runoff. Direct runoff is water that drains from saturated or impermeable surfaces,

into stream channels, and then into natural or artificial storage sites (or into the ocean in

coastal areas).

The amount of available surface water depends largely upon rainfall. When rainfall is

limited, the supply of surface water will vary considerably between wet and dry years.

Surface water supplies may be further divided into river, lake, and reservoir supplies.

Dams are constructed to create artificial storage. Canals or open channels can be

constructed to convey surface water to the project sites. The water is also conveyed

through pipes by gravity or pumping.

In general, the surface sources are characterized by soft water, turbidity, suspended

solids, some colour and microbial contamination.

GROUND WATER

Part of the precipitation that falls infiltrates the soil. This water replenishes the soil

moisture, or is used by growing plants and returned to the atmosphere by transpiration.

Water that drains downward (percolates) below the root zone finally reaches a level at

which all the openings or voids in the earth's materials are filled with water. This zone is

called the zone of saturation. The water in the zone of saturation is called the ground

water.

Page 19: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

19

Ground waters are, generally, characterized by higher concentrations of dissolved

solids, lower levels of colour, higher hardness (as compared with surface water),

dissolved gasses and freedom from microbial contamination.

A well that penetrates the water table can be used to extract water from the ground

basin. The extraction of ground water is mainly by:

1. Dug well with or without straining walls

2. Dug cum bore wells

3. Cavity bore

4. Radial collector wells

5. Infiltration galleries

6. Tubewells & bore wells.

Ground water that flows naturally from the ground is called a Spring.

SURFACE WATER MANAGEMENT AND MAJOR SOURCES OF POLLUTION: USE OF

SURACE RESERVOIRS

Methods of managing lakes and reservoirs used for domestic supplies vary widely

depending on local conditions. In addition to serving domestic water needs, a reservoir

may be used for flood control purposes, for hydroelectric power generation, for

regulating releases, for recreational purposes or for providing water for agricultural,

municipal and industrial uses. The amount and type of public use allowed on reservoirs

also varies according to individual situations.

The methods of treating water depend upon raw water quality and range from

disinfection only to complete treatment.

Page 20: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

20

3. BASIC DESIGN CRITERIA

Sl. No

Items Design period (Years)

Remarks

1. Storage by dams 50

The dam may be constructed in two stages. In the first stage, the height of dam may be kept just sufficient for requirements of the 30 years period. But foundation and base for both the phases.

2. Infiltration works 30

The infiltration works may be designed and constructed for intermediate requirements of 15 years and may be extended later to meet the ultimate requirements.

3. Pump sets

i) All prime movers, except

electric motors 30

ii) Electric motors and pumps 15

4 Water treatment units 15

5 Pipe connections to the several treatment units and other small appurtenances

30

6. Raw water and clear water conveying mains

30

The comparative merits to cover the full 30 year period v/s a main so cover the first 15 years supplemented by another, either for the entire length or part of it, for the next 15 years should be examined to decide on the most economical arrangement.

7.

Clear water reservoirs at the head works, balancing tanks and service reservoirs (overhead or ground level) in the distribution network

15

Additional units may be added after the 15-year period.

8. Distribution system 30

Feeder mains to area under developed, however, may be limited to the needs of the first 15 years, and replaced or additional mains added after that period to meet the ultimate requirements.

Page 21: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

21

Recommended per capita water supply levels for designing schemes

Sl.No. Classification of Towns / Cities Recommended maximum water supply levels (lpcd)

1 Towns provided with piped water supply but without sewerage system

70

2 Cities provided with piped water supply where sewerage system is existing / contemplated

135

3 Metropolitan and mega cities provided with piped water supply where sewerage system is existing / contemplated

150

4

Fire demand

For fixing capacity of service reservoirs. For towns with population exceeding 50,000, fire demand should be taken as (100p) Kilolitres/day, where p is population in thousands. One-third of fire demand is to be provided as a part of service storage.

Note:

1) In urban areas, where water is provided through public stand posts, 40 lpcd should

be considered.

2) Figures exclude ―Unaccounted for Water‖ which should be limited to 15%.

3) Figures include requirements of water for commercial, institutional and minor

industries. However, the bulk supply to such establishments should be assessed

separately with proper justification.

(Ref.: Manual of Water Supply and Treatment by CPHEEO – Third Edition – May, 1999).

4. QUALITY ASPECTS

Nutrients

Moderate or large quantities of nutrients such as phosphates, nitrates and organic

nitrogen compounds may act as a fertilizer in a reservoir to stimulate the growth of algae

which may cause algal bloom.

The problems related to algal blooms are:

i) Taste, odour and colour,

ii) Increased pH

iii) Shortened filter runs of treatment plants,

iv) Dissolved oxygen variation,

v) Organic loading.

Page 22: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

22

Thermal Stratification

Thermal stratification develops in lakes and reservoirs when the surface water begins to

warm. The warm surface waters expand and become lighter than the lower waters. The

water temperature difference causes variation in water densities, which create

resistance to mixing. This ultimately results in anaerobic conditions in lower zones.

Anaerobic Stratification

Anaerobic conditions make water unpalatable due to colour and odour which are difficult

to treat. Another major problem in anaerobic water occurs when iron and/or manganese

exist in bottom sediments in the reduced state and pass into solution. Due to the

presence of either iron or manganese in appreciable quantities within the domestic

supply the water looks reddish, brown or just plain dirty and may stain clothes during

washing and stain porcelain fixtures

Classification of water resources based on Suitability of USE (IS : 2291) 1982 : Indian Standards Institute

Pa

ram

ete

r

Un

its

Ma

x/M

in

Dri

nkin

g w

ate

r w

ith

ou

t

co

nve

nti

on

al tr

ea

tme

nt,

bu

t a

fte

r d

isin

fecti

on

Ou

tdo

or

bath

ing

org

an

ize

d

Dri

nkin

g w

ate

r w

ith

co

nve

nti

on

al tr

ea

tme

nt,

bu

t a

fte

r d

isin

fecti

on

Pro

pag

ati

on

of

wild

life

an

d f

ish

eri

es

Irri

gati

on

, in

du

str

ial

co

oli

ng

, etc

.

Dissolved oxygen Mg/1 Min 6.0 5.0 4.0 4.0 -

Biochemical oxygen demand

Mg/1 Min 2.0 3.0 3.0 - -

Total coliform bacteria MPN/100ml Max 50.0 500.0 5000.0 - -

Total dissolved solids Mg/1 Max 500.0 - 1500.0 - 2100.0

Chloride as chlorine Mg/1 Max 250.0 - 600.0 - 500.0

Color Hazen Max 10.0 300.0 300.0 - -

Sodium absorption ratio Mg/1 Max - - - - 26.0

Boron Mg/1 Max - - - - 2.0

Sulphates Mg/1 Max 400.0 - 400.0 - 1000.0

Nitrates Mg/1 Max 20.0 - 50.0 - -

Free ammonia as Nitrogen

Mg/1 Max - - - 12.0 -

Conductivity mS/cm Max - - - 1.0 2.3

pH - - 6.5-8.5 6.5-8.5 6.5-8.5 6.5-8.5

6.0-8.0

Arsenic Mg/1 Max 0.1 0.2 0.2 - -

Iron Mg/1 Max 0.3 - 50.0 - -

Fluorides Mg/1 Max 1.5 1.5 1.0 - -

Lead Mg/1 Max 0s.1 - 0.1 - -

Copper Mg/1 Max 1.5 - 1.5 - -

Zinc Mg/1 Max 15.0 - 15.0 - -

Page 23: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

23

Drinking water – Specification (IS : 10500 – 1991 with amendment No. 1 Jan, 1993) Standards for Physical and Chemical Parameters

Sl. No.

Parameter Requirement

(Desirable limit)

Undesirable effect outside the

desirable limit

Permissible limit in the absence of alternate source

1 Colour 5 Above 5, consumer acceptance decreases

25

2 Odor Unobjectionable - -

3 Taste Agreeable - -

4 Turbidity 5 Above 5, consumer acceptance decreases

10

5 pH 6.5 – 8.5

No relaxation, beyond this range the water will affect the mucous membrane

No relaxation

6 Total hardness 300

Encrustation in water supply structure and adverse effect on domestic use

600

7 Iron 0.3

Beyond this limit, taste/appearance is affected, has adverse effect of domestic uses

1.0

8 Chlorides 250

Beyond this limit, taste, corrosion and palatability are affected

1000

9 Residual chlorine 0.2 - -

10 Dissolved solids 500

Beyond this palatability

decreases and may cause gastro-

intestinal irritation

2000

11 Calcium 75

Encrustation in water supply structure and

adverse effect on domestic use

200

12 Copper 0.05

Astringent taste, discoloration and

corrosion of pipes, fittings and utensils

will be caused beyond this

1.5

Page 24: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

24

13 Magnesium 30

Encrustation to water supply

structures and has an adverse effect on

domestic use

100

14 Manganese 0.1

Beyond this limit, taste/appearance is

affected, has an adverse effect of

domestic use

0.3

15 Sulphate 200

Beyond this causes gastro-intestinal

irritation when Mg. or Na are present

400

16 Nitrate 45 Beyond this,

methamoglobinemia 100

17 Fluoride 1.0

Fluoride may be kept as low as possible. High

fluoride may cause fluorosis

1.5

18 Phenol compounds

0.001 Beyond this,

objectionable taste and odour

0.002

19 Mercury 0.001 Beyond this, the

water becomes toxic No relaxation

20 Cadmium 0.01 Beyond this the

water becomes toxic No relaxation

21 Selenium 0.01 Beyond this the

water becomes toxic No relaxation

22 Arsenic

0.05

Beyond this the

water becomes

toxic

No relaxation

23 Cyanide

0.05

Beyond this the

water becomes

toxic

No relaxation

24 Lead

0.05

Beyond this the

water becomes

toxic

No relaxation

25 Zinc 5

Beyond this,

stringent taste 15

26 Anionic detergents 0.2

Beyond this, light

froth in water 1.0

Page 25: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

25

Standards for Bacteriological Quality

Quality of water in distribution system

Ideally, all samples taken from the distribution system including consumer premises

should be free from coliform organisms. In practice, this is not always attainable.

1. Throughout the year, 95% of the samples should not contain any coliform organisms

in 100ml.

2. No sample should contain E. Coli in 100ml.

3. No sample should contain more than 10 coliform organisms per 100ml.

4. Coliform organisms should not be detectable in 100ml of any 2 consecutive

samples.

27

Chromium 0.05

May be

carcinogenic above

this limit

No relaxation

28 Polynuclear

aromatic

hydrocarbons

-

May be

carcinogenic -

29

Mineral oil 0.01

Beyond this,

undesirable taste

and odour takes

place after

chlorination

0.03

30 Pesticides Absent Toxic 0.001

31 Radioactive

material

a) Alpha emitters - - 0.1

b) Beta emitters - - 1

32

Alkalinity 200

Beyond this, taste

becomes

unpleasant

600

33 Aluminium 0.03

Cumulative effect is

reported to cause(?) 0.2

34 Boron 1 - 5

Page 26: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

26

If any coliform organisms are found, the minimum action required is immediate re-

sampling. The repeated finding of 1-10 coliform organisms in 100ml or the appearance

of increased numbers in individual samples suggests that undesirable material is

gaining access to the water and measure should be taken to discover and remove them.

Constituents of ground water and their effect and usability

Constituent Source

Normal concentration

in ground water

Effect on usability of water

Hardness Calcium and Magnesium ions

Less than 1000 ppm, may be higher in arid regions.

Low causes hardness corrosion. High hardness consumes excess soap and detergents.

pH - 6.0 to 8.5 pH less than 6.0 causes corrosion.

Colour Decaying vegetation lignite industrial wastes

- Aesthetically objectionable

Tubidity Silt and clays from soil erosions

Little or no turbidity

Aesthetically objectionable

Iron

Igneous rocks, sandstone rocks, ferrous or ferric compounds, well casing pipe, pump parts, etc.

Up to 10 ppm when pH is less than 8. Normally reduced to 0.5 ppm after aeration.

Turbidity, stains on plumbing fixtures, laundry and cooking utensils.

Manganese Metamorphic and sedimentary rocks

10 ppm Tastes, deposits, stain growth in reservoirs.

Calcium

Felspars, dolomite, clay, minerals, amphiboles

600 ppm

Scales forming when combining with bicarbonatescarbonatessulphates and silica.

Magnesium

Oilvine, amphibole, dolomite, magnesite

220 ppm Same as calcium, in addition has a laxative effect on new users.

Sodium or potassium

FelsparMirabilite 100 ppm More than 50 ppm cause forming and scale formation.

Carbonates Limestone, dolomite

10 ppm Scales

Bicarbonates Limestone, dolomite

100 ppm Scales

Sulphates Gypsum 1000 pm Bitter taste above 500 mg/l

Chlorides Sedimentary rock saline intrusion

100 ppm More than 100 mg/l imparts salty taste.

Page 27: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

27

Fluorides Apatite, fluorite, mica

10 ppm

More than 1.5 mg/l causes mottled enamel – more than 6ppm causes disfiguration of teeth.

Nitrates Plant debris, animal excreta, fertilizers

10 ppm

Physiological distress if more than 100 mg/l. More than 45 mg/l in shallow wells causes infant diseases.

Silica Felspar, ferro magnesium, opal

100 ppm Scale forming

Total dissolved solids

Mineral constituents water

1000 Depends on constituents

Hydrogen sulphide

Bacterial reduction of sulphides

1 ppm

‗Rotten egg‘ odour, forms iron sulphides which clog on the screen openings. Causes corrosion.

5. TRANSMISSION MAIN

The overall objective of a transmission system is to deliver raw water from the source to

the treatment plants and transmit treated water from treatment plants to the storage

reservoirs for onward supply into distribution networks. Transmission of raw water can

be either by canals or by pipes whereas, transmission of treated water is by pipes only.

Transmission through pipes can be either by gravity flow or by pumping.

The objective of O&M of transmission system is to achieve optimum utilization of the

installed capacity of the transmission system with minimum transmission losses and at

minimum cost. To attain this objective the agency has to evolve operation procedures to

ensure that the system can operate satisfactorily, function efficiently and continuously,

and last as long as possible at lowest cost.

Routine and emergency operating procedures should be in writing and clear to all

operators with the authority to act in emergencies. Further specific operational

procedures are required for inspecting, monitoring, testing, repairing and disinfecting the

system as well as for locating the buried pipes and valves. System records and maps

should be updated and have sufficient details of the system facilities.

NORMAL CONDITIONS

Routine Operations

Normally the operations involve transmission of required water within the available head

or within the pumping head. Operations of valves at reservoirs from which transmission

channels/mains start and operation of pumps (in case of pumping mains) from which the

Page 28: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

28

transmission mains start are the routine operations. Operation of chlorinators where

installed are also included in the routine operations.Record of flow, water levels and

pressures

(a) Gravity Channels and pipes

A record is kept at the transmitting and receiving reservoirs about the valve operations,

water levels and flows. Flow meters are installed at start and end points of transmission

channels/pipes for monitoring the flows. Water levels in the reservoirs from which the

channels/pipes transmit water and water levels in the receiving reservoirs are measured

either by visible gauges or by automatic instruments.

(b) Pumping transmission mains

Water levels in the sumps from which the water is being pumped are measured. Critical

points are selected in the transmission system for monitoring of pressures by installation

of pressure recorders and gauges. In the pumping systems, whenever water pressures

in the pumping station drops below the designed system pressure, the operators are

alerted to search for possible leaks in the pumping system. Similarly at the receiving

end, if the required water levels are not building up at the storage reservoir, it indicates

that the required quantity is either not pumped or there may be leakages enroute. At

times whenever the maximum levels in the receiving reservoirs are reached the pumps

will have to be stopped or the outlet valves of the reservoir have to be opened.

(c) Continuity

Operators are required to check that the transmission of water takes place continuously

and as per the requirement. Normally, the flow meter readings, water levels in reservoir

and pressures in transmission mains are recorded and transmitted to the control room.

The operators have to ensure the accuracy of the measuring instruments for flows,

pressures and levels so as to perform the operations properly. Analysis of the records

will enable the agency to evaluate how well the transmission system is working.

TRANSMISSION THROUGH CANALS OR OPEN CHANNELS

Open channels and Canals are exposed watercourses for transmission of water from

one specific point to another. Whereas ‗Open Channel‘ is a general name for such a

watercourse, a ‗Canal‘ normally forms a part of canal network taken off from a river, a

dam or a reservoir. Following discussion relates to a canal. The criteria for design,

operation, and maintenance for open channels are identical to those of a canal.

Page 29: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

29

The canals are meant primarily for irrigation purposes. The canal water is, however,

liberally made available for drinking water supply schemes. While designing new canal

projects the requirement for drinking purposes is pre-determined and necessary

provision made in the design of the canal projects.

Under special circumstances, however, a specific canal may be constructed exclusively

for a drinking water supply project. There are, however, a large number of small water

channels taken off from the main canal system and are meant exclusively for the

drinking water supply schemes.

MAPS

Survey maps may be procured or prepared for the entire existing and proposed

canal network, which could be the probable source of raw water for drinking water

supply projects. These maps shall show the contours, spot levels and important land

features for the whole area where the water supply schemes are to be implemented or

augmented.

Alignment of all main canals, branches, distributaries, smaller major and minor

channels shall be marked on the maps. The old maps shall be updated from time to time

particularly when an important project is to be undertaken.

6. TREATMENT METHODS

Aim

To improve the raw water quality to the drinking water standards and stop water-borne

transmission of epidemics.

Methods of treatment

Depends on the nature of source and its water quality.

Sub-surface source

Generally, chlorination will be sufficient except where iron is present.

Surface source

Aeration (if required), pre-chlorination (optional), sedimentation – either plain or with

coagulation a flocculation, filtration and post chlorination.

Page 30: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

30

Aeration

Aim

i) To remove objectionable tastes and odours.

ii) For expulsion of carbon dioxide, hydrogen sulphide.

iii) To precipitate iron and manganese present in ferrous and manganeocous state.

iv) For increasing the dissolved oxygen content of water.

Types

i) Spray Type

Nozzle dia 10 – 40 mm

Spacing 0.5 – 1.0 m

Head required 2 – 7 m

Rating of aerator 300 – 600 lpm per nozzle

Floor area of aerator 360 to 1080 m2 per mld

ii) Multiple tray or water fall

Dia. of filter media 50-150mm in various trays

Height of tower 2 m

No. of trays 4 – 9

Spacing of trays 0.30 – 0.75 m

Space required 180 to 540 m2 per mld

iii) Cascade Type

Head required 1 to 3 m

Space required 180 to 540 m2 per mld

iv) Mechanical aerators Not in general use because of high operational cost.

Pre-clorination

Aim

i) to prevent algal growth in raw water.

ii) for destruction of some taste / odour producing compounds.

iii) for oxidation of iron, manganese and hydrogen sulphide.

iv) to aid coagulation.

Dosage

1 to 5 ppm depending on the degree of pollution so as to leave 0.2 to 0.5 ppm

free residual chlorine in the final delivered water.

Page 31: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

31

Table 1

The approximate values of lethal doses of Chlorine for various organisms.

Name of organism Lethal dose, mg/l

1. Diatoms

Achnantes 0.25

Asterionella 0.5 to 1.6

Cyclotella 1.0

Melosira 2.0

Synedra 1.0

Tabellaria 0.5 to 1.0

2. Chlorophyceae (Green algae)

Coelastrue 1.0

Dictyosphaerium 0.5 to 1.0

Protococcus 1.0

Spirogyra 0.7 to 1.5

Tetrastrum 1.0

Volvox 0.3 to 1.0

3. Cyanophyceae (Blue-green algae)

Anabena 0.5 to 1.0

Aphanizomenon 0.5 to 1.0

Clathrocystis 0.5 to 1.0

Coelosphaerium 0.5 to 1.0

Oscillotoria 1.1

4. Protozoa

Ceratium 0.3 to 1.0

Dinobryon 0.3 to 1.0

Entamoebahystolytica 3 to 100

Synura 0.3 to 1.0

Uroglenopsis 0.3 to 1.0

5. Crustaceans

Cyclops 1 to 3

Daphnia 1 to 3

6. Fungi

Achlya 0.6

Crenothrix 0.5

Didymothelix 0.25

7. Miscellaneous organisms 15 to 50

Chironomus (Bloodworm) 3.0

Chironomus (Midges) 1.0

Nais 1.0

These doses must be adjusted according to alkalinity and temperature of water.

Page 32: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

32

Plain sedimentation

Aim

To separate suspended impurities from water by gravitation.

Detention period

One to several days for sedimentation without subsequent filtration:

3 to 4 hours for sedimentation in conjunction with filters (much longer setting time for

basins preceding slow sand filters than for rapid sand filters).

Loading rate

30 – 40 m3/day/m2

Chemical dosing

Aim

i) for coagulation, flocculation.

ii) Disinfection and softening.

iii) Algal and corrosion control.

iv) For fluoridation.

Types

i) Dry feed

ii) Solution feed

Strength of solution

To be 5% for manual feed and 10% for mechanical feed.

Alum is the most common coagulant used. Lime is also added when pH and alkalinity

are low.

Dosage for alum : 20 – 100 mg/l (1-5 grain/gallon)

Dosage for lime : About one-third that of alum

Density of alum : 980 kg/m3

Density of lime : 670 kg/m

Flash mixing

Aim

To disperse the coagulant evenly in the water.

Generally used when flow exceeds 300 m3/hour.

Detention period

Page 33: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

33

20-100 mg/l (1-5 grain/gallon)

Head loss

0.20 to 0.60m of water.

Ratio of tank dia to height

1.1 to 3.0

Speed of propeller shaft

100 rpm

Power required

24 to 72 MW/mld.

Coagulation and flocculation

Aim

The addition of a coagulant like alum promotes the formation of micro flocs which are

the nuclei for the absorption of turbidity and colour causing particles. During flocculation,

the micro floc particles formed during rapid mixing are brought together to form larger

rapidly setteleableflocs by controlled agitation of water.

Detention period

15-30 minutes in flocculation zone.

2-3 hours in setting or clarifier zone.

Dosage

To be decided by jar test.

Flocculator

1) Ave. velocity of flow 0.3 m/min

2) Paddle area 10-25% of the area swept

3) Max. peripheral velocity 0.6 m/sec.

4) Speed 2 rpm

5) Allowable head loss 0.15m

6) Power required 80-120 MW/mld.

Clarifier

i Ave. velocity of flow 0.5 m/sec

ii Max.peripheral velocity 0.5 – 1.0 cm/sec.

iii Tank dimension

Page 34: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

34

a) For rectangular tanks

Length to width ratio 2 to 4

Depth 2.5 to 4.0 m (and additional 0.15 to 0.30

m if sludge storage is to be provided).

b) For circular tanks

Dia Not more than 60m

Depth 2.5 to 4.0m and a space equivalent to

25% of volume for setting and sludge

storage.

iv Surface loading for gritty particles

of sp. gravity 2.65

12-160 m3/day/m (depending on sizes of

the particles 2.0 to 0.5mm)

For amorphous slow setting solids

for flocculent material

32-80 m3/day/m2

A surface overflow rate of 36

m3/day/m2 is equivalent to a setting

velocity of 1.sm/hr and amounts to

a detention period of 2 hours in

basin 3m deep.

v Weir overflow rate Not to exceed 600 m3/day/m and

preferably to held below 300m3/day/m.

vi Sludge removal Min. size to be used

For non-mechanized units 200 mm diadesludging pipe.

For mechanized units 100 mm to 150 mm diadesluddging pipe

vii Bottom slope

For manual scraping 1 in 10

For mechanical scraping 1 in 12

viii Allowable head loss 0.50m

ix Power required 0.15-0.20 kw/mld.

Note: mid rating implies for functioning of plant for 24 hrs.

Filtration

Aim

i) To separate suspended and colloidal impurities in water.

ii) To produce sparkling and aesthetically attractive water free from disease-

producing organisms.

Page 35: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

35

Types

Filters

Note :

1. Slow sand, rapid gravity filters and pressure filters alone are dealt with here.

2. A schematic representation of water treatment system is given in systems 1 and 2

Slow Sand Filters

Influent turbidity Should not be more than 30 J.T.U.

Pretreatment Nil.

Except plain sedimentation which is required when there is

no raw water storage in source.

Length of filter run (not less than) 6-8 weeks with loss of head not more than

1.3m.

Filtration rate 100-150 lph/m2

Allowable head loss 0.6 to 1.3 m

Depth of sand 75-80 cm thick E.S.O. – 0.3mm

U.C. – 2.5 mm

Depth of gravel 20-30 cms in 4 layers graded from 2 to 45mm

Depth of water over

sand

1.0 to 1.5 m

Under drain system Baked clay or concrete pipes 30-40 cms long at 2m.

spacing laid with open joints. The max. spacing under

drains being 3m, velocity of flow in drain pipes 25 cm/sec.

Granular Media

Water Filters Diatomaceous

Earth Filters

Rapid Sand Filters or

Mechanical Filters

Slow Sand Filters

Pressure Filters Gravity Filters

Declining Rate Constant Rate

Page 36: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

36

Rapid Sand Filters

Influent turbidity After pretreatment, should not exceed 20 J.T.U.

Pretreatment Required (chemical dosing, flocculation and clarification)

Length of filter run 24 hours with loss of head not 2 m.

Filtration rate 80-160 lpm/m2 (240 lpm/m2 can be achieved with improved

pretreatment and careful grading).

Head loss allowed 1.8 to 2.0 m

Depth and sand 60-75 cm thick

E.S. = 0.45 – 0.70 mm

U.C. = 1.30 – 1.75 (graded with finest at top)

Depth of gravel 30-60 cm thick graded into 4 or more sizes varying from 25

to 85mm at bottom and 2 to 5mm at top.

Depth of water over

sand

1.0 – 2.0 m

Under drain system Central manifold with laterals with perforations on their

bottom or having umbrella type strainers on top. Other

types are wheelers bottom or a porous plate floor

supported on concrete pillars.

Minimum depth of under

drains

20cm

Dia. Of perforations 5 to 12 mm (straggered at a slight angle from the vertical

axis of the pipe)

Spacing of perforations

along laterals

8 cm for a perforation of 5mm.

20cm for a perforation of 12mm.

Ratio of total area of

perforations to total

cross-sectional area of

laterals

0.50 for 12mm size

0.25 for 5mm size

Ratio of length of lateral

to its dia

60

Spacing to laterals 30 cm

Cross sectional area of

manifold

1.5 – 2.0 times the total area of laterals.

Wash water gutter Horizontal travel of dirty water over the surface of filter shall

not be more than 0.5 to 1.0 m before reaching the gutter.

Bottom of gutter should clear the top of expanded sand by

Page 37: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

37

50mm or more. Upper edge of gutter should be placed far

above the surface of the undisturbed sand surface as the

wash water rises in 1 minute.

Back wash Pressure should be such that the sand expands to about

130 to 150% of its undisturbed volume or 5m head of water

as measured on underdrains.

Normally, the rate at which wash water is applied where no

over-agitation is provided, is 600 lpm2 of filter surface

equivalent to a rise of 60 cm per minute in the filter box for

a period of 10 minutes. The capacity of wash water storage

tank should be sufficient to supply wash water to 2 filter

units at a time, where the units are 4 or more to give a

normal wash to filters for about 10 minutes at the maximum

rate without requiring refilling of the tank.

Velocity in filtered water outlet :

1.0 – 1.8 m/sec.

Velocity in filtered water outlet :

2.4 – 3.6 m/sec.

Pressure Filters Same principle as gravity type rapid sand filters but water

is passed through the filters under pressure.

Tank axis may be vertical or horizontal.

Disadvantages i) Pretreatment is not possible without secondary pumping.

ii) Complicates effective feeding, mixing and flocculation.

iii) Adequate contact time for chemicals not possible.

iv) Observance of effectiveness of back wash not possible.

v) Difficult to inspect, clean and replace.

Advantages i) Secondary pumping is avoided for treated water.

ii) Filter backwash is less complicated.

iii) Suitable for small industries and swimming pools.

Page 38: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

38

Post chlorination

Aim Disinfection of potable water by the use of gaseous

Chlorine or Chlorine compounds to destroy bacteria

through the germicidal effects of Chlorine may be done at

head works/treatment works and supplemented by

additional chlorination in loose pockets of distribution

system.

Dosage When pre-chlorination is adopted, relatively small doses

will be required, generally 1 to 2 mg/l.

Contact period 30 minutes (minimum)

Residual Chlorine 0.2 – 0.8 ppm throughout the distribution system.

pH value 6-7 7-8 8-9 9-10 10-11

Residual or free

available Chlorine in

ppm

0.2 0.2 0.4 0.8 0.8

Quality of chemical

required in kg/day

Dosage in mg/l x quantity of water to be treated in mld.

Specific gravity of

Chlorine

2.49

Density of Chlorine 3.214 g/litre

Appropriate chlorine doses for

Purpose of addition Dose mg/l

1. Colour removal 5 to 100

2. Iron Bacterial control 2 to 10

3. Iron Precipitation 0.63 times iron content

4. Manganese precipitation 1.3 times manganese content

5. Hydrogen sulphide odour removal 2.1 times HS content

6. Ammonia removal 10 times the ammonia content

Bactericidal and cysticidal concentrations of free residual chlorine

pH value Free residual chlorine mg/l

Bactericidal 0o to 25oC Cysticidal 22o to 25oC

6.0 0.2 2.0

7.0 0.2 2.5

8.0 0.2 5.0

9.0 0.6 20

Page 39: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

39

Table for TCL requirement

Sr.

No. Chlorine Mg/l

Capacity of Water Treatment Plant (thousand litres/day)

1.0 1.50 1.75 2.0 2.5 3.0 4.5

1 2 0.30 0.45 0.55 0.60 0.75 0.90 1.35

2 3 0.40 0.60 0.70 0.80 1.10 1.22 1.80

3 4 0.55 0.85 0.95 1.10 1.45 1.65 2.45

4 5 0.70 1.65 1.25 1.40 1.75 2.10 3.15

Note : 30% chlorine in TCL is assumed

7. STORAGE RESERVOIRS

The main function of Reservoirs and Service Reservoir (SR) is to cater for daily

demands and especially peak demands of water. Operators/managers must be

concerned with the amount of water in the storage reservoir and the corresponding

water levels at particular times of the day. Procedures for operating the Service

Reservoir will depend upon the design of its storage capacity and on the water demand.

NORMAL PROCEDURES FOR OPERATION OF SERVICE RESERVOIR (S.R.)

Service Reservoirs have to be operated as per the design requirements. Normally the

service reservoirs are constructed to supply water during periods of high water demand

and hence the SRs are filled in low water demand period. At times pumps may be used

only for filling the SR before the next supply timing or can be used also during supply

hours to maintain the levels in the SR.

In some systems reservoirs are allowed to float at the end of distribution system when

pumps are used to pump directly into the distribution system and excess water flows

into the SR. In such systems multiple pumps are used to cater to varying demand and

pressures in the system.

Small changes in the distribution system such as pipeline extensions or the addition of

few more connections will not require additional storage requirement. Major system

changes such as addition of larger size of main pipelines and increase in large number

of connections may require additional storage.

Page 40: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

40

OPERATION OF SRS DURING ABNORMAL CONDITIONS

Abnormal operating conditions arise:

• Whenever demand for water goes up suddenly due to fire demand, or due to

excessive demand on one command area/zone of a system.

• Due to failure or breakdown of water supply of another zone of the distribution

system.

• Breakdown or out of service pumps or pipelines or power breakdowns or out of

service SRs.

The operator/manager must have a thorough knowledge of the distribution system

emanating from the SRs. Closure or adjustment of valves at strategic points in the

distribution system can focus or divert the flow of water towards the affected areas.

Emergency plans must be developed in advance to cope with such situations.

STORAGE LEVELS

Most of the distribution systems establish a pattern of levels for assuring the required

supplies at the required pressures. A water usage curve over a 24 hour period should

be prepared for each SR. It can be seen from the usage curve that the pattern varies

not only during the different times of the day but also during different days of the week

especially on week-ends, holidays and festivals. Demand pattern also changes during

different times of the year depending on the weather conditions such as summer, winter

etc. From the usage curve the operator can better anticipate and be ready for the

expected high consumption periods. The maximum water levels to be maintained in the

SR at each morning should be known to ensure that the system demands are met for

the day.

In case of intermittent supply, timings for supply of water in the areas are fixed in

advance. In large command areas, the water can be supplied to sub-zones during

particular fixed hours by operation of the necessary valves. The operator should work

out a programme for compliance.

STORAGE CAPACITY

Capacity of storage reservoir at different levels can be calculated and charts or tables

can be prepared and kept at the SR site. Proper functioning of water level indicators is

required to read the water level in the SR and assess its capacity. Usually water levels

are read at the same time each day and the readings recorded. Checks of water levels

at other times of the day will enable to determine if any unusual consumption conditions

Page 41: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

41

have occurred. If any significant increase in consumption is anticipated the operations

should ensure a corresponding increase in supply into the SR. Automatic valves are

used to prevent overflows from SR and maintain a constant level in the SR as long as

the pressure in the distribution system is adequate. Often the pumps feeding into a SR

are switched off or switched on as per the water levels in the SR. In some SRs advance

warning alarms are provided to signal when water levels in SR are either too low or too

high. The operator shall ensure that the automatic operations work as and when

needed. Sometimes time clocks are often used to control the water coming into the

reservoir. At some places the overflow is connected to the distribution system; in such

cases some mechanism must be in place to indicate that the reservoir has started

overflowing.

Routine valve operations are normally done at the SRs. Problems in operation of valves

in SRs can also be caused by valve seat getting jammed, and hence cannot be opened,

or non-seating of valves, and hence cannot be closed properly. Sometimes two valves

are fixed in series on the outlet and the downstream valve only is usually operated.

Whenever the valve under operation is jammed the upstream valve is closed and the

jammed valve is repaired. Such an arrangement enables repair of valves without

emptying the SR. In some SRs a by-pass line is provided direct from the inlet line to the

outlet line for drawing water without feeding the SR. Identification of the valves as to

their intended purpose such as inlet, outlet, scour, bye-pass etc. and their direction of

opening are to be prominently marked. The operator/manager shall ensure that all

valves in a SR are in good working condition and are operated as per the schedule for

such operations.

STORAGE LEVEL CONTROL

A simple system used to read and control the levels in SRs is a gauge/water level

indicator. Whenever the SR reaches the maximum water level, the operator informs the

pump house to stop pumping. In place of the traditional telephones, mobile phones or

dedicated wireless units can also be used. Electrodes, ultrasonic signals or solid state

electronic sensors are also used to sense the rise and fall in water levels and send

signals to the pumps to be stopped or started through cables or wireless or radio

frequencies.

It is also desirable to have an indication of levels of SR in the pump house. Automation

of level controls at SR s is to be attempted with caution since most of the authorities

require only a small amount of instrumentation and control. It is desirable that only

Page 42: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

42

simple level control instruments are chosen keeping in view availability of skilled

personnel. However, it is desirable that trained and qualified operators only are

permitted to repair the instruments.

SAMPLING FOR WATER QUALITY

Water from all SRs should be regularly sampled especially once, before and after

monsoon to determine the quality of water that enters and leaves the SR. Sampling data

can help in setting up periodic cleaning of SR. Indicators that help to decide when the

tank is due for cleaning for its turbidity, excessive colour, taste and odour.

Water quality problems may be of microbiological type which could be caused by loss of

residual chlorine due to bacterial contamination. Chemical water quality problems may

also occur due to leaching from reservoir lining and coating for RCC and masonry tanks

and due to corrosion of steel tanks. Common cause of physical water quality problems

includes collection of sediment, rust and chemical precipitates. Water quality in a SR

may also deteriorate due to excessively long periods of stagnant conditions. Sometimes

poor design, and improperly applied/and or cured coatings and linings may also cause

water quality degradation. Proper investigation is required to find the reasons for water

quality degradation determine the source of the problem and address the same.

Wherever seasonal demands fall and the residual chlorine levels get depleted, it may be

necessary to add additional chlorination facilities.

8. OPERATION AND MAINTENANCE

The efficiency and effectiveness of a water supply system depends on the operating

personnel's knowledge of the variables that affect the continuity, reliability, and quantity

of water supplied to consumers. The operational staff should be able to carry out

changes in the hydraulic status of the system as required depending on those variables

promptly and effectively. Routine operations shall be specified which are activities for

adjusting the valves and operation of pumps to match the prevailing conditions (flows,

pressures, levels and operation of pumps). Valve and pump operations will have to be

controlled as per a schedule. The schedule shall contain procedures for operating the

distribution system. It should contain procedures to obtain, process, and analyze the

variables related to water flows, pressures and levels as well as the consequences of

manipulating control devices, such as operation of valves and or pumps so that the

hydraulic status of the system can match the demand for water. When operators change

their shifts information on valve closure and opening must be exchanged.

Page 43: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

43

OPERATIONS IN OTHER THAN NORMAL CONDITIONS

Operations other than routine viz. during breakdowns and emergencies have to be

specified and should be carried out in specific circumstances when normal conditions

change i.e. when flows, pressures and levels and operation of pumps change.

MEASUREMENT OF FLOWS, PRESSURES AND LEVELS

It will be necessary to monitor regularly operational data concerning flows, pressures

and levels to assess whether the system is functioning as per requirements. Analysis of

data may reveal overdrawal of water to some reservoirs and or bulk consumers. At such

places appropriate flow control devices may be introduced to limit the supplies to the

required quantity. A list of priority points in water supply system have to be identified

such as installation of meters to measure flows, pressures and levels. A detailed map

showing location for each measuring point has also to be prepared. The degree of

sophistication of the devices used at each measuring point with regard to indication,

integration, recording, transmission and reception of data depends mainly on the skills

of the O&M personnel available with the agency and affordability of the agency.

EVALUATION OF HYDRAULIC CONDITIONS

Evaluation of the hydraulic conditions of the water supply system can be done by the

O&M personnel after obtaining the data on water volumes and flows at various points in

the system, the water pressures and levels in the reservoirs and comparing with

expected performance. This evaluation shall lead to identification of operational

problems and or system faults. Depending on the type of problems actions have to be

initiated to ensure that the system functions as per the requirement.

SYSTEM PRESSURES

Maintenance of a continuous positive pressure at all times (during supply timings) to

consumers is the main concern of O&M. Negative pressures can cause contamination

of water supplies especially in intermittent supplies. Very high pressures may damage

the pipelines and valves, which can be corrected with pressure reducing valves.

Complaints from consumers about low pressures have to be promptly investigated if

necessary by measuring pressures with pressure gauges. Low pressures may be under

the following circumstances:

• Purposefully or accidentally a line valve is left closed or partly closed or blockage

due to any material causing loss of pressure.

• Too high velocities in small pipelines.

• Low water levels in SR.

• Failure of pumps/booster pumps (either due to power failure or mechanical failure)

feeding the system directly.

Page 44: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

44

SIMULATION OF NETWORK

Operations have to be planned for specific circumstances such as failure at source,

failure of pumps, leakages or bursts or sudden changes in demand etc. Criteria have to

be determined on the basis of analysis of the effects of particular operations on the

hydraulic configuration of the water supply system. These effects can be seen in

simulated operating conditions. Mathematical simulation models can be developed from

basic data on the network such as length, size, flow, characteristics of pumps, valves,

reservoir levels etc. This approach can be very useful for analyzing the effects of

variables on large and complex distribution networks/water supply systems.

SAMPLING FOR QUALITY OF WATER

The agency operating the water supply system is charged with the primary responsibility

of ensuring that the water supplied to the consumer is of an appropriate quality. To

achieve this objective it is necessary that the physical, chemical and bacteriological

tests are carried out at frequent intervals. The minimum number of samples to be

collected from the distribution system should be as prescribed in the Table 15.1 of

Chapter 15 of the Manual on ―Water Supply & Treatment‖. Samples should be taken at

different points on each occasion to enable overall assessment. In the event of epidemic

or danger of pollution more frequent sampling may be required, especially for

bacteriological quality. For each distribution system a monitoring programme has to be

prepared showing the location of sampling points. Based on historic records of a system

it will be possible for the manager of the system to decide locations for bacteriological

sampling and residual chlorine testing.

8a) MAINTENANCE SCHEDULE

A maintenance schedule is required to be prepared to improve the level of maintenance

of water distribution networks and house connections through improved co-ordination

and planning of administrative and field work and through the use of adequate

techniques, equipment and materials for field maintenance.

• The schedule has to be flexible so that it can achieve team action with the available

vehicles and tools.

• Co-ordination of activities is required for spares and fittings, quality control of

materials used and services rendered.

• Training of maintenance staff shall include training to achieve better public relations

with consumers apart from the technical skills.

Page 45: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

45

ACTIVITIES IN MAINTENANCE SCHEDULE

Following activities are to be included in the schedule:

• Establishment of procedures for setting up maintenance schedules and obtaining

and processing the information provided by the public and the maintenance teams.

• Formation of maintenance teams for each type of service with provision for

continuous training.

• Establishment of repair procedures for standard services.

• Specification of appropriate tools.

• Allocation of suitable transport, tools and equipment to each team.

• Establishment of time, labour and material requirement and output expected; time

required and other standards for each maintenance task, and

• Monitoring the productivity of each team.

PREVENTIVE MAINTENANCE SCHEDULE

A preventive maintenance schedule for Servicing of Valves and Maintenance of Valve

Chambers, Maintenance of the pipelines: may include the tasks, set priorities, issue of

work orders for tasks to be performed, list of scheduled tasks not completed, record of

when the tasks are completed and maintaining a record of tools, materials, labour and

costs required to complete each task.

8b) MAINTENANCE SCHEDULE FOR PIPE LINE

Pipeline bursts/main breaks can occur at any time and the utility shall have a plan for

attending to such events. This plan must be written down, disseminated to all concerned

and the agency must always be in readiness to implement the plan immediately after the

pipe break is reported. After a pipe break is located, a decision is to be taken as to

which valve is to be closed to isolate the section where the break has occurred. Every

consumer (some important consumers may be having an industrial process dependent

on water supply which cannot be shut down as fast as the water supply lines are cut off)

should be notified about the break and informed about the probable interruption in water

supply and also the estimated time of resumption of water supply. After the closure of

valve, the dewatering/mud pumps are used to drain the pipe break points. The sides of

trenches have to be properly protected before the workers enter the pit. The damaged

pipe is removed, and the accumulated silt is removed from inside the pipe and the

damaged pipe is replaced and the line is disinfected before bringing into use. After

every pipe break a report shall be prepared in regard to the cause of such break, the

resources required for rectification and the time and cost required for repairing etc. so

that the agency can follow up with measures for avoiding such breaks and also modify

their plan to address such breaks in future.

Page 46: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

46

Deterioration

Pipes deteriorate on the inside due to corrosion and erosion and on the outside due to

corrosion from aggressive soil and water/moisture. Depending on the material of pipes,

these are subjected to some deterioration, loss of water carrying capacity, leaks,

corrosion and pitting, tuberculation, deposition of sediment and slime growth. Preventive

maintenance of distribution system assures the twin objectives of preserving the

bacteriological quality of water in the distribution system and providing conditions for

adequate flow through the pipelines. Incidentally, this will prolong the effective life of the

pipeline and restore its carrying capacity. Some of the main functions in the

management of preventive maintenance of pipelines are assessment, detection and

prevention of wastage of water from pipelines through leaks, maintaining the capacity of

pipelines, cleaning of pipelines and relining. The topic of assessment of leaks is dealt in

detail in Chapter 15 on Water Audit and Leakage Control in this manual.

Flushing

Flushing is done to clean the distribution lines by removing impurities or sediment that

may be present in the pipe. Routine flushing of terminal pipelines is often necessary to

avoid taste and odour complaints from consumers. It is advisable that a programme for

flushing is prepared and followed so that water mains are flushed before consumers

start complaining. The routine for flushing can be prepared by taking into consideration

the consumer complaints and type of deposits found while cleaning. Since in distribution

system flushing is not the only solution for water quality problems, proper operation of

treatment process and cleaning of service reservoirs supplying water to distribution

system shall also be planned along with the flushing of distribution system. Flushing is

usually done during low water demand, when the weather is favourable. Prior planning

and good publicity with public will allow the flushing to proceed quickly and without

confusion.

Cleaning

Mechanical cleaning devices such as swabs and pigs are sometimes used if flushing

does not improve the water quality. Scrapers or brushes are used in pipelines with

hardened scales or extensive tuberculation. Sometimes scrapers and brushes are used

before taking up lining works. The topics of cleaning of pipelines including cleaning and

swabbing are dealt in Chapter 10 of Manual on ―Water Supply & Treatment‖.

Page 47: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

47

Cement Mortar lining

The present trend is to use Cement Mortar lined Ductile Iron (DI) pipes or Mild Steel

(MS) pipes so that they will not lose their carrying capacity with use and age. Still many

new pipelines are proposed with unlined metallic pipes and there are several existing

pipelines with bare metal surface such as CI or MS. With passage of time these

pipelines deteriorate and require rehabilitation. Cement mortar stifles corrosion through

its ability to develop high alkalinity. The application of cement mortar lining to pipe in

place is done by a lining machine, containing a device that projects cement mortar

against the pipe wall. Directly behind this device are mechanically driven rotating

trowels, which give the surface smooth finish. In-situ Cement Mortar lining of existing

metallic water mains has been beneficial where:

• Pipe carrying capacity may reduce due to tuberculation.

• Water quality is affected due to release of corrosion products from the pipes to the

water, and

• Leaks occur through joints and pipe walls.

LEAKAGE CONTROL

Wastage of water in the system and distribution network occurs by way of leakage from

pipes, joints & fittings, reservoirs and overflow from reservoirs & sumps. The objective of

leakage control programme is to reduce the wastage to a minimum and minimize the

time that elapses between the occurrence of a leak and its repair. The volume of water

lost through each leak should be reduced by taking whatever action is technically and

economically feasible to ensure that the leak is repaired as quickly as possible. To

achieve this, the organization shall prescribe procedures for identifying, reporting,

repairing and accounting for all visible leaks. It will be beneficial for the agency if the

procedures involve the conscious and active participation of the population served by

the agency apart from its own staff. For details on detection and leakage control, please

refer chapter 13.0. Water Audit and Leakage Control. The Management has to process

the data and evaluate the work on detection and location of leaks and for dissemination

of the results and initiate actions to control the overall problem of water loss. Interim

measures for reduction/control of leakage can be initiated by controlling pressures in the

water distribution system where feasible.

HOUSE CONNECTIONS

Leakage can be controlled at the point of house connection and in the consumer pipe by

adopting correct plumbing practices and improving the methods used for tapping the

main and giving house connection and strict quality control on the pipe material used for

Page 48: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

48

house connection. An analysis of leaks in house connections and investigation of

reasons for leaks in the house connections shall be carried out to initiate action on

reducing the leakage through house connections.

VISIBLE LEAKS

The water utility has to establish procedures whereby the population served by the

agency can notify the visible leaks. The agency staff can also report visible leaks found

by them while carrying out other works on the water supply system. Utility has to

establish procedures for prompt repair of leaks and for attending efficiently and

accurately to the leaks. Critical areas where leaks often occur have to be identified and

appropriate corrective measures have to be implemented.

INVISIBLE LEAKS

Establishment of procedures for detecting and locating non-visible leaks shall be

compatible with the technological, operational and financial capability of the agency.

Selection and procurement of equipment for detection and location of leaks must take

into account the cost effectiveness and the financial capability of the Organization.

CROSS CONNECTIONS

Contaminated water through cross connections of water supply lines with sewers and

drains is a problem prevailing widely. Intermittent supply further aggravates the problem

since, during non-supply hours polluted water may reach the supply mains through

leaking joints, thus polluting the supplies. In certain instances, when there are extremely

high water demands, the pressures in the supply mains are likely to fall below

atmospheric pressure, particularly when consumers start use of pumps with direct

suction from supply mains. Regular survey has to be undertaken to identify potential

areas likely to be affected by cross connections and back-flow. All field personnel should

be constantly alert for situations where cross connections are likely to exist. After

identifying the cross connections, remedial measures are taken up which include:

providing horizontal and vertical separation between the water main and the

sewer/drain, (refer to para 10.11.1 of Chapter 10 of Manual on ―Water Supply &

Treatment‖), providing a sleeve pipe to the consumer pipes crossing a drain, modifying

the piping including changing corroded piping with non-corrodible piping, providing

double check/non return valves at the consumer end etc.

Page 49: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

49

CHLORINE RESIDUAL TESTING

A minimum chlorine residual of about 0.2 mg/l at the selected monitoring point is often

maintained to ensure that even a little contamination is destroyed by the chlorine.

Hence, absence of residual chlorine could indicate potential presence of heavy

contamination. If routine checks at a monitoring point are carried out, required chlorine

residuals and any sudden absence of residual chlorine should alert the operating staff to

take up prompt investigation. Immediate steps to be taken are:

• Re-testing for residual chlorine.

• Checking chlorination equipment.

• Searching for source of contamination, which has caused the increased chlorine

demand.

• Immediate stoppage of supplies from the contaminated pipelines.

MONITORING SYSTEM PERFORMANCE

Normally the managers of O&M of water utilities monitor levels in service reservoirs,

pressures and flows in the distribution system and operation of pumps such as hours of

pumping, failure of pumps and monitor water quality by measuring residual chlorine. The

manager usually uses telephone line or wireless unit to gather the data, maintain

records analyses, uses his discretion gained with experience and takes decisions to

ensure that the system is operating with required efficiency. Manual collection of data

and analysis may not be helpful in large undertakings if water utilities have to aim at

enhanced customer service by improving water quality and service level with reduced

costs. In such cases Monitoring system performance can be done with use of Telemetry

and SCADA which are discussed in Chapter 11 –Water Meters and Instrumentation

including Flow Meters.

PLUMBING PRACTICES

The internal plumbing system of the consumer shall conform to the National Building

Code and also particularly to the bye laws of concerned water utility/local authority.

QUALITY OF PIPE MATERIAL FOR HOUSE CONNECTION

The water utility shall ensure that the connection and communication pipe from the

street main up to the consumer premises is laid as per correct plumbing practices and

adopt improved methods for tapping the main. Strict quality control is required on the

pipe material used for house connection. The bye Laws shall lay down rules for defining

the ownership and responsibility for maintaining the point of connection and the

communication pipe. In several utilities the communication pipes are leaking since they

are corroded; however these are not replaced by the consumer or by the utility

particularly where the O&M responsibility for consumer pipe rests with the consumers.

Page 50: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

50

CONTAMINATION

While laying the consumer a connection pipe there is a need to avoid contamination of

water supplies. This can be achieved by maintaining horizontal and vertical separation

between the water supply communication pipe and the sewer/drain, (refer to para

10.11.1 of Chapter 10 of manual on ―Water Supply & Treatment‖). In some instances a

sleeve pipe may be required to be provided to the consumer pipes crossing a drain. It is

always recommended to provide a non-corrodible pipe material for the consumer

connection. Contamination by possible back flow can also be prevented by ensuring

provision of double check/non-return valves at the consumer end.

RULES FOR CONSUMER CONNECTIONS

The water utility shall formulate rules for sanction of consumer connection, tapping the

mains and laying the connection piping. Water utility shall undertake inspection of the

consumer premises before releasing the connection to ensure that the internal plumbing

system of the consumer conforms to the National Building Code. Water utility shall

supervise the process of drilling/tapping of the main for giving connection and laying of

the consumer piping. The process of submission of applications for connections by

consumers and carrying out the connection work through licensed plumbers is also

prevalent in some utilities. In such cases the utility shall formulate procedures for

licensing the plumbers including the qualifications to be possessed by the plumber,

facilities and tools to be available with the plumber for the work to be undertaken by the

plumber. The utility shall closely observe the quality of materials used and works done

by him and he should act as per procedures laid down in the bye laws for approval of

the connection works, renewal or cancellation of the plumbers‘ licenses or any other

requirement depending on their performance or non-performance.

8c) CHECKS IN DISTRIBUTION SYSTEM

PROGRAMME FOR CARRYING OUT CHECKS

A programme has to be prepared for each zone of the distribution system which shall

contain procedures for routine tasks, checks and inspections at intervals viz. daily,

weekly, quarterly semi-annually or annually. This plan shall fix responsibility, timing for

action, ways and means of completing the action as to when and who should take the

action and mention the need to take these actions. Simple checklists for use by the

managerial staff can be prepared to ensure that the O&M staff has completed the tasks

assigned to them.

Page 51: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

51

CHECK LIST

Sl.No. Checks required / undertaken Status Suggested

frequency of reporting

1. Check whether the Operation of valves in smooth without any abrupt stoppage during closure

2. Check whether closure of a valve results in complete stoppage of flow or if any flow passes the valve (passing valve)

3. Check for status of scouring and then proper closure of washout valves.

4. Check for leaks through pipes

5. Check for leakage through valves at gland, bolts or any other place

6. Check for leaks at the appurtenances

7. Check for any signs of corrosion of pipelines

8. Check for the status of Manhole covers over the chambers; are they corroded

9. Inspect for any possibilities of pollution of the distribution system water stored.

10. Status of out-fall drain for scour and overflow

11. Assess the need for painting of the piping work

12. Check for availability of spares for valves and pipes and jointing materials

13. Review the method of giving consumer connections in the field

14. Preparation of water budget for each zone served by one reservoir

15. Number of connections given

16. Number of meters out of order

17. Status of hydrants and PSPs

18. Status of Distribution System

19. Review of pressures

20. Review of flows

21. Age of pipes/C value of pipes

22. Corrosive water

23. Study of inflows and outflows

24. Identify source of leakage

25. Metering

26. Status of bulk metering and consumer

27. Review facilities for repair of consumer meters

28. Unauthorised connections if any

29. Status of fire hydrants and PSPs

30. Availability of updated system map

31. Need for any interconnections

Page 52: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

52

8d) SERVICING VALVES & VALVE CHAMBERS

Seating of valves which are subject to operations several times is likely to become leaky

or pass the flow downstream even after closing tight. Periodical servicing will be

required for valves on hydrants and public taps, flow meters and pressure gauges.

Corrosion of valves is a main problem in some areas and can cause failure of bonnet

and gland bolts. Leaks from spindle rods occur and bonnet separates from the body.

Stainless steel bolts can be used for replacement and the valve can be wrapped in

polyethylene wrap to prevent corrosion.

SPARES

Spares required for the distribution system shall be prepared and the spares shall be

procured and kept for use. The list should indicate the minimum level at which action for

replenishments should be initiated. The list of probable spares to be kept in stock may

include the following:

Spare check nuts and spindle rods and assorted bolts, nuts and washers for the flanged

joints, gaskets for flanged joints for all sizes of sluice valves installed in the distribution

system, spare manhole covers and consumables like the gland rope, grease, cotton

waste, spun yarn, pig lead and lead wool.

TOOLS

The necessary tools to properly repair and correct both the routine problems and for

facilitating repairs and replacements in a distribution system have to be identified and

provided to the maintenance staff.

Some of the tools for the maintenance work in a distribution system are: Key rods for

operation of all sluice valves, hooks for lifting manhole covers, pipe wrench of

appropriate sizes ( 200, 300 or 450 mm ), Double ended (DE) spanner set, Ring

spanner set, Screw Drivers, Pliers, Hammers, Chisels, caulking tools for lead and spun

yarn, ladles and pans for melting and pouring lead joints, excavation tools such as crow

bars, spades, iron baskets, buckets and de-watering pumps.

MAINTENANCE OF VALVE CHAMBERS FOR APPURTENANCES

Valve chambers shall be checked to ensure that they are not damaged, nor filled up

with earth nor buried in pavement. Covers of valve chambers are stolen or broken up by

vandalism or by accident resulting in damage to the valves or may lead to accidental fall

of a person into the open valve chamber. Such situations have to be corrected on

priority. Road improvement works require constant attention of water utility staff since

the valves may be lost or at times the valve chambers in the roads have to be

reconstructed to match the renewed road surface.

Page 53: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

53

Monitoring of Internal Mobilization

Some of the important activities relating to the mobilization of the internal activities are

summarized below;

a) Necessary information to the Senior Level Management may be submitted and their

interim approval sought. Details approval can follow in due course of time.

b) The entire staff must be made fully aware of the likely activities required to be

undertaken so as to ensure minimum possible interruption in the system.

c) Alternative arrangement for water supply may be planned and duties of staff fixed

accordingly.

d) The operation of the water supply system with regard to Intake, Headworks,

Pumping machinery, Treatment Plant, Piping system etc. must be co-related with

the proposed repair work.

e) Necessary staff may be arranged for the following duties;

1. Location of section;

2. Isolation of section;

3. Scouring of section;

4. Arranging transport, material, machinery, equipment, tools, pipes, fittings etc.

5. Other miscellaneous duties.

f) These details are variable and depend upon various factors as per the local

situation. Some of the factors to be considered are;

The importance, utility and function of the affected pipeline with the piping

network. This may be the only transmission main of the system. It may be one of

the two or many parallel transmission mains. It may be initial portion of the

distribution system serving as the only main to supply water to the rest of the

area to be served. It may be a distribution pipe serving only a part of the system.

Size and material of the affected pipe.

These are very important factors which determine the magnitude of the repair to be

undertaken.

Depth of the pipeline. Deeper pipes require more labour work for repairing.

Subsoil water table.

If the pipe is laid much below the local water table, additional work will be required to

dewater the trenches excavated for repair.

Other unforeseen factors.

Page 54: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

54

Depending on these factors the requirement of manpower, material, machinery, tools,

equipment, pipes, specials, fittings etc. is to be worked out. Given below is a list to meet

the requirement of a big transmission main which is a life for the water supply system.

This may be considered as a guideline only. Exact requirement may be worked out

depending upon the local conditions.

Tools

Scour rod with lever, motor driven pipe cutter with extra cutters, H.T.wire cutter, sheet

cutter, screw jacks, hammers, spades, buckets, baskets, crow bars, hammers, showels,

caulking tools (spun caulking, cement caulking, lead caulking), power wrenches 36 in. to

15 in., adjustable spanner 18 in. to 12 in., chain tong 36 in. long, ring spanner set, DE

spanner set, screw drivers, cutting plier, knife, nose plier, knife, chisels, lead pan with

sport and bucket, Temporary platforms, files, bench vice and pipe vice.

Pipe Specials

MS gap special, MS barrels, MS split collars (different types available), MS girder, MS

angle.Wireless set, mobile wireless set, cell phone, pager.Flood lighting, tube light

fittings, wire, 3 core cable, insulation tape, main switch, fuse wire, kit kats, welding

cable, emergency lights, torch lights, gas lights.First aid box, helmets, headlight, gum

shoes, hand gloves (rubber, leather), gas masks, oxygen cylinder.Tents, water cans,

jugs and glasses, tarpaulins, electric heaters, rain coats, food (tea and snacks, meals)

Detection of Pipe Failure

1. Inspect site and ascertain the nature of the failure.

2. Assess any possible damage or dispute that may arise and take steps to face such

situations.

3. Investigate the access to the site so as to plan the arrangement of plant and

equipment.

4. Assess urgency of repair, availability of men and equipment, effect on consumers

and fix time and day of repair.

5. Locate isolating valves for proper control of requisite activities required for repair

work.

6. Depending upon the seriousness of the leakage or burst, the likely effect on the

local supplies, decision may be taken on

i) maintenance of supplies as long as possible

ii) prevention of possible contamination of the pipeline and

iii) quick location of the actual position of the pipeline.

Page 55: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

55

7. Establish control and communication network after deciding the time of repair work

to be undertaken.

8. Ascertain the sensitivity of the affected area and take steps to avoid undesirable

situations.

9. Issue notification and warnings of the likely interruptions.

10. Mobilize men, material and equipment for repairs.

Repair work

For small local defects such as pinholes a single split collar or wraparound clamp may

be all that is required. The repair can be carried out at as a ‗wet‘ or ‗dry‘ operation. In

case of ‗wet‘ repair care should be taken to maintain a steady, gentle flow so as not to

dislodge the sealing elements.

For a more extensive damage e.g. a longitudinal fracture, a section of pipe is cut out

and replaced by the use of two appropriate couplers. If full extent of the fracture is not

clearly defined cuts should be made at least 300mm beyond each end of the visible

crack or defect and in case of any doubt the full length of damaged pipe should be

replaced. This necessitates cutting out the joint at both ends of the affected pipe, thus

the repair normally requires two replacement pipe sections and three couplers.

• Carryout correct measurements and give allowance for expansion;

• All cuts should be made clean and square;

• In A.C. pipes, cuttings should be avoided;

• All cut edges should be prepared (scraped, deburred, chamfered etc.) to the

manufacturer‘s recommendations.

• Both exposed ends of the existing pipe should be similarly treated;

• Couplers should have their sealing rings lubricated if recommended;

• Correct expansion gaps should be allowed;

• Good alignment is essential particularly if narrow couplers are used;

• All couplers and collars should be centralized;

• Tighten all bolts evenly;

• Do not over tighten bolts or compression joints;

• Restore any damaged coatings on the parent pipe;

• Ensure full protection to the bolts and any exposed bare metal before burial.

9) LEVEL GAPS INFORMATION – QUALITY & QUANTITY

The flow of information between and within the water supply and surveillance agencies

is necessary to maximize the quality of service to consumer and protection of public

Page 56: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

56

health. The report provided by the surveillance agency to water supply provider should

include:

1. The summary reports of condition of water supply and water quality analysis.

2. Highlight those aspects, which are considered inadequate and needs action.

3. Recommendation of remedial action in case of emergency.

The report should not be limited to complain about failures but the water supply and

surveillance agencies should coordinate their activities to ensure good quality of water

to consumers. Such a report should specify actions in order of priorities for intervention

based on public health criteria. If consistently, unsatisfactory results are reported in a

particular area, the cause for the same should be investigated and remedial measures

taken, such as repair of leakage, replacement of corroded and leaking consumer pipes

etc.

Local laboratory under surveillance agency should maintain detailed field reports

regarding inspections and water analysis of all water supplies available in the area. It

should include the results of all inspections and analysis. The local surveillance office

should report to the relevant supply agency as soon as possible after field visits. The

information should also be passed on to regional authorities to allow follow-up; if

recommendations for remedial action are not implemented. However, there must be a

rapid means of reporting in case of emergency.

The consumers have the right to know about the quality of water being supplied to them.

Therefore, the agencies responsible for monitoring should develop strategies for

informing public the health-related results obtained by them along with

recommendations for action (e.g. boiling during severe faecal contamination, household

water storage education etc.) through publicity, pani-panchayats etc.

Local government should ensure that the agency that supplies drinking water to the

area complies with the quality standards.

WATER SAMPLING AND ANALYSIS

Periodic drinking water analysis is necessary to ensure safe quality water supply. Water

samples should be analyzed for various microbiological and physicochemical

contaminants. However, the authenticity of water analysis greatly depends on the

sampling procedure. The objective of sampling is to collect a small portion of water

which can be easily transported to laboratory, without contamination or deterioration and

which should accurately represent the water being supplied. It should cover locations

which are most vulnerable in the supply system.

Page 57: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

57

For recommended sampling procedures and guideline values regarding physical and

chemical parameters, kindly refer to Manual on Water Supply and Treatment, III Edition,

May 1999, Government of India, Ministry of Urban Development, New Delhi.

DATA ANALYSIS, INTERPRETATION AND REPORTING

Data analysis and interpretation are fundamental components of surveillance process. It

aims at generation of data, which contributes to protect public health by promoting

adequate, safe, potable water supply to communities.

DATA ANALYSIS

Evaluation of community water supply requires consideration of number of factors, such

as quality, quantity, coverage, continuity of water supply and never the least, its

production cost.

QUALITY

Quality of water supplied to communities is an important consideration for human health

and well-being. Remedial and preventive measures also form an important part of water

supply quality maintenance. Annexure 9.7 gives details about the suggested guidelines

for the same. Water quality data, generated and summarized by surveillance agencies

are useful tools to promote improvement and design action strategies for quality water

supplies in compliance with national standards.

QUANTITY

Along with quality, quantity of supplied water to the community plays an important role

for maintenance and improvement of public health. Personal and domestic hygiene

greatly depends on per capita quantity of water supply to the consumers. In case of

inadequate quantity of water supply, community may use alternate source of water,

some of which may be not be safe and affect the public health.

10) REVENUE MANAGEMENT SYSTEM

Revenue management system is an important aspect of any Water supply System as it

governs the financial aspect. Besides fixing a tariff structure, billing and collection of

revenue play an important part.

TARIFF FIXATION

The water charges to be fixed by the utility take into account the ability of the system to

meet the expenditure on the following heads. (i.e.)

Page 58: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

58

• Operating Cost (excluding establishment cost).

• Establishment Cost.

• Depreciation.

• Debt Services & Doubtful Charges.

• Asset replacement fund.

Tariff structure should be fixed and revised periodically. Automatic increase of tariff

periodically on index basis can also be adopted. Where the same authority also

provides sewerage system, charges for this can also supply through Public stand post,

may be charged and also be included as a percentage of the water charges.

CATEGORIES OF CONSUMERS

The various categories of consumers are:

i) Domestic,

ii) Commercial (Business entities, Hotels, Industries etc.),

iii) Government Authorities,

iv) Partly Commercial,

v) Bulk Consumers.

Among the five categories, the domestic consumers are the privileged class of people in

terms of supply of water and collection of taxes mainly because they use water for their

healthy existence. The other categories of consumers largely use water while carrying

out commercial/business activities. Therefore, the distribution of cost incurred on the

maintenance of such system to each class of consumers should be logically and

appropriately determined with reference to the level of service rendered. Finally, a

projected income on account of water charges should take into account the various

factors stated in the paragraph above.

WATER CHARGES

The methods of levying water charges can be any one or more of the following:

A. Metered System:

1. Actual consumption of water.

2. Minimum fixed charge.

B. Non-Metered System:

• Fixed charge per house per month.

• Fixed charge per family per month.

• Fixed charge per tap per month.

• Percentage of rate able value of the property.

Page 59: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

59

BILLING PROCESS

The various stages in the Cycle of Water Billing Process are:

• Data gathering (Meter reading in case of metered billing).

• Generation of bill based on this data.

• Distribution of bill to consumer.

• Payment of the Bill by the Consumer.

• Sending the receipt details to billing section.

• Related accounting.

Irrespective of the basis of the billing-metered/unmetered the billing system needs three

major databases:

• Master Data - This is the data, which needs to be entered only once when the

consumer/connection is added into the database. This data is relatively static in

nature and does not change periodically. Various data items, which need to be

stored, (depending on the type of water charges) are:

Consumer number, name of consumer, address, type of use, type of consumer, tap

size, data of connection, details of feeder line, locality, house number, water

connection number, number of taps, number of families, meter make, meter number,

first reading, ownership of meter, deposit amount etc.

• Data for each billing cycle - This data will be entered for every consumer for every

cycle and will be used for calculating the demand of that billing cycle. Various data

items which need to be stored are-

Consumer number, data of meter reading/period for which billed, status of the

connection and any changes in master data etc.

• Receipt Data - This data will be the data related to the payments made by the

consumer against the bill issued. This data will be entered on daily basis irrespective

of the billing frequency. Various data items which need to be stored are:

Consumer number, date of receipt, receipt number, details of the collection center,

cash/cheque (If cheque - cheque no, bank branch) Part payment/adhoc payment/

deposit, account head for posting etc.

DATA COLLECTION

For better administrative control over the complete billing process the city/town is

divided into various zones/sections geographically or as per the distribution networks

(service reservoir wise). It is observed that the cities already have ward numbers or

localities which can be used as they are but if the billing is as per the distribution

network the billing system can provide very important feedback as far as water/revenue

losses are concerned (unaccounted for water - UFW).

Page 60: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

60

These zones are further divided into smaller area (Wards) for better control. The person

responsible for gathering data from these areas is the meter reader/ward clerk. In case

of metered system the number of consumers who can be handled by one-meter reader

will depend upon the geographical spread of the area and other office jobs to be

performed by the person. In many utilities the range varies from 800 to 1500 consumers

per month. In case of unmetered system the number can be increased.

The prime responsibility of meter reader/meter clerk will be to gather all the data related

to the water connections in the given area, to collect all the data related to new

connections/disconnection or any change in the category.

BILLS

The water rates/tariff structure may have one or more aspects from the following -

consumption based, flat rate, minimum charges, fixed charges, average consumption

based etc.

Depending on the data gathered the demand for a particular billing period is calculated.

The outstanding amount is worked out on the basis of details of payments received. The

charges for delayed payments or amounts not paid are calculated as per the rules. The

bills are generated area-wise.

DISTRIBUTION OF BILLS

The distribution of bills can be done using any one of the following:

i) By post or courier,

• By persons specially appointed for this purpose

• By concerned meter readers/ward clerks

ii) In a special round for distribution of bills,

iii) At the time of meter reading for the next round.

(This option saves effort/manpower but there is delay in one complete cycle in

reading and distribution of bills).

PAYMENT OF BILLS

The payments can be accepted at any one or more of the following:

• Counters at various offices of the Board/Corporation/Utility.

• Various branches of bank/banks authorized for accepting payments.

• Door to door/on the spot recovery by concerned person/team.

• Electronic fund transfer through various banks offering such option/directly.

Page 61: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

61

• By cheque through post or drop boxes.

• Through societies authorized by government, such as cooperative societies.

• On line payments.

• Automatic kiosk.

FREQUENCY OF BILLING

The frequency of Billing governs the cash flow of the water billing system and thus more

frequency means regular cash flow.

The frequency of billing depends mainly on the type of system used. For non-metered

system the billing could be quarterly and for the metered system the billing could be bi-

monthly. But in both cases all non-domestic, Industrial, Bulk Consumers must be billed

monthly. The only other factor which can be considered in this respect is the availability

of manpower for billing process and the cost of issuing bills in one complete billing cycle.

DELAYED PAYMENTS

Since water is being treated as a commodity consumed the advance billing is generally

not carried out. It is therefore ‗a must‘ to levy penalty/interest on the delayed payments

of the bills.

COMPUTERISED BILLING

Computers are now widely used in day to day activities. For a water billing system,

which is complex, repetitive and has voluminous data, computerization is

recommended. Computerization overcomes many of the defects in the manual system,

is fast and gives a control on the system. Computerization helps in decision-making.

The output formats can be tailored to suit quick retrieval of information that is necessary

for decision making. Consultants and experts are now available to help in setting up a

computerized system.

COMPUTERISATION OF BILLING

The advantages of the computerization of billing and collection are as follows:

• Listing of customer accounts with unserved bills.

• Quantity analysis on line.

• Query for list of debtors.

• Quick MIS for on the spot analysis of important parameters.

• Bills generated for the month.

• Amount collection up to the date.

Page 62: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

62

• Number of connections.

• Total working and Nonworking meters.

• Disconnection.

• Water consumption.

• Demand Collection Balance (DBC) statement.

• Receivables monitoring and fixation of targets for billing.

• Performance indicators.

• Meter reader performance.

• Collection efficiency.

• Billing pattern.

• Water consumption.

• Billed units.

• Reports on debtors requiring continuous persuasion.

Metering and Tariff

Water Tariff is the rate levied for the water supplied to the consumers in order to

develop sufficient revenues to provide for operation and maintenance and also for debt

services. The tariff must attempt to distribute the cost of supply of water equitably to all

consumers in relation with the benefit they derive or the expenses they cause the

system. The principle of ―paying in proportion to the cost of water used‖ has generally

worked in advanced western countries. But in developing Countries the funds for the

implementation of water supply schemes have come from the government either loan or

grant to the local bodies concerned. However to make the utility self-financing, charges

must be geared to replacement cost and operation and maintenance cost.

Basis for Water Tariff

The total revenue of public water – supply system should be adequate to cover;

1. The cost of operation and maintenance.

2. Interest and depreciation or amortization of the investment of water supply system

and their components.

3. An additional, amount for implementing certain facilities like extension of distribution

system, meter and service instillations, replacement of pumping plants which are

more or less continuously taking place.

It is one of the primary responsibilities in a water supply system management to see that

the revenues are adequate and are equitably collected from those using the service.

Page 63: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

63

The total revenue requirements are made up of:

i) Operation and maintenance expenses as estimated for 3 to 5 years in advance of

proposed rate change.

ii) Debt service in obligations outstanding and to be issued in the succeeding 3 to 5

years.

iii) Depreciation allowance of 1 ½ to 2% per year on investment less unamortized debt.

iv) Estimated average annual expenditure for ordinary capital addition during next five

years.

Techniques must be developed continuously and they should be based upon sound

engineering and economic principle. The ability of the techniques to provide sufficient

revenue and accomplish an equitable distribution of cost must be continually

reevaluated.

Water Tariff

The simplest form of water rate is flat rate payable monthly or quarterly by the

consumers regardless of the quantity consumed, the services being metered. Many

local bodies also adopt the system of a fixed tap rate charges per tap irrespective of the

quantity used. This rate is easily fixed by dividing the total revenue required by the total

number of consumers of taps. But this system leads to waste of water and is therefore

not satisfactory.

Most equitable method will be based on metering of all supplies. The quantity actually

accounted for by the meters is invariably less than the produced since there is

considerable wastage as unaccounted water which also should be considered in fixing

the water rates some local bodies allow a free allowance for the metered supplies based

on the water taxes collected and charge only for the excess. This is also not desirable

as revenue collected by water rates is to finance the operation and maintenance cost

fully. A worthwhile alternative is to collect a fixed charge called service charge per

consumer in addition to the charge for water consumed. The fixed charge is to provide

for the meter rent where the meters are supplied by the department and the overhead

charges for meter reading billing etc. The entry supply as measured by the meter is to

be charged for at either uniform rate or graded rates. There must be separate meters for

measuring the supply for domestic and non-domestic uses. The rates for non-domestic

and industrial purposes may be fixed higher. The rates are to be carefully fixed taking

into account the following.

Page 64: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

64

i) The rate must be high enough to fetch the necessary revenue and not excessive as

to discourage consumers from making need based use of water.

ii) The rate should be such as to make the amenity more or less self-paying and

worked on no profit no loss basis.

Metering

In a water supply organization (WSO) supplying potable water to the people it is

important to distribute the water for daily use and to measure the quantity of water

consumed by the people. Measuring the quantity of water supplied by the organization

or the quantity consumed is generally known as metering helps to assess the demands.

Quantities pumped, quantities consumed by individual consumers and to assess the

leaks in the distribution systems.

Types of Meters

Most commonly used meters are:

1. Venturi meters

2. Electro flow meters

3. Orifice meters

4. Water meters for bulk consumers (inferential semi positive)

5. Water meters for domestic consumers (Inferential semi positive) venturi meters.

Electro flow meters and Orifice meters are used for measuring the flow of water in the

Head Works and trunk mains. These meters are provided with recording arrangements

for recording rate of flow against time meters used for rerecording flows in the service

connections of bulk consumers and domestic consumers are of dial type and are

installed inside the premises in a meter chamber.

It is important that these meters are properly selected. Installed and maintained so that

reading are taken with ease and accuracy of the reading maintained.

Domestic Water Meters

Domestic water meters are of two types viz. Inferential (horizontal) and semi positive

type of water meters and are available as both wet dial and dry dial. The nominal sizes

are 15, 20, 25, 40 and 50 mm dia. The domestic water meter consists of meter body.

Registration box cap lid, impeller chamber, measuring chamber and deregistration

device.

Page 65: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

65

Registration Device

It is the unit which comprises the recording gear train and the indicating device

consisting of a cyclometric type counters or pointers working on a dial on a combination

of both, it registers in suitable volumetric units the quantity of waters which has passed

through the meter.

A Dry dial type meter is one in which the counter mechanism is isolated from water

flowing through the meter. A wet dial type meter is one in which the complete counter

unit is in contact with water flowing through the meter. The inferential type of water

meter measures the velocity of flow from which the discharge is measure. The

inferential type of water meter measures the velocity of flow from which this discharge is

measured. The semi positive type of water meter volumetrically records practically down

to zero flow of the water that has passed through. The impeller and pistons used in

inferential and semi positive meters respectively shall be durable and shall work with low

frictional resistance. These are generally made of non-absorbent materials such as

plastics, ebonite, bronze, stainless steel or nickel alloy. The movement of the impeller or

piston is transmitted to move the pointers on the dial through gears and pinions. The

gears and pinions are constructed to fully and smoothly mesh with each other‘s and are

made of stainless steel, nickel alloy or suitable plastics.

Selection of Domestic water Meters

Water meters shall be selected according to flow to be measured.

i) The maximum flow shall not exceed the nominal capacity of the meter specified in

Table 11.1 (IS 779-1968).

ii) The continuous flow shall be not greater than the continuous running capacity

rating as per (Table 1).

iii) The maximum flow to be measured shall be within minimum starting flows as per

(Table 11.1)

iv) Inferential meter has the same accuracy as the same positive type and is lower in

cost.

v) The normal working flow shall be well within the continuous running capacity

specified (Table 11.1) as high rates of flow over short period may cause excessive

wheat if the meter chosen is too small.

vi) Owning to the fine clearance in the working part of meters, they are not suitable for

measuring water containing sand or similar foreign matters. In such cases a filter or

dirt box should be fitted on the upstream side as shown in Fig. 11.1. It should be

noted that the strainer fitted inside a meter is not a filter.

Page 66: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

66

Installation of water meters

i) A meter shall not be run with free discharge to atmosphere, if the static pressure on

the main exceeds 10m head of water, otherwise the meter is liable to be

overloaded and damaged. For hose connections and similar applications, there

shall always be some resistance on the downstream side of the meter.

ii) A meter shall be located where it is not liable to get severe shock of water hammer,

which might break the piston or damage the rotor, and the position shall be such

that it is always full of water, a recommended method of making connection to

achieve the purpose is shown in Fig. 11.1 if the meter body or adjacent pipes

become partially drained of water the accumulated air, when passed through the

meter, is registered as water and may cause inaccuracies and perhaps damage.

The inaccuracies may be more pronounced in the case of inferential meters in such

situations suitable devices like air release valve may be fitted on the upstream side

of the meter. In the case of intermittent water supply system, where there are

frequent changes of air locks, the piston of the semi positive meter often breaks in

such a case, it is advisable to ensure that the top of the meter is below the level of

the communication pipe.

iii) Semi positive meters may be fixed in any position with the dials facing upwards or

sideways, and they may be installed in horizontal or vertical pipe runs without

affecting wearing properties of accuracy at normal service flows where backward

flows are anticipated, reflux valves are recommended to be provided. A stop valve

should be provided on the upstream side as shown in Fig. 11.1 to isolate the meter

whenever necessary.

iv) Inferential meters shall be installed imposition for which they are designed in the

case of meters conforming to IS 779-1958 they shall be placed horizontally with dial

facing upwards. However, where meters are to be installed in vertical pipe lines

details shall be as agreed to between the manufacturer and the purchase.

v) Turbulent flow of water affects the accuracy of the meter. There shall, therefore be

straight lengths of pipes upstream and downstream of meter for an equivalent

length of ten times the nominal diameter of the pipe.

vi) Meters should be fixed below ground level if they are located outside the building

or, if in exposed portion inside the building. The bodies of the meters should be

protected with some form of lagging: in the case of meters installed below ground

depth at which the meter should be fixed to afford frost protection will depend on

the nature of the soil.

Page 67: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

67

Range of Registration and Capacities of Domestic Water Meters

Size in mm

Range of Registration

Nominal capacity discharge in Litres

per hour

Continuous running capacity discharge litres

per hour

Minimum starting flow

litres per hour

Min

imu

m

Lit

res

Ma

xim

um

Millio

n L

itre

s

Se

mi

po

sit

ive

typ

e

Infe

ren

tial ty

pe

Se

mi

po

sit

ive

typ

e

Infe

ren

tial ty

pe

Se

mi

po

sit

ive

typ

e

Infe

ren

tial ty

pe

15 1 10 2000 2500 100 1500 10 40

30 1 10 3400 3500 2000 2500 15 60

25 1 10 5500 5500 3000 3500 20 75

40 10 100 10000 16000 6000 8000 25 100

50 10 100 15000 23000 9000 14000 35 175

Range of Registration and Capacities of Bulk Water Meters

Size in

mm

Range of Registration

Nominal capacity discharge in Litres

per hour

Continuous running capacity discharge

litres per hour

Minimum starting flow

litres per hour

Min

imu

m L

itre

s

Ma

xim

um

Milli

on

Lit

res

Va

ne-w

heel

Typ

e a

t

10m

ma

x h

ea

d l

oss

He

lic

al ty

pe a

t 3 m

ma

x h

ea

d l

oss

Va

ne

wh

eel ty

pe

at

3m

ma

x h

ea

d l

oss

He

lic

al ty

pe a

t m

ax

hea

d l

oss

Va

ne

wh

eel ty

pe

He

reti

cal ty

pe

50 10 100 30000 50000 17000 20000 250 500

80 10 100 50000 125000 27000 62000 500 1000

100 100 100 70000 20000 40000 100000 700 1500

150 100 100 150000 50000 80000 250000 1000 3500

200 100 1000 250000 800000 150000 400000 2400 5500

250 100 1000 400000 1000000 220000 550000 3200 9000

300 100 1000 500000 1500000 300000 750000 6400 14000

350 100 1000 - 2000000 - 1000000 - 200000

400 1000 10000 - 3000000 - 1500000 - 25000

500 10000 10000 - 50000000 - 2500000 - 35000

Page 68: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

68

vii) Before installing a meter, the section of line to be metered shall be thoroughly

flushed to remove all foreign matter and when starting up control valves shall be

opened slowly until the line is full, as a sudden discharge may damage the meter.

viii) Water meters may be installed underground, either the carriage way outside the

premises or at a convenient place within the premises. In order to enable the

meters to be accessible for periodical reading.

ix) Reading, inspection, testing and repairs they shall be housed in water meter boxes

confirming to IS 2104-1962. Top of the meter box shall be places at a slightly

higher level than the surrounding ground level so as to prevent ground water

entering in and flooding the chamber during rains.

Bulk Water Meters

Bulk water meters are of two types viz (1) Vane-wheel (Impeller) type meters (with size

ranging from 50 to 300 mm bore) and (2) Helical type water meters (with size ranging

from 50 to 500 mm bore).

Van Wheel Type Meters

It has runner or impeller mounted on a vertical spindle which has several vanes

symmetrically spaces round its axis. The water impinges of the runner over a part or the

whole of its circumference. There are dry dial and wet dial type meters in vane wheel

meters.

Helical Meters

They are axial flow meter whose runner is provided with number of vanes forming a

multithreaded helix.

Page 69: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

69

INTRODUCTION

Sewage damage poses significant environmental and health risks. Sewage damage

cleanup, therefore, should be done in a speedy manner in order to contain and minimize

its damage to structural materials of homes and potential health risks to occupants.

Sewage damage cleanup consists of two parts: physical cleanup and chemical

disinfection.

Physical sewage damage cleanup requires removal of sewage water, sewage wastes,

and debris. Whereas, chemical disinfection requires use of disinfectants to eliminate

microbial organisms like bacteria and viruses.

Prime factors for consideration in sewage damage cleanup include extent of damage,

type of materials contaminated, duration of contamination, and amount of ventilation

available.

For instance, if sewage damage is minor and contained only to your bathroom flooring,

then you do not need to worry about contaminated carpets or upholstery. However, if

sewage that has contaminated your house is a result of flooding or sewage backup,

then cleaning and disinfecting will be more extensive. In such serious cases, even, use

of professional cleaning services is recommended. The thing is,sewage contamination

should be properly handled in order to kill all harmful microbes that have contaminated

your people.

Before working, it is important that the worker wears protective suits to avoid any

contact or inhalation of contaminated particles.

Again, sewage damage cleanup should be initiated very briefly after start of

contamination. Sewage damage poses negative impact against people and adversely

changes the indoor air quality of your home. The longer the contamination remains

untreated or properly treated, the greater are the chances for development of microbes.

The longer you prolong start of sewage damage cleanup, the more you and your family

are exposed to health threats of sewage contamination.

Operation& Maintenance of Sewerage System

Page 70: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

70

Some of the diseases that people can develop as a result of contact with sewage -

contaminated water or item include Hepatitis A, salmonella, bacillarydysentery,

balontidiasis, and skin infection.

Now there are some myths surrounding sewage contamination that you would better

dispel.

Myth 1: The sewage-contaminated river, lake, or ocean is clean: Any body of water

contaminated by sewage water or waste is positive with microorganisms,

viruses, pathogens, microbes, germs, and bacteria. When sewage-

contaminated water floods homes, these microorganisms soon become

odorous health hazards once trapped under carpets, floor coverings, or

walls.

Myth 2: Carpets saturated by sewage-contaminated water is salvageable: This is

absolutely false. The same is true for other porous materials like beddings,

sofas, papers, and upholstery. The rule of the thumb is, anything you can't

disinfect with hot water has to be thrown away.

Myth 3: Buildings which have only been partially contaminated by sewage flood is

safe: There is no truth to the preceding statement. This can only be true if the

contaminated area has been sealed off to prevent spread of contamination to

other areas of the building.

Now, should you do sewage damage cleanup yourself or should you call a professional

sewage remediation services? Again, look at the extent of the damage. If it is contained

to a small area of your house such as your bathroom (caused by clogged john), then

perhaps it is a problem you can manage yourself. However, if sewage-contaminated

flood has entered your entire home, it is better to call sewage-cleaning experts. Health

risks are higher in such cases.

Cleaning experts have the equipment and expertise to ensure that your home is

completely cleaned of harmful microbes for safe use again.

Page 71: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

71

Sewerage and sewage treatment

Design Criteria Period of Design

Components

Design Period (Years)

Clarifications

1. Trunk, Main Branch Sewers and Appurtenances

30

2. Pumping Stations (Civil Works)

30

3. Pumping Installations 15 With due provision for future additions at the end of 15 year period.

4. Rising Mains 30 The comparative merits of alternatives viz., a single main for the full 300 year period as against a main for the 15 year period supplemented by another main either for the entire length or part of it to meet the additional needs for the next 15 years may be examined to decide on the most economical arrangement.

5. Treatment Units 30 The layout should envisage the complete needs of the design period of 30 years. Sufficient area around the treatment works may be reserved to prevent development of the areas for residential purposes and to act as a buffer zone. Treatment works may be designed in sufficient number of units to meet immediate needs supplemented by additional successive units later on in a phased manner.

Density of Population

The following rates may be adopted for design if detailed census figures are not

available.

Population Density per Hectare

Up to 5,000 75 to 150

5,000 to 20,000 150 to 250

20,000 to 50,000 250 to 300

50,000 to 1,00,000 300 to 350

Above 1,00,000 350 to 1000

Page 72: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

72

Per Capita Sewage Flow

Unless data is available to the contrary, this may be taken as the average water supply

rate and is exclusive of ground water infiltration.

Ground Water Infiltration Rate

The following infiltration rates may be adopted for sewers laid below ground water table:

5,000 to 50.000 lpd / hectare or 500 to 5,000 lpd / km of sewer per cm of sewer per cm

of sewer dia. Plus 250s to 500 lpd / manhole

Peak Factors

Contributory Population Peak Factor

Up to 20,000 3.0

20,000 to 50,000 2.5

50,000 to 7,50,000 2.25

Above 7,50,000 2.0

Self-Cleansing Velocity

i) Sewers

For Design Peak Flow 0.8 metre / sec

For Present Peak Flow 0.6 metre / sec

ii) Open Drains 0.75 – 0.90 metre/sec

iii) Inverted Siphon 1.0 metre /sec

iv) Minimum Velocity for Force Mains 0.3 metre / sec

(When Lowest Duty Pump is Working)

Maximum Permissible Velocity

Stoneware Pipes 1.4 metre / sec

Brick Drains 1.8 to 2.1 metre / sec

Concrete Drains 2.5 metre / sec

Cemented Drains 3.0 metre / sec

Cast Iron Pipes 3.0 metre / sec

Maximum Permitted Depth of Flow

Diameter in mm (d) Depth of Flow which will Convey Designed

Quantity

Up to 400 0.50 d

400 to 900 0.67 d

Above 900 0.75d

Page 73: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

73

Recommended Design Flows

Recommended Design Flows computing Sewer Systems:

Street Sewers 6 DWF

Trunk Sewers 3 DWF when Excess storm water flow is diverted

and 6 DWF otherwise

Force Mains 3 DWF, storm water flow is surplus

Preliminary Treatment Units 3 DWF

Primary and Secondary 1 DWF

Treatment Units

Piping in Treatment Units 3 DWF

Useful gradients for design of Sewer Systems

Diameter mm Grade 1 over Capacity lpm

150 150 700

200 270 1180

225 295 1510

250 365 1850

300 460 2680

350 570 2620

375 640 4190

400 680 4670

450 840 6030

Sewage Treatment

Typical Analysis of Sewage

Constituents Strong Medium Weak

Solids Total 1200 500 200

Volatile 500 350 120

Fixed 700 150 80

Suspended Solids Total 400 300 100

Volatile 300 250 70

Fixed 100 50 30

Dissolved Solids Total 800 200 100

Volatile 200 100 50

Fixed 600 100 50

B.O.D. 300 200 100

C.O.D. 800 600 400

Oxygen consumed 150 75 30

Dissolved Oxygen 0 0 0

Nitrogen, Total 85 50 25

Nitrogen, Organic 35 25 10

Free Ammonia 50 30 15

Nitrites 0.10 0.05 0.00

Nitrates 0.40 0.20 0.10

Chlorides 225 100 50

Alkalinity 400 100 50

Fats 40 20 0 Note : 1. All values in mg/l.

2. The values furnished are the yearly averages for sewage collected from Pumping stations.

Page 74: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

74

Some Waste Water Treatment Methods and their Characteristics

The methods range from physic-chemical to biological and in the latter group, from

aerobic to anaerobic (see fig.). To give a quick overview, some biological waste water

treatment methods are briefly described in this section.

Processes of Sewage Treatment

1. Preliminary Treatment

a) Screening

Coarse Screens made of bars with opening of 7.5 to 1.5cm.

Bar Screens made of bars with opening of 5 to 10cm.

Amount of 3 to 180 cum/million

Material removed cum of sewage

By screens screened

b) Grit Removal

Velocity in grit 30 cm/sec.

Channels

Size of grit 0.15 mm to 0.20

Particles removed grains of sp. Gr. 2.30 to 2.65

Amount of grit removed 6 to 72 cum/million cum sewage treated.

Treatment Methods

Biological

Anaerobic

Contact beds UASBs,

Sludge digesters,

Anaerobic ponds

Aerobic

Suspended growth

Activated sludge Extended

aeration Aerated lagoons

Waste Stabilization ponds

Attached growth

Trickling filters Rotating bio-discs Land treatment, Root zone reed beds Vermisiabilization

Physico-chemical

Screens and grit removal

sedimentation, plate settlers

sludge thickeners Vacuum

filters, Centrifuges Ion-

exchange Reverse osmosis

Ultra-filtration

Page 75: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

75

II. Primary Treatment

Plain setting of sewage to remove organic matter to the extent possible.

Usual efficiencies 30% B.O.D. removal and 50% suspended solids removal.

III. Secondary Treatment

By (a) Intermittent sand filters

(b) Trickling filters or

(c) Activated sludge units.

Involves complete removal of organic matter.

IV. Low Cost Treatment

By (a) Waste stabilization ponds (aerobic, anaerobic and facultative)

(b) Aerated lagoons

(c) Oxidation ditches

Features

Screens

Velocity through screens 0.30 m/sec (at average rate of flow) for

hand raked bar screen 0.75 m/sec. (max.

velocity during wet weather periods) for

mechanically cleaned screens.

Submerged area of the screen

surface including bars and opening

200 to 300 per cent of the cross sectional

area of the approach sewer.

Net submerged screen area 0.04 to 0.06 sq.m/mld

Head loss through the screens Up to 0.75 m

Drop of floor level below the screen

a) For mechanically operated screens 75 mm (min)

b) For manually operated screens 150 mm (min)

Top of screen to be above highest flow level 300 mm

Minimum free board 300 mm

Grit Chambers

Horizontal velocity flow 0.15 to 0.30 m/sec.

Detention time 60 sec. (for 3 DWF)

Surface loading rate 40 Cum/Sqm/hour

Grit collection 12 to 27 cum/million cum

Page 76: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

76

Grit Chambers

Horizontal velocity flow 0.15 to 0.30 m/sec.

Detention time 60 sec. (for 3 DWF)

Surface loading rate 40 Cum/Sqm/hour

Grit collection 12 to 27 cum/million cum

Settling Tanks: (Plain Sedimentation)

Detention time 2.0 to 2.5 hours

Overflow rate 27 to 45 Cum/day/Sqm

Depth of tank 3.0 to 4.0 m

Velocity of flow 0.30 to 1.50 m/min.

Solids loading 30 kg/sqm/day

Intermittent Sand filters

Design loading on filters Million litres/hectare/day

For raw sewage 0.5

For presettled sewage (after screen

and grit removal)

1.0

Primary treatment complete (after

settling)

3.0

Dosing Tanks Enough flow to flood one unit of filter to a

depth of 5 to 10cm. Each filter bed should

receive 1 or 2 doses per day.

Average rate of dosage 30 litres / sec for 500 Sqm. (with

intermittent dosing and resting on sand

beds).

Trickling Filters

Low rate High rate

Hydraulic loading (in million litres/hectare metre/day) 10 to 40 100 to 400

Organic loading (in tone BOD/hectare metre/day) 1.1 to 3.5 3.5 to 17.5

Depth in m 1.8 to 3.0 1.0 to 2.4

Recirculation None 1.1 to 1.4

Filter volume 5 to 10 times 1

Power requirements (kw / million litres) None 30 to 180

Dosing interval 5 min. 15 sec.

Nature of dosing Intermittent Continuous

Page 77: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

77

Activated Sludge Units

Design parameters for Activated Sludge as per Ten State Standard Aeration Tank

Capacities and Permissible Loadings

Process

Plant

design

flow in

mld

Aeration

Retention

Period

(Hours)

Plant

Design kg

BOD / day

Aerator

loading

kg BOD /

cum

Kg BOD / day

Kg MLSS

Conventional Upto

2.25

7.5 Upto 450 0.50 050 to 0.25

2.25 to

6.75

7.5 to 6.0 450 to

1350

0.50 to

065

-

6.75 up 6.0 up 1350 up 0.65 up -

Modified or High

rate

All 2.5 up 900 up 1.60 1 or less

Step Aeration 2.50 to

6.75

7.5 to 5.0 450 to

1350

0.50 to

0.80

0.5 to 0.2

6.75 to

up

5.0 up 1350 up 0.80 up

Contact

Stabilization

up to

2.25

3.0* Up to 450 0.50

2.25 to

6.75

3.0 to 2.0* 450 to

1350

0.50 to

0.80

0.5 to 0.2

6.75 to

up

1.5 to 2.0* 1350 up 0.80 up

Extended Aeration All 24 All 0.20 0.10 to 0.05

* Detention time in contract zone which is 30 to 35% of total aeration capacity.

Re-aeration zone comprises the balance of the aeration capacity.

Waste stabilization ponds

a) For small schemes, a single facultative pond will suffice and is designed as below:

BOD loading 220 Kg/hectare/day

Water depth 1.5 to 1.7 m

Detention period 18 to 24 days obtained by adjusting surface area.

BOD removal 80 to 90%

Page 78: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

78

b) For large schemes where minimum clearance of 0.5 to 1 km from habitation is

available, anaerobic pond followed by facultative pond is preferable to save land

area and is designed as below.

Anaerobic Pond

B.O.D. Loading 880 Kg/hectare/day

Water depth not less than 2.5m.not greater than 3.0 m.

Detention period 4 days

B.O.D. 50 to 60%

Grass variety Para Grass

Grass yield 370-400 tonne/hectare/year in 11 cuttings.

Facultative Pond

Same design criteria as in (a) but influent B.O.D. would be less.

For hospitals, educational institutions, small colonies, etc., even chance odours

must be absent and single facultative pond is designed as below:

B.O.D. Loading 110 kg/hectare/day

Water depth not greater than 1.5m to 1.7m

Detention period 35 to 40 days

Fish ponds

Where practicable, fish ponds can be used for facultative pond effluents with the

following design criteria.

Water depth 1.5 m

Detention period 5 days

Cyprinuscarpie (Carp) is the most profitable variety of fish with yields of 4

tonne/hectare/year.

Grass Farm

The facultative pond effluent or the fish farm effluent can be used for grass

cultivation for cattle feed. The following criteria will apply. Application rate = 60 to

120m3/hectare/day (clay to gravely soils). For clayey soils, under drains system not be

recommended and only peripheral collection channels are to be provided.

Grass variety Para Grass

Grass yield 370-400 tonne/hectare/year in 11 cuttings.

Page 79: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

79

Aerated Lagoon

Where land cost exceeds Rs. 2, 00,000/- hectare, facultative waste stabilization

ponds would be uneconomical for a flat adoption and aerated lagoons can be used to

pretreatment economically with the following design criteria:

Detention time 1 day

Water depth 2.5 m

Oxygen required 1 kg / each kg. B.O.D. removal

BOD removal 60%

Aerator sizing 0.8 kg. O2/Kwh

SEPTIC TANK

A septic tank is a combined sedimentation and digestion tank, where sewage is held for

some time and the suspended solids settle down to the bottom of the tank. The sludge

is digested by the anaerobic bacteria. By this action the sludge is reduced in volume

sufficiently and a liquid is released as effluent. In this reaction gases are Carbon

dioxide, methane and hydrogen sulphide are released. The smell of hydrogen sulphide

is very pungent. The effluent though clarified to some extent, but still contains

considerable amount of dissolved and suspended putrifiable organic solids and viable

pathogens. Thus the disposal of effluent and requires a careful disposal. Due to the

difficulty of disposal of effluent and difficulty in providing a proper system of disposal for

it, the septic tanks are recommended to be adopted for isolated buildings, small

institutions and big hotels and camps. Thus septic tanks are suitable for isolated or

undeveloped areas of the locality where municipal sewers are not laid and there is no

facility to convey and treat the sewage in the public sewage treatment plants.

For the satisfactory functioning of septic tanks, adequate water supply is essential.

Water containing excessive detergents and disinfectants are unsuitable for treatment of

septic tanks and should not be allowed to enter in septic tanks. Septic tanks are should

not be located in swampy areas or areas prone to floods.

Disposal of effluent

As the effluent from the septic tank is highly odorous, it should be disposed off carefully.

It can be disposed off in the following ways.

It may be disposed off through underground trenches. If the soil of underground

trench is porous it is best as the effluent will be absorbed by it.

Gardening. After proper treatment, this effluent may be used for gardening.

Soak pits. A soak pit is a hollow circular or rectangular pit. It is lined from 1.2m to

1.8m or more depending on the situation. The effluent falls in the pit and is allowed

to be absorbed by the surrounding soil. The pit may be filled with brick bats etc.

Page 80: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

80

DESIGN ASPECTS OF THE SEPTIC TANK

1. Capacity: The volume of septic tank can be decided on the following two

considerations.

a) By the consideration of quantity of flow and the detention period. The volume per

head may be kept from 57 to 85 lit.

b) It can also be designed on the per capita flow, which varies from 60 to 110 litres

per person per day to be served by the tank. The space for sludge usually is kept

at the rate of 15 to 45 litres per capita per year.

2. Detention Period: detention period varies from 12 to 72 hours. The common period

is taken as 24 hours.

3. Free board: 40 to 60cm free board is sufficient.

4. Shape of tank: generally septic tanks are designed as rectangular, with length to

breadth ratio as 1:2 to 1:4.

5. Height: Height of septic tank may be kept from 1.8m to 3m. The height for smaller

septic tanks may be kept as 0.9m. The dimension of septictank depends on the

number of users.

CONSTRUCTION OF SEPTIC TANK

1. The materials of construction of septic tank should be corrosion resistant.

2. The construction of septic tank should be such that no direct current is established

between inlet and outlet. This is achieved by providing baffle walls near the inlet and

outlet ends. The level of outlet should be about 15cm lower than the inlet.

3. Septic tank should be properly ventilated by means of air vent pipes.

4. The top cover of septic tank usually is made of RCC. A man hole is also provided in

RCC slab for inspection and cleaning it. Cast iron steps may also be provided to

facilitate the descending down in the tank.

5. The sludge is allowed to accommodate at the bottom of the tank and can be

removed either manually or by pumping at desired interval of 6 month or 1 year.

6. At the start of working of the tank, it should be filled with water. Effluent of the tank

should be disposed off properly.

7. A septic tank combines the function of a sedimentation tank, a sludge digestion tank

and a sludge storage tank.

8. A septic tank should be cleared every 6 to 12 months as the deposition of sludge at

the bottom decreases its capacity. But the period of clearance should not be more

than 3 years in any case.

Page 81: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

81

Recommended sizes and capacities of septic tanks

(Number of users less than 50) IS – 2470 (small capacity)

No. of

users

Length Breadth Liquid depth for cleaning interval of

Liquid capacity for cleaning

Sludge to be removed for

cleaning interval of

Depth of sludge to be

withdrawn for cleaning

interval of

Lm

Bm

6 M

th m

1 y

ea

r m

2 y

ea

r m

6 M

th

m3

1 y

ea

r

m3

2 y

ea

r

m3

6 M

th

m3

1 y

ea

r

m3

2 y

ea

r

m3

6 M

th

m3

1 y

ea

r

m3

2 y

ea

r

m3

5 1.5 0.75 - 1.0 1.05 - 1.12 1.18 - 0.36 0.72 - 0.32 0.64

10 2.0 0.90 - 1.0 1.40 - 1.80 2.52 - 0.72 1.44 - 0.40 0.80

15 2.0 0.90 - 1.3 2.00 - 2.34 3.60 - 1.08 2.16 - 0.60 1.20

20 2.3 1.10 1.1 1.3 1.80 2.53 3.30 4.55 0.72 1.44 2.88 0.28 0.57 1.14

50 4.0 1.40 1.0 1.3 2.00 5.60 7.28 11.20 1.80 3.60 7.20 0.32 0.64 1.28

Note : A provision of 30 cm. should be made for free board.

Recommended sizes and capacities of septic tanks

(Number of users more than 50)

No. of users

Length Breadth Liquid depth for

cleaning interval of Liquid capacity

for cleaning

Baffle m

L m B m Yearly or

less m Two yearly

m

Yearly or less

m3

Two yearly

m3

For Housing Colonies

100 8.0 2.8 1.0 1.04 22.4 23.3 5.3

150 10.6 2.8 1.0 1.15 28.6 32.9 7.1

200 12.4 3.1 1.0 1.15 38.4 44.2 8.3

300 14.6 3.9 1.0 1.15 56.9 66.5 9.7

For Hostels and Boarding Schools

50 5.0 1.6 1.3 1.40 10.4 11.2 3.3

100 5.7 2.1 1.4 1.70 16.8 20.4 3.8

150 7.7 2.4 1.4 1.70 25.8 31.4 5.2

200 8.9 2.7 1.4 1.70 33.6 41.0 6.0

300 10.7 3.3 1.4 1.70 49.5 60.0 7.2

Page 82: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

82

Recommended methods of septic tank effluent disposal

Soil and sub-soil conditions

Sub soil water level

Porous soil with percolation rate not

over 30 mm

Porous soil with percolation rate over 30 and below 60 mm

Dense and clay soils with percolation rate

over 60 mm

Within 1.8 m from ground

Dispersion trench located partly or fully above ground level in a mound

Dispersion trench located partly or fully above ground level in a mound

Biological filter located partly or fully above ground with underdrains and effluent laid to surface drain or gardening

Beyond 1.8 m Seepage pit or dispersion

Dispersion trench Subsurface biological filter with underdrains and the effluent laid to surface drain or gardening

MANHOLES

The straight lines between manholes are limited in length to 30 metres for sewers up to

300 mm dia. where manual rodding is adopted. For large sewers, they may go up to 100

metres or more. Manholes are also necessary at every junction, change in size, grade

and depth of sewer.

It is construction, provided to connect the ground level with the opening made in the

sewer line, to enter a man in the sewer line easily and safely to carry out the usual

maintenance and inspection of the sewer line. Man holes are provided to carry out

inspection, cleaning and maintenance of sewer lines. Man holes also allow joining of

sewers of changing of direction or changing of alignment or both.

LOCATIONS

Man holes are provided on straight sewer lines at intervals depending upon the

diameter of the sewer line. For sewer line having diameter up to 50cms, the interval

usually is kept as 75m. For sewer lines having diameter of 90cms, the distance is kept

as 120m, for sewers of 150cm diameter the distance is kept as 250m, sewers having

diameter more than 150cm, the distance may be 300m or more. For larger sewers the

distance may be more as a man can enter the sewer for inspection. Man holes are also

provided at every bend, junction, and change of diameter of sewer line. Change of

gradient etc. as far as possible sewer line between two man holes should be laid

straight with even gradient.

Page 83: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

83

Classification of man holes

Man holes may be classified as follows:

a) Shallow man holes: These man holes are constructed at the beginning of branch

sewers or places not subjected to heavy traffic. These man holes are also known

as inspection chambers. The depth of such man holes varies from 0.75 m to 0.9m

and size 0.75 X 0.75m. It is approved with light. A cover at top is provided.

b) Normal Man Holes: The depth of such manholes may be about 1.5m. It‘s size may

be 1.0 X 1.0m or 0.8 X 1.0m. It is of rectangular or square in shape. Its section is

not reduced. It has heavy cover at top.

c) Deep Manholes: the depth of such man holes may vary from 1.5m to 2.0m and its

section 1.2 X 0.9m rectangular or 1.4m diameter with heavy cover at top. Fig shows

a deep man hole with intercepting trap. Its size is reduced and offset is constructed

of brick masonry or cement concrete.

PRINCIPLE OF DESIGN

a) A man holes should be structurally strong. Stable to resist all forces likely to act on

it.

b) It should be safe for workers to enter in it.

c) The walls and floor of man hole should be impervious. The surface of walls should

be cement plastered.

d) The man hole should not be an obstruction for the smooth flow of sewage and

should not unnecessarily become a source of foul gases.

e) In case the inlet and outlet of the sewers are of different diameters, then the crown

of sewers should be kept nearly the same level by giving required slope in the

invert of the manhole chambers. If this precaution is not taken then the smaller

sewer will get back flow while larger sewer will run full.

Steps or ladder in man holes

The steps should start about 40cm below from ground or road level and upto 30cms

height from bottom level of man hole. Figure shows man hole with steps, section and

plan

Walls

Walls of man hole may be made of brick, stone masonry or cement concrete. Usually

brick walls are very common. The thickness of wall should not be less than 20cm. The

brick wall thickness may be found out from the following rule

Page 84: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

84

t = 10 + 4d

Where,

t = wall thickness in cm

d = depth of excavation in meters

Cover to man holes

The weight of cover and frame of light duty and medium duty traffic should be as

follows. Further the cover should not create noise on passing vehicles over it. If it makes

noise, it should be attended and its seal should be replaced.

APPROXIMATE WEIGHT OF MANHOLE FRAME AND COVER

Clear opening mm Grade designation Approximate weight in kg

Light Duty 450 X 450 mm

600 X 450 mm

600 X 600 mm

18 – 31

26 – 38

32 - 57

34 – 43

37 – 51

60 – 75

Medium Duty 500 mm dia

600 X 450

600 X 600

102

142

178

-

-

-

DROP MAN HOLES

An opening constructed to connect a high level branch sewer to low level main sewer

with minimum disturbance is called a drop man hole as shown in fig.

FUNCTIONS OF DROP MAN HOLE

A drop manhole serves the following functions:

1. We know that a main sewer usually is laid at greater depth below ground level and a

branch sewer situated near the ground level. Thus to join the branch sewer with

main sewer, construction of drop manhole avoids unnecessary steep gradient of the

branch sewer and thus reduces the quantity of earth work.

2. Construction of drop man hole allows the discharge of branch sewer to fall at the

bottom of the man hole and avoids the possibilities of sewage being falling on the

person who enters the chamber of man holes for inspection.

Maintenance of sewers

For efficient and proper working of sewer lines, their proper maintenance is essential. All

sewer lines are liable to corrosion, erosion and deterioration. Maintenance of sewers

Page 85: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

85

mainly consists of removal stoppages, cleaning of sewers and other sewer

appurtenances and repair work. Maintenance of those sewers is costly which are laid on

flat slopes as they are more prone for heavily clogged by the entrance to tree roots

through faulty joints are costly to maintain.

Cleaning of clogging, sewers due to silt, grease and oily materials are one of the major

problems of maintenance of sewer line. It is also most costly operation. Major causes of

cleaning a sewer line are their breakage, clogging and odours. The breakage of sewer

may take place due to poor foundation, excessive super imposed loads, impact due to

vibrations etc., and the corrosive matter of sewerage eats away slowly the material of

the sewer resulting in its failure or breakage.

The clogging mainly occurs in small sized sewers, where a man cannot enter into them

to clean. The clogging may be due to the deposition of sand, silt, grit and waster

building materials and ashes etc., It may also be caused by the deposition of grease

and oily materials contributed by hotels, garages, soap industries etc., Odours in sewers

is developed due to the decomposition of organic matter present in the sewage. Thus it

is essential to clean the sewer line.

For good maintenance of sewer system, its uptodate plans showing location of

manholes and other appurtenances, direction of flow, house sewers and grades of

sewer line etc.., should be available. Before starting actual cleaning and repair work, the

inspection of the sewer line and its appurtenances must be carried out. In some cities

inspection and maintenance works are carried out when difficulties arises, where as in

some cities inspections and repair works are carried out periodically as per schedule.

The period of inspection generally followed is as follows:

1. Sewers on flat grades ……………… ………………………………3 months

2. Sewers not likely to be affected by tree roots……………………….3 months

3. Trouble free sewers……………………………………………… ….6 to 12 months

4. Intercepting sewers…………………………………………………..1 to 4 weeks

5. Flushing tanks………………………………………………………..1 month

6. Storm water over flows……………………………………………during rains only

CAUSES OF DAMAGES TO SEWER

Main causes of damages to sewers are as follows:

o Use of poor quality materials and bad workmanship.

o Excessive super imposed loads and faulty design.

Page 86: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

86

o Settlement of foundation due to low bearing capacity of soil.

o Small soil covers on the crown of the sewer to withstand the shock, impact,

vibrations due to moving vehicles.

o Explosion inside the sewer due to improper ventilation of the explosive gases

developed inside the sewer.

o Abrasion of sewers due to grit, sand etc., flowing with the sewage and corrosion of

sewer pipe due to the corrosive gases which eat away the sewer material resulting

in its breakage.

PROBLEMS OF SEWER MAINTENANCE:

Following are the main problems of sewer maintenance:

Clogging of sewers

1. Clogging of silt, grit or other such material cause stagnation of sewage causing to

decompose organic matter present in the sewage, producing poisonous gases and

unpleasant odour in the sewer. The oily and greasy matter from the discharge of

hotels kitchens, garages, soap factory‘s etc. deposited on the side of the sewer,

reducing its cross section, which in course of time clog the sewer.

2. Penetration of tree roots through faulty joints or cracked sewer pipes choke the

sewer.

3. Growth of fungi forms a network of tendril which floats on the surface of the sewage

and obstructs its free flow.

4. Stagnation of sewage in sewers due to improper working of pumping units leads to

the settlement of grit and other materials and dumping of solid waste in the man hole

clogs the sewer line.

HAZARDS

The staff engaged in the operation and maintenance operations of the sewerage system

is exposed to the different kinds of hazards such as physical injuries caused by

chemical and radioactive wastes, infections caused by pathogenic bacteria present in

the sewage, damages from explosive vapours and oxygen deficiency. These hazards

can be minimized to a great extent by adopting suitable safe guards at the time of

designing sewers, their appurtenances and pumping stations. Hazards at the time of

maintenance stilt can be reduced by using safety equipment and taking precautions

against likely hazard. Maintenance work should be supervised and executed by trained

persons.

Page 87: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

87

As stated above also, sewerage contains high percentage of carbon dioxide, methane,

hydrogen sulphide, hydrogen and low percentage of oxygen. The main hazard is due to

the presence of high level of methane forming an explosive mixture or oxygen deficiency

or hydrogen sulphide excess of permissible limit gases like ammonia, chlorine and

sulphur dioxide are also found in the sewer and man holes.

When gases like nitrogen, methane, and hydrogen breathed in high concentration act

mechanically by excluding oxygen. When carbon monoxide inhaled, combines with the

has of the blood, either prevents oxygen from reaching the blood or its tissues or

prevents tissues from using it. Chlorine is an irritant substance which when inhaled

injures the air passage and lungs and produces inflammation on the surface of the

respiratory tracts.

PRECAUTIONS AGAINST HAZARDS

Before entering a manhole for inspection and cleaning an obstruction in the sewer, it

should be ensured that the sewer and manhole is free from all injurious gases and

vapours. Following precautions should be taken before entering a manhole either for

inspection or cleaning the obstruction.

No smoking should be allowed inside the manhole or sewer. No flames and sparks

should be allowed near the manhole.

While cleaning the sewer, traffic warning sign board should be placed on road near

the work.

In the manhole safety explosion proof electric lighting equipment or light reflection

mirrors should be used.

Atmosphere should be tested for the presence of noxious gases and oxygen

deficiency.

When the atmosphere is normal, the worker should enter the manhole or sewer with

safety equipment and two persons should be deputed at the top for emergency help.

In case oxygen deficiency or presence of noxious gases is detected, emergency or

forced ventilation should be restored using portable blowers.

In case, forced ventilation is not possible and workers have to enter into the sewer in

emergency then they should wear the gas mask and carry only the permissible

safety and should wear rubber shoes and non-sparking tools should be used.

Only the experienced persons fully equipped with safety equipment should be

allowed to enter the sewer in such conditions.

Page 88: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

88

SAFETY EQUIPEMENT

Usually following equipment is used by workers connected with sewer maintenance:

1. Gas mask: A gas mask consists of face cloth, small cylinder (canister) containing

purifying chemicals, a timer for indicating duration of service and a support piece.

The gas mask provides necessary respiratory protection against organic vapours,

acid gases, and carbon monoxide upto 2%. Concentration, toxic dust fumes and

smokes. However they cannot be used in oxygen deficient atmosphere or

unventilated locations etc.

2. Oxygen Breathing Apparatus: This apparatus protects the workers fully against all

gases, vapours, dust, smokes, oxygen deficiencies etc. This is a dependable device.

3. Portable Lighting Equipment: portable hand lamps of permissible type as

explosion air blowers may be used.

4. Non Sparking Tools: During sewage maintenance works, tools made of alloy

(containing at least 80% copper) should be used as they will not produce spark

when struck against other objects and metals.

5. Portable Air Blowers: To provide forced ventilation in man holes, tanks etc.,

portable air blowers may be used.

6. Inhalators: These are used to bring back to consciousness drowned or electric

shocked or collapsed persons. It contains a mixture of oxygen and carbon dioxide.

Carbone dioxide used in small percentage stimulates deep breathing, so that more

oxygen should be used only when the collapse of persons has occurred due to

chlorine or hydrogen sulphide gas known as irritant gas.

7. Safety Belt: This belt is consisting of a body belt with a buckle and shoulder

harness or device. The life line is of a steel cable or high quality manila rope,

anchored with safety straps for securing to a stable support. The length of life line

should be 15m and it should be capable to withhold a load of 2000 Kg. The safety

belt and life line should be tested daily before use.

SEWERAGE CLEANING

The cleaning of large sewers is done manually. The worker enters the sewer through

man hole and scrapes the sides with tools carried for this purpose. The bottom is

cleaned of rubbish and collected at the platform of manhole. This scraped material is

taken out through man holes. All necessary precautions as stated above should be

taken when entering the sewer.

Small sewers are cleaned by flushing with the help of automatic flushing tanks. The

automatic flushing tank is installed on the sewer line and a fire hose with nozzle is

Page 89: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

89

inserted in the sewer. Water under pressure is discharged through the nozzle to clean

the sewer. When flushing is found inadequate to clean the sewer other methods are

employed to clean the small sewers.

METHODS OF SEWER CLEANING

Following methods may be employed for this purpose.

a) Flexible Rod

A flexible rod about 30m length is inserted into the sewer and pushed to forward and

backward. The movement of the rod dislodges the obstruction, which is removed easily

by flushing. In place of flexible rod a steel tape may also be used. The steel tape may

be 3mm thick and 20mm to 50mm wide. This method is found useful for small sewers

where a man cannot enter the sewer.

b) Use of Balls (Pills)

In this method balls made of wood, hollow metal balls or rubber balls covered with

canvas are used. A small ball is put in the man hole above obstruction. The ball floats in

the sewage and when it comes in contact of the obstruction it is caught there and blocks

the passage of sewage. Thus sewage starts collecting there behind the obstruction

raising the head up stream side. When the sufficient head is developed, it exerts a force

on the obstruction and dislodged obstacle flows with the sewage. The ball is collected in

the next manhole. Then a ball slightly larger diameter than the previous one is used and

the process is repeated. A ball having diameter about 25mm less than the diameter of

the sewer passes easily from one manhole to the other.

Now days some improved version of this method has been adopted. The balls used

generally are made of rubber, which can be inflated upto varying degree of inflation. The

balls are available from 150mmto 750mm in diameter when fully inflated. For cleaning

the sewer, the ball is inflated and covered in a canvas cloth and the edges of the cloth

are sewed together. A trail line little longer than the distance between two man holes is

attached to the covering cloth securely. The size of inflated ball with cover should be

such so that it may fit into the sewer tightly.

Immediately after placing the ball in the sewer, sewage starts heading up in the

manhole till the pressure developed is sufficient enough to force sewage under the ball

and moving it to down steam side. The ball acting as compressible floating plug, affords

enough obstruction to produce a continuous high velocity jet of sewage under the ball

Page 90: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

90

and to some extent around it moving the material ahead to the next manhole. If the ball

encounters an immovable obstruction, it indents as per need and moves forward. By this

method bricks, bottles, broken pieces of pipes, gravel, sand etc. can be moved ahead

easily and collected at man holes and removed manually outside. When the ball stops

momentarily, a pull is exerted on the trail line to set the ball in motion again.

3. Use of portable pump set

These pumps are used to clean the sewer in situations where sewers are blocked

completely and sewage has accumulated in man holes. These pumps should be self-

primed and non-clogging type.

4. Sectioned Rods

These rods are used for cleaning small sewers. These rods may be of bamboo, teak or

light metal of about 10m length. At the end of these rods a coupling is attached which

remains intact in the sewer but can be taken out or disjoined easily at manhole.

Sections of rod are pushed in sewer line till the obstruction is reached and dislodged. To

cut and remove the obstacle, the front edge of the rod is fitted with a cutting edge.

These rods may also be used to locate the obstruction from either manhole.

5. Use of Sandwiched flexible rods

Such flexible rods are used for routine sewer cleaning work. This type of rod is made by

sandwiching a manila rope between bamboo strips and tying at short intervals. The end

of this rod is tied with a thickness rope.

The flexible rod is lowered into the manhole by a person standing on top, while another

worker inside the manhole pushes the rood into the sewer in the direction of flow. As

soon as the end of the 60m rod is thrust into the sewer it is connected to a thick manila

rope. The worker deputed in the next downstream manhole receives the end of the rod

and pushes it out of the manhole.He catch holds the manila rope end and drags through

the sewer. This manila rope is got coiled at the drawn out of the sewer into the

downstream manhole, from where it is taken out manually. Now the process is repeated

for the next section and continued till the full sewer line is cleaned. Along with cleaning,

other repairs inside the manhole, footsteps etc., can do simultaneously.

6. Use of ferret and fire hose

Fire hose is attached to the fire hydrant and the nozzle of the hose pipe is inserted into

the sewer through manhole. This method is used for breaking and removing sand

Page 91: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

91

blockade. From the fire hydrant a high velocity jet stream of water is sent towards

upstream and downstream side of the sewer. The forward stream loosens the

accumulated sand debris ahead of the ferret tool and the rear jets of ferret admit water

to wash the sand back to downstream. This sand can be removed from the next

manhole manually.

7. Sewer Cleaning Bucket Machine

This machine consists of two power driven winches and a cable between them. For

cleaning a section of the sewer the winches are placed over the two adjacent manholes.

Cable from one which to the other has to be taken through the sewer line by means of

sewer rods. The cable from the drum of each winch is tied or fastened to the barrel on

each end of an expansion sewer bucket. This bucket is also fitted with a closing device.

This bucket can be pulled in either direction by machine on the appropriate end. The

bucket is pulled into the loosened material of the sewer till it is full with the debris. Now

the motor is thrown out of gear and appropriate winch is operated. On the application of

opposite pull, the bucket automatically closes and the debris is put in a truck or trailer.

This operation is repeated till the sewer line is clear. This machine can also be used with

other scraping instruments for loosening sludge banks of detritus or cutting roots and

removing obstruction from the sewer line.

8. Roding Machine With Flexible Sewer Rods

This machine consists of a flexible rod to which the cleaning tools are attached. The

flexible rod consists of a number of steel rods with screw couplings. The flexible rod is

guided through the man hole by vent pipe. The rod is rotated by the machine with the

help of a tool attached to one end. The rotating rod is pushed manually into the bent

pipe with clamps having long handles, holding the rod near the cleaning the obstruction,

rod is pulled out by means of clamp keeping the rod rotating which facilitates the quick

and easy removal of the obstruction.

9. Sewer Scrapers

For sewer of more than 750mm diameter scraper is used for cleaning the sewer. It

consists of wooden planks assembled in the sewer shape of slightly smaller size than

the cleaned. The scrapper can be assembled outside and lowered through the man

hole. If it is not possible to lower it through the man hole, then it can be assembled in

the man hole. The scrapper chain is attached to a central chain in the man hole where it

is lowered. Now this chain is connected to a winch on the next downstream man hole by

means of a chain.

Page 92: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

92

Now the winch is operated to push the debris ahead of the scraper. The heading up of

the flow behind the scraper also helps in pushing the debris in the forward direction. The

movement of the scraper ensures the thorough cleaning of sides and bottom of the

sewer. The scraped debris can be removed manually from the sewer through man

holes.

10. Dredger

Dredgers are used for cleaning large diameter sewers. The system consists of a crane

pulley block and grab bucket. The grab bucket is lowered into the sewer with the help of

pulleys. The bucket is dragged in the opposite direction of the flow. In this operation, the

bucket scrapes the bottom deposits. The bucket is raised when it is full of debris to fall.

The bucket is brought on the ground over the truck, where the bucket opens and drops

the debris into the truck automatically. However a dredger cannot clean the corners

deposits of the man hole.

11. Flush Bags

In situations where rods cannot be used for cleaning the small sewers, this method has

proved a very effective tool for cleaning the sewers. The flush bag is a rubber or canvas

bag. At one end of this bag a fire hose coupler is attached while on the other end a

reducer. The flush bag is connected to the fire hose and is placed on the downstream

side of the chocked location. The bag is allowed to fill with water till it expands and seals

the sewer fully. Due to the blockage of sewer, water heads up on upstream side and

creates water pressure and breaks the obstruction. Pressure should not be allowed to

develop so high, which may cause the flow of sewage back into the hose connections or

break the sewer or its joints.

12. Sewer Scooter

This is an improved version of the scrapper method and consists of two jacks, a

controlling rope and a scooter with a light shield. The scooter completely stops the flow

of sewage. The scooter is attached to the control rope and lowered into the sewer line

through the man hole. The downstream manhole jack is lowered into place from the

road and the upstream manhole jack is set across the top of the manhole.

When the scooter is lowered into the sewer, it stops the flow of sewage and builds up a

head behind the shield. The resulting pressure makes the scooter to move through the

sewer till it accumulates enough debris to stop its movement. The head is allowed to

Page 93: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

93

build upto 1.0 m of water approximately, before the control rope is pulled to fold back

the shield to allow the accumulated sewage to gush to the downstream flushing the

sewer debris to the next man hole. Now again the control rope is released, cleaning the

shield against sewage and causing the scooter to advance further till the debris stops its

movement. The process is repeated till the scooter reaches the downstream man hole,

where it can be taken out or allowed to continue through the next section.

Preventive Maintenance

The clogging of sewer may be prevented by periodical removal of silt etc. from the

sewer line and repairs of manholes. Sewer maintenance gang should work under the

supervision of a competent and experienced person well trained in the use of necessary

tools and equipment.

Cleaning of catch basins or pits

Catch pits are provided for collecting storm water and should be cleared after every

storm. Catch pits contain silt, sand and debris etc. Water contained in catch pits may

become the breading place of mosquitoes. The traces of organic matter in the silt of

catch pits will give unpleasant odour. The oil and grease traps should also the

periodically cleaned to avoid nuisance due to unpleasant odour.

PERIODICAL REPAIRS

To prevent the heavy damage and deterioration of the sewers, periodical repairs are

necessary. The sections of sewer which need repairs should be marked during the

inspection and they should be attended immediately. Usually following repairs are

required.

1. Brick Sewers: Brick sewers require frequent repairs of the following elements;

a) Pointing of joints and replacement of fallen arch bricks.

b) Plastering and painting of manholes.

c) Replacement of manhole frames and covers which that have worn out or broken

and have become noisy.

d) Replacement of broken or cracked and crushed portions of pipe.

e) Raising or lowering the manhole heads to keep them flush with the road level

due to change in roads and street levels.

f) Tightening of manhole covers which have become loose and give noise under

the vehicular traffic.

g) Replacement of broken pipes.

Page 94: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

94

h) Re construction of damaged house connections etc.

i) Repair of defective house sewer connections and street sewers.

j) The ventilating shafts should be checked frequently to ensure their proper

functioning.

k) The joints of lateral sewers with branch sewers should be made water tight

periodically.

EXPLOSION IN SEWERS

If the sewers are not properly ventilated, there are chances of occurring explosions in

the sewer lines blowing manhole covers into the air. The main cause of such explosions

is the presence of combustible gases produced due to the presence of gasoline,

methane gas, neptha, grease solvents etc, These materials come to the sewer line from

the discharges of filling stations, garages, chemical industries etc. Calcium carbide may

also causes explosion in sewer line.

Precautions to be taken before entering into the sewer line:

Before entering a sewer line, the workers should take the following precautions.

a) The covers of at least three consecutive man holes should be opened at least one

hour before entering into the sewer line.

b) Before entering into the man hole, a burning candle should be lowered into the man

hole to check the presence of explosive gases. If there are explosive gases, an

explosion will takes place, giving a warning to the workers.

c) Only Electric lamps or dry cell torches should be used inside sewer line for light.

d) The presence of hydrogen sulphide gas may be detected by lowering a wet lead

acetate paper inside the manhole.

Flushing Tanks

Located at the head of sewer. They are designed for 10 minutes flow at a self-cleansing

velocity of 0.6 metre / sec.

Capacities : 150 mm sewer – 6400 litres

200 mm sewer – 11000 litres

250mm sewer – 18000 litres

The capacity of these tanks is usually 1/10 of the cubic capacity of the sever length to

be flushed.

Page 95: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

95

Ventilating Shafts

Usually provided at first manhole and at intervals of 180m.

INFORMATION MANAGEMENT

The flow of information between and within the water supply and surveillance agencies

is necessary to maximize the quality of service to consumer and protection of public

health. The report provided by the surveillance agency to water supply provider should

include.

1. The summary report of condition of water supply and water quality analyses

2. Highlight those aspects which are considered inadequate and needs action.

3. Recommendation of remedial action in case of emergency

The report should not be limited to complain about failures but the water supply and

surveillance agencies should coordinate their activities to ensure good quality of water

to on public health criteria. If consistently, unsatisfactory results are reported in a

particular area, the cause for the same should be investigated and remedial measures

taken, such as repair of leakage, replacement of corroded and leaking consumer pipes

etc.

Local laboratory under surveillance agency should maintain details field reports

regarding inspiration and water analysis of all water supplies available in the area. It

should include the results of all inspection and analysis. The local surveillance office

should report to the relevant supply agency as soon as possible after field visits. The

information should also be passed on to regional authorities to allow follow – up; if

recommendations for remedial action are not implemented. However, there must be a

repair means of reporting in case of emergency.

COMMUNITY BASED MONITORING AND SURVELLLANCE

Community participation is an essential component of the monitoring and surveillance

framework. As the primary beneficiaries community can play an important role in

surveillance activity. They are the people who may first notice the problems in water

supply and report it to concern agency or taken remedial action if possible. Establishing

a genuine partnership with the community creates a climate of trust and understanding,

which generation interest and enthusiasm. It also provides a good foundation for other

education activities such as promotion of good hygiene practices.

Page 96: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

96

The community based monitoring and surveillance can be carried out in two ways:

1. Selection of community volunteers, including woman, to undertaken surveillance

activity after training.

2. Providing encouragement to local worker to carry out certain jobs pertaining to

surveillance.

In both the cases, preliminary training is necessary for field workers to identify sanitary

hazards associated with the water supply, as well as regarding reporting system.

Department or water supply agency should help in providing necessary training while

community water committee health committee can supervise the work. The community

participation includes.

Assisting field workers in water sample collection, including sample location points,

existing damage networks, casing /likely to cause contamination of drinking water.

Assisting in data collection.

Monitoring water quantity, quality and reporting findings to surveillance staff

regularly.

Ensuring proper use of water supply.

Setting priorities for sanitation and hygiene and educate community members.

Undertake simple maintenance and repair work.

Refer problems which require special attention.

Disseminate results and explain the implication with respect to health with the

objective to stimulate involvement in action to keep water clean, safe and

wholesome.

SURVEILLANCE ACTION

Surveillance action comprise of:

1. Investigation action to identify and evaluate all possible factors associated with

drinking water, which could pose a risk to human health.

2. Ensure preventive action to be taken to prevent public health problem.

3. Data analysis and evaluation of surveys.

4. Reporting to concerned authorities.

SANITARY SURVEY

Sanitary survey is an on-site inspection and evaluation of all conditions, devices and

practices used in waste supply system, which pose an actual or potential danger to the

health and well-being if consumer by trained persons. It is a fact –finding activity, which

identifies actual sources of contamination as well as point out inadequacies in the

system that could lead to contamination.

Page 97: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

97

The two important activities of sanitary survey are sanitary inspection and water quality

analysis; which are complementary to one another. The inspection identifies potential

hazards, while analysis indicates actual quality of water and intensity of contamination.

SANITARY INSPECTION

Sanitary inspection covers the inspection of water system, including source,

transmission mains, treatment plants, storage reservoirs and distribution system.

Basically it is a fact –finding review to uncover deficiencies and inadequacies, which

could lead to contamination of water. Sanitary inspection is indispensable for the

adequate interpretation of laboratory results. It provides essential information about the

immediate and ongoing possible hazards associated with a community water supply. It

is an essential tool to pinpoint target areas for remedial action, required to protect and

improve the water supply system.

SANITARY INSPECTION REPORT

The sanitary inspection report shall cover the following:

1. Identify potential sources and points of contamination of the water supply.

2. Quantity the hazards attributed to the source and supply.

3. Provide a clear, graphical means of explaining the hazards to the operator/user.

4. Provide clear recommendation for taking remedial action, to protect and improve the

supply.

5. Provide basic data for use in systematic, strategic, and planning for improvement.

Moreover inspection report should not be restricted to water quality but should take into

account other services condition such as coverage, cost, condition and quantity. Such

surveys are important form the point of view of operation and maintenance. Annexure

9.5 shows suggested inspection forms for different water sources.

WORK CHART FOR SANITARY SURVEY

For collection of adequate information and follow –up work, proper work chart should be

prepared considering local requirement. Following should be taken care of:

1. Prior knowledge of source, and type of water supply; and map of distribution system.

2. Notify the visit in advance, where the assistance of community member is needed.

3. Carry prescribed forms and necessary accessories, like sample bottle, sample carry

box, analysis kit etc.

4. Verify basic data with community.

5. Interview community member for drinking water supply service.

Page 98: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

98

6. Verify information gathered by observation during survey.

7. Inspection and water sampling should not be haphazard, should follow specific

guideline.

8. Water sample should be analyzed immediately for residual chlorine and thermo -

tolerant coliform, or transported quickly to laboratory in iced boxes.

9. Complete the sanitary report on site, and send it immediately to appropriate

authority for follow- up remedial action if necessary.

10. Undertake appropriate small repairs at the time of survey in remote areas such as

washer changing for leaking taps.

11. For pictorial forms, each risk point should be circled and given to member of water

committee for followup action.

Page 99: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

99

WATER SUPPLY PUMPS

PUMPING MACHINERY AND PUMPING STATION

Pumping machinery and pumping station are very important components in a water

supply system. Pumping machinery is subjected to wear, tear, erosion and corrosion

due to their nature of functioning and therefore is vulnerable for failures. Generally more

number of failures or interruptions in water supply is attributed to pumping machinery

than any other component. Therefore, correct operation and timely maintenance and

upkeep of pumping stations and pumping machinery are of vital importance to ensure

uninterrupted water supply. Sudden failures can be avoided by timely inspection, follow

up actions on observations of inspection and planned periodical maintenance.

Downtime can be reduced by maintaining inventory of fast moving spare parts.

Efficiency of pumping machinery reduces due to normal wear and tear. Timely action for

restoration of efficiency can keep energy bill within reasonable optimum limit. Proper

record keeping is also very important.

Components in pumping stations

The components in pumping station can be grouped as follows.

i) Pumping machinery

- Pumps and other mechanical equipment, i.e. valves, pipe work, vacuum

pumps

- Motors, switchgears, cable, transformer and other electrical accessories

ii) Ancillary Equipment

- Lifting equipment

- Water hammer control device

- Flowmeter

- Diesel generating set

iii) Pumping station

- Sump/intake/well/tubewell/borewell

- Pump house

- Screen

- Penstock/gate

Operation & Maintenance of Electrical and Mechanical

components of Pumping Machineries in Water and

Wastewater Treatment Systems

Page 100: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

100

Type of pumps

Following types of pumps are used in water supply systems.

i) Centrifugal pumps

ii) Vertical turbine pumps

iii) Submersible pumps

iv) Jet pumps

v) Reciprocating pumps

Obviously due attention needs to be paid to all such aspects for efficient and

reliable functioning of pumping machinery. This chapter discusses procedures for

operation and maintenance and addresses pertinent issues involved in O&M of pumping

machinery and associated electrical and mechanical equipment.

Preventive and regular breakdown maintenance

Following procedure may be followed:

1. Internal mobilization.

2. Detection of pipe failure: Inspection of site

3. Notification of interruption in water supply and related issues.

4. Location and demarcation

5. Repair planning

6. Repair work: Selection of most appropriate method for repair.

7. Testing of ‗dry‘ repair.

8. Restoration

9. Completion

10. Hygiene

11. Notice of restoration and completion

SEWAGE PUMPS

Use of portable pump set

These pumps are used to clean the sewer in situations where sewers are

blocked completely and sewage has accumulated in man holes. These pumps should

be self-primed and non-clogging type.

Page 101: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

101

Sewage Pumps: Essential design features / criteria

a) The size of solid should not be greater than 80% of impeller outlet.

b) Casing and impeller should be of adequate size to allow free passage of specified

size of solid. Normal size of soil is 80mm, suction and delivery of the pump not less

than 100 mm.

c) Hand holes should be provided in the casing to allow early access to the impeller

eye and to close as possible as to the casing.

d) Provision should be made in stuffing boxes for the abrasive nature of sewage of

ensure clear water supply or grease Lubrication to the glands shall be provided

from external source.

e) For working out H.P., Sp. gravity 1.05 should be considered.

f) Material for impeller should be either C.I. or Stainless Steel.

Types of Pumping Installation

a) Wet well and dry well with horizontal centrifugal pump and motor at dry well.

b) Wet well and dry well with vertical dry pit pump and motor on upper floor driven by

line shafts.

c) Wet well installations with vertical pump mounted at bottom of floor and motor on

upper floor and driven by line shaft.

d) Submersible non-clog pump and motor set with chain-pulley block and pump motor

set sliding on guide rails/wires while removing. The arrangement is such that when

pump reaches bottom base, its delivery nozzle sits automatically on delivery pipe.

From maintenance, it is preferable to adopt installation (b) above, though it is costlier

than three installations. Recently, the installation (d) i.e. with submersible non-clog

pumps are introduced and becoming popular, in view of ease of removal, handling,

practically no maintenance and low civil cost.

Coarse Screen

It is a coarse screen with clear opening of about 40-50 mm is provided before admitting

sewage in the well. This is necessary as solid handling capacity of pump is usually

80mm.

Page 102: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

102

Installation of Pump

Foundation

Foundation, whether concrete or structural, steel should be heavy enough to afford

permanent rigid support to the full area of base plate absorb vibration, Shock and

normal stain.

Loads

Following loads should be considered

a) Constructional load i.e. foundation.

b) Three times total mass of pump.

c) Two times total mass of motor.

Design of supporting girder

Say constructional load Nil

Pump weight 2 ton

Motor weight 3 ton

Hence, total dynamic load = 2 x 3 + 3 x 2

= 6 + 6

= 12 tons

= 12000 kgf.

Say a pump is supported on two ISMBs with span of 4M i.e. 400 cm.

Max. Bending Movement at Centre = 4

WL= 12,00,000 kg./cm.

Permissible safe stress, f = 1500 kgf/cm2

Z Section modules = f

BM=800 cm3

Hence, Z for ISMB 250 as per steel table having Z = 410.5 cm3

Laying Suction Pipes

a) Suction pipes shall be at least one size above the suction size of the pump or

designed for velocity not exceeding 2 m/s.

b) Bends should be long, short bends should not be used.

c) Eccentric taper with top of taper in flat position be used. Concentric taper should

not be used.

d) The suction pipe should be straight or gradually rising. No portion of suction pipe

should be above suction nozzle of pump, which causes air-trapping and reduction

in discharge.

Page 103: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

103

Strainer / Foot Valve

Net area of opening in Strainer / Foot Valve should be at least 3 times entrance areas of

bell mouth or suction pipe.

Delivery pipe

a) Delivery pipe should be at least one size above delivery of pump or designed for

velocity not exceeding 2.5 m/s.

b) After pump delivery, non-return valve should be installed first and then sluice valve.

Recommended height of the pump house

A) For V.T. Pumps

i) Single floor pump house

Sl. No.

HP of Pump

Pump floor to corbel

top

Corbel top to roof slab

bottom

Pump floor to bottom of

roof slab Total

Lifting equipment

1 Up to 50 HP - - 5.5 m Monoralli

2 From 51 HP to 150 HP 5 m 1.5 m 6.5 m Hand operated

3 From 151 HP to 300 HP 5.5 m 1.5 m 7 m Crane

4 From 301 HP to 500 HP 5.5 m 2 m 7.5 m Electrical Operated

5 501 HP ad above 5.5 m 2.5 m 8 m Crane

ii) Double floor pump house

Generally, double floor arrangement shall be provided for the delivery pipes of

diameter 350 mm or above.

The height for pump house shall be as below.

Pump floor to Panel floor - 2.5 m

Panel floor to Corbel - 5 m

Corbel to bottom of roof slab - 2.5 m

B) For Centrifugal and submersible pumps

Sl. No.

HP of Pump

Pump floor to corbel

top

Corbel top to roof

slab bottom

Pump floor to bottom

of roof slab Total

Lifting equipment

1 Up to 150 HP - - 4 m Monoralli

2 From 151 HP to 300 HP 3.5 m 1.5 m 5 m Hand operated Crane

3 From 301 HP and above 4 m 2.5 m 6.5 m Electrical operated Crane

Page 104: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

104

Governments worldwide understand that adequate infrastructure is needed for

sustained economic growth and for reducing poverty. Infrastructure is also critical to the

provision of basic services such as water, electricity, sanitation, transportation,

education and health. Because of its importance, a substantial portion of government

resources have traditionally been allocated to meeting infrastructure needs - often

entailing significant public debt from both domestic and external sources. Despite the

positive externalities derived from infrastructure improvements, such debts are being

seen as a major economic burden by countries worldwide.

Public Private Partnership is becoming a popular alternative for the provision of

infrastructure services worldwide, not only for financial reasons but also because of

experience in demonstrating many other benefits of well executed PPPs.

PPP in the Urban Local Bodies Context:

According to the National Development Council (NDC), ―massive investments are

needed in infrastructure sectors such as power, roads, ports, airports and railways if

India is to be able to grow at 8 percent per year.‖ Moreover, the NDC has declared that

the total investment needs are so large that ―a substantial portion will be through public

private partnership in the form of BOT projects.‖

India at the national level, has already achieved important, albeit limited, private

investments in infrastructure. In order to attract the desired levels of new investments, a

concerted effort is needed to build upon this success and to replicate more successful

PPP transactions across sectors.

Public services need to remain committed to meeting current challenges, which may

demand a radical shift in culture and the way things have been done in the past. The

citizens apart from other stakeholders of the society including civic officials would have

to recognize an increasing need to become pro-active in problem solving, fund-raising

apart from securing best value for the citizens. Towards this end; embracing new culture

of openness, transparency, accountability and strong leadership are vital. Yet the

opportunities for wider scope, greater diversity and innovation also bring with them

several potential risks, pitfalls and liabilities many of which may be all-together

unfamiliar.

PPP in Water and Wastewater Management

Page 105: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

105

Given the country‘s growth aspirations and the current inadequacies of infrastructure

which are sought to be overcome by the centrally administered schemes viz. Jawaharlal

Nehru National Urban Renewal Mission (JNNURM), Urban Infrastructure Development

for Small & Medium Towns (UIDSSMT), Basic Services for the Urban Poor (BSUP),

Integrated IHSDP, these schemes are getting implemented at the level of the Urban

Local Bodies (ULBs).

In order to attract the desired levels of new investments, the ULBs need to build upon

this success and to replicate more successful PPP transactions across sectors. On its

part, the private sector has also shown much readiness to respond. The ULBs need to

foster speed, efficiency and transparency in the bidding process for the infrastructure

contracts to ensure sanctity of contracts, encourage competition, and promote market-

driven tariffs and separate regulatory and adjudication authorities.

While the technical knowledge housed among potential sponsoring entities even within

the Indian ULBs are strong, the conceptualizing, selecting, procuring and managing of

PPP-based projects by the ULBs in a consistent and effective manner requires a new

set of knowledge, skills and techniques, that are very different - and much more

complex - than traditional methods of infrastructure procurement.

PPP: Public – Private Partnership

In this both the public and private sectors play equally important role. Both share equal

responsibility and equal authority and they are in this entirely different and stand out and

cannot be compared to privatization ventures.

PPPs are vouched for as it –

Brings in financial and other benefits.

Is useful for infrastructure and other basic urban services

Proactive problem solving, fund raising

Public services to meet current urbanization challenges

Best value for citizen

Definition:

A PPP is an arrangement between a public (government) entity & a private (non-

government) entity by which services that have traditionally been delivered by the public

entity are provided by the private entity under a set of terms and conditions that are

defined at the outset.

Page 106: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

106

Public Private Partnership (PPP) Project means a project based on a contract or

concession agreement, between a Government or a statutory entity on the one side and

a Private Sector Company on the other-side, for investing in construction and

maintenance of infrastructure asset and / or delivering an infrastructure service.

The Need for PPP:

Economic reasons

- Inadequacy of resources

- leveraging on lower government funding

Optimal transfer of risks – to the entity best suited to manage the risks

– Design, Financing, Construction, Operations and Maintenance – all are

commercially understood and manageable

– Change of scope, defective designs, time overrun, cost overruns, leakage of

revenues, high maintenance costs

Transfer of responsibilities – efficiency gain

– Appropriate technology, innovative design solutions, project management, better

collection practices, and life cycle costing

What a PPP is not & what it is?

PPP is not privatization or disinvestment

PPP is not about borrowing money from the private sector.

PPP is more about creating a structure

– in which greater value for money is achieved for services

– through private sector innovation and management skills

– delivering significant improvement in service efficiency levels

This means that the public sector

– no longer builds roads, it purchases miles of maintained highway

– no longer builds prisons, it buys custodial services

– no longer operates ports but provides port services through world class

operators

– No longer builds power plants but purchases power

PPP Benefits

Benefits to people

– Better quality of service – National Highways, Telecom, Air travel

– Decreased user fees – Telecom and Air travel

Page 107: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

107

– Happy that Government using taxes not for salaries but for general public – High

tax payers

Benefits to private sector

– Return on investment – Paradise Island

– Business opportunity – Hotel Metropole, Mysore

– Long term involvement and guaranteed income due to lower market risk – BIAL

Airport

Other benefits:

Enhanced bankability – more rigorous project preparation

Incentive to deliver whole life solution – not just asset creation

Focus shifts to service delivery – integrated with construction, measurement of

quality & payment linked to service delivery

Acceleration of programme – time-bound implementation

Better overall management of public services – transparency in prioritization,

selection and ongoing implementation

Possible Areas for Urban PPPs

Solid Waste Management

Urban Transport

E governance

Outsourcing of municipal services

Urban renewal and regeneration (land and building redevelopment)

Development Authorities/Housing Boards

Urban roads and bridges

Heritage and Public space development

Water Supply

Sewerage, drainage, sanitation

And other sources including railway stations and airports

Some Examples – India

Solid Waste Management: Delhi, Bangalore, Chennai, Jodhapur, Sirsa

Urban Transport: Bus Terminal at Deharadun, Amirtasar

Public Transport: Indore Bus Transport System

Metro in Mumbai and Hyderabad: Versova, Andheri-Ghatkopar

Land & Building redevelopment-Urban renewal & regeneration: Bhopal and Gwalior

Page 108: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

108

Urban Roads & Bridges: Thiruvananthpuram city

Water Supply, Sewerage, Drainage and Sanitation: Tirupur Water Supply and

Sewerage Project, AlandurUrderground Sewerage Scheme, Desalination Plant at

Chennai

Key Projects in Karnataka

BIAL

HMRDC

MSW Treatment and landfill at Mavallipura

Madivala Market

Bangalore-Maddur State Highway

NICE Road

Hotel Metropole and Hotel KRS

Hotels &YatriNiwas across State

CSB to Karnataka Border – Elevated Expressway to E City

KUWASIP

Swachha Bangalore

MCC, Devanahalli

Page 109: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

109

CASE STUDIES

Annexure I

AUGMENTATION OF WATER SUPPLY SOURCE IN UDUPI CITY

Udupi city is located at western coastline of Karnataka having east longitude 74o-45‘ and

north latitude 13o-23‘. The city is connected by Konkan Railway and National Highway

No.17. Bajpe is the nearest airport located at a distance of 60KM. The municipality

celebrated its Platinum anniversary of formation of the council in this year 2010. The city

is having undulations; the RL varies from 0 to 103M. Because of the undulated

topography and the soil conditions the water table varies as high as 0.0M in the rainy

season and as low as 20M in the summer season. Near to the sea shore below 6M the

water contains traces of oil with sporadic turbidity which is not potable.

The Town Municipal Council came in to existence in 1935 was upgraded to City

Municipal Council in the year 1995. The CMC has 35 wards. Present population is

around 1, 25,000 and 17000 connections and 23000 households have been covered

under the scheme.

Situation before

Since from the formation of the

municipality in the year 1935,

(9.83Sq.KM area) the source of water

supply is ground water (Open well).In

the year 1971 a protected water supply

scheme to pump 9MLD of water was

executed with Swarna River as source.

In the year 1995 TMC Udupi became

CMC Udupi by merging five notified

areas which amounts to total area of

68.23sq.km.The water supply in these

notifiedareas was maintained by Village Panchayats by open wells and bore wells. The

total number of Open wells was 28 and Bore wells were 101and total water supply form

these sources is only 7.75MLD. The water supply system had 80Km distribution lines of

Figure: River Swarna

Page 110: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

110

diameter ranging from 50mm to 375mm PVC and CI pipes and covered only 15% of the

road length with maximum amount of leakage due to old PVC pipe network.

There used to be scarcity of water supply during summer due to inadequate water

availability in the open wells and bore wells as well as in Swarna River. Hence, water

was supplied through tankers to meet the basic demand of the town. The revenue

generated through water supply was very meager due to 8860 tap connections and

more than 236 public stand posts. Water storage facility was inadequate and there was

no Water audit, Energy audit & Recovery audit. Due to more number of public stand

posts there was an increase in percentage of Non-Revenue Water

Description of the initiative

The Udupi City Municipal Council (CMC) intends to take up the third stage of Swarna

River Drinking Water Project to cater to the increasing water demand in the city. At

present, drinking water is supplied to the city from the first and second Stages of

Swarna River at Baje and Shiroor, respectively.

The project was initiated by the KUIDFC and the preparation of detailed project reports,

construction supervision and quality assurance was carried out by M/s. Dalal

Consultants and Engineers Limited, Mumbai.

The Stage I of the dam was built at a cost of Rs. 25 lakhs; a loan amount provided by

the LIC of India in 1971 and is being repaid. The Stage II of the dam was built in 2004

and was supported by the Asian Development Bank (ADB).

The second stage works included lying of 650 km of water pipelines, building of two 25

lakh litres Ground Level Storage Reservoirs (GLSRs) in Manipal and building of a water

treatment plant. The cost of second stage was Rs. 60 crores.

The storage capacity of the Baje and Shiroor dams taken together is 520 million gallons

of water. The capacity of water treatment plant of first stage is 9 million litres a day while

that of the water treatment plant of the second stage is 27.4 million litres a day.

The project was kick started to achieve the following objectives.

To have an energy efficient and sustainable water supply system for the entire City

To augment existing storage capacity at source

To supply treated water by having water quality monitoring system

To reduce the quantity of Non-Revenue water in the system

To increase Water storage capacity

To increase in supply level from 62 lpcd to 135 lpcd for households

Page 111: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

111

To increase the number of hours of water supply with a residual head of 6M

Discouraging the public stand posts

Increasing individual house connections

100% metering for efficient revenue generation

To maintain entire water distribution system by gravity for energy savings

To have fully efficient distribution system including water and energy audit

The operation and maintenance works are carried out by the Udupi CMC. The water

demand up to 2026 AD was estimated along with augmentation of water supply source

from the nearby river ―Swarna‖ which is 14Km from the city. Construction of a dam,

intake well, jack well, water treatment plant of capacity 27.24MLD, seven new OHT‘s of

capacity 5Lakh and 10 lakhs liters, raw water MS raising main, clear water MS raising

main of 14 Km length, two Mother GLSR of each 25Lakhs capacity and 540Km HDPE

distribution pipe lines was carried out, which cover entire CMC area except ManchiKodi,

Manjusreenagar and Padukere area under KUDCEMP at a cost of 60Crores.

Operation and Maintenance

During the design and execution of the above said system, the topography of the city

was taken as an advantage in the following manner-

All the OHT‘s in the distribution system were filled by gravity flow from mother

GLSR.

The OHT‘s were constructed at strategic places which helped in formation of Zones

so that 6M of residual pressure is maintained.

Figure: Water treatment facility at Udupi

Because of the above facts there is a substantial savings of energy for CMC as well as

the consumers as they have stopped pumping water from sump to their overhead tanks.

Page 112: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

112

The Udupi CMC implemented the water quality monitoring system along with revision of

water tariff with respect to Kilo liter consumption. Water Adalats are conducted to

redress the grievances during transition period. The water supply in old distribution lines

was stopped and the number of public stand posts was reduced in a phased manner.

Setting up of 24/7 Public Grievance Redresser cell as well as online complaint

registration system in CMC‘s own web site is a success as the public can lodge their

grievances along with the leakage in the water supply network. Computerized billing

system is introduced and consumers are allowed to remit the bills in any of the

Branches of Syndicate bank in the CMC limits. Twice a week a special squad under the

leadership of AEE of CMC redress the consumer grievances illegal connections and to

take necessary actions.

Outcome and Importance

The system currently provides sufficient quantity of potable water with adequate

pressure. It has reduced the water contamination level very close to zero. There is

better cost recovery and lower production cost along with better Revenue management

due to 100% metering and customer satisfaction. Because of Reduction in NRW, CMC

is motivated to give Free Drinking water to the public by setting up water booths near

Bus shelters and also free connections for poor people which is appreciated by NGO‘s.

There is excellent consumer satisfaction with willingness to pay bills promptly motivated

the CMC to go for 24/7 water supply to the entire area .Eight neighboring

Gramapanchayat are given drinking water for their habitation with a reasonable cost.

Consumers are saving on electricity bills because of the residual head of 6M.

Figure: Water Production Cost

Figure: Energy Savings for the Consumers in Udupi

Page 113: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

113

Figure: Energy Savings for the Udupi CMC

Key learning

The system provides sufficient quantity of potable water with adequate pressure.

Better Revenue management due to 100% metering and customer satisfaction.

Energy Savings

Since distribution lines are of HDPE and connection are of electro fusion saddles,

less number of leakage problems registered

Sustainability

The system is 100% sustainable because the water source is the river and is perennial.

All project components are commissioned based on the long term operation and

maintenance standards. Water tariff restructuring and metering policy which has come

in to force since 2007 has ensured. The water wastage is negligible and O & M cost is

recovered.

Replicability

This system of augmentation of water supply source is a commendable practice and can

be replicated by the ULBs for the following.

Systematic Revenue generation.

Energy savings due to gravity flow and less water losses.

Regulation of Non-Revenue Water (NRW)

Recognition/Awards

Best ULB award 2010

Page 114: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

114

Costing

Particulars Details

Total Cost of the project The first stage dam built in 1971 across Swarna river = Rs. 25 lakhs

The second stage dam built in 2004 across Swarna river = Rs. 60 crores

Operation and Maintenance cost Rs. 5 crores /year

No. of staff employed 03

People/Officials met

Mr. ShashidharHegde

Junior Engineer, CMC, Udupi

Phone: +91 8722583095

Email:[email protected]

Design and Supervision Consultants

M/s. Dalal Consultants and Engineers Limited

44, KhannaConstr House, Dr R G ThadaniMarg,

Sea Face Road, Worli, Near Podar Hospital, Worli,

Mumbai, Maharashtra 400018

Phone:022 2581 0649

Page 115: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

115

Annexure II

REDUCTION IN NON-REVENUE WATER IN KUNDAPURA MUNICIPAL WATER

SUPPLY

Kundapura is prominent town in Udupi district and developing along the western coast

line of Karnataka. Town municipality was facing tremendous pressure to supply water

regularly to its citizens as the resources were limited. The municipality decided to fix this

issue by augmenting the supply and distribution network under Karnataka Urban

Development and Coastal Environmental Management project of KUIDFC. With the

change in the system, today the municipality is able to supply 24/7 water supply to few

zones and has drastically reduced its non-revenue water to 13%. The increased citizen

confidence has witnessed significant increase in revenue from the water charges.

Situation before

The Kundapura TMC

was established in

the year 1973. Since

then, the source of

water supply was

ground water. There

were 11 open wells

maintained by the

town municipal

council for supplying

the water to the

entire town. Water

was supplied from

these wells for drinking purpose without any treatment. The water quality was not

monitored by the municipality. Water from 11 municipalities owned wells was pumped to

the nearby OHTs located at various places within the town and then distribution used to

take place. In some parts of the town water was supplied through pumping water from 6

private wells directly.

In some parts of the town, water from open wells was pumped directly to the distribution

lines. The total quantity of water supply before the initiative was 0.6MLD with a supply

rate of 23 LPCD with a frequency of 2-3 hrs/day, which was practically inadequate.

Figure: Old System (some Open Wells)

Page 116: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

116

SI. No Location Type Capacity (Lakh Liters)/

Staging height (m)

1 2 3 4

Gandhi park Ferry Road

Maddugadde Ashraya Colony

OHT OHT OHT OHT

4.50 / 12m 0.50 / 12m 0.50 / 9m

0.50 / 12m

Table: The details of Elevated Service Reservoirs in the Old Scheme

The previous water supply system had 29km of distribution lines of diameter ranging

from 50mm to 200mm PVC and covered only about 60% of the road length. Most of

these lines were leaking and damaged. Also most of the valves were not functioning as

expected.

Severe water scarcity was faced in summers due to inadequate water availability in the

open wells, because of which water pressure could not be maintained constantly at all

times. Hence, the water was supplied through tankers to meet the basic demand of the

town. There were only 405 metered connections of which again most of them were

defunct and 1100 public stand posts. The tariff was Rs.45 for first 10KL and Rs.6 for

every additional KLs. Most of the meters were not working. The demand for water

supplied was calculated at a flat rate of @Rs.45.00/month/connection which is meager

amount compared to the expenditure incurred.

Figure: Tanker Supply

Description of the Initiative

The Kundapura Town Municipal Council an Urban Development Department jointly took

the initiative to improve the town water supply through augmentation. A new water

supply and distribution system was provided under Karnataka Urban Development &

Coastal Environment Management Project (KUDCEMP) to the ULB by Government of

Karnataka. KUIDFC was the funding agency to get the entire water supply work done.

The project in turn motivated to provide good quality drinking water (potable) throughout

the year to the entire town population. The project also intended to improve the income

Page 117: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

117

of the municipality for complete operation and maintenance of the new system. The

steps and measures mentioned in the activity chart had motivated municipality to go

ahead with the reduction in public stand posts and encourage in having the individual

metered connections and billing of water with respect to quantity consumed.

The KUDCEMP project came into existence with the following specific objectives to

completely improve the municipal water supply:

To have sustainable water supply system for the entire town

To identify a permanent source of water

To supply the treated water by having water quality monitoring system

To increase water storage capacity

To increase in supply level from 23 lpcd to 135 lpcd for households

To increase the number of hours of water supply at least to 8 hrs

To discourage the public stand posts

To increase the individual house connections

To bring all consumers under 100% metering of efficient revenue collection

To maintain entire water distribution system by gravity for energy savings

To have fully efficient distribution system including water and energy savings

To reduce the quantity of Non-Revenue water in the system

The water supply strategy was worked out firstly by estimating the water demand up to

the year 2026 AD. A permanent source of water supply from the nearby river ‗Jambu‘

which is 12km away from the town was identified. Construction of an intake well, jack

well, water treatment plant of capacity 7.6MLD, three new OHTs of capacity 5 lakh liters

each, raw water raising main, clear water raising main of 13 km length and 53km HDPE

distribution pipe lines, which covers entire TMC area except Kodi area under KUDCEMP

was carried out at a cost of 13.1 crores.

There was strong resistance from citizens for land acquisition and laying pipes and by

elected representatives while disconnecting the public stand posts Objections received

during installation of meters to household connection and also by highway authority

while laying the pipelines across the road. En route village panchayats demanded to

share water while laying the transmission main. Implementing the water quality

monitoring system eventually reduced the water supply connection deposit amount.

Operation and Maintenance

The Kundapura Town Municipal Council handles the operation and maintenance works.

The water tariff was revised with respect to Kilo liter expenditure. A flat rate

Page 118: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

118

@Rs.45.00/month/connection is charged. The water connections were made

compulsory and the public were encouraged to have individual house connections by

allowing them to pay water connection deposit charge in 3-4 installments. This reduced

the public stand posts in phased manner. Setting up 24/7 Public Grievance Redresser

Cell as well as online complaint registration system in TMCs own web site, helped the

public lodge their grievances along with the leakage in the water supply network and

thus amending the water leakage complaints within the span of 24hrs time.

Figure: Water treatment facility at Kundapura town

Outcome and importance

The system provides sufficient quantity of potable water with adequate pressure

Out of three water distribution zones, in two distribution zones the supply was almost

24 hrs with adequate pressure

Due to less number of public stand posts there is a reduction in percentage of non-

revenue water

As distribution lines are of HDPE material, less number of leakages complaints

registered

Percentage of Non-Revenue water is drastically come down due to negligible

leakage and loss and prompt attending of complaints

Treated water supply for a minimum of 8 hrs in the town is ensured

No drinking water scarcity during summer seasons

The system has reduced the water contamination level very close to zero

Better demand management due to metering

Excellent consumer satisfaction with willingness to pay the bills which motivate the

TMC to go for 24/7 water supply

Page 119: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

119

Three en route gramapanchayats have obtained drinking water for their habitation

with a reasonable cost

Table: Water Production Cost

Figure: Current Scenario

Key Learnings

Council agrees to the initiatives if they are convinced systematically with genuine

reasons

Citizens agree to the improvement in basic amenities and pay the tax once the

uninterrupted service is ensured

Page 120: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

120

Adequate capacity building/awareness programmes are necessary to conduct in

connection to new schemes and projects

All objections from various sections of the society could be solved only through

discussion across the table

Water supply/benefits of the project need to be shared with surrounding/en route

villages to ensure no-illegal tapping

Sustainability

The system is 100%sustainable because the water source is river and is perennial

All project components are commissioned based on the long term operation and

maintenance standards

Water tariff restructuring and metering policy which has come in to force since

01/04/2006 is ensured that

The water wastage is negligible

Poor are benefitted

O&M cost is recovered

Replicability

This system can be replicated if proper source and funds are available to create

infrastructure. Commendable practices shall always be shared with other municipalities

directly for,

Water supply system monitoring

Operation and maintenance practices

Systematic Revenue generation

Energy savings because of gravity flow and less water losses

Regulation of Non-Revenue Water (NRW)

Recognition / Awards

The initiative has bagged first prize in National Urban Water Award 2009 under

technical innovations. Smt. Pratibha Devising Patil, President of India, conferred the

award in New Delhi at VigyaanBhavan

Won Best Initiative Award from Govt. Of Karnataka in the year 2010-11

Appreciation from NGOs

Page 121: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

121

Costing

Particulars Details

Total Cost of the project Construction of an intake well, jack well, water treatment plant of capacity 7.6MLD, three new OHTs of capacity 5 lakh liters each, raw water raising main, clear water raising main of 13 km length and 53km HDPE distribution pipe lines =13.1 crores

Operation and Maintenance cost

A flat rate @ Rs. 45.00/month/connection is charged

No. of staff employed 03

People/Officials met

Mr. Raghavendra.B.S.,

Environmental Engineer, TMC, Kundapura

Phone: +91- 08254- 230410

Email: [email protected]

Page 122: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

122

Annexure III

SEWAGE TREATMENT PLANT OF 10 MLD CAPACITY AT JAKKUR, BANGALORE

Bangalore was once called the city of a thousand lakes but over time, it lost most of

them due to urbanization, sewage dumping and encroachment. In 1960, there were

approximately 282 lakes while today barely 34 remain. The city has lost 82% of the

lakes from 1960 to till date due to growing demands of urbanization.

The Jakkur Lake is in the north-eastern part of the city and is one of the largest and

cleanest water bodies in Bangalore. It is the main lake in the chain of lakes comprising

of the Yelahanka Lake upstream and the Rachenahalli Lake downstream. It is about

140 acres large and has recently been rejuvenated by the Bangalore Development

Authority (BDA). A pristine, quiet spot of nature in the midst of Bangalore, this lake

stands testimony to the potential that exists to manage urban water sustainably, and in

an integrated manner.

Situation Before

Prior to the construction of the Jakkur sewage treatment plant, all the wastewater from

Yelahanka town, Maruthi layout, Kogilu were directed to the Jakkur Lake without any

treatment. This had deteriorated the water quality there by rendering the lake useless. It

was of major concern as many people in and around the lake were dependent on it for

drinking, washing, fishing and other activities. It posed threat to a lot of migratory birds

that visited the lake frequently.

Description of the initiative

The Bangalore Water Supply and Sewerage Board (BWSSB) is the premier

governmental agency responsible for sewage disposal and water supply to the

Indian city of Bangalore. It was formed in 1964. The BWSSB is committed to providing

drinking water of required quality in sufficient quantity and to treat the sewage generated

to the required parameters. As the leader in providing water and sanitation services,

BWSSB is recognized as an effective instrument of change through adopting state-of-

the-art technologies for improving the quality of its services to the general public.

The additional water supplied to the city in turn converts into wastewater and there was

a necessity to convey and treat this additional wastewater. For treating this Board has

constructed seven treatment plants. One of them is the Jakkur 10million litres per

Page 123: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

123

day(MLD) Wastewater Treatment project which was taken up under CWSS Stage IV

Phase I, Department of Urban population control, Bangalore city.

Jakkur Lake was fenced and developed by the Bangalore Development Authority (BDA)

a few years ago. The Bangalore Water Supply and Sewerage Board (BWSSB) then set

up a Wastewater Treatment Plant upstream of Jakkur Lake, with the capacity to treat 10

MLD of wastewaterin the year 2001 with a financial aid from the Japan Bank for

International Co-operation (JBIC). The construction of the plant was outsourced to a

private company named GSJ infrastructure and was set-up at an estimatedcost of

approximately Rs. 2 crores. At present, the operation and maintenance of the plant is

managed by a private company, NrityaGanapathi, on a 3 -year contract with the

BWSSB.

Figure: Map of Jakkur Sewage Treatment Plant

On similar lines of wastewater treatment at the K.R.Puram 20 MLD wastewater

treatment plant, the process of primary treatment and secondary treatment at the Jakkur

plant is using the Up-flow Anaerobic Sludge Blanket or UASB technology.

In UASB process, the waste to be treated is introduced in the bottom of the reactor. The

wastewater flows upward through a sludge blanket composed of biologically formed

granules or particles. Treatment occurs as the waste comes in contact with the

granules. For high organic loads, UASB certainly offers advantages in terms of almost

insignificant energy consumption, low O&M cost and recovery of significant amount of

bioenergy.

Page 124: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

124

The treated water from the Jakkur plant is then being released into a wetland of about

1.5-2 acres where the flourishing plants further treat it and improve its quality. The water

then reaches the lake and by the time it infiltrates through the ground and emerges in

the well, the earth has it filteredclean. Waste water is now well-water ready for use.

Operation and Maintenance

Currently, the way the system works is that raw sewage is pumped in to the plant, and

the solid waste is separated from the liquid waste. The liquid waste is then treated at the

anaerobic wastewater treatment plant.

The UASB uses an anaerobic process whilst forming a blanket of granular sludge which

suspends in the tank. Wastewater flows upwards through the blanket and is processed

(degraded) by the anaerobic microorganisms. The upward flow combined with the

settling action of gravity suspends the blanket with the aid of flocculants. The blanket

begins to reach maturity at around 3 months. Small sludge granules begin to form

whose surface area is covered in aggregations of bacteria. In the absence of any

support matrix, the flow conditions create a selective environment in which only those

microorganisms, capable of attaching to each other, survive and proliferate. Eventually

the aggregates form into dense compact biofilms referred to as granules.

Page 125: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

125

Figure: Flow chart of UASB Technology

To the right of the plant is a constructed man-made wetland, into which the treated

wastewater is diverted. This wetland further purifies the treated wastewater through

natural processes, before letting the water flow into the main Jakkur Lake.

Page 126: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

126

Figure: A sketch of a wetland with a horizontal flow through filters, vegetation, and towards a specific outlet

There are two big underground tanks at the treatment plant and they fill up every 15

days to a month. Usually, if there is a lot of sludge, in one day, at least 5 of the10 beds

are filled with sludge. So, in two days, all the 10 beds are filled. This is only when there

is a lot of sludge and both the underground tanks are opened up. If only one of them is

opened, approximately 3 beds can be filled up.

If there is a lot of sunlight, then it takes approximately 15 days for a full bed to dry up

and reach a state when it can be sent off. If rainy or if there is less sunlight, then it can

take longer. The filtered pump system present pumps out all the excess water from the

sludge beds and sends it out via the water chambers. If the whole bed is full, at least 3

truckloads of sludge can be produced from each bed. Each truckload can be sold for

about Rs.7,000-8,000. The selling of the sludge created covers almost the entire

monthly electricity bill of Rs.3 - 3.5 lakhs and helps sustain the plant.

Page 127: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

127

Outcome and importance

By serendipity, a sewage treatment plant (STP) with a capacity to treat 10 million litres a

day was set up north of Jakkur Lake by the Bangalore Water Supply and Sewerage

Board (BWSSB). This treatment plant receives wastewater from about 12,500

households from areas around Jakkur like Yelahanka and Kogilu.

The plant is currently able to let out 6 million litres of treated water into the man-made

wetland that further purifies the water by a natural process before letting it enter the

lake.Therefore the lake is fed with around 6 million litres of treated water every day,

which in turn recharges the ground, increases the water table and fills up the bore-wells

and the beautiful old open wells — heritage structures that adorn this area and are in

need of preservation.

For a flow of 6.2 - 6.5 MLD, the outcome of water quality post-treatment is at 50% and

the remaining is taken care of by the wetland. The pH is maintained at 7-7.5 before

letting the treated water into the wetland.

The constant water inflow has helped the lake become a hotspot for biodiversity of all

sorts. It also ensures that the lake is always full, thus providing potable water to the

communities who use the wells around the area. This is what makes the system so

special. By this fantastical process, raw sewage is transformed into potable water,

whose origins even the communities dependent on it, is unaware of.

The civic bodies are always conducting some programmes but the people do not know

what they are about or what it is meant for. There is always an information gap.

Everyone knows about some part of the system, but not how the entire thing functions.

The lake itself has become a hotspot for biodiversity, attracting birds and hosting a

variety of plants. During peak fishing season, fishermen haul in up to 500 kgs of fish

daily – an astounding achievement for a lake in the middle of a bustling metropolis like

Bangalore.

Page 128: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

128

Some of the sludge from the treatment plant is used to grow a small vegetable garden

at the back of the plant. The vegetables are cooked and eaten by the employees of the

treatment plant.

Key learning

There is still some way to go for Jakkur Lake

to become a sustainable model for urban

water management. There are several

private bore wells on the boundary of the

lake, all extracting groundwater in an

unregulated fashion. One bore well is known

to extract groundwater and sell it as tanker

water to parts of the city that do not get

municipal water supply. Buildings around

the lake are getting their water supply from

bore wells on the boundaries of the lake,

which depletes the groundwater.

If these buildings tie their water supply and wastewater to the lake, they would not need

to extract groundwater from bore wells. The surrounding buildings should send their

wastewater to this treatment plant, where it can be let into the lake. Instead of bringing

wastewater (that too, periodically and erratically) from neighbouringYelahanka, the

waste from Jakkur itself can be brought to this plant, treated and then let into the lake.

This cycle would ensure that the lake is full even in the dry summer months.

On the consumption end, they can augment their water supply from the lake as the

water is perfectly fit for domestic use. Thus it becomes an end-to-end solution for the

area – what sector people call Integrated Urban Water Management.

Sustainability

The fact that people are making a living off an urban lake is truly an achievement, and a

step towards reestablishing our connection to water. In spite of a capacity of 10 MLD,

the plant treats only about 6 MLD on average, when it is functioning. Sewage from

Figure: Map of Closed loop Integrated Urban Water Management System at Jakkur

Sewage Treatment Plant

Page 129: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

129

neighbouringYelahanka is brought here, while sewage from Jakkur itself is not treated

here. A lot of the buildings in Jakkur are high rises, with their own Sewage Treatment

Plants. It is doubtful whether they are even aware of the BWSSB Sewage Treatment

Plant upstream of the lake. If citizens and the utility communicated with each other,

Jakkur could become a closed loop of integrated urban water management in the very

heart of Bangalore city.

Replicability

The UASB method of wastewater treatment yields very high loading rates and biogas

productivity. This growing application is ideal for more recalcitrant wastewaters. Hence it

is highly recommended technology for wastewater treatment.

Champions

The Bangalore Water Supply and Sewerage Board (BWSSB) and the Bangalore

Development Authority (BDA) are considered the champions of this initiative for

restoring the lake, promoting sustainability and communicating the idea of integrated

urban water management through various activities.

Costing

Particulars Details

Total Cost of the project Approximately Rs.2,00,00,000

Operation and Maintenance cost

For a flow 6.5 MLD of wastewater, on an average, Rs.1800 is spent on treating 1 MLD of wastewater.

Rs.3-3.5 lakhs/month is spent on electricity. The income generated by selling dry sludgemeets most part of this expenditure.

Rs.2.5 lakhs/month is spent by the contractor towards manpower, salary and other technical maintenance works

No. of staff employed A total of 34 people work in two shifts

People/Officials met

Mr. Preetham

Plant Manager, Jakkur Sewage treatment plant

Phone: +91 9964411169

Email: [email protected]

Mr. Girish

Chemist, Jakkur Sewage treatment plant

Mr. B.M.Narayanaswamy, Assistant Engineer, BWSSB

Page 130: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

130

Annexure IV

SOIL BIOTECHNOLOGY BASED WASTEWATER TREATMENT PLANT OF 15,000

LITRES/DAY CAPACITY AT ACCEPT SOCIETY, BANGALORE

ACCEPT (AIDS Counseling, Care, Education, and Prevention Training) Society is

an AIDS-care hospice located near Hennur Cross (Bangalore). This 5-acre campus

provides inpatient and outpatient care and counseling for AIDS-affected people and has

a children‘s home for HIV+ orphans. Additionally, ACCEPT Society engages in

horticulture and agricultural activities as a source of food as well as income.

Situation Before

The water supply to the hospital is from a bore well on campus. The supply was not

adequate and was often supplemented through a water tanker service, twice a day

during the summer months and once a day for the rest of the year. In order to increase

their water supply, ACCEPT Society installed rainwater harvesting (RWH) system.

However due to various issues, the system was not being fully utilized.

Sewage was originally draining into a main septic tank from a secondary tank and soak

pit on the campus. However, due to the clayey properties of the soil in the campus, the

tanks encountered severe flooding problems for which they had to be emptied very

frequently. In addition, inadequately treated grey water was disposed of in dug and

recharge wells which could be affecting groundwater quality.

Description of the initiative

Arghyam, a public charitable foundation setup with a personal endowment from Ms.

RohiniNilekani, installed the SBT at ACCEPT Society which has largely served its

purpose, thus enabling Arghyam to understand SBT better and verify the technology

claims. Arghyam seeks to support strategic, equitable and sustainable efforts in the

water sector that address basic water needs for all citizens. Arghyam's strategy is

integrated around five focal areas ie. Project Grants, Urban Water Initiative, India Water

Portal (www.indiawaterportal.org) Research and Advocacy and Government

Partnership.

The current sanitation scenario of urban India is one of severe lack of collection,

treatment and disposal systems for domestic sewage. In order to tackle this problem

and protect water resources from contamination, while also augmenting usable water

Page 131: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

131

resources, there is an urgent requirement to identify appropriate technologies for

wastewater treatment. Decentralized technologies are increasingly attractive because of

several advantages, especially in the Indian context.

SBT is a decentralized wastewater process which makes use of respiration,

photosynthesis and mineral weathering in order to purify domestic, municipal and some

types of industrial wastewater.

SBT incorporates the use of specific micro-organisms. These are part of the process

that cleans organic waste through oxidation and releases carbon dioxide. Nitrification

followed by de-nitrification convert the nitrogen load in the wastewater to elemental

nitrogen gas. Primary minerals, which form the base media in the bioreactors within

which the purification processes take place, create a pH buffering effect. Whilst

earthworms serve to aerate and regulate bacterial populations, trees and shrubs planted

on the surface of the bioreactor act as bio-indicators to signal a properly functioning

plant.

The wastewater treatment plant of 15000 litres/day capacity was constructed in 2011at

a cost of Rs.21, 00,000 with an estimated life of 20 years. The technology provider for

this project was Vision EarthcarePvt Ltd, Mumbai and the construction work was carried

out by Hinren Technologies, JP Nagar, Bangalore. Financial support was offered by

Arghyam.

The physical (civil) structures consist of a raw water tank, a bioreactor containment

structure, a treated water tank and associated piping, pumps and electrical installations.

The process is meant to handle domestic sewage and industrial sewage containing

primarily organic effluent. Treated water quality of various levels can be obtained, from

river discharge quality up to near drinking-water quality, from an SBT depending on the

requirement and investment potential.

Page 132: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

132

Figure: Design aspects of the SBT wastewater treatment plant at ACCEPT Society, Bangalore

Following is the description of the design aspects of the SBT wastewater treatment plant

at ACCEPT Society, Bangalore.

1. Wastewater is collected from kitchen, bathroom and toilets in the hospital

2. Septic tank for holding and settling of wastewater

3. Wastewater pumped into primary bioreactor‘s main pipeline

4. Wastewater is spread on bioreactor‘s top layer and percolates through multiple

layers

5. Treated water collects in separate tank. Water is now clean and fit for irrigation use

6. Treated water used for irrigating garden and plantation

Page 133: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

133

Hence, the hospice was searching for a solution for their wastewater treatment

problems. This provided an excellent platform to test and validate SBT as a technology

and at the same time support a charitable initiative.

In order to assess the efficiency of the plant, numerous water quality tests were carried

out over a period of two years. The chemical parameters measured reflect satisfactory

results thereby proving the technical feasibility of the plant, enabling the recycled

wastewater to be used for local irrigation. The wastewater is treated at a cost of Rs.

8.50/KL. A cost-benefit analysis undertaken shows the economic feasibility of SBT, with

a Rate of Interest (RoI) of 22 years.

Operation& Maintenance

The wastewater is first collected in a holding tank constructed by excavation and made

waterproof. The under drain is laid at the base. The tank is then filled with layers of

media and culture. The surface of the bioreactor contains rows of plants. A network of

perforated pipes is constructed on the surface that spreads the incoming wastewater

evenly over the surface of the bioreactor. Another set of pipes is also laid vertically

extending into the bioreactor for aeration after which it is pumped into a trapezoidal-

shaped bioreactor.

Water is pumped over the bioreactor through the perforated pipe network and begins to

trickle down the filtering media. The suspended solids in the wastewater are held back

by the top media. As the water seeps through the rest of the layers, dissolved pollutants

are removed, and finally treated water passes through an outlet at the bottom of the

tank and is collected in a treated water storage tank constructed alongside.

Figure : Typical layout of SBT media

If required, recirculation pumps can be added to transport the water back into the

bioreactor. This creates a second round of purification, obtaining the desired hydraulic

retention and improved output water quality to the desired level. Shrubs and trees are

planted on top of the bioreactor to act as bio-indicators, organisms used to monitor the

health of the environment. In this case the growth of these plants will determine their

ecological health thereby indicating the quality of the recirculated water.

Page 134: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

134

This entire treatment process can be operated on a batch or in continuous mode and is

based around three fundamental reactions:

Respiration

Mineral weathering

Photosynthesis

Considering the reduced volume of wastewater and the automatic functioning of pumps,

a total of 12 man days/month of unskilled labour is identified in order to manage the

plant. The main activities involve weekly maintenance of pumps and pipes and monthly

supervision and cleaning of tanks.

Outcome and importance

The plant is currently performing well and providing water that is being used to support

the agricultural and horticultural activities on campus. 75% of ACCEPT Society‘s 5-acre

campus is used for agricultural activities. Treated water from the SBT plant is pumped

directly through pipelines to the field and is used to irrigate a variety of vegetables and

horticultural crops such as banana, mango and grapes.

With some exceptions, the plant is meeting the standards specified at the time of project

design. These standards are high, and match or exceed international standards for

many parameters including nitrogen and phosphorus. These parameters are important

in the context of pollution and eutrophication of natural water bodies and contamination

of drinking water supplies (typically groundwater).

Table: Comparison of Wastewater Treatment technologies with the SBT at Accept Society, Bangalore

Page 135: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

135

The SBT plant plays a significant role in the conservation of freshwater since it

encourages reuse through the treatment of wastewater. Moreover, since the output

wastewater quality is improved, the operation of a SBT plant reduces groundwater

pollution. More specifically:

There is no sludge generation and thus no requirement to dispose of any sludge.

According to technology providers, the residue on the surface of the bioreactors can

be directly used as biofertilizer.

SBT has very little odour problems.

It is aesthetically appealing and adds to the landscape rather than consuming land

to build up a STP.

Key learning

SBT has the potential to meet high water quality standards for use in agriculture, toilet

flushing as well as discharge to rivers and water bodies. The technology has a relatively

high startup cost and a land footprint that may be larger than other technologies on

offer. However its great benefit is that it requires no power for the wastewater treatment

per se. Overall the ongoing operation and maintenance (O&M) expense is very low.

Therefore, while comparing the Total Cost of Ownership (TCO), SBT is found to be

substantially less expensive than many conventional technologies at the lower end of

the capacity scale (10-200 KLD). The other major advantagesare that there it requires

less mechanical equipment and there is no necessity for skilled manpower for operation

uses.Finally, it is a green technology, which uses less power and discharges no

methane as part of the treatment process.

Table: Conventional Technology (ASP, SBR, MBR, MBBR, UASB) Vs. Soil BioTechnology

Page 136: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

136

Sustainability

SBT holds a significant advantage when considering the quality of treated wastewater.

Based on the results of the installation of this SBT, it is capable of showing quite high

levels of BOD/COD reduction, as well as nitrate and phosphate reduction. Therefore

SBT may have a stronger case when a facility wants to reuse the water and has very

definite and stringent output water quality requirements. Hence, SBT is worth

considering in any wastewater treatment technology decision up to the capacities of a

few million litres per day (MLD).

Replicability

In places like Bangalore it has become a requirement for large apartment complexes,

gated communities and similar campuses to treat their wastewater to some level before

discharging into a sewer or to the environment. Where finance and space are serious

constraints as is often the case with these installations, none of the available

technologies really work well, as reflected in an epidemic of malfunctioning wastewater

treatment plants in apartment complexes.

Hence, where land is not too much of a constraint, SBT will be a good competitor due to

its low O&M cost, competitive Total Cost of Ownership and non-requirement of skilled

manpower. Moreover, the fact that the SBT plant simulates a garden-like environment

means that the land requirement is somewhat ‗softened‘ since the land use can be

integrated into landscaping. Also, to manage the larger initial capital requirements, SBT

can be considered in a decentralized, phased installation approach.

Champions

The SBT system was developed after two decades of research by Prof. H.S. Shankar

and associates at the Chemical Engineering Department of Indian Institute of

Technology (IIT), Bombay. Following this development, Prof. Shankar founded Vision

Earthcare, a company which seeks to provide wastewater treatment solutions using this

technology. Other service providers have also licensed this technology. Since then, SBT

has been installed in more than 20 locations, treating wastewater volumes between 5-

10 MLD in industries, housing societies, resorts, schools, universities, ashrams, hotels

and municipal corporations.

Page 137: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

137

Costing

Particulars Details

Total Cost of the project Rs.21,00,000

Operation and Maintenance cost

Treatment costof Rs. 8.50/KL of water

Technical maintenance cost once in a while

Rs.20,000/month is spent on drinking water

No. of staff employed 02

People/Officials met

Mr.Santosh, Administrator, ACCEPT Society

Contact no.: 9886769948

Email: [email protected]

Mr.Raju Mathews, Director, ACCEPT Society

Mr.Nagappa, Field worker, ACCEPT Society

Technology Provider

Vision EarthcarePvt Ltd

SINE 3rd Floor CSRE Bldg

IIT Bombay - 400076

Phone: 91-22-27718444, 25721317

Email: [email protected]

Construction Agency

Hinren Technologies

# 495, 11 Cross, 8 Main, 2nd Phase,

J.P.Nagar, Bangalore 560078, Karnataka

Phone: 090 35 625364

Page 138: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

138

Annexure V

STP ’B’, VIDYARANYAPURAM, MYSORE, AN INNOVATIVE SEWAGE TREATMENT TECHNOLOGY

Mysore lies in the Southern Plateau of Karnataka. It covers an area of around 128.42

Sq. Km located between latitude 11°45' to 12°40' N and longitude 75°57' to 77°15' E.

According to the provisional results of the 2011 national census of India, the population

of Mysore is 887,446 and the total population of the urban agglomeration (UA) is

983,893. Mysore city was one among the earliest cities in India to have underground

drainage systems. The Mysore City Corporation has three sewage treatment plants for

the four divided drainage districts, named A, B, C and D. Sewage treatment plant at

Rayanakere for the drainage district A and D, Vidyaranyapuram sewage treatment plant

for the drainage district B and the Kesare sewage treatment plant for the drainage

district C.

Situation Before

The city of Mysore has three Sewage Treatment Plants (STP) to treat municipal the

wastewater for a total design capacity of 157.5 MLD and is receiving sewage from 4

zones of the city. All the STPs design comprises of Facultative Aerobic Lagoon (FAL)

and Maturation Pond. They were commissioned in 2000 and taken up under KUIDP –

ADB assistance.

The Sewage Treatment Plant in Vidyaranyapuram covers an area of around 27.21 Sq.

km between latitude of 12.284361 and longitude of 76.652760, with a sewer length of

7000 meters. The STP was constructed in 2002 and was designed for a capacity of 67.5

MLD, but actually receives 50 MLD. It receives sewage from Kabeer road, Ashokpuram,

Dhanavanthri Road, CFTRI, Chamaraja Double Road, JSS, Kanakagirinagar and

GunduRao Nagar areas. It was mainly designed as a Facultative Lagoon with 36

aerators (each - 20 HP blower) and consumes nearly 3, 00,000 units of electrical

energy.

In December 2008, the labour Contractor left the STP and all blowers were out of order.

This resulted in very bad odour emanating from the plant and sludge blanket formed at

the top.

The O & M expenditure per year was around Rs.1.44 Crores of which energy charges

alone accounted for Rs.1.1Crore. There were a lot of complaints from the residents of

that area on account of foul odour.

Page 139: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

139

Description of the initiative

It said the rapid and unabated influx of rural population into the urban areas and

consequent urbanization has given rise to proliferation of slums and put pressure on the

available infrastructure, more so in case of sanitation, where the issue is not of mere

water scarcity but also contamination of the available resources. While Government and

local bodies are constantly engaged in addressing issues by trying to provide basic

facilities in these areas, there is a demand for waste water treatment plant. But the

reality is that most small and medium-sized sophisticated waste water systems are not

affordable and besides the initial capital investment, these systems are also unpopular

as they are energy-inefficient and require a high-level of maintenance.

Jalavahini Management Services (JMS) Pvt. Ltd. established in 2003, is one of the

leading Civil and Environmental Engineering Consultancy and also Turnkey projects

implementation organizations in Karnataka. It is an ISO 9001:2008 Company and works

for various Govt., agencies and corporate sector in India.

JMS Biotech Pvt Ltd is manufacturing and marketing Bio - Enzymes for Waste

Treatment.

Jalavahini Management Services (JMS) Pvt. Ltd had earlier submitted proposal for

treating sewage using Bio- remediation measures to improve the functioning of the STP

with guarantee to eliminate foul odour and reduction of energy and sludge.

The plant is now operated using JMS Enzymes which are prepared on-site with Bio-

reactors installed. This is a very efficient process. JMS Enzyme consists of a mixture of

specially cultured beneficial microorganisms and enzymes which function synergistically

towards degrading the organic waste in the sewage wastewater. They are not

genetically modified but naturally occurring. Photosynthetic bacteria (PSB), Bacillus

Nato (BN) are the main ingredients in JMS Enzyme. The combination of PSB and BN

produces a large volume of enzymes that liquefy organic waste. The liquefied organic

waste is then very easily digested by the native microorganisms and protozoa that

convert the organic waste into CO2 and water.

Following are the advantages of using the JMS Bio-enzymes:

They are not genetically modified but naturally occurring.

They are not harmful in any way to the environment. Rather they work towards

cleaning the wastes.

Page 140: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

140

Increase autolysis – controls build-up of sludge.

Fermentative rather than putrefying.

Degrades complex organic substances to simpler ones.

Synthesizes pathogens, H2S and removes foul odour.

Reduction in aeration time

Reduction in release of foul odour

Enhances capacity of the STP by 25%

Figure: Facultative Lagoon

Operation & Maintenance

The figure shows the Bio-reactors being

installed at Mysore STP. About 3000 lit

of enzyme solution is produced every

24hrs cycle and dosed in the freshly

entering city sewage to the STP. The

production of bio-enzyme requires

optimal temperature (incubation)

between 30-37C, oxygen, and

substrate. For substrate, raw fresh

sewage is used instead of processed

organic source such as jaggery that is

expensive.

Figure: Bio-reactor installed in the plant

Page 141: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

141

The JMS Bio-Enzyme is a blend of enzymes and specially selected eco-friendly

microorganisms that carry out the process of Enzyme Liquefaction.Enzyme Liquefaction

is a process by which certain types of enzyme (e.g., lipase, amylase, protease, etc.)

liquefy complex organic molecules (e.g., carbohydrates, protein, oil, etc.) into simple

organic compounds that can very easily be digested by the native microorganisms and

protozoa. Enzyme Liquefaction yields a relatively small amount of energy compared with

bacterial fermentation process that requires longer decomposition process of the

organic waste by the same group of microorganisms. The aerobic-facultative

decomposition of organic waste is about 80% faster and saves processing cost. It also

suppresses the generation of the harmful gas that is often generated under anaerobic

condition.

Most pathogens that are present in the sewage are not able to survive due to the certain

mechanisms of enzyme. The JMS Bio-enzyme liquefies organic waste quickly under

aeration and the native microbes and protozoa start decomposing liquefied organic

waste.

Those microbes that multiply after the enzyme application decomposition of liquefied

organic waste enter an autolysis mode and start to consume its own dead cells, thereby

reducing and maintaining the sludge volume.

Outcome and importance

The Organization is successful in controlling the foul odors, pests, mosquitoes, electrical

energy and reduction in sludge. Raw sewage is being used for JMS Enzyme

preparation and as such no fresh water required.

Even after 13 years the STP has not been de-sludged and that helped in saving of huge

amount of mechanical de-sludging (this is costly, cumbersome and requires partial

closure of STP).

The total Treatment cost now is Rs. 88 lakhs which means a saving of 46% compared to

the conventional treatment cost. The power consumption is reduced by 96% which is

significant.

The treated water is being re-used by Forest Dept. for watering the trees on the hill

slope of Chamundi Hills and by Mysore Golf Course at a cost of Rs. 1.80 /KL. This

treated water has nutrients that help the growth of plants. All the capital investment for

setting up of facilities to re-use is done by Forest Department and the Mysore Golf

Course. The O & M is also done by them and they have to pay MCC for the water

drawn.

Page 142: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

142

Figure: Raw sewage and Treated water samples

Key learning

The new system is an example of an alternative method of wastewater treatment

and is the first of its kind to be set up in Mysore

It obviates the use of chemical processes or machines

The treated waste water can be used for agricultural purposes

The technology bridges the gap between the usual septic tank and the more

expensive and conventional sewerage system.

Sustainability

The salient features of the treatment plan are the wide range of wastewater type that

can be treated at an affordable price and fulfillment of discharge standards and

environmental laws. The plant is resource-efficient and non-dependent on energy and

requires minimum maintenance. The treated wastewater can be recycled for use in

agriculture and the installed system has many tangible benefits.

The incorporation of Decentralized Wastewater Treatment System (DEWATS)

technology in community-based sanitation guarantees reliability, efficiency and

affordability and has multiple benefits. The system also has other benefits and protects

the soil and water from contamination, ensures environmental hygiene, and the treated

water and sludge can be reused for agricultural purposes.

Replicability

The Mysore City Corporation has benefitted enormously during the last 5 years in terms

of reduced O & M cost, sludge, manpower and energy. This initiative is replicable and

technology adapted to any volume of sewage flows.

Page 143: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

143

Similar Initiatives

STP - Udupi [capacity 5 MLD], City Municipal Council, Udupi

STP - Hassan, City Municipal Council, Hassan

STP - Maddur, Town Municipal Council, Maddur

Recognition / Awards

Costing

Particulars Details

Total O & M Cost of the project before the intervention

Rs. 1.50 crores

Operation and Maintenance cost

The total Treatment cost now is Rs. 88 lakhs which means a saving of 46% compared to the conventional treatment cost.

The power consumption is reduced by 96%

The treated water is being re-used by Forest Dept. for watering the trees on the hill slope of Chamundi Hills and by Mysore Golf Course at a cost of Rs. 1.80 /KL

No. of staff employed 02

People/Officials met

Lt. Col (Retd.) Satish M. Kulkarni

JMSPL, Mysore

Phone: +91- 08254- 230410

Email: [email protected]

Mr.Basavaraj

Plant Supervisor, JMSPL, Mysore

Page 144: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

144

Annexure VI

Discussion – LD Authority bill passed in assembly on 7th July

The following lakes were leased out to private parties; the Hebbal Lake to E.I.H, the

Nagavara Lake to Lumbini Gardens and the Venkanayakere to ParC Ltd out of which

the first two were initially allotted. In May 2006, LDA leased out the Hebbal Lake, one of

the largest lakes in Bangalore, to East India Hotels (the Oberoi group) for a period of 15

years for an annual lease amount of Rs. 72,10,000 (about US$ 1.44 million) and an

annual escalation of 1.5% in the amount and an Investment of Rs.16,75,00,000 (about

US$0.34 million) with a security deposit of 1.5% (Rs.25,12,500 – about US$0,50million)

under the Public-Private Partnership policy. The Nagavara Lake was leased to Lumbini

Gardens Pvt Ltd in April 2005 for a period of 15 years for an annual lease amount of

Rs.4023, 000 (about US $0.80 million) with an annual escalation of 1.5 % of this amount

every year for the 15–year lease period and with Investment of Rs.7,01,00,000 (about

US$ 14.02 million) with a security deposit of 2% of this amount (Rs.14,20,000 – about

US$0.284million).

As per the lease agreement, the above referred agencies were to carry out the

development and maintenance of the lakes by:

• Setting up water treatment plant

• Deweeding the lake

• Controlling of storm water entry by building check dams

• Do landscaping; build a rose garden and also a rock garden

• Build jogging tracks and erect fountains

• Put up 4.5 m (14.8 ft) high Buddha statue.

• Develop an artificial beach as an amusement activity

• Develop water sport activities such as aqua karting, water scooter rides and

paragliding

• Set up food courts, restaurants, including a floating restaurant

Page 145: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

145

Impact of Privatization

The social damage caused due to privatization, as reported by a researcher, is:

• There is dichotomy in the functions allocated by the vesting of powers with LDA to

maintain only the water body and some part of the shore line while the shore and

lands adjoining the lakes, which also play an important role in the overall

maintenance and health of lakes, are with district bodies. This state of affairs creates

a complex situation of not addressing the lake as a continuum with land.

The lakes are being developed as stand-alone water bodies without a linkage to

other lakes

• Land use regulations are violated as the private developers of the two lakes have

not sought permission for change in land use from the Bangalore Development

Authority for converting the Nagavara and Hebbal Lakes for commercial use; a case

of non-compliance of the law.

• Fauna dependent on the lake, like birds, fish and others are disturbed by the excess

and disturbing human activity

• Conversion of the lakes and their surrounding areas into exclusive resorts, with entry

fee access to the lake areas. The private developers are in the real estate/hospitality

business with profit motive

• Violation of land use regulations by the private organizations while implementing the

scheme

• Proposed construction of a 223–room Hotel at the side of Hebbal Lake is indication

that private developer has taken the lease purely for commercial and business

purposes. Such a development would exclude access to the lake for the general

public.

• Lakes are Common Property Resources, in which a group of people have co–user

rights. The impact of the privatization scheme would, therefore, need to be

addressed legally

• The socio–economic impacts or apprehensions of the people such as fishermen

dependent on the lake for livelihood is that there could be restrictions on their fishing

rights and washer–men (dhobis) also have similar apprehensions.

Page 146: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

146

LDA’s Contention

The Lake Development Authority contends that the organization is not adequately

staffed and that they do not have the finances for maintaining lakes on an ongoing

basis. Hence, the alternative is leasing out lakes to private parties.

Public Interest Litigation (PIL)

A Public Interest Litigation (PIL) has been filed in 2008 by an Environmental Support

Group (a Trust) and a public spirited individual of Bangalore in the High Court of

Karnataka citing 16 respondents with the Lake Development Authority (LDA) as the

second main respondent and the favoured respondents (at serial number 14,15 and 16)

namely M/s Biota Natural Systems (I) Pvt. Ltd, M/s Lumbini Gardens Ltd., and M/s E. I.

H. Limited, in respect of the ongoing privatization of lakes/tanks in Bangalore. The PIL

contends that:

Actions taken by the respondents are against settled legal norms in respect of

Management and conservation of such ecologically sensitive water bodies (also

wildlife habitats) and which support a variety of customary and traditional rights

Water bodies are located in prime areas of the city and beneficiaries of privatization

of these are largely hoteliers and builders, as it is not an environmentally

progressive purpose but more a manipulation of the policy with profit motive

The constitution of the Lake Development Authority (Respondent) expressly

prohibits privatizing these public water bodies against the wider public interest

PIL has sought redress from the Honorable High Court by way of issue of writ or order in

the nature of Mandamus repealing the ‗Lease Deeds‘ executed by Respondent (the

LDA) in favour of the beneficiary respondents (to whom the lakes were leased –

Respondents 14, 15 and 16) and requested the Court to direct the Government of

Karnataka (as first Respondent) to ensure full compliance with the law and policies

relating to protection and conservation of lakes/tanks/wetlands.

The High Court of Karnataka on Tuesday, 4th November, 2009 directed the Lake

Development Authority (LDA) not to enter into fresh agreements enabling private parties

to own lakes. A division of the HC bench, comprising Chief Justice PD Dinakaran and

Justice VG Sabhapathi, took the State government to task, observing that the

government was trying to commercialize lakes by handing them over to the private

parties.

Page 147: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

147

The bench also ridiculed government bodies by saying that the LDA is working like an

agency and not an authority. From one side it is behaving like an agency for the

government and from the other side for the private parties. It also mentioned that the

LDA went ahead with the commercialization ignoring the objections from the Forest

Department and the Karanataka State Pollution Control Board. At the same time the

government was also criticized for its laid back attitude towards the case.

"If the government was serious enough in performing its duties towards the

maintenance of the lakes then there would have been no need to create the LDA and

then further make way for privatization," said the justices. The bench further mentioned

that there are many talented officials in the government who possess tremendous

knowledge about preserving lakes, but their talent has not been effectively utilized.

Hence, such officials are selling their talent to private parties, the bench noted.

The High court bench observed that, "The government is making all efforts to prevent

citizens from enjoying natural beauty. The Court cannot be a mute spectator to such a

development. There can be no development at the cost of the nature. If allowed to act

as per its whims and fancies, the government will soon privatize Cubbon Park and

LalBagh".

The High court bench concluded by saying that the government was not serious and

undertook all the supposed development as just eyewash to the public. It asked the

government to give powers to the tourism department to take up lake development and

stop LDA from entering any fresh agreement or commercialization activities.

From the above case law it could be observed that, there was lack of proper monitoring

mechanism and conservation methods, which resulted in unwarranted litigation. Public

private participation could be rendered feasible by placing suitable mechanism for

monitoring, maintenance and conservation of lake.

Page 148: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

148

Annexure VII

INTEGRATED URBAN WATER MANAGEMENT IN MULBAGAL, KOLAR DISTRICT

Mulbagal is a Class III town according to the Census data of 2011, meaning that it has a

population between 20,000- 49,999. It is located in Kolar district of Karnataka and

spread over a geographical area of 9.8 square kilometers. The town population was

close to 50,000 in 2008 and consisted of about 14,000 households. About 31% of the

total population resides in 16 slums (14 registered and 2 unregistered). The TMC is

administratively divided into 27 wards with a population ranging from 600 to 4,350

people per ward. The TMC has a 27 member council, headed by the president. The

annual rainfall of the town varied between 570-875 mm.

Situation Before

Mulbagal lies in an over-exploited zone as classified by the Central Ground Water Board

(CGWB) and the Department of Mines and Geology, Karnataka. The subsequent

groundwater study showed that the depth of groundwater inside the town ranged from 4

to 14 metres. With absence of viable surface water sources, Mulbagal‘s water supply is

totally dependent on groundwater drawn through bore-wells in and around the town.

The town water supply system consists of 114 municipal bore-wells (all 114 wells are

not operational all the time due to various reasons), five pumping stations, and one

ground level reservoir (GLR) which supply water to different parts of the town. The town

also has a few lakes and tanks. The water supply to the population is through 3,841

domestic connections and 741 public taps which do not have any metering system. The

town does not have an underground drainage system. Waste disposal is mostly through

septic tanks but waste from those defecating in the open enters the storm water

drainage system.

Several engineering, scientific, and social studies were carried out to assess the water

situation in the town, including a groundwater study, water quality study, an energy

audit, a household survey of water and sanitation assets, and GIS mapping of all toilet-

less households in the town.

From the town‘s perspective, there were several implications arising out of these

studies. There was sufficient quantity of groundwater to meet the town‘s needs.

Increased pumping inside the town could increase the recharge and therefore address

the issue of poor water quality. Protecting the catchment of the lakes and tanks which

Page 149: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

149

recharged the groundwater in the town was essential. Thus, there was a dire need to

address the following.

Achieve Energy efficiency in pumping stations

Implement Rainwater harvesting

Solid Waste Management

Revival of Kalyani

Description of the initiative

Arghyam, a charitable foundation set up by RohiniNilekani, has been working on

domestic water and sanitation in India since 2005. As a donor, Arghyam‘s primary focus

has been grant-making to NGOs, research and other institutions in the field of domestic

water and sanitation. Apart from that, Arghyam drives several initiatives as action-

research projects in emerging or niche areas, where it is difficult to find grantees. They

include the India Water Portal (www.indiawaterportal.org) – an online, open platform for

sharing information and knowledge among the water community, and A Survey of

Household Water and Sanitation (ASHWAS) in rural Karnataka to assess and share

citizens‘ perspectives.

Arghyam initiated the action-research programme on Integrated Urban Water

Management (IUWM) in the town of Mulbagal, Karnataka, in mid-2008. This initiative

was taken up in partnership with the Urban Development Department (UDD),

Government of Karnataka, and the Town Municipal Council (TMC) of Mulbagal.

MYRADA (a Karnataka based NGO), the Indian Institute of Science (IISc), and other

organizations that have supported various aspects of the programme.

IUWM approach broadly means managing freshwater, wastewater, and storm water as

components of a basin-wide plan in an urban area. For developing countries like India,

issues of universal access to water, assured water quality, safe sanitation, and strong

governance gain prominence.

The IUWM approach is based on three core principles as the basis for a sustainable and

equitable urban water model. These are:

i. Sustainability

Closing the urban water loop and integrating all aspects of water from source to

sink.

ii. Good governance

Balancing the demand, supply, and resource availability.

People‘s participation in all stages.

Page 150: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

150

Universal access to water and sanitation facilities.

iii. Empowering local government

Subsidiarity, i.e. decisions are made at the lowest appropriate level – giving

priority to managing water resources locally.

Empowering, strengthening, and building local institutions to be able to carry out

these functions.

IUWM was conceived as an approach to urban water management based on

participatory principles, on integrated, source-to-sink planning, and on inclusive,

sustainable interventions. The key hypotheses underlying this initiative were the

following:

By considering all the available local water sources, (ground, surface, rain, and

treated wastewater), small towns may better be able to meet their water demand.

By creating a local support institution with skilled human resources, and

strengthening the capacities of the existing staff, the town would be able to improve

implementation of its water-related schemes/projects.

By involving the community in all aspects of water management through

appropriately designed structures, increased equity and accountability, and higher

performance of assets could be achieved.

By adopting the principles of change management to guide and involve local

stakeholders through small, incremental efforts, the larger goal of IUWM could be

achieved in a phased and sustained manner.

The high level process of the IUWM approach consists of five phases.

Preparatory phase which aimed at engaging the local and state government

stakeholders and developing the partnerships.

Foundation phase which involves scientific studies that are carried out to understand

the water situation in the town. The community is mobilized, ward level groups are

formed, and capacities of local municipal staff and the council are strengthened

Planning and design phase, during which appropriate interventions were planned,

based on the evidence generated and prioritized by the local stakeholders

Implementation phase which involves guiding the local actors in implementing a few

targeted interventions.

Operations and Maintenance (O&M) phase which work towards building local

capacities and strengthening institutional or community structures to manage the

interventions.

Page 151: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

151

Figure: Five phases of Integrated Urban Water Management Process

The studies helped to identify three main tracks as areas for intervention – energy

efficiency in pumping stations, rainwater harvesting in schools and solid waste

management. These interventions were embedded in existing programmes/schemes,

approval and funding for which came from the DMA. These activities were seen as ways

to address tangible issues faced by the town‘s population. The IUWM principles of

sustainability, good governance, and empowerment of local government were implicit in

the design of each activity.

The success achieved in the intervention tracks over an eighteen month period is

noteworthy. A locally customized solid waste management initiative has been designed

and is running successfully in 750 households. Wet and dry waste is segregated and

collected by a newly formed local group called the ‗NirmalaBalaga‘ that takes

responsibility for daily collection and disposal of the wet waste. Fees from the

households are being regularly collected by the group as of May 2012. Councilors have

shown interest to initiate a similar programme in other wards. A defunct rainwater

harvesting structure in a local school was also repaired and made functional. The

applications are advancing slowly through the various stages of approval, and are being

tracked. Proposals were prepared for pump replacements in two more pumping stations

and rainwater harvesting in seven institutions. These proposals were going through a

tendering process at the time of writing. An unplanned bonus was the revival of an

ancient temple tank (kalyani) in the town.

Page 152: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

152

Figure: Schematic of minimum elements of a Mulbagal IUWM Model

Operation& Maintenance

a) Preparatory phase

Preparatory phase involves setting up the partnerships with the town, state level

government departments, NGOs and other key expert partners for the scientific and

engineering studies.

Town selection

The first step was identifying the town based on several criteria. It had to be small

enough (under 100,000 population), be located in Karnataka and preferably close to

Bengaluru, be representative of other small towns in the country, have credible local

partners for Arghyam to work with, and be politically uncomplicated to maneuver.

Interactions with the president, councilors, commissioner, engineers, and accounts

officers were held to gauge their interest in the programme.

At the end of this six-month process, Mulbagal was selected as it best met the

above criteria. A MoU with its TMC was signed with the approval of the UDD,

Government of Karnataka (GoK).

Building partnerships

At the state level, a State Level Coordination Committee (SLCC) with the

Commissioner, DMA as the nodal officer was created. The SLCC had representation

from the UDD, Karnataka Urban Infrastructure Development Finance Corporation

(KUIDFC), Karnataka Urban Water Supply and Sewerage Board (KUWSDB), Mines and

Geology Department, Lake Development Authority (LDA) etc. This was important

Page 153: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

153

because a key pillar in the IUWM approach was the integration between various

government agencies responsible for water and the SLCC was a space to facilitate such

integration.

b) Foundation phase

This phase included the studies of the water resources and systems in the town, the

community mobilization activities, and the PSU formation. There were six studies that

were carried out in total. They included the groundwater study, the water quality study,

the energy audit, the household water and sanitation survey, the water asset survey and

the toilet-less household mapping.

Urban groundwater behaviour study

Groundwater acts as a decentralized source to provide ‗safe drinking water‘ for millions

in rural and urban areas. As urbanization increases, towns and cities become more

dependent on groundwater, formally or informally, to meet their growing water demand.

Urbanization modifies the groundwater cycle impacting well yields, deteriorating the

quality and reducing the base flow. The objective of Mulbagal‘s groundwater study was

to develop a hydrogeological model which could guide the town in decision making,

simulate the groundwater system under future scenarios, and provide inputs into policy

formulation.

Mulbagal depends entirely on the groundwater pumped (~ 5 million litres per day, MLD)

from within, and in the neighbourhood of the town by the municipality through 100 plus

wells. Since the entire town would not have the same behaviour with respect to

groundwater use and aquifer response, an extensive and innovative groundwater level

monitoring network covering 250 bore-wells was set up.

Activities under the study included analyses of spatiotemporal behaviour of groundwater

levels, spatial variations in recharge and bore-well yields with respect to rainfall

variations, calculating the groundwater balance at the scale of an administrative ward as

well as for key pumping stations in the town. Models were developed to estimate the

fraction of groundwater recharge from rainfall and that due to leakage from water and

wastewater utilities. The groundwater model was calibrated and used for simulations

and future scenarios.

Page 154: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

154

The study showed higher than average pumping in the Pumping Station wells which are

located outside or at the periphery of the town, lesser for the Inner Town Series (ITS)

wells and average pumping in the rural agricultural area. The pumping stations also

showed higher recharge, while there was average recharge over the town and rural

areas. The higher daily extraction at the pumping station areas lead to higher decline of

groundwater levels, which in turn facilitated better recharge. The studies also, showed

that groundwater levels were shallow inside the town but the water quality was poor. On

the other hand, water levels were deep at the outskirts of the town, but the water quality

was good.

To lower the groundwater levels, an option to consider would be pumping out the

groundwater within the town and utilizing it through a suitable water treatment system.

This would also result in higher rainfall recharge in the town than the current levels.

Water quality study

Due to its low cost and generally high quality, groundwater has been a preferred source

for public water supply for private domestic use in many urban towns and cities. The

objectives of this study were to:

Uncover and establish the nexus between groundwater quality and sanitation

practices.

Develop a template for a Water Safety Plan that would enable towns to sustainably

manage and protect the quality of their water resources.

The majority of the OTS well contaminant readings are clustered around the desirable

limit and the majority of the ITS well contaminant readings are clustered around the

permissible limit.

The TDS levels in the ITS bore-wells were in excess of the desirable limit (500 mg/L)

for drinking water and most values ranged between 800 and 1500 mg/L. This implies

that the community would find this water unpalatable and ‗salty‘. Comparatively, the

TDS levels in OTS bore-wells mostly ranged between 500 and 850 mg/L.

The total hardness levels of water samples from ITS bore-wells ranged from 400 to

800 mg/L classifying the water as ‗hard‘. The hardness levels of water samples from

OTS bore-wells were lower and ranged between 150 and 500 mg/L.

Page 155: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

155

The nitrate levels in the ITS bore-wells were in excess of the permissible limit (45

mg/L) for drinking water and most values ranged between 50 and 300 mg/L

exposing the community to health risks associated with nitrate contamination. Nitrate

levels in OTS bore-wells were mostly below the permissible level of 45 mg/L.

In response to the water quality findings, and the resulting perception that groundwater

was not safe for drinking, the TMC took the initiative to launch a project with a private

sector entity to set up and run a treatment plant on a commercial basis. Going with a

reverse osmosis treatment mechanism, which is not the most environmentally friendly

option, and outsourcing it to a private sector entity was outside the model of IUWM that

was envisioned. Still, it was good that the TMC took initiative on a problem that was

critical.

Energy audit

The transport of water, from above or below the ground, to human settlements often

involves high use of energy. Water treatment processes in the water supply systems are

often dependent on energy intensive systems. This often results in huge production

costs. The key to understanding this improved and efficient system would be through

unbundling the lifecycle costs of various components.

Schneider Electric Conzerv India Pvt. Ltd was commissioned to undertake the energy

audit of all pumping stations, and measure the efficiencies and performance levels. It

also included evaluating the revenue savings possible and supervising the

implementation of energy saving measures on a pilot basis.

Figure: Comparison of TDS levels of inside town and

outside town wells

Figure: Comparison of total

hardness levels of inside town

and outside town wells

Page 156: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

156

Mulbagal town supplies drinking water to the entire town in two ways, namely

Through five pumping stations and overhead tanks (OHTs). These, in turn, get water

from the bore wells drilled at different places – inside and outside the town.

Directly through bore-wells. Here, the bore-wells pump water directly into distribution

system.

Figure: Schematic of Water Supply System in Mulbagal

Both these processes are highly energy intensive and there was a growing concern over

the mounting energy consumption for pumping water. In addition, it was reported that

the TMC was paying huge penalties for not maintaining the power factor and load

factors prescribed by the KPTCL.

The reasons for the high energy consumption included internal factors like the decline in

yield of the bore-wells, increase in the number of bore-wells in operation, increased

demand, increased wastages including leaks, and inefficient pumps and motors.

External factors like power outages and voltage fluctuations also escalate the costs of

energy utilized for water supply.

The recommendations from the study for an energy efficient water system included

improving power factor, installing energy efficient pumps in three pumping stations,

replacing bore-well pumps, implementing automation in the pumping stations and

revamping the present electrical distribution in the system. These were expected to

reduce the cost of water supply by almost Rs. 2 per kilolitre. With an overall investment

of Rs. 64 lakhs for a complete set of interventions, there could be a saving of Rs. 31

lakhs annually.

Page 157: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

157

Based on the above recommendations, the Mulbagal TMC decided to undertake some

corrective measures as a pilot in the Seegenahalli pumping station. Rs.9.6 lakhs were

spent on civil, electrical, and mechanical improvements which included a multi-stage

high efficiency (77%) pump, demand and PF controllers, and monitoring systems. The

findings showed that penalties were reduced from around 15% of the monthly energy

bills down to zero. Owing to increased hours of use of the new pump, there was a 25 to

35% increase in water drawn from the well.

Table: System performance of five pumping stations at Mulbagal

Household water and sanitation survey

MYRADA, the partner NGO, planned a baseline survey to understand the

demographics, service levels, and citizen viewpoints. A 20% sample size was chosen

with six to seven samples per street in every ward, with households depending on public

and private water supplies equally represented in the sample. The water supply service

levels were not uniform in all the wards. Only 26% households received water supply

daily and that was for a maximum of two hours. 25% of the households‘ water was used

for human consumption daily. Only 40% of the households felt that the current water

supply levels were adequate. Given the few households covered under daily supply,

bins, pots, and buckets were found to be the predominant form of domestic storage.

This allowed for storage of about 340 litres, which was less than the daily household

requirement at current levels. 37% of the households had household water connections.

Only 40% of the households spent money on water supply.

Other studies

A water asset survey was carried out by TTI Consulting Engineers (India) in 2009. This

resulted in mapping of the entire distribution network in the town, and studying its

performance. The total length of the water supply network is 92 km. This included

transmission, feeder, and distribution mains. Very rough estimates indicate that on an

average nearly 30% of water is being lost from the system due to leaks, breakdown and

theft.

Page 158: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

158

The water asset survey database and maps have been used by the ULB as part of their

regular reporting mechanisms to the State subsequently. The maps/ databases created

were also used to verify ground status prior to proposing projects under various

schemes by the Municipal Engineer.

An attempt at data-based decision making though initiated, required consistent hand

holding. The reasons for this include – absence or low capacities of manpower, absence

of state-driven protocols for reporting, inability of the Municipality to procure expensive

GIS software and no precedence of the decisions taken using data/ maps among

elected representatives in small towns.

c) Planning and design phase

Planning and design phase, a participatory plan is developed by the people and the

local government for water management in the town. The plan, based on the results of

the studies of the previous phase, reflects the actual needs of the people as well as the

unique situation of water in that town. It is guided by IUWM principles of sustainability.

Interventions are chosen from best practices tried elsewhere or locally evolved. Given

the complexity and challenges on the ground, this is not envisioned as a one-shot

process. Small steps must be taken in each year‘s plan to build upon the previous year‘s

interventions.

Since the IUWM approach is an integrated, holistic one, several activities were

considered necessary in the Planning and design phase to make the subsequent

implementation more effective. They were:

Entry-point activities

The objectives of entry-point activities were to demonstrate best practices in water

management and keep the stakeholders interested and engaged with the idea of IUWM.

A rainwater harvesting system was set up in a government school that was facing water

shortage problems. Leaky taps in public areas were identified and 250 of them were

replaced. Sanitary seals were constructed for 15 bore-wells to demonstrate how to

prevent contamination of the water. A week-long sanitation drive involving citywide

cleaning up of streets, drains, minor repairs to drains, transport and disposal of collected

waste in the municipal landfill was taken up.

A few of the above did generate desirable outcomes but overall, their contribution in

earning the goodwill or sustaining the interest of the town was not substantial may be

because of the lack of an overarching communications campaign to take these efforts to

citizens, lack of careful planning involving all the stakeholders, and the activities being

too few and spread out to create a visible impact.

Page 159: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

159

Community mobilization

Ward NeeruMathuNairmalyaSanghas(WNNS) were built by MYRADA on top of the

existing SHG network. Although people‘s involvement was slow to start with, it rose

gradually as they were made aware of the need for better sanitation and cleanliness.

But as the system wasn‘t responsive to most of the issues, the frustration of the

community rose. The lack of a clear engagement plan with outcomes for the WNNS

led to a lack of focus and some disillusionment.

Urban planning with Water Evaluation and Planning (WEAP)

WEAP is an open-source tool developed by the Stockholm Environmental Institute and

is a widely used planning and policy-oriented Decision Support System (DSS)

specifically designed for modeling water resources and evaluating alternative

management scenario. The WEAP model for Mulbagal would represent all the aspects

of IUWM – household needs, socio-economic situation, groundwater and surface water

sources, the different demands, water supply and wastewater distribution systems, and

financial elements.

The highly technical nature of the tool and the limited technical capacities of the town‘s

decision-makers made communication a big challenge. The vision was to apply

scientific tools to diagnose the problems facing the town and develop a needs-based

action plan, while the TMC was accustomed to preparing a more generic plan to avail of

funds available to it.

Participatory planning

The idea was that there should be a space for citizens to participate in the planning

process with their elected representatives, and that the town plan should be built up

from ward level micro-plans. WNNS with the ward councilor at the head were created for

this purpose. The effort was to begin with sub-ward level exercises aimed at identifying

individual and street level issues. This would then feed into the discussions held at the

ward level. The outputs from the ward level discussions would be collated and, from

these, town level needs would be distilled. These would form the basis of a visioning

exercise to draw a 25 to 30 year plan for water and sanitation for the town.

The participatory planning process could not be carried out due to several reasons, the

primary one being that the stakeholders wanted their immediate problems to be fixed

and showed little interest in developing a model for the long-term sustainability of water.

It was very challenging to mobilize and get the sanghasto engage in this process. The

studies, especially the scientific ones, were too complex to be communicated effectively

to the stakeholders.

Page 160: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

160

Institutional strengthening

To increase involvement and ownership of councilors in the IUWM programme and

create a space for decentralized planning and decision-making, an untied-fund scheme

was explored. The idea was to give untied funds of Rs.1 lakh each to the WNNS, led by

the councilor, to be used for high-priority micro-improvement works in their respective

wards. Guidelines were developed to ensure this would be used and monitored

effectively. This idea was however not implemented due to political risks and fear of

furthering a culture of patronage.

Infrastructure improvement

A key component in IUWM is the water infrastructure which is the mandate of the

Government. The strategy was to work with existing Government schemes on

infrastructure and improve their effectiveness on the ground through advisory support.

In 2007, KUWSDB had prepared the designs for the underground drainage system in

Mulbagal under the Urban Infrastructure Development Scheme for Small and Medium

Towns (UIDSSMT). The proposed design consisted of a single sewage treatment plant

(STP) of 9.9 MLD capacity outside the town along with three intermediate wet wells and

was based on the topography such that the sewage flowed by gravity to the wet wells

and, from there, it would be pumped to the STP. Upon following visits to the STP and

wet well sites, suggestions were made for the establishment of decentralized

wastewater treatment systems instead of the wet wells. These are suited for low

volumes of sewage flows, are more environment friendly and less expensive than

traditional treatment plants. The expenditure involved in pumping of sewage to the

centralized STP would be avoided. The problems of bad odour and inconvenience to

the habitations in the vicinity would also be addressed.

Another area of infrastructure improvement was the water distribution system. Under the

present system, water is distributed from an overhead tank (OHT) to the town through a

main pipeline. As the need for water increased, a few of the influential councilors tapped

directly into this main distribution pipeline resulting in several illegal connections. This

affected the service for the people further down the distribution line, with lowered

quantity and pressure. Rather than take on this difficult political issue head-on, the TMC

staff decided to use the provision under the proposed highway-widening project to

refurbish the water supply system. This would allow them to create a new section of the

distribution system replacing the old one.

Page 161: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

161

IUWM framework The Institute for Resource Analysis and Policy (IRAP), Hyderabad

was engaged to develop an IUWM framework and toolkit in parallel with the field

programme in Mulbagal. The two-year effort involved compiling water management

practices under different urban contexts and documenting the entire IUWM process

as a guide for interested towns. The immediate value to the IUWM programme was

limited. This was primarily because it was not possible to incorporate the field

lessons and challenges into the framework and to align them closely. The

framework, however, is comprehensive, covering all aspects of the IUWM cycle from

scientific and financial models to engineering and community mobilization best

practices.

Communication

The interactions with local leaders, authorities, and citizens revealed a mismatch of

expectations and responsibilities regarding various aspects of IUWM. An external

partner, Centre of Gravity, which specializes in communication design, was hired. As a

first step they conducted interviews with multiple stakeholders in Mulbagal as well as

focus group discussions in some of the neighborhoods where activities had been going

on. Their findings confirmed the need for clarity, synergy, and a resetting of

expectations.

In the light of these findings, communications architecture was developed, which

included:

Renaming IUWM as JalaJagruthi, a much more accessible and simple-to-

understand name that also establishes a direct connection with the central focus of

the programme i.e. water. Also, JalaJagruthiwas articulated as a town-pledge that

the leaders and the citizens of Mulbagal needed to commit to.

Creative ideas at three levels – first, developing pictograms for individual initiatives

like rainwater harvesting, solid waste management, upgradation of pumping

technology etc. Second, consistently presenting various facets of JalaJagruthiand

third, presenting all of this as a part of an overall initiative to transform Mulbagal into

a model town with citizen‘s participation.

d) Implementation phase

It was realized that to address multiple aspects of IUWM, such as citizens‘ participation,

urban planning, subsidiarity, environmental sustainability etc., the town would require a

different level of organizational skills, capacities and some structural changes. Hence

five implementation projects were undertaken, namely

Page 162: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

162

Energy efficiency in pumping stations

The objective was to maximize water transfer from pumping stations to OHTs/reservoirs

with optimal consumption of energy. This would be achieved by replacing low-efficiency

equipment and installing electrical equipment to facilitate clean power availability.

Site visits were carried out by the consultants and technical specifications for the

pumping and electrical machinery at the pumping stations were developed. The project

was repeatedly stalled at various points due to the absence of a strong leader from the

town or from the external support agencies, because of which projects such as this will

be subject to delays, changes and partial fulfillment of goals.

Rooftop rainwater harvesting

The objectives were to create rainwater harvesting structures in educational institutions

to meet non-potable water requirements and to thus save the treated municipal water for

other higher priority uses.

Detailed analysis on the water flows, location of sumps/tanks, volume of tanks required,

sanitation improvements and other site specific requirements were undertaken. The pilot

was taken up in two schools. The pipes were broken down by children playing in the

grounds after school hours and the structure was rebuilt to be more robust. But overall,

there was little ownership from the TMC to avail the funds for other schools and

implement the project.

Solid waste management (SWM)

The rampant practice of open defecation and of dumping garbage on the roads and in

the drains has led to deterioration of quality of ground and surface water in Mulbagal.

Objectives were to set up a system of door-to-door collection of garbage, segregated at

source. This would contribute to reduction in the contamination of groundwater,

improvement in general hygiene and town aesthetics and to explore options for setting

up an equitable and sustainable economic model in solid waste management.

The model of solid waste management proposed for the pilot wards involves collection

of segregated waste at the doorstep with the wet waste being transported to the landfill

and the dry waste sent to the local kabadivalasfor recycling. The Mulbagal model was

developed picking some elements from the other models like segregation and waste

treatment but with unique aspects like the formation of the ‗NirmalaBalagagroup to run

the solid waste management programme. A workshop to debate this model was

conducted. This was followed by formal resolutions passed by the TMC to select the

pilot areas, create the NirmalaBalagagroup, approve the tariff and bylaws, release funds

for the auto-tippers (vehicles for waste-collection), and banning plastic bags less than 40

microns thick.

Page 163: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

163

In one of the pilot areas, a Police Colony, the local Deputy Superintendent of Police

(DSP) emerged as a strong champion of the effort. Today the pilot areas are visibly

better with cleaner drains, less odour, and fewer stray animals or mosquitoes compared

to other wards.

Revival of a kalyani

This effort was outside the purview of the five implementation projects approved under

the DMA proposal. It began as an offshoot of the solid waste management project. For

over 40 years, this ancient tank was filled with solid waste, sewage, and was infested

with snakes.

A beautiful, ancient structure has been revived and has generated awe and pride

amongst the citizens. Some rare artefacts were uncovered during the cleanup process.

Beneficial side-effects of cleaning up the kalyaniinclude reduced groundwater

contamination, reduced mosquito breeding and possibly waterborne diseases. The

kalyanitriggered interest within and outside the town for reviving other structures. By

revitalizing these tanks, there is an opportunity for improving the groundwater potential,

both in quantity and quality.

Outcome and importance

At the outset, it was understood that interventions in a single, sectorally defined area of

urban water management would not be able to address all the issues, since it is shaped

by, so many other intersecting areas, such as energy, institutions, land, social issues,

and the environment. Several of the interventions needed could be legal, policy-related

or structural and therefore, beyond the scope of the programme. It was also accepted

that this approach needed a change in mindset of stakeholders at all levels, and

consequently was bound to be a long-drawn-out process.

At the same time, it was found that there has been an increasing ownership and interest

from the TMC, which has led to them taking several steps demonstrating their

commitment. Land has been allocated for a solid waste treatment plant. A lake has

been saved from becoming home to a wastewater treatment plant. Close engagement

with the Karnataka Urban Water Supply and Drainage Board (KUWSDB) led to several

important design changes in the ongoing underground drainage system and the planned

wastewater treatment plants.

IUWM is not defined through a limited set of actions. It is a commitment to a continuous,

regularly evaluated procedure with on-going choices designed to cope with changing

circumstances. It therefore requires:

• Communication, coordination & collaboration across institutional boundaries

• Cross-disciplinary interaction

• Multi-stakeholder involvement

Page 164: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

164

• Experimenting – learning – sharing

• Regular review and adjustment

• Importance of joint vision

Some of the benefits of IUWM are

• Increased water availability – by targeting inefficient use and promoting water

recycling increases the availability of water for economic development.

• Reduced cost of water treatment - by exploring pollution prevention and control

opportunities

• Increased biodiversity – by restoring urban rivers and constructing natural systems

for water treatment

• Identification of more cost effective and viable solutions – by cross-sectoral

coordination and multi-stakeholder involvement

Key learning

An idea externally conceived, however robust and sound theoretically and however

relevant it seems to be for the town, is still one that is externally imposed. It requires

time and effort to be internalized and owned by the town. The translation of the idea of

IUWM into an actual town experience assumes certain neatness in the idea of bringing

citizens action, science, and governance together, aided by a PSU, to develop an

approach that combined efficiency with fairness. The idea of embedding an externally

imposed model of social cohesion backed by good science and institutional clarity and

integrity, requires time. Also, the challenges in trying to change ways of thinking which

have historically been based on a culture of patronage are understood.

Figure: Issues affecting good water management in cities

Sustainability

Sustainable urban water management may in brief be defined as water management

that meets current social, economic and environmental needs while creating conditions

that allow these needs to also be met in the future.

Page 165: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

165

The main thrust of the IUWM programme in Mulbagal was to initiate an institutional

model where the local government promotes sustainable approaches to water resource

management with participation of the people, especially the poor, namely;

Environmental sustainability:

Preserves / restores aquatic ecosystems – Maintains the ecological balance of natural

water systems by not abstracting more than can be replenished and preventing

pollution.

Social sustainability:

Provides access to affordable water and sanitation, and protection from the water

related risks, without discrimination between different groups of society.

Economic sustainability:

Ensures the necessary financing for managing the water resources and for meeting

society‘s needs – Cost efficient operation and maintenance of water services.

Coping with an uncertain future:

Greater resilience (e.g. to climate change and uncertain future water demands) –

Through greater ability to cope with uncertain weather patterns and unknown future

water demands

Replicability

The overarching driver for adopting IUWM is to provide a sustainable urban water

service to the community, which improves human welfare while maximizing ecological

integrity of the surrounding environment.

Adopting IUWM and its iterative processes will help cities to significantly reduce the

number of people without access to water and sanitation by providing water services of

appropriate quantity and quality, and improving the health and productivity of urban

residents.

Transitioning to IUWM can be initiated by anyone, and can start at any time, using

existing planning knowledge of the urban water system. Successful adoption, however,

needs commitment to change from all parties involved. The key stakeholder groups,

together with the project champion, carry the process through to the creation of

implementation plans.

Page 166: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

166

Since the aim is to achieve sustainability, even after construction and implementation

are nominally complete, IUWM plans should be reviewed and updated on a regular

basis.

Champions

The people of Mulbagal town who volunteered and contributed to the sustenance of the

integrated urban water management are considered the champions of this initiative.

Similar Initiatives

Integrated Urban Water Resource Management (IUWRM) Programme at

Doddaballapur, Bangalore Rural, Karnataka

Costing

Particulars Details

Total Cost of the project Installation of energy efficient pumps in three pumping stations, replacing bore well pumps, implementing automation in the pumping stations and revamping the electrical distribution systems = Rs. 64 lakhs

Page 167: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

167

Annexure VIII

CONSTRUCTION OF COMMUNITY AND INDIVIDUAL TOILETS IN MULBAGAL,

KOLAR DISTRICT

Mulbagal town is located in MulbagalTaluk, Kolar district, Karnataka State; India. The

town is located at distance of 95 km from Bangalore. The town geographically lies

between 78o4‘ & 78o24‘ E longitude and 13o17‘ & 13o10‘ N latitude and has an

average elevation of 827 m (2713 feet). According to the Census data of 2011, it has a

population between 20,000- 49,999.

Situation before

Pollution of groundwater resources are geogenic and anthropogenic in origin.

Contamination of groundwater by fluoride, arsenic and dissolved salts are mainly

contributed by geological activities. Contamination of groundwater resources by

organics, heavy metals, cyanides, aluminum and nitrates are anthropogenic in origin

and arise due to uncontrolled discharges from industries, sewage treatment plants and

agricultural applications of fertilizers and in addition, groundwater contamination from

infiltration of pit toilet leachates is an alarming source of anthropogenic contamination in

India.

Of the total 14500 houses in Mulbagal, 1375 houses are toilet-less. Toilet-less

households resorted to open defecation which create nuisance. Eventually all water

sources are polluted with Nitrates and bacteria. To address the issue of water quality, it

had to be ensured that all households had toilets and that the toilets were connected to

septic tanks or to the underground sewerage system.

Description of the initiative

Arghyam, a charitable foundation set up by RohiniNilekani, has been working on

domestic water and sanitation in India since 2005. As a donor, Arghyam‘s primary focus

has been grant-making to NGOs, research and other institutions in the field of domestic

water and sanitation. Apart from that, Arghyam drives several initiatives as action-

research projects in emerging or niche areas, where it is difficult to find grantees. They

include the India Water Portal (www.indiawaterportal.org) – an online, open platform for

sharing information and knowledge among the water community, and A Survey of

Household Water and Sanitation (ASHWAS) in rural Karnataka to assess and share

citizens‘ perspectives.

Page 168: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

168

Arghyam initiated the action-research programme on construction of community toilets

and individual toilets under the Government of India (GoI) Integrated Low Cost

Sanitation (ILCS) scheme,

Applications for toilets for 240 households under the ILCS scheme were developed,

approved by the local authority, and submitted to the Government of India (GoI).Twelve

defunct community toilets were repaired and their ownership was transferred to the TMC

by the Slum Board that had originally built them 10 years ago. Four community toilets

were brought back to use with a community-managed model. In one of them, a

caretaker has been employed by the community and is sustained by the fees paid by

the households.

Operation and maintenance

Mulbagal depends on groundwater for its potable water requirement and simple on-site

pit disposal systems for human waste disposal. The study involved rigorous testing of

the water quality of 75 drinking water wells for 28 parameters in Bureau of Indian

Standards Drinking Water Specifications (IS 10500–1991) in the pre-monsoon,

monsoon and post-monsoon periods.

The implications for the Mulbagal town are several. The relatively shallow groundwater

levels within the town are not desirable from the groundwater quality perspective. There

is lesser assimilation of wastewater leaking from soak pits and the shallow groundwater

medium could connect the water supply pipelines and wastewater drainage systems,

leading to a contamination of the water supply.

The monitoring threw up a distinct pattern. The bore wells inside the town (ITS) showed

high dissolved salts, nitrates, total coliform, and E.coli presence. Comparatively, the

bore-wells located on the periphery or outside town (OTS) were mostly free of

pathogens and nitrates. It was surmised that leachates from on-site pit disposal systems

for wastewater had severely impacted the groundwater quality rendering them non-

potable.

Most bore-wells belonging to ITS series showed presence of total coliform and

E.coli, while the reverse was true of OTS bore-wells. This implied fecal

contamination from sewage infiltration and put the community at risk of contracting

waterborne diseases

Page 169: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

169

One of the key outcomes of the analysis was on pathogen movement and removal by

the soil. Bacteria and pathogens travel in the ground, and have varying survival times in

anaerobic groundwater environments. The average for coliform bacteria is 5.5 days. It

was also found that an unsaturated or vadose zone (the zone above the water table) is

the best line of defense against faecal pollution as it is less permeable. Based on this, it

will be possible to calculate the size of the zone required to protect drinking water

sources from bacteria, and similarly from nitrates and other contaminants.

The Mulbagal study showed that faecal bacteria are less mobile in dry soil, and

therefore thicker vadose zones or lower groundwater levels are beneficial in preventing

faecal contamination.

Figure: Reduction of E.coli in water with increase in vadose zone

Figure: Comparison of nitrate levels of inside town and

outside town wells

Figure:Comparison of total coliform levels of inside town

and outside town wells

Page 170: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

170

Household baseline studies on sanitation indicated that four-fifths of the town had

access to household, community, or public toilets, while the rest defecated in the open.

Bathrooms were mostly separate units inside the house. The toilets were mostly Indian

style with pour-flush model of usage. While cost of toilet construction was around Rs.

10,000, its monthly maintenance was around Rs. 105. Open defecation was observed in

23 of 27 wards, often near a water body or on open ground. Septic tanks and soak pits

constituted 77% of major on-site wastewater disposal system from the toilets. Drains

carried domestic wastewater from kitchens and bathrooms in 63% households, while

88% dumped solid waste on the streets. The critical parameters for households in

deciding service satisfaction level were quantity, quality, and supply period. Nearly all of

them were either unaware or uninvolved in any water and sanitation projects.

Community toilets

The groundwater inside Mulbagal town was found to be heavily contaminated by

nitrates and bacteria. A primary attribution was the practice of open defecation by 1,375

households, as well as inadequate treatment of sewage from existing toilets.

Objectives were to repair and revive community toilets built under the2003 Nirmal

Bharat AbhiyanScheme, which were in a state of neglect and disuse and to set up a

sustainable mechanism for maintenance of the repaired community toilets with the

involvement of citizens and the TMC.

With the help of the TMC, PSU, Arghyam, and an Anganwadi teacher, the beneficiaries

developed a management mechanism for one of the community toilets where a local

resident was appointed as the caretaker. She resides in the existing caretaker room on

the community toilet site and is paid Rs. 50 per month by each of the 35 families. She

was given training for manufacturing detergents, cleaning liquids, and growing

vegetables in the vacant land of the site. The TMC has agreed to pay for the water and

power.

About 200 people started using this community toilet facility regularly and there is no

more open defecation in that area. The caretaker and teacher are the local champions,

and the caretaker has made a livelihood out of this. A defunct public asset has been

restored and is in use. After the completion of the first toilet, three more have been

repaired and are now in use. Issues like shortage of water have cropped up and

sustainability may require continued support.

Page 171: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

171

Figure: Map of community toilets in Mulbagal

Individual toilets

In 2010, a GPS survey was conducted revealing that 1,375 of 14,500 households were

without toilets. The Government of India‘s ILCS scheme offers a subsidy of Rs. 9,000 to

build individual toilets for households below the poverty line under the condition that

they must have the:

Necessary space to construct the toilet.

Valid documents to prove ownership of the land.

Latest tax paid certificate.

Together with MYRADA, the TMC assisted households in applying for the ILCS scheme,

distributing application forms to 1,375 households through the respective councilors and

it was concluded that 240 households were best suited to qualify for the scheme. The

process of getting individual toilets under the ILCS scheme has been a long-drawn effort

and approval has not yet been received.

Page 172: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

172

Figure: ‘JalaJagruthi’ logo and pictograms developed as a part of communications

strategy

Outcome and Importance

The convergence of Community, Governance and Technology has provided the

following benefits to the community of Mulbagal.

All 35 toiletless households - 200 people are using the toilet daily.

Livelihood opportunity for a family and dignity for beneficiaries.

The unit is sustaining itself successfully.

Key learning

On-site sewage disposal system is a reality in the country and cannot be easily replaced

with more expensive offsite systems. Also, a large percentage of the country depends

on groundwater for its drinking water needs. Keeping the two realities in mind, it is

necessary to explore modifications to the on-site sewage disposal systems so that they

are able to capture the generated nitrates and not release them into the groundwater.

Replicability

The crux of matter for community toilets is maintenance. While professional contractors

carry out the construction, the caretakers maintain the facility in the coming years. As a

result, the community run model is very replicable wherever there is the willingness by

the project implementers to build the capacity of the slum residents by way of extensive

community-based federation activity.

Page 173: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

173

Costing

Particulars Details

Total Cost of the project Cost of toilet construction in each household = Rs.10,000

Operation and Maintenance cost

Maintenance of toilet in each household = Rs.105/ month

Caretaker of the community toilet is paid Rs.50/month by each of the 35 families

Page 174: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

174

Reading Material - Draft

WATER AND WASTEWATER MANAGEMENT

INDEX

Sl. No. Topics Page No.

1 Introduction to Water Management : KUDWSP, 2003 01-04

2 Operation and Maintenance of water supply system 05-56

3 Operation and Maintenance of sewerage system 57-86

4 Operation & Maintenance of electrical and mechanical components of pumping machineries in water and waste water

87-91

5 Urban lake management 92-103

6 PPP in water and waste water management 104-108

Case Studies

Annexure I: Augmentation of water supply source in Udupi City

Annexure II: Reduction in Non-Revenue Water in Kundapura Municipal Water Supply

Annexure III: Sewage Treatment Plant of 10 MLD Capacity at Jakkur, Bangalore

Annexure IV: Soil Biotechnology Based wastewater treatment Plant of 15,000 Litres/Day Capacity at Accept Society, Bangalore

Annexure V: STP ‘B‘, Vidyaranyapuram, Mysore, An Innovative sewage treatment technology

Annexure VI: Discussion - LD Authority bill passed in assembly on 7th July, 2014

Annexure VII: Integrated urban water management in Mulbagal, Kolar District

Annexure VIII: Construction of community and Individual toilets in Mulbagal, Kolar District

Page 175: Karnataka Urban Drinking Water and Sanitation Policy, 2003 · discouraging over exploitation of resources and preventing wastage. ... not have adequate capacity. Similarly, the appropriate

175

Comprehensive Capacity Building Programme

(CCBP) Under Jn-NURM,

WWWaaattteeerrr aaannnddd WWWaaasssttteeewwwaaattteeerrr MMMaaannnaaagggeeemmmeeennnttt

State Institute for Urban Development

ATI Campus, Lalitha Mahal Road, Mysore- 570 011

Tel. No. 0821-2520116/163, Fax:0821-2520164,

website:-www.siudmysore.gov.in e-mail:[email protected]