REAL WORLD APPLICATIONS FOR INDUSTRIAL PARTNERS How do you reroute a 14-foot diameter sewer line under downtown Chicago’s famous double-decker Wacker Drive? Very carefully and with a lot of power. As part two of the City of Chicago’s Revive Wacker Drive project, F.H. Paschen/Cabo Joint Venture was awarded the task of rerouting, reconfiguring and reconstructing the Wacker Drive interchange at Congress Parkway on the city’s west side. A new 3.5-acre surface pedestrian park will top off buried, half-cloverleaf off ramps and a re-routed 14-foot diameter interceptor sewer pipeline. To handle this multi-dimensional construction product, special equipment with particular power requirements was needed including a 30-foot tunnel boring machine. REROUTE WACKER DRIVE TUNNEL Challenge continues CASE STUDY Story EARTHMOVING SOLUTIONS KOHLER® Rental met with F.H. Paschen/Cabo — engineer to engineer — to learn and fully understand the scope of the project. KOHLER Rental was able to offer a complete solution by sourcing specialty items outside of Kohler’s standard fleet. The additional equipment, a 480 to 4160 volt transformer and a ground fault disconnect monitoring system, were combined Customer F.H. PASCHEN/CABO JOINT VENTURE The joint venture between F.H. Paschen Construction and Cabo Construction brought together two award-winning construction companies with extensive expertise in construction, rebuilding, renovation and repair work in a broad range of avenues. KOHLERPOWER.COM “The level of detail that KOHLER Rental offered for our project was unparalleled.” Duncan Kopp-Richardson Superintendent F.H. Paschen

K O H L E R P O W E R . C O M R E A L W O R L D A P P L I

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

R E A L W O R L D A P P L I C A T I O N S F O R I N D U S T R I A L P A R T N E R S

How do you reroute a 14-foot diameter sewer line under downtown Chicago’s famous double-decker Wacker Drive? Very carefully and with a lot of power.

As part two of the City of Chicago’s Revive Wacker Drive project, F.H. Paschen/Cabo Joint Venture was awarded the task of rerouting, reconfiguring and reconstructing the Wacker Drive interchange at Congress Parkway on the city’s west side. A new 3.5-acre surface pedestrian park will top off buried, half-cloverleaf off ramps and a re-routed 14-foot diameter interceptor sewer pipeline.

To hand l e t h i s mu l t i - d imens i ona l construction product, special equipment with particular power requirements was needed including a 30-foot tunnel boring machine.

REROUTE WACKER DRIVE TUNNEL

Challenge

continues

CASESTUDY

Story

EARTHMOVING SOLUTIONSKOHLER® Rental met with F.H. Paschen/Cabo

— engineer to engineer — to learn and fully

understand the scope of the project. KOHLER

Rental was able to offer a complete solution

by sourcing specialty items outside of Kohler’s

standard fleet. The additional equipment, a 480

to 4160 volt transformer and a ground fault

disconnect monitoring system, were combined

CustomerF.H. PASCHEN/CABO JOINT VENTURE

The joint venture between F.H. Paschen Construction and Cabo Construction b r o u g h t t o g e t h e r t w o award-winning construction companies with extensive expertise in construction, rebuilding, renovation and repair work in a broad range of avenues.

K O H L E R P O W E R . C O M

“The level of detail that KOHLER Rental offered for our project was unparalleled.”

Duncan Kopp-RichardsonSuperintendent

F.H. Paschen

THE EQUIPMENT

n One 1,500 kW KOHLER® Generatorn Two 20 kW KOHLER Generatorsn 480 volt to 4160 volt Transformern Ground Fault Disconnect

Monitoring Systemn 800 Amp I-Line Distribution Panel

with three generators and an I-line distribution panel

to power the tunnel boring machine and the lighting

and ventilation in the tunnel. The comprehensive power

package backed by KOHLER® Rental’s uncompromising

customer service allowed F.H. Paschen/Cabo to focus

on crushing through 5,000 cubic yards of dirt, rock,

concrete, brick and wood.

“The level of detail KOHLER Rental offered with

our project was unparalleled,” said Duncan Kopp-

Richardson, Super intendent for F.H. Paschen.

“Not only did KOHLER work with us to understand our

power requirements, they sourced specialty equipment

outside their usual rental offering to

ensure we had the comprehensive

solution we needed. The company was

in constant communication with us

about the equipment before, during

and after the tunnel project. KOHLER

worked with our construction schedule

to ensure preventative maintenance and

inspections were done during off hours.”

R E A L W O R L D A P P L I C A T I O N S F O R I N D U S T R I A L P A R T N E R S

By sourc ing specia l ty equipment, KOHLER Rental was able to offer the power and safety needed to maneuver a 150 ton tunnel boring machine under one of Chicago’s most famous streets.

“F.H. Paschen/Cabo was a true partner in this project,” said John Chowaniak, Senior Account Manager, KOHLER Rental.

“By listening and understanding the project needs, KOHLER Rental combined our normal rental offering with sourced specialty equipment to supply power safely and consistently for the three-month venture.”

“Great support, flexibility and attention to the details of the project are why KOHLER Rental will continue to be our power partner,” said Kopp-Richardson.

Result

continued from cover

“KOHLER Rental ensured we

had the comprehensive

solution we needed.”

Duncan Kopp-RichardsonSuperintendent

F.H. Paschen