KAREHAMN WINDFARM FOUNDATIONS, SWEDEN
Studiedag PIANC Jongeren, 26 april 2012
2
1. GENERAL
2. 3 PHASES:
COMBINED WORKS – Civil & Marine Works:
1. DESIGN
2. ONSHORE – Prefabrication
3. OFFSHORE – Installation
TOPICS
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN
3
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN1. GENERAL
EMPLOYER: E.ON Vind Sverige AB
(subsidiary of E.ON AG, Düsseldorf)
CONTRACTOR: Jan De Nul N.V.
CONTRACT: Design & Build of 16 GBF’s (Gravity Based Foundations)
Main Subcontractor: Heavy Lift RAMBIZ with SCALDIS
CONTRACT PRICE: ~ 25,6 mio €
SCHEDULE: 7 SEP 2011 – Time for Completion: 30 SEP 2012
9 10 11 12 1 2 3 4 5 6 7 8 9
DESIGN and ENGINEERINGCONSTRUCTIONINSTALLATION
6 months5 months
4 months
4
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN
LOCATION: ÖLAND, SWEDEN – 5km offshore
1. GENERAL
Baltic Sea
Glacial Tillwith boulders
5
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN
V112 3 MW Turbines of VESTAS
16 GBF’s in reinforced concrete
Varying height 12.5 – 24.5m
Dia. Foundation 18m
1,800 Tonnes
1. GENERAL
6
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.1 DESIGN
TENDER DATA
1st PHASE: 1st iteration – 3 cases
-> Draft Design Basis and Design Loads by Employer
-> Draft Design, including stiffness, mass distribution and drawing withgeometric dimensions by Contractor
2nd PHASE: 2nd iteration – 4 cases
-> Final Design Basis and Design Loads by Employer
-> Final Detailed Design by Contractor (after 5 months)
-> Certification DNV (after 6 months)
7
Natural Frequency
Extreme Events
Corrosion and cathodic protection
Ship impact analysis
Geotechnical design
Hydrodynamic design
Structural design
Gravel bed design
Scour protection
Implementation of WTG connection
Fatigue check
Physical model tests
Incorporate Contractor’s functional requirements to the structure duringtransport and installation
Calculate weight and centre of gravity of foundation structure
Ballast analysis (martite…)
Secondary Steelwork; Detailed design
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.1 DESIGN
8
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.1 DESIGN
9
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.1 DESIGN
10
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.2 ONSHORE
Port of Zeebrugge
DN143 (24,000T barge) – 12 elements
DN120 (10,000T barge) – 4 elements
Barge deck preparations
Steel reinforcement prefabrication
4 Tower cranes, 1 Mobile crane 60T, telehandler, generators
11
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.2 ONSHORE
Main Quantities:
• 10,000 m³ concrete C45/55 CEMIIIALA S4
• ~ 630 m cooling pipes in the icecone (~ 10km total)
• XXX Tons of reinforcement steel
• Some sections 435 kg/m³reinforcement
• Average of 3.5 complete steelformwork sets
• Upto 60 pax manpower – 1 shift of12hr
12
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.2 ONSHORE
Secondary (steel) items / element:
BAC (Bolted Anchor Cage) – 12T; 160 bolts M36
2 J-tubes & cable hang-offs
10 anodes per element
Lightning protection
Railings & gates
Bollards
Emergency ladder
4 lifting points
External Working platforms
Water inlets, drainage outlets, ballast openings…
13
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.3 OFFSHORE
1. SEABED PREPARATION
Excavation/dredging with backhoe dredger type ‘Jerommeke’
Check of soil parameters
Placing of the gravel bed + survey check
14
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.3 OFFSHORE
2. INSTALLATION OF GBF’s
Installation of the GBF’s with RAMBIZ
15
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN2.3 OFFSHORE
3. BALLASTING & SCOUR with multipurpose pontoon DN109
Ballasting of the shaft part
Ballasting of the ballast chambers
Installation of Scour protection
16
1. GENERAL2. 3 PHASES
1. DESIGN2. ONSHORE3. OFFSHORE
Studiedag PIANC Jongeren, 26 april 2012KAREHAMN WINDFARM FOUNDATIONS, SWEDEN
Questions … ?
END