Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Embed Size (px)

DESCRIPTION

No time to work on improvements? Find it with Kanban! Here I share practical experience from case of insurance company in Russia. I've installed Kanban board as a tool for IT management team to execute IT Service Management programme. Kanban board is great for workflow visualisation and can be used to improve efficiency of teams managing services and portfolios not only in IT, but also marketing, sales, production, operations etc. Want to learn how to do it yourself? Vladimir Ivanov is consultant and trainer in Project Management and IT Service Management, certified IPMA-B and ITIL Expert. Board member at International Project Management Association at Latvia and IPMA 4 level certification system assessor (taking exams in Latvian, English and Russian). Helps companies to develop IT Service Management by adopting ITIL, COBIT and other frameworks in an Agile way. Gives knowledge and skills in Project, Programme and Portfolio Management.

Citation preview

Page 1: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

1

Page 2: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

http://youtu.be/X1c2--sP3o0

2

Page 3: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

• No time “culture” – you start inventing chewing gum instead of brushing your teeth... • No resources to work on improvements

3

Page 4: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

No surprise many have told they feel like this... especially in the operations. • Top10 insurance company in Russia • >100 IT staff, >10M$ IT budget • Many branches in the regions • Multiple Help Desks • Low process maturity level • No SLAs with business

4

Page 5: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

If things would continue in the same direction, it would be matter of time when talks about outsourcing IT would start.

5

Page 6: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

6

Page 7: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

First agilist Walter Shewhart, Deming’s mentor

7

Page 8: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Key players – manage closely Important – keep satisfied Affected – keep informed Others – monitor

8

Page 9: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

People know issues well enough and often they also see possible solution Involvement creates engagement – needed for quality input Expert adds recommendations CIO sets priorities

9

Page 10: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

What you get is your own strategic plan on the yourney towards business and IT alignement. While working on “the big picture” do not forget to show progress by implementing quick-wins and building-up credibility. This is where many “ITIL implementation“ projects fail and stuck in “analysis-paralysis”.

10

Page 11: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

What is Kanban? (literally signboard or billboard) is a scheduling system for lean and just-in-time (JIT) production. Create Kanban board to visualise the effort and “pull the work” instead of work piling-up. Helps avoiding becoming bottleneck, idle or pending.

11

Page 12: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Backlog + priorities Goal Decomposed tasks Choosen for implementation and prioritised In process Done Effect confirmed

12

Page 13: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

13

Page 14: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Define values instead of rules – give more space to the “commanders in the field” “The commander in the field is always right and the rear echelon is wrong, unless proved otherwise...” Colin Powell, Joint Chiefs of Staff of the USA Ex We have listed all the agreed values/rules on one A4 paper and placed on the board

14

Page 15: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

1. Bring ideas - everybody shall top-up backlog

15

Page 16: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

2. Participation - regular meetings, everybody tells: A. Done B. Planned C. Barriers – need help with

16

Page 17: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

3. Ownership - ‘Product Owner’ corrects priorities weekly, but does not micromanage (self-managing team) Initially CIO, later transferred to product owner

17

Page 18: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

4. Decomposition to the chunks of work that can be done within a week. Don’t define too small or too big tasks, be fair to other teammates.

18

Page 19: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

5. Scope – ITSM programme

19

Page 20: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

6. Limit number of tasks that have been started and are not finished e.g. 2 per person Can be flexible while team is working on “understanding” it’s capacity

20

Page 21: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

7. Any agreed value/rule can be changed by the team decision, also possible to remove or add new

21

Page 22: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Apply and follow Lean principles. What is Lean? Lean, is a production practice that considers the expenditure of resources for any goal other than the creation of value for the end customer to be wasteful, and thus a target for elimination. Waste types - muda, muri and mura.

22

Page 23: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

In addition - Do it right the first time

23

Page 24: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Also - Focus on what is important today / what matters

24

Page 25: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Also – talk less, more action!

25

Page 26: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Also - Always think about improvements and efficency

26

Page 27: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Also – solve the root cause, not the side effects

27

Page 28: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Also - Fight the waste

28

Page 29: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Regularly review the efficiency of the process and implement improvements Ex After several rounds of iterations came-up with following improvements: 1. Minimise time spent in front of the board by:

• Moving debates to separate meetings • Strictly following agenda • Avoiding waste in communication

2. Improve process of decomposition of goals to tasks by: • Learning to define work into equal chunks (not too small, not too big) • Preparing definitions of the decomposed tasks prior the meeting • Updating backlog immediately when idea hits your head

3. No PC/phone during the meeting policy 4. Remove column “Effect approved” – waste 5. Do not avoid talking about barriers – ask others and PO for help

29

Page 30: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Results - they are able to execute ITSM programme without costly consultants. One was needed to kick this off ;)

30

Page 31: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

10 Kanban boards and their context: http://dl.dropbox.com/u/1638038/publikationer/10%20kanban%20boards%20and%20their%20context/10%20different%20kanban%20boards%20and%20their%20context%20-%20mskarin.pdf 10 pitfalls when implementing Kanban: http://gotocon.com/dl/goto-cph-2011/slides/MattiasSkarin_10PitfallsWhenImplementingKanban.pdf Introducing Kanban in Operations: http://blog.crisp.se/mattiasskarin/files/slides/introducing_kanban_in_operations.pdf By Mattias Skarin, Crisp

31

Page 32: Kanban applied to ITSM Vladimir Ivanov at Agile Tour Lithuania

Follow @vivanovs and let’s share our experiments!