24
Page 1 of 24 Mahatma Gandhi National Rural Employment Guarantee Act, 2005 Karnataka State Convergence Plan Commissionerate of Rural Development Rural Development & Panchayath Raj Department Government of Karnataka June 2014

Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 1 of 24

Mahatma Gandhi National Rural Employment Guarantee Act, 2005

Karnataka State Convergence Plan

Commissionerate of Rural Development Rural Development & Panchayath Raj Department

Government of Karnataka

June 2014

Page 2: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 2 of 24

Karnataka State Convergence Plan

Index

Sl.No. Particulars Page No.

1 MGNREGA Act, 2005 1

Objective of the Scheme 1

2 MGNREGA in Karnataka 1 – 2

3 Why Convergence? 3

4 Modes of Convergence 3

5 Possible Schemes for Convergence 3

6 Convergence framework 4 – 7

7 A State level workshop on Convergence 7 – 8

8 MGNREGA State Convergence Plan for 2014 – 15 8

9 Convergence Road Map for 2014 – 15 to 2016 – 17 9

10 Implementing agency wise Convergence Plan

I. MGNREGA – NBA Convergence 9 – 10

II. MGNREGA Convergence with Forest Department 11 – 13

III. Convergence with Horticulture 14 – 16

IV. Convergence with Sericulture 16

V. Convergence with Watershed 16 – 17

VI. Convergence with Agriculture 17

VII. Convergence with Animal Husbandry 18

VIII. Convergence with Fisheries 18

IX. Convergence with Minor Irrigation 18

11 Hon’ble Chief Minister’s 15 Point Programme 19

12 Asset Creation 19

13 Summary of guidelines / directions 19 – 21

14 Financial Progress of Line Department works 21 – 22

Page 3: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 3 of 24

KARNATAKA STATE CONVERGENCE PLAN

Convergence of MGNREGA with other Departments & their programmes in Karnataka

1. Mahatma Gandhi National Rural Employment Guarantee Act, 2005

The Mahatma Gandhi National Rural Employment Guarantee Act, 2005 (MGNREGA) was notified on September 7, 2005. It was started in the first phase in 200 Districts from February 2nd 2006 and then gradually extended to entire country with effect from April 1, 2008. In accordance with the Act, Mahatma Gandhi National Rural Employment Guarantee Scheme has been launched, is centrally sponsored right based programme, which legally ensures 100 days employment guarantee to rural job card holder/wage seekers. It also provides to take steps for economic development in rural areas and ensure Social Justice. MGNREGS is being implemented in the state in phased manner since 2006-07. Karnataka has taken keen interest in implement of the act along with creation of assets.

Objective of scheme (that is goals)

The core objectives of the Scheme are as following:

a. Providing not less than one hundred days of unskilled manual work as a guaranteed employment in a financial year to every household in rural areas as per demand, resulting in creation of productivity assets of prescribed quality and durability.

b. Strengthening the livelihood resource base of the poor; c. Proactively ensuring social inclusion and d. Strengthening Panchayath Raj institutions

2. MGNREGA in Karnataka

a. Statistics • No of Districts: 30 • No of Taluks: 176 • No of GPs: 5631 • No of Villages: 30890 • Population in the State: 5.28 crores • Area (in Sq. ft.): 1.91 lakh sq km • No of SCs registered: 12.10 Lakhs • No of STs registered: 6.06 Lakhs • No of BPL families registered: 12.77 Lakhs • Total No of Registered Households: 57.23 Lakhs • Total No of HHs issued Job cards : 57.23 Lakhs

b. Implementation status 1. 96% of the work execution by Gram Panchayaths 2. Full integration with MIS of MoRD viz. NREGA Soft 3. 100% e-FMS (Direct Benefit Transfer) based Wage payment to Labourers

electronically to their Bank accounts in all 30 districts.

Page 4: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 4 of 24

4. 100% Electronic Muster Rolls (e-NMR) 5. Setting-up of Toll-Free Call Center: 1800 4258 666 6. About 6.70 Lakh Aadhaar seeding with MGNREGA 7. Independent Social Audit Directorate 8. Ombudsmen: Appointed in all the 30 districts; Ombudsman Appellate Authority also

set up & working. 9. SEGC have been constituted and meeting regularly 10. Biometrics & Geo-stamping introduced

c. Progress of Karnataka State MGNREGS: since inception

Year OB (In Crores)

Releases

Total Availability

(In Crores)

Expenditure (in Crores)

% (percentage)

of Utilisation

Total person

days Generated

(In Crores)

Women (In Crores)

SC/ST (In

Crores)

Average person days per family

out of 100days

(No. of days)

Central (In Crores)

State (In Crores)

Other (In Crores)

2006-07 78.49 242.5 20.34 0.00 341.33 251.9 73.80 2.22 1.12 1.08 41

2007-08 124.63 268.52 25.54 0.56 419.25 236.69 56.46 1.97 0.99 0.97 36

2008-09 235.65 379.39 43.98 8.75 667.77 357.87 53.59 2.88 1.45 1.19 32

2009-10 353.42 2407.08 253.71 24.68 3038.89 2216.93 72.95 20.04 6.85 5.07 57

2010-11 821.87 1941.55 143.53 49.46 2956.41 1860.47 62.93 10.98 4.91 2.80 49

2011-12 1095.93 662.87 159.06 37.81 1955.68 1640.99 83.90 7.01 3.23 1.68 42

2012-13 314.68 1231.94 205.99 36.15 1788.76 1457.03 81.45 6.21 2.87 1.60 46

2013-14 320.43 1596.07 265.03 11.36 2192.89 2095.22 95.54 7.18 3.34 1.71 50

d. MGNREGS Financial status of 2013-14

Sl.No Details of Grants (Rs in Crores)

1 Approved budget for 2013-14 2133.03

2 O.B. as on 01.04.2013 320.40

3 Grants received from GOI 1596.07

4 Grants received from GOK 265.03

5 Misc Receipts 11.36

Total receipts 2192.89

A Grants released to PRIs 2025.09

B Total Expenditure as on 31.03.2014 2095.22

e. Physical status of 2013-14, as on 31.03.2014

Sl.No Subject Value

1 Job Cards issued 57.24 lakh

2 No. of HHs to whom Employment is Provided 14.47 lakh

3 Person days Generated 718.86 lakh

4 HHs completed 100 days 1,17,343

5 Total works taken up (on-going+ completed) 5,44,224

6 Completed works 39,377

f. Labour Budget for 2014 – 15

1. Total Labour budget: Rs. 3151.76 Crore 2. Total Person days: 934.05 Lakh 3. Families to be covered: 18.681 Lakh

Page 5: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 5 of 24

3. Why Convergence?

The MoRD Notification dated 20th December 2013 states that

“The State Government shall take concrete steps to achieve effective inter-departmental convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the quality and productivity of assets and bring in synergy to holistically address the multiple dimensions of poverty in a sustainable manner.”

The objective of MGNREGA namely creation of durable assets and securing livelihood of rural households can be facilitated through Convergence of MGNREGA works with resources of other programmes / schemes available with Panchayaths and other line departments. These resources are not restricted to availability of funds but include technical expertise and knowhow that officials of the line departments may be endowed with.

4. Modes of Convergence There are basically three modes of Convergence: a. Labour work under MGNREGS, Material component under departmental programmes b. Each work divided into two parts-one part under MGNREGS, another under

departmental programmes c. Entire work under MGNREGS implemented by Line Department, either before or after

the departmental work (Pre / Post Convergence) Examples – Provision of seeds and fertilizers from NRHM to farmer, whose land has been improved using MGNREGA funds. Providing micro -irrigation using funds available under RKVY for horticulture plantation done under eligible MGNREGA. Supply of fingerlings by Fisheries department for a dugout pond created under MGNREGA. In these cases too, there are two distinct parts of the project.

5. Possible Schemes for Convergence

Sl.No. Scheme For Technical & Managerial

expertise

1 Central / State Finance Commission Grants Concerned line department and GPs

2 National Rural Livelihood Mission (NRLM) RD&PR Department

3 Integrated Watershed Management Programme (IWMP) Watershed Department

4 Total Sanitation Programme (TSC) Nirmal Bharath Abhiyan

5 Backward Region Grant Fund (BRGF) RD&PR Department

6 Rashtriya Krishi Vikas Yojana (RKVY) Agriculture Department

7 RRR (Ministry of Water Resources) Minor Irrigation Department

8 National Afforestation Programme (NAP) Forest Department

9 Pradhan Mantri Gramin Sadak Yojana (PMGSY) RD&PR Department

10 National Horticulture Mission (NHM) Horticulture Department

11 Schemes funded from State budget Concerned line department and GPs

Page 6: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 6 of 24

6. Convergence framework:

a. Modes of implementation: i. At Gram Panchayath level: Gram Panchayath as Programme Implementing

Agency- PIA. Karnataka has 5631 GPs, of which 5628 GPs are implementing MGNREGS Works, with technical support of line Departments.

ii. At Block/Taluka level by Line Departments, as Programme Implementing Agency (PIA): yet to be started in the state in a big way, because of certain issues, which needs resolution; only after which the Line Department will be able to really become a major player in MGNREGS implementation. Line Department can pool their own funds & can utilize MGNREGS funds under Convergence Framework; or can take up works with exclusive MGNREGS funds.

b. Implementing Agencies: A total of 9 line departments have been declared as implementing agencies of MGNREGS, in addition to the Panchayath Raj Institutions, as per the State Govt. Order No. RDP/186/MGNREGS/2012 Dt. 23.10.2013.

1. Forest Department 2. Horticulture Department 3. Water resources (Minor Irrigation) 4. Agriculture Department 5. Watershed Department 6. Sericulture Department 7. Animal Husbandry Department 8. Fisheries Department 9. Panchayath Raj Engineering Department

Officers and staff of these departments have been trained on all the critical aspects of

MGNREGA Act, Operational guidelines of 2013, 4th edition and the notification of MoRD, GOI Dt. 20.12.2013 on Schedule – I and Schedule – II. These departments have been given detailed guidelines regarding identification of eligible works, preparation of shelf of projects, preparation and approval of action plan, uploading of information on MIS, work execution, payment procedure (e-FMS), audit, social audit, maintenance of records and other relevant subjects.

c. Implementation and Monitoring Mechanism

Each Line Department at state level nominated a senior officer as Nodal Officer. Monthly review meeting with Line Department Nodal Officers is conducted by Commissioner/ Special Commissioner (Forest).

RD & PR Commissionerate conducts weekly review through video- conferencing. SATCOM Review & Training reaching out to all tiers of PRIs are conducted every 4th Saturday at SIRD Mysore/Bangalore by Additional Chief Secretary to Government, RD& PR himself.

District Convergence Resource Group constituted recently involving all concerned Line Department District Level Officers & Programme Officers headed by Zilla Panchayath Chief Executive Officer. Block Convergence Resource Group involving all Taluka level Line Department Officer headed by Taluka Panchayath

Page 7: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 7 of 24

Executive Officer. Preparation of District and Block Convergence Plan are in progress. All districts have been directed to identify 3-4 areas for Convergence and focus on them. Every Block / Taluka instructed to take up one or two cluster for intensive MGNREGA & Convergence Works for better handholding and intensive monitoring.

d. Enabling Environment:

Government orders issued for entire work, including maintenance years are to be sanctioned at one go by Gram Sabha and also the administrative approval of the same by ZP CEO. Line department District Level Officer is given power to launch the works, based on seasonality and labour availability. For line departments, unit of implementation is Taluka, accordingly is e-NMR to be given to Line Department by Taluka Panchayath Executive Officer, who is Programme Officer. 60:40 ratios for wage and material to be maintained at Taluka level for line department implementation and at GP level for GP implementation.

e. Delegation of Power:

Delegation of power for all the concerned departments on according technical sanction, administrative sanction, recording measurement and check measurement were issued as per the Govt. Order No. RDP/05/MGNREGS/2008 Dt. 06.05.2010 and an addendum No. RDP/167/MGNREGS/2010 Dt. 29.11.2010.

f. Model Cost Estimates issued:

44 number of model estimates under various categories of eligible works have been obtained, scrutinized, approved and issued. They are as under – i. Construction of dug out open wells – measuring 6, 9, 12 and 15 Mtr. Depth. ii. Water percolation structure iii. Development of 1 Ha. Forestry Plantation of Teak and or Silver iv. Development of 1 Ha. Forestry Plantation of Fruit Trees v. Development of 1 Ha. Bio Fuels Plantation vi. Development of Fruit / Bio Fuel / Fodder Garden vii. Development of Institutional Plantations – Hospitals, Schools, Hostels etc. viii. Development of Forestry / Horticulture Gardens under irrigation ix. Road side plantation (Muzafurpur Model) x. Horticulture works – Development of 1 Acr. each of Fruit Plantations of major

fruit crops like Mango, Sapota, Pomegranate, Guava, Citrus fruits, Grapes, Pineapple

xi. Horticulture works – Development of 1 Acr. each of less known fruit crops like Seetapal, Amla, Jamun, Ber, Tamarind

Page 8: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 8 of 24

xii. Horticulture works – Development of 1 Acr. each of plantation crops like Coconut, Arecanut, Oil palm, Cashew

xiii. Horticulture works – Development of 1 Acr. each of spice crops like pepper xiv. Horticulture works – Development of 1 Acr. each of perennial vegetable crops

like drum stick xv. Plantation around IHHL Toilets – Planting Mango, Sapota, Coconut, Guava,

Amla, Karibevu xvi. Integrated agriculture works – construction of vermi-compost unit, NADEP

compost unit, Liquid Bio Manure Unit xvii. Sericulture development works – development of mulberry nursery,

development of 1 Acr. of mulberry plantation, 2nd and 3rd Year maintenance of the mulberry plantation, construction of compost unit

xviii. Construction of Anganawaadi, Construction of Bharat Nirman Rajiv Gandhi Seva Kendra

g. Payment of works through e-FMS:

All MGNREGA implementing officers have been authorized to make both Wage and Material payment through e-FMS. Dongals (Digital Signatures) with password & login ID given to all G.P. implementing officers & Line Deptt. Taluka and District Officers. All Payments are to be made Jointly by PDO & Adhyaksha, in case of GP implementation and by Taluka & District Officers, in case of Line Department implementation. Biometrics started for both signatory. Geo-stamping with date for all 3 stage photos being made mandatory to be uploaded before FTO generation.

1st and 2nd Signatories: Block level officers of all the line departments are declared as first signatories and district level officers as second signatories. All these officers have been provided with DSC Dongles. Department wise number of dongles issued is as given under-

i. Forestry - 206 ii. Watershed - 102 iii. Horticulture - 136 iv. Agriculture - 147 v. Sericulture - 85

vi. Animal Husbandry - 135 vii. Panchayaths Raj & Engineering Department - 06 viii. Minor Irrigation - 03 ix. Fisheries - 25

h. Training: Two rounds of intensive training were provided at state level during December 2013 and January 2014 to the implementing officers of block and hobli/mandal level. Such kinds of training were also conducted at all the four divisions of the state, at district level and block level as well. All the modalities in implementing the scheme were dealt at length. Another round of training conducted for the District Resource Teams (DRTs) at Abdul Nazir Saab State Institute of Rural Development, Mysore on 24th, 25th and 26th of April 2014.

Page 9: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 9 of 24

i. Recruitment of Technical Officers:

Technical officers with graduate qualification on Agriculture, Horticulture, Forestry and Engineering have been recruited to assist the implementing officers of these line departments. Sector wise numbers of technical officers recruited are as under-

Engineering - 982 Agriculture - Horticulture - Forestry -

Details of job chart, responsibilities and accountability of these technical officers have been provided to all the implementing officers as per the letter No. RDP/406/MGNREGS/2014 Dt. 11.04.2014. These officers have been trained on all critical aspects of the scheme, mode of implementation and with regard to their role in implementation.

7. A state level workshop on Convergence: A state level workshop on convergence of MGNREGA with other programmes of line departments was conducted on 21.12.2013. Officers of the all the line departments – State / District / Block Level Officers, Officers of Panchayath Raj Institutions, Heads of the Rural Development Departments of West Bengal, Tamil Nadu took part in the workshop. MoRD Director MGNREGA and senior consultant guided the workshop participants. Various initiatives undertaken in the state and other participating states were discussed at length. The decisions taken at the end of the workshop were:

i. Obtaining convergence action plan of the all the line departments for the next 3

financial years (2014-15, 2015-16 and 2016-17). Line departments to separately list the programmes to be implemented fully under MGNREGS, the programmes that are to be implemented through financial convergence with the departmental schemes and those involving technical convergence.

ii. All the line departments to make budgetary provision under their departmental schemes to enable convergence with MGNREGS for the financial year 2014-15.

iii. Each district to constitute a District Convergence Resource Group and a Taluk Convergence Resource Group under the chairmanship of CEO of Zilla Panchayat and EO of Taluk Panchayath respectively.

iv. Each district to indentify 3 to 4 priority sectors for convergence and stressing on them while implementing.

v. Each block to demarcate 1 or 2 clusters, execute the converged programme for better results.

vi. Line departments to prepare model estimates of the works to be undertaken and submit the same to the Commissionerate of Rural Development for approval.

vii. Line departments to identify and mobilize the workers required for implementation of departmental works, register these groups as KAYAKA SANGA’s and to take up execution of approved works by employing them.

305

Page 10: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 10 of 24

viii. All the officers at block and district level belonging to all the nine line departments to immediately apply for obtaining DSC Dongles.

ix. Commissionerate of Rural Development having conducted elaborate training programme on MIS and e-FMS, to conduct more training programmes on demand basis.

8. MGNREGA State Convergence Plan for 2014 – 15

Sl. No

Department

Financial Convergence Technical &

Pre/post Convergence

Total convergence plan amount

under MGNREGA

Remarks Target under Departmental programmes

Target under

MGNREGA

Total amount under Financial

Convergence

Amount required under

MGNREGA

1 2 3 4 5 6 7 (4+6) 8

1 Nirmal Bharath Abhiyan

27600.00 32400.00 60000.00 0.00 32400.00 Towards construction of 6 lakhs IHHL with Rs.5400/- per IHHL under MGNREGA

2 Forest 41037.42 1520.26 42627.68 14994.01 16514.27

i.Towards SMC works in departmental plantations in forest areas. ii.For raising of 3000 km. PMGSY & other roadside plantations and 3000 Km advance works iii.100 lakh seedlings raising & planting under Farm Forestry iv.5000 Ha planting in Government/Forest land

3 Horticulture 6817.99 3869.65 10687.64 4013.23 7882.88

i.For Drip Irrigation, Nutritional Gardens and convergence of INM and IPM ii.For individual water storage structures iii.For area expansion programme under MGNREGS

4 Sericulture 4190.00 4695.80 8885.80 378.125 5073.925 i. For raising Mulberry Plantations and its

maintenance ii. For compost pits and percolation pits

5 Watershed Development

0.00 0.00 0.00 4551.36 4551.36 For saturating IWMP Batch – I watersheds

6 Animal Husbandry

506.69 1542.10 2048.79 0.00 1542.10 Towards construction of 4406 Cattle Sheds for SC/ST beneficiaries

7 Agriculture 451.00 1200.00 1651.00 0.00 1200.00 Towards construction of vermi-compost pits and liquid bio-manure pits

8 Fisheries 0.00 0.00 0.00 771.78 771.78 For 600 Fish Ponds and 30 Fish drying yards

9 Minor Irrigation 0.00 0.00 0.00 1113.65 1113.65 Towards tank rejuvenation works

10 Panchayath Raj Engineering

0.00 0.00 0.00 2500.00 2500.00 Towards 2500 Play Grounds @ 1 in each Grama Panchayath at an average unit cost of Rs. 1.00 Lakh each.

0.00 0.00 0.00 2500.00 2500.00 Towards 2500 Threshing Yards @ 1 each Grama Panchayath at an unit cost of Rs. 1 lakh each.

0.00 0.00 0.00 2250.00 2250.00 Towards 500 Grave Yard development at an unit cost of Rs. 4.50 lakh each

0.00 0.00 0.00 3000.00 3000.00 Towards 1000 Tank rejuvenation at an average unit cost of Rs. 3.00 lakh each.

0.00 0.00 0.00 630.00 630.00 Towards 1000 Drinking Water Borewell recharge structures @ Rs. 63,000/- each.

Total 80603.10 45227.81 125900.91 36702.155 81929.965

Page 11: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 11 of 24

9. Convergence Road Map for 2014 – 15 to 2016 – 17

Sl.No. Department 2014-15 2015-16 2016-17 Remarks: Annual program

1 NBA 324.00 350.00 375.00 For 6 lakh IHHL every year

2 Forest 165.14 200.00 250.00 3000 Km. /100 lakh seedlings

3 Horticulture 78.83 86.71 95.38 Drip irrigation/nutritional garden

4 Sericulture 50.74 55.81 61.39 2000 Ha Mulberry plantation

5 Watershed 45.51 57.82 37.73 IWMP Watershed saturation

6 Animal Husbandry 15.42 16.96 18.86 Cattle sheds to SCs/STs

7 Agriculture 12.00 13.10 14.54 Vermi-composting etc

8 Fisheries 7.72 8.50 12.44 Fish ponds and Fish drying yards

9 Minor Irrigation 11.14 12.25 13.50 Tank rejuvenation

10

PRED: Playground 25.00 27.50 30.00 2500 playgrounds every year

-do-: Threshing Yard 25.00 27.50 30.00 2500 threshing yards every year

-do-: Graveyard development 22.50 24.75 30.23 500 graveyards development

-do-:Tank rejuvenation 30.00 33.00 36.30 1000 tank rejuvenation

-do-: Borewell recharge structure

6.30 6.93 7.25 1000 drinking water bore-well recharge structure every year

TOTAL 819.30 920.83 1012.62

10. Implementing agency wise Convergence Plan

I. MGNREGA – NBA CONVERGENCE

• MGNREGS Rs. 04,500/- increased to Rs. 05,400/- • NBA Rs. 04,600/- Rs. 04,600/- • Beneficiary Rs. 00,900/-

TOTAL Rs. 10,000/- Rs. 10,000/- Rs. 10,000/- per unit of IHHL can be constructed even exclusively with MGNREGS funds. 5 Fruit Plants of Drumstick, Karipatta, Guava, Aonla, Mango/Sapota planned around every IHHL sump.

IEC ACTIVITIES

Door to door visits by Asha workers, Anganavadi workers, Saksharatha Preraks . Bill Collectors and Panchayath workers were used for extension activity. SHG’s and Elected Grama Panchayath Members were used for extension and in planning process. Appeal by CEO of ZP to all ZP,TP,GP and SHGs to involve and motivate community to Construct their toilets by using NBA & MGNREGA funds Kala Jathas, Street Plays, Film Shows, School Competitions, Grama Sabhas, Ward Sabhas, Exhibitions were conducted in convergence with all the Line Departments. Workshops were conducted to Engineers, PDOs and Related officers of district level, block level and Panchayath level. Capacity building programmes were conducted to Grama Panchayath Chairman, Zilla Panchayath Members, Block Panchayath Members and Grama Panchayaths Members. Shramadhan programmes conducted at many places.

A special social audit of all IHHLs constructed during 2013-14 were conducted in March 2014 and the findings were encouraging, regarding quality, completion of construction and their usage. There are some shortcoming on which follow up actions are underway.

Page 12: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 12 of 24

CONVERGENCE PROCESS

IHHL: 2013 – 14 Progress

Sl.No. State Total IHHL Target Total Ach., till

31.3.2014

1 BAGALKOT 12000 10075

2 BANGALORE RURAL 17919 10544

3 BANGALORE URBAN 18000 9003

4 BELGAUM 30000 38606

5 BELLARY 22000 13998

6 BIDAR 15000 9289

7 BIJAPUR 22000 16109

8 CHAMARAJANAGAR 16000 14403

9 CHICKMAGALUR 30001 13637

10 CHIKBALLAPUR 20000 17311

11 CHITRADURGA 20000 14119

12 DAVANGERE 30000 24572

13 DHARWAD 18000 19884

14 GADAG 24000 14246

15 GULBARGA 20000 14731

16 YADGIR 12000 17187

17 HASSAN 25000 13108

18 HAVERI 22000 6895

19 KODAGU 12000 15992

20 KOLAR 30000 54051

21 KOPPAL 15000 17033

22 MANDYA 25030 4477

23 MANGALORE(DK) 5950 29046

24 MYSORE 30000 13519

25 RAICHUR 10000 18247

26 RAMANAGARA 16000 12473

27 SHIMOGA 20000 34780

28 TUMKUR 30000 10669

29 UDUPI 16218 9282

30 UTTAR KANNADA 15920 8231

GRAND TOTAL 600000 505517

Page 13: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 13 of 24

II. MGNREGA CONVERGENCE WITH FOREST DEPARTMENT

a. Entire work under MGNREGS-Implementation and Technical supervision by

Forest Department:

i. All Block plantations of 10 acres and above in Forest/Government

land/Institutional area

ii. All Roadside Plantations, except those within the village

iii. All Nursery Seedlings raising works

iv. Individual Farmer’s land planting & maintenance works

v. Soil & Moisture Conservation works in forest/wildlife/government land by

DCF (T)/DCF (WL)/DCF(SF) respectively

b. Entire work under MGNREGS-Implementation by Gram Panchayath and

Technical supervision by Forest Department

i. All Block plantations in Government land/ Institutional area below 10 acres

ii. Individual Farmer’s land planting & maintenance works

iii. Planting alongside roads within the village

iv. Soil & Moisture Conservation works outside Forest areas

c. Implementation methodology: The Action Plan of works for the entire duration of 5 years in case of plantation works, including advance works, creation & maintenance, shall be prepared by Line Department Taluka Level Officer, based on model cost estimates given by Head of the Forest department/Commissionerate of Rural Development. The Line department District Level Officers shall obtain the Action Plan of works; scrutinize them and send them for obtaining Gram Sabha Approval. After Gram Sabha approval, the same is sent by P.O. for obtaining approval of ZP. CEO ZP, who is the District Programme Coordinator, shall give administrative and financial approval to the Action Plan. The Line department shall give technical sanction to the Estimate of Work, for the entire duration of 5 years in case of plantation raising works, as per financial delegation and shall get the DPR frozen in P.O. Login and issue work launching order, based on seasonality and labour availability. The Taluka level officer of line department shall obtain e-NMR from P.O. The line Department shall after executing the works and after closure of NMR and Check-Measurement shall make payment through joint login of Taluka and District Officer into bank account of job-card holder and vendor, in case of material payment.

The line department shall assist Gram Panchayaths in preparation of Action Plan, Sanctioning of Estimates and Check- Measurement of works for implementation of works, which are taken up by them.

d. Ownership of trees: In case of Roadside plantations, tree- patta shall be given to all adjoining farmers as per TREE PATTA SCHEME G.O. No. FEE 50 FAP 2000 dated 19.6.2002. Wherever adjoining farm land is not there or he/she is not willing, in such cases

Page 14: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 14 of 24

tree- patta shall be given to the Job Card holder working for creation and maintenance of roadside plantation, in line with Mujaffarpur model, communicated by MoRD.

As per above G.O., in case of trees planted in Institutional areas and lands of other Government Departments, the cost of raising and maintenance of plantations for 3 years shall be under Departmental scheme /or MGNREGS. However, protection and further maintenance is the responsibility of concerned institution/community/ department, who shall have full rights regarding usufructs. However, the net income from final harvest of trees raised under the scheme shall be shared in the ratio of 50:50 between Government and the concerned institution/community/department. In case of trees planted in Forest and in other Government Land, as per the scheme of Joint Forest Planning and Management in G.O. No. FEE 50 FAP 2000 dated 19.6.2002, Village Forest Committee shall be constituted and further maintenance and revenue sharing shall be carried out accordingly.

Fruit plants of Seetaphala, Aonla, Grafted Mango, Grafted Tamarind, Grafted Jackfruit etc planted inside or adjoining village may be entrusted to SHGs for protection and maintenance @ 1 km each, who will have usufruct rights, while the trees will belong to the Gram Panchayath.

e. Outcome measurement:

Survival and growth are the primary criteria to monitor success. However, department need to provide the expected outcomes and methodology to measure them.

f. MGNREGA Convergence Framework: FOREST DEPARTMENT

Sl. No.

Activity With Schemes Annual physical

target Implementing

Agency Remarks

1 SMC Works in plantations and Forest areas

NAP, Bamboo Mission, KFDF, CAMPA , 13th FC, DDF, etc.,

10,000 Ha. Territorial DCFs

100 Ha per Taluka

2 Afforestation outside forest area

PMGSY roadside planting 3000 Km

Social Forestry DCFs

30-40 Km per Taluka

Other roadside planting 1000 Km 10-20 Km per Taluka

Institutional area planting 3000 Ha 30 Ha per Taluka

Canal Bank / Other Govt., Land planting

3000 Ha 30 Ha per Taluka

10,000 Ha/Km

3

Farm Forestry (Individual beneficiary work, including kitchen garden at homestead/NBA toilet sumps)

Exclusive MGNREGS funds 100 lakh seedling Social Forestry DCFs

Not more than 10 lakh per District

4

Wildlife Improvement works- SMC like Check dam, Nala Bunds / Water Hole creation/ Tank Rejuvenation

Wildlife Management programmes

As per actual requirement

Wildlife CFs/DCFs

Page 15: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 15 of 24

g. MGNREGS-Forest Convergence Framework:

Sl. No.

Particulars of Plantation Works

Type of activities to be executed under Dept. Budget Head

Type of activities to be executed under MGNREGS

1 Advance Works -Nursery Development -Raising of Seedlings

-Pitting works -Trenching works

2 Creation of Plantations

Planting, Cattle Proof Trenches Watch & Ward

-SMC Works -Weeding/Soil Working/Hoeing

3 Maintenance of plantations

-Casualty replacements - Watch & Wards

-Soil Working -Weeding -Fire tracing

h. Forestry Model Cost Estimates sanctioned during 2013-14

Model

No. Type of Plantation No. of Plants 2013-14 2014-15 2015-16 2016-17 2017-18 Total

Wage: Material

Date of issue

09 1. Roadside plantation 200/Km

(Pit model) 76900 76500 41510 43320 46470 284700 70:30 13-8-2013 &

05-10-2013

01 2. Farm Forestry – Teak

100/Ha (Pit model)

960 4670 900 870 - 7400 78:22 29-10-2013

02 -do- – Silver Oak 100/Ha

(Pit model) 1150 4670 910 870 - 7600 75:25 29-10-2013

03 -do- – Fruit Yielding / Bio-fuel

100/Ha (Pit model)

1800 7860 1170 870 - 11700 73:27 29-10-2013

3. Plantation in Govt. land

04 Fruit/Fodder/Bio fuel Plantation

400/Ha (Pit model)

35150 16780 12300 12120 14250 90600 84:16 29-10-2013

06 Irrigated Fruit Orchard

100/Ha (Pit model)

37100 30650 17500 17200 9850 112300 74:36 29-10-2013

07 Fruit/Fodder/Bio fuel Plantation

800/Ha Trench

61750 32700 20600 20500 22050 188500 88:12 29-10-2013

08 Firewood Plantation 1200/Ha Trench

54400 27700 17100 15500 13100 127800 89:11 29-10-2013

05 4. Plantation in School / Institutions

200/Ha (Pit model)

25750 39900 5500 1520 1530 74200 75:25 29-10-2013

10 -do- – Bio- fencing Plantation

270/100 m Trench

1850 23240 5870 5280 4960 41200 86:14 08-01-2014

03 (II) 5. Farm Forestry – (Melia dubia)

140/Ha (Pit model)

2750 10905 1660 1215 - 16530 66:34 08-01-2014

01 (I) 6. Farm Forestry (Teak block pltn)

640/Acre 5000 29000 6200 5450 - 45650 77:23 11.02.2014

Page 16: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 16 of 24

III. CONVERGENCE WITH HORTICULTURE

a. Present status Horticulture Department is one of the major departments since 1963 with 410 farms & nurseries (15732 acres) and 23 parks & gardens. The state is one of the leading Producer of Flowers, Plantation crops, Vegetable & Fruits. Karnataka stands 3rd & 7th rank in Horticulture Area & Production in the country respectively.

b. Requirements identified Sustainable land development activities Strengthening soil and water conservation Maintenance of Horticulture garden /plantation Rejuvenation of unproductive gardens /senile plantations

c. Activities considered for convergence Development of fruit gardens/ plantation crop gardens Bund plantation of horticultural crops Rejuvenation of coconut, mango, cashew and lime orchards Drip irrigation in new AEP plots Water storage tanks. Opening of trenches for laying out main and sub- main pipes in drip irrigation

systems Opening of trenches/catch pits, Pitting, Watering, Weeding, Bio- fencing Nutritional gardens

d. Schemes considered for convergence Central Sector Schemes-National Horticulture Mission (NHM)

- National Mission on Micro- Irrigation - Coconut development Schemes

State/District Sector Schemes Assistance to farmers for development of horticulture gardens Comprehensive Development of Horticulture(CHD)

e. Expected outcome of convergence

Enabling higher number of beneficiary coverage

Page 17: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 17 of 24

Effective channelization of production resource & investment Conversion of unproductive and senile orchards/ plantations Development of quality orchards Economic and nutritional improvement and sustainability.

f. Cost models approved and issued

SI. No

Crops Spacing

(m) Material cost

(in Rs.) Labour cost

(in Rs.) Total

(in Rs.)

1 Grape (seedless) 3.5X1.8 159958 66128.3 226086

2 Grape (seeded) 7.5X3.5 124050 27989 152039

3 Areca nut 2.7X2.7 22785 64914 87699

4 Drumstick 2X2 14940 35554 50494

5 Mango 6X6 14045 26396 40441

6 Pomegranate 5X5 17797 17554 35351

7 Custered apple 4.5X4.5 10023 23833 33856

8 Pepper (in Areca garden)

2.7X2.7 12389 20884 33273

9 Amla 5X5 7584 21433 29017

10 Coconut 9X9 7800 21121 28921

11 Tamarind 8X8 8801 19868 28669

12 Guava 6X6 12021 14566 26587

13 Mango 10x10 11707 14684 26391

14 Sapota 10X10 11707 14684 26391

15 Oil palm 9X9X9 12963 12619 25582

16 Ber 6X6 6214 17233 23447

17 Cashew 7.5X7.5 7238 12176 19414

18 Jamun 8X9 3821 13200 17021

19 Pepper (in Coconut garden)

8X8 2491 5772 8263

g. Horticulture department Convergence Plan for 2014-15 (Rs. in Crores)

SI. No

Programme Total Area (in Acre)

Dept. share

MGNREGA share

Total Budget

1 Installation of Drip irrigation in new AEP plots 5625 46.96 12.84 59.80

2 Rejuvenation of coconut gardens 1050 1.13 0.17 1.30

3 Individual Water Storage Tanks under NHM, in convergence

105 1.04 1.43 2.47

4 Installing Drip and sprinkler irrigation facilities in already est. gardens under MGNREGS

4036 14.77 1.30 16.07

5. Planting 5 Fruit Plants around IHHL/Houses under IAY/Ashrya Yojana

95,000 (No.) 1.00 3.05 4.05

6 Nutritional garden in schools/hostels/ hospitals 1200 (No.) 0.24 0.56 0.80

7 INM/IPM in already established gardens under MGNREGS

6,000 (No.) 0.96 0.02 0.98

8 Water storage tanks in already est. gardens under MGNREGS

2,500(No) 0 47.14 47.14

9 Area Expansion Programme 1950 0 12.32 12.32

Total 12766 66.10 78.83 144.93

Page 18: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 18 of 24

h. HORTICULTURE ROADMAP for 2014-15 to 2016-17 (Rs. in Crores)

SI. No

Programme 2014-15 2015-16 2016-17

1 Installation of Drip Irrigation in new AEP plots 12.84 14.17 15.00

2 Rejuvenation of coconut gardens 0.17 0.19 0.20

3 Individual Water Storage Tanks under NHM, in convergence with NREGS

1.43 1.58 1.75

4 Installing Drip and sprinkler irrigation facilities in already est. garden under MGNREGS

1.30 1.42 1.50

5. Planting 5 Fruit Plants around IHHL/Houses under IAY/Ashrya houses etc

3.05 3.36 3.50

6 Nutritional garden in schools/hostels/ hospitals 0.56 0.62 0.75

7 INM/IPM in already established gardens under MGNREGS

0.02 0.02 0.03

8 Water storage tanks in already established gardens under MGNREGS

47.14 53.03 60.33

9 Area expansion programme 12.32 12.32 12.32

Total 78.83 86.71 95.38

IV. CONVERGENCE WITH SERICULTURE

a. Model Cost Estimate sanctioned:- 1. Raising of Mulberry Nursery (1065 plants/acre): Rs. 143,000/- 2. Raising of Mulberry Plantation (5445 plants/acre): Rs. 1,39,666/- 3. Maintenance of 2nd/3rd year Mulberry Plantation: Rs. 1,71,074/- 4. Compost Pit: Rs.3300/-

b. MGNREGA –Sericulture Dept. Convergence Plan (Rs. in lakhs)

Sl No

Year Programme Total area

(acre) Department

share

MGNREGS share Convergence Total Labour Material Total

1 2 3 4 5 6 7 8 9 (5+8)

1 2014-15 Est. of New Mulberry plantation

5,000 4190 3628 1446 5074 9264

2 2015-16 -do- 6,250 5238 3991 1591 5582 10820

3 2016-17 -do- 6,250 5238 4176 1694 5870 1110.8

V. CONVERGENCE WITH WATERSHED PROGRAMMES

i. Convergence of IWMP WITH MGNREGA IWMP • The objectives are to reduce and prevent soil erosion, regenerate natural

vegetation, increase rain water impounding and recharge ground water table • IWMP adopts a sub-watershed approach consisting of hydro geological units

normally averaging 5000 ha. Cutting across several GPs jurisdiction. • All activities of soil & water conservation measures on all lands within watershed

irrespective of land ownership and socio-economic restriction

Convergence of IWMP with MGNREGA • Unit Cost under IWMP: Plain Areas: Rs.12000/ha (Rs.7200/ha for work

component); Hilly & Desert Areas: Rs.15000/ha (Rs.9000/ha for work component)

Page 19: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 19 of 24

• The additional activities planned in excess of IWMP grants to saturate these watersheds are proposed for taking up under MGNREGA.

• The additional activities mainly on common land and drainage line and eligible individual farmers land shall be taken up under MGNREGA.

• Preparation of entire action plan through PRA, • Obtaining approval of Grama Sabha for entire action plan.

ii. CONVERGENCE of IWMP with MGNREGA

Sl. No.

Batch / Year

Year for MGNREGS

Works Activities Proposed

Extent in Ha.

No of Structures

Amount (Rs. In Crores)

1 BATCH-1 (2009-10)

2014-15 Check Dams, Nala Bunds, Vented Dams etc

37,928 2188 45.51

2 BATCH-2 (2010-11)

2015-16 Check Dams, Nala Bunds, Vented Dams etc

52,103 2976 57.82

3 BATCH-3 (2011-12)

2016-17 Check Dams, Nala Bunds, Vented Dams etc

31,443 1797 37.73

TOTAL 1,21,474 6961 141.06

VI. MGNREGA CONVERGENCE WITH AGRICULTURE DEPARTMENT

Model Cost Estimates sanctioned for: 1. Vermi-compost pit Rs.. 20,500/- 2. NADP Compost pit: Rs. 22700/- 3. Liquid Bio-manure Pit: Rs. 2983/-

Agriculture Department Convergence Plan for the year 2014-15 under MGNREGA (Rs. In Crores)

Sl. No.

Particulars of Components Planned

Physical Nos.

Total Cost

Cost under MGNREGS

Cost to be borne by KSDA

Cost to be borne by beneficiaries

1 Vermi-compost pits 6250 12.81 6.9 2.50 3.41

2 Liquid bio-manure pits 40200 11.99 5.1 2.01 4.88

Total 46450 24.80 12.0 4.51 8.29

Convergence Plan for the year 2015-16 under MGNREGA (Rs. In Crores)

Sl. No.

Particulars of proposed work

Physical Nos.

Total Cost

Cost under MGNREGS

Cost to be borne by KSDA

Cost to be borne by beneficiaries

1 Vermi-compost pits 6875 14.09 7.4 2.75 3.94

2 Liquid bio-manure pits 45000 13.42 5.7 2.25 5.47

Total 51875 27.51 13.1 5.00 9.41

Convergence Plan for the year 2016-17 under MGNREGA (Rs. In Crores)

Sl. No.

Particulars of proposed work

Physical Nos.

Total Cost

Cost under MGNREGS

Cost to be borne by KSDA

Cost to be borne by beneficiaries

1 Vermi-compost pits 7500 15.38 8.,27 3.00 4.11

2 Liquid bio-manure pits 49950 14.90 6.27 2.50 6.13

Total 57450 30.28 14.54 5.50 10.24

Outcome: Increasing production organic manure in farmer’s field, thus enriching the soil organic matter content which in turn leads to enhanced agricultural productivity.

Page 20: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 20 of 24

VII. CONVERGENCE WITH ANIMAL HUSBANDRY DEPARTMENT

Animal Husbandry department has programme during 2014-15 under state SCP and TSP to provide 3326 scheduled caste and 1080 scheduled tribe beneficiaries @ Rs. 70,000/- each for providing two cows to each. Out of this, Rs. 11500/- is towards cattlesheds, which shall be converged with MGNREGA for construction of proper Cattlesheds at an unit cost of Rs. 35,000/- each to SC/ST beneficiaries

(Rs. in lakhs)

Sl. No.

Important components

planned

Financial Convergence Technical &

Pre/post Convergence

Total convergence plan amount

under MGNREGA Target under Departmental programmes

Target under MGNREGA

Total amount under Financial

Convergence

Amount required under MGNREGA

1 2 3 4 5 6 7

1 Cattle-sheds 506.69 1035.41 1542.10 0.00 1035.41

Total 506.69 1035.41 1542.10 0.00 1035.41

VIII. CONVERGENCE WITH FISHERIES DEPARTMENT

Fisheries department during the year do not have any programme to provide fish fingerlings. Hence MoRD has been requested to include Fisheries as one of the eligible income generating works under individual category. Till then only Fish ponds and Fish drying yards have been approved under MGNREGA and accordingly technical convergence plan with Fisheries department has been planned.

(Rs. in lakhs)

Sl. No.

Important components planned

Financial Convergence Technical & Pre/post

Convergence Total convergence plan amount under

MGNREGA Target under Departmental programmes

Target under MGNREGA

Total amount under Financial Convergence

Amount required under MGNREGA

1 2 3 4 5 6 7

1 Fish Ponds 0.00 1244.410 1244.410 0.00 1244.410

2 Fish Drying Yards 0.00 41.886 41.886 0.00 41.886

Total 0.00 1286.296 1286.296 0.00 1286.296

IX. CONVERGENCE WITH MINOR IRRIGATION DEPARTMENT

There is a lot of scope for tank rejuvenation works. However most of the Minor irrigation tanks have recently been tackled either under World Bank assisted Karnataka Community Based Tank Management project and remaining being tacked under RRR programme. They have been requested to take up tank rejuvenation works under MGNREGA for works, which can be undertaken by MGNREGA Workers, viz Feeder channel clearance, Shrubs and weeds removal from Bund and irrigation canal desiltation and after which tender work under departmental programmes to be undertaken.

(Rs. in lakhs)

Sl. No.

Important components planned

Financial Convergence Technical & Pre/post

Convergence Total convergence plan amount under

MGNREGA Target under Departmental programmes

Target under MGNREGA

Total amount under Financial Convergence

Amount required under MGNREGA

1 2 3 4 5 6 7

1 Rejuvenation of Tank Works

0.00 1113.65 1113.65 0.00 1113.65

Total 0.00 1113.65 1113.65 0.00 1113.65

Page 21: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 21 of 24

11. Hon’ble Chief Ministers 15 point programme

Hon’ble Chief Minister of Karnataka on 26th October launched 15 RD&PR programmes, out of which 10 programmes are being implemented under MGNREGA. With a purpose to take the programmes of the scheme to the people, 50,000 sets of Kannada and 1000 sets of English booklets on the below mentioned subjects were released and made available to all the Gram Panchayaths and field level functionaries. Details of the works and mode of implementation have been covered in local, easily graspable language.

i. Farmers’ Land Development

ii. Toilet to every home

iii. Our Village – Our Water

iv. Our Village Tank (12,000 tanks targeted to be rejuvenated)

v. Sheep / Cattle Sheds

vi. Developing Burial Grounds (5000 targeted @ one per GP)

vii. Our Land- Our Way

viii. Play Grounds (5000 no, @ one per GP)

ix. Farmers’ Threshing Yard

x. Rajiv Gandhi Seva Kendra

12. Asset Creation

Asset creation has been given due importance under the scheme – whether implemented fully under MGNREGS or in convergence with other programmes of line departments. Enough measures are in place to ensure creation of tangible / measureable assets while providing employment. To quote a few such assets:

i. Water harvesting and conservation structures like farm ponds, check dams, contour trenches, farm bunds, boulder checks, drip and sprinkler irrigation systems, de silting of irrigation tanks and other water bodies.

ii. Forestry Plantation – Block Plantation, Road Side Plantation, Plantation along bunds, irrigation tanks, Farm forestry, etc.

iii. Horticulture Plantation – Fruit, Plantation and Spice Crops Plantation in eligible farmers’ farms, Govt. Horticultural farms etc.

iv. Sericulture Plantation of mulberry in eligible farmers’ land. v. Flood preventing protective structures. vi. Construction of IHHL, IAY Houses, Anganawaadi Buildings, Bharath Nirman Rajiv

Gandhi Seva Kendra. vii. All weather roads – building and maintenance.

13. Summary of guidelines / directions issued to the heads of the line departments and State Nodal officers of MGNREGS (through regular meetings and video conferences)

i. Field level officers and staff to conduct survey at village level in due consultation with the Villagers, Gram Panchayat members and other organizations to find out the

Page 22: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 22 of 24

demand for work and the works which are in demand in public land as well as the lands of private individuals. Based on this, concerned department and Chief Executive Officers of Zilla Panchayats to prepare a list of indicative eligible works along with indicative targets after due consultation with the field level and district level officers. The same to be communicated to the field level officers, who would in turn, would place the list with suitable alterations suiting to the local needs before the grama sabha for approval.

ii. Heads of the departments to make financial provision under their departmental schemes, to enable financial convergence with the MGNREGS. Line departments to prepare a comprehensive action plan with financial and physical indicative targets for

a. Works to be taken up fully under MGNREGS b. Works involving financial convergence with departmental schemes c. Works involving technical convergence only

iii. Line departments to prepare road map of convergence for the next three financial years – 2014-15, 2015-16 and 2016-17.

iv. Commissionerate of Rural Development to conduct meeting of state level nodal officers every month. Video conference with the implementing officers to be conducted every month.

v. Executive officers of Block Panchayat at block level and Chief Executive Officers at Zilla Panchayat level to conduct regular review meetings exclusively for line departments to review the progress, issue necessary guidelines and clarifications and to solve field level problems.

vi. Since, taluk (block) has been declared as implementation unit for the line departments, Executive Officers (Programme Officers) of Block Panchayat to create and issue e-NMRs to the taluk (block) level implementing officers of line departments. Taluk / Block level line department officers to place work demand online only to programme officers of block Panchayat, to ensure timely issuance of e-NMR and such other follow ups.

vii. Line departments especially developmental departments like – Agriculture, Horticulture, Forestry, Sericulture and Animal Husbandry to prepare and get approval for a variety (in terms of capacity, design, needs etc.) of model estimates to have better flexibility, while implementing and to provide different needy options for the beneficiary.

viii. Wage, Material and Administrative expenses incurred from the login of block level officers of implementing departments only to be computed for the progress of the concerned line department from here afterwards.

ix. Ridge to Valley Concept: A joint circular by Additional Chief Secretary, RD&PR Department and Principal Secretary, Agriculture Department have been issued, vide No. RDP/186/EGS/2013 for taking up comprehensive development of watershed. Watersheds identified and chosen for implementing Integrated Watershed

Page 23: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 23 of 24

Management Project (IWMP) to be considered as a single unit for treating the entire area comprehensively to have better impact. Under MGNREGA all soil and moisture conservation works in public land and individual Land development works in the lands of eligible beneficiaries are to be taken up, so as to saturate the watershed.

In watershed areas which do not fall under IWMP, entire public land treatment and land development works of eligible beneficiaries are to be taken up under MGNREGA. In both these kinds of watersheds, if there are any private lands belonging to farmers other than those eligible ones under the act, like those of medium and large holdings, watershed works to be taken up under IWMP or other schemes of Watershed Development Department. The entire watershed has to be treated comprehensively until saturation.

x. Benefits to eligible beneficiaries only: A clear directive from the Commissionerate of Rural Development has been issued to all the implementing officers as per the circular No. RDP 417 MGNREGS 2014 Dt. 21.04.2014, clarifying the selection of eligible beneficiaries listed in the MoRD Notification Dt. 21.12.2013, on priority basis for implementing individual works. It has been directed to first take up the beneficiaries belonging to Scheduled Cast and Scheduled Tribes and then consider the other 8 categories, after exhausting which only the beneficiaries belonging to small and marginal categories to be considered. In cases, where the works are executed fully under MGNREGS, all the works bearing more than 40% material cost are to be invariably earmarked and executed in fields of Scheduled Cast and Scheduled Tribes only. If the beneficiaries belonging to other eligible categories come forward to contribute to meet the excess material cost (of more than 40%), then they could be considered for such material intensive works, like Cattlesheds, under individual category.

xi. Line departments have been directed to identify and mobilize workers of their own, register them in groups of 15 to 20 members (called as KAYAKA BANDHUS)

xii. Block wise and district wise list of beneficiaries who were provided with cattle under Special Component Plan (SCP) and Tribal Sub-Plan (TSP) by the State Animal Husbandry Department during the financial year 2013-14 is available at the block and district level. The department has been requested to take action to build cattle sheds to those beneficiaries who don’t have the one, under MGNREGS. The department has also been requested to furnish the list of identified beneficiaries under SCP and TSP for the financial year 2014-15, to take up building of cattle shed to the beneficiaries.

xiii. Administrative Expenditure: Permission has been accorded to implementing officers of line departments to utilize one percent of the wage expenditure incurred from their login for essential administrative requirements, as per letter no.RDP/186/NREGS/2013, dated 30-04-2014.

14. Financial Progress of Line Department works:

A total of Rs. 18484.00 lakhs has been incurred as expenditure for the works of line departments during the year 2013-14, of which Rs. 9761.00 lakhs was from the login of Gram Panchayaths and Rs. 8723.00 lakhs was from the login of implementing officers

Page 24: Karnataka State Convergence Plan · convergence till the last mile implementation level of the works under the Scheme with other Government Schemes / programmes so as to improve the

Page 24 of 24

of line departments. Out of this, Rs. 4227.00 lakhs was incurred from the login of officers of Forest Department and Rs. 3635.00 lakhs was booked from the login of officers of Watershed Development Department. As all the payments (of both wage and material) in the state are being realised online through e-FMS, the less incurrence of expenditure from the login of implementing officers of line departments is obvious because of the time taken to bring all the implementing officers of line departments under e-FMS net. However, the expenditure from their login is expected to pick up during the financial year 2014-15. For this it is requested to provide i) DPR Freezing, ii) NMR Generation and iii) Material bill generation from the login of Line Department.

(T. M. Vijaybhaskar) Additional Chief Secretary to Government

Rural Development & Panchayath Raj Department Government of Karnataka, Bangalore