25
Kansas Renewable Energy & Efficiency Conference ‘07 Smoky Hills Phase I Wind Project Update

Kansas Renewable Energy & Efficiency Conference ‘07

  • Upload
    marcus

  • View
    33

  • Download
    0

Embed Size (px)

DESCRIPTION

Kansas Renewable Energy & Efficiency Conference ‘07. Smoky Hills Phase I Wind Project Update. TradeWind An Experienced Power Team. Founded 2001 Lenexa, Kansas Based Senior managers have 60+ years Utility and IPP experience Directly managed - 5,300 MWs valued at over $5 Billion - PowerPoint PPT Presentation

Citation preview

Page 1: Kansas Renewable Energy & Efficiency Conference ‘07

Kansas Renewable Energy & Efficiency Conference ‘07

Smoky Hills Phase I Wind Project Update

Page 2: Kansas Renewable Energy & Efficiency Conference ‘07

• Founded 2001

• Lenexa, Kansas Based

• Senior managers have 60+ years Utility and IPP experience

• Directly managed - 5,300 MWs valued at over $5 Billion

• 2,300 MWs of wind development in central USA

Owned by local investors and Enel S.p.A.

TradeWind An Experienced Power Team

Page 3: Kansas Renewable Energy & Efficiency Conference ‘07

TWE/Enel- Leaders in Renewable Power Development

• TWE Form’s Strategic Alliance with Enel - 2006• Enel S.p.A. is Italy’s Largest Electric Utility

– $65 billion market capitalization

– $51+ billion revenue

– Over 53,000+ MW’s of electric generation worldwide

– 19,000 + MW’s of renewable electric generation

Enel will invest $ 6 billion in renewable energy worldwide

Page 4: Kansas Renewable Energy & Efficiency Conference ‘07

Smoky Hills – Centrally Located

Page 5: Kansas Renewable Energy & Efficiency Conference ‘07

Smoky Hills Development Highlights • 1st Met tower – June 2003 • Land leasing - 24+ months• Public meetings - multiple

meetings ‘03 through ‘06• Environmental evaluation• Power contracting – 2006• Turbine selection – 3Q ‘06 • BOP selection – 3Q ‘06• Start of construction 2Q ‘07

Page 6: Kansas Renewable Energy & Efficiency Conference ‘07

Environmental Due Diligence • TWE conducted the environmental work on this project with

the assistance of the following groups and contractors:– TRC Mariah, Inc.– Burns & McDonnell, Inc.– Chatman & Associates, Inc.– United States Fish and Wildlife Service– Kansas Department of Wildlife and Parks– Kansas Department of Health and Environment– United States Corps of Engineers– Lincoln County, Kansas– Ellsworth County, Kansas

Page 7: Kansas Renewable Energy & Efficiency Conference ‘07

Environmental & Archeological• Environmental Studies conducted for the project:

– Threatened and Endangered Species review and Critical Habitat Delineation (2005)

– Raptor nest inventories (2005 and 2007)– Prairie Chicken Lek and population counts (2005, 2006, and 2007)– Wetland inventory mapping– Migratory corridor review– Cultural resources review– Paleontological Resources review

Page 8: Kansas Renewable Energy & Efficiency Conference ‘07

250 MW site

Phased construction

230 kV system

22,000+ acres

40 leases

I-70 good access for construction

Smoky Hills Site

Page 9: Kansas Renewable Energy & Efficiency Conference ‘07

Smoky Hills Project Construction

Phase I-100.8 MW Smoky Hills Phase I Schedule

I. Start – April 2007

II. Turbine erection – August 2007

III. Substation Complete – November 2007

IV. Commissioning & COD-December 2007

Page 10: Kansas Renewable Energy & Efficiency Conference ‘07

Vestas – V80 1.8 MW Turbines

56 Vestas V 80 1.8 MW TurbinesTower – 78 m / 13.5 ft diamBlade – 80 m diam.Tower – 197 tonsNacelle & rotor – 104 tons

Turbine erection by Vestas

Page 11: Kansas Renewable Energy & Efficiency Conference ‘07

M.A. Mortenson – Balance of Plant MAM a leader in USA wind power construction

Access Roads – 22 miles

Underground cable – 22.5 miles

Overhead line - 7 miles

Page 12: Kansas Renewable Energy & Efficiency Conference ‘07

Foundation Excavation ~ 15 feet deep

Page 13: Kansas Renewable Energy & Efficiency Conference ‘07

Rebar & Tower Bolt – 60+ Tons

Page 14: Kansas Renewable Energy & Efficiency Conference ‘07

Foundation Pour – 490 cubic yards

Page 15: Kansas Renewable Energy & Efficiency Conference ‘07

Foundation w/o Pedestal Pour

Page 16: Kansas Renewable Energy & Efficiency Conference ‘07

Kannapolis Rail Yard

Page 17: Kansas Renewable Energy & Efficiency Conference ‘07

Site Lay Down & Staging Yard

Page 18: Kansas Renewable Energy & Efficiency Conference ‘07

Tower Delivery – Area 2

Page 19: Kansas Renewable Energy & Efficiency Conference ‘07

Setting Tower Base Section

Page 20: Kansas Renewable Energy & Efficiency Conference ‘07

Setting Second Tower Section

Page 21: Kansas Renewable Energy & Efficiency Conference ‘07

Setting 1st Nacelle – September 21st

Page 22: Kansas Renewable Energy & Efficiency Conference ‘07

Blade Delivery ~ 131 feet

Page 23: Kansas Renewable Energy & Efficiency Conference ‘07

Avoided Emissions & Energy ProductionSmoky Hills Phase I Eliminates

~ 203,000 tons CO2/ year

~ 665 tons S02/year

~ 455 tons NOx/ year

Energy supply equivalent to ~35,000 homes

Page 24: Kansas Renewable Energy & Efficiency Conference ‘07

Smoky Hills Energy Supply CustomersOver 235,000 customers will benefit from Smoky Hills renewable energy

Phase I Power Purchasers Include :

Sunflower Electric – Hays, KS

Board of Public Utilities – Kansas City, KS

Midwest Energy – Hays, KS

All Phase I energy will be consumed in Kansas

Page 25: Kansas Renewable Energy & Efficiency Conference ‘07

Economic Development BenefitsSmoky Hills will bring significant economic benefit to central Kansas

Over 150 construction jobs – at peak

$14 million in local spending during construction

Over $ 16 million to county government & local land owners

Over $ 8 million in salary & benefits for operations staff